Decommissioning Development Project in Esbjerg<br />

Foredrag hos Skibsteknisk Selskab<br />

By <strong>Peter</strong> <strong>Blach</strong>, Offshore Center Danmark<br />

1


Background<br />

• More than 7000 off-shore constructions world wide<br />

• More than 600 off-shore constructions in the North Sea<br />

• In due time the platforms will have reached their<br />

lifetime limit and will have to be decommissioned<br />

2


The OSPAR aggreements<br />

The Oslo/Paris aggrements (OSPAR) of 1988, states with regard to<br />

the North Sea off-shore constructions:<br />

"No off-shore installations or off-shore pipelines shall be dumped<br />

and no off-shore installations shall be left wholly or partly in place<br />

in the maritime area”<br />

OSPAR-konventionen, Annex III Article 5,2<br />

3


Decommissioning in Esbjerg<br />

Through several years, a group of companies, consultants,<br />

educational institutions and politicians in Esbjerg has<br />

made sincere efforts to enable the Port of Esbjerg to be able to<br />

handle off-shore construction projects<br />

Port of Esbjerg<br />

Denmark<br />

Esbjerg:<br />

Denmarks Offshore City No. 1<br />

4


The off-shore constructions to be<br />

decommissioned in Esbjerg is<br />

expected to come from the<br />

North Sea areas of:<br />

• Denmark<br />

• Norway<br />

• UK<br />

Mainly topside and jacket constructions<br />

between 1,000 – 10,000 tons as well as<br />

other parts of larger constructions<br />

5


Miljørigtig fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

(<strong>Dekommissionering</strong>)<br />

Projektdeltagere:<br />

1. Mærsk Contractors<br />

2. Esbjerg Offshore Services<br />

3. Uniscrap<br />

4. Promecon<br />

5. Rambøll<br />

6. Det Norske Veritas<br />

7. Force Technology<br />

8. Esbjerg Havn<br />

9. Aalborg Universitet Esbjerg<br />

10. Esbjerg Kommune<br />

11. Ribe Amt<br />

12. Offshore Center Danmark<br />

Løft<br />

Klipning<br />

Opskæring<br />

6


<strong>Dekommissionering</strong> <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Administration<br />

Udviklingsprojektet er støttet <strong>af</strong> Videnskabsministeriet med 1,1<br />

mio. kr. De involverede parter erlægger det samme beløb i<br />

egne timer<br />

Pengene anvendes til projektledelse, rejser,<br />

konsulent/rådgivning og formidling <strong>af</strong> projektresultatet<br />

Projektet løber over 4 år, med start august 2003 og <strong>af</strong>slutning<br />

juni 2007<br />

Offshore Center Danmark er administrativ projektleder på<br />

Projektet<br />

Øvrige deltagere er: RAMBØLL, Mærsk Contractors, Uniscrap,<br />

DNV, EOS, Force Technology, Promecon, Esbjerg Havn,<br />

Esbjerg Kommune, Aalborg Universitet Esbjerg<br />

7


6 fjernelsesmetoder<br />

5. Rambøll Metoden<br />

Kan anvendes i Nordsøen og undersøges nærmere<br />

8


6 fjernelsesmetoder<br />

2. Pramløsningen<br />

Kan anvendes i Nordsøen og undersøges nærmere<br />

9


6 fjernelsesmetoder<br />

6. Flydekran og pram<br />

”Baglæns” <strong>af</strong> den oprindelige installation og kan anvendes. Meget dyr<br />

10


Miljørigtig fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

(<strong>Dekommissionering</strong>)<br />

Offshore<br />

Tre ud <strong>af</strong> seks fjernelsesmetoder er blevet vurderet:<br />

1. Pramløft - problematisk<br />

2. Borerig/pram (Rambøll-metoden) - problematisk<br />

3. Versatruss - egnet<br />

Se mere på medlemsdelen <strong>af</strong><br />

www.<strong>offshore</strong>center.dk<br />

Versatruss løft<br />

11


Miljørigtig ophugning og fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Hvad skal tilbydes i Esbjerg?<br />

Planlægning, kvalitetssikring og fjernelse<br />

Klipning<br />

Opskæring<br />

Genbrug<br />

12


With regard to decommissioning of off-shore<br />

constructions Esbjerg offers the following operations:<br />

Lifting<br />

Shredding<br />

Cutting<br />

Recycling<br />

13


Miljørigtig ophugning og fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Hvor lang er vi?<br />

VVM redegørelse pågår<br />

Offshore Modtageanlæg for<br />

ophugning <strong>af</strong> konstruktioner er placeret<br />

14


Miljørigtig ophugning og fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Hvor på Esbjerg Havn?<br />

Offshore Modtageanlæg<br />

15


Miljørigtig ophugning og fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Indretningsplan for Offshore Modtageanlæg<br />

Service faciliteter<br />

Evt. Rig Repair<br />

<strong>Dekommissionering</strong><br />

16


Miljørigtig ophugning og fjernelse <strong>af</strong> <strong>offshore</strong> <strong>platforme</strong><br />

Fokus er på<br />

• Økonomi– billigste og bedste total løsning<br />

• Miljø<br />

• Sikkerhed<br />

• Sundhed<br />

• Kvalitet<br />

Hvad angår dekommissionering tilbyder Esbjerg<br />

• Egnet sted og infrastruktur<br />

• Dygtige og kapable virksomheder<br />

• Viden og erfaring<br />

17


Location of the planned new site<br />

18


Refitting of rigs may take place within the harbour<br />

19


At present the focus is on the important<br />

enviromental assesments and approvals<br />

20


Environmental Assesment of decommission facilities<br />

• What is the nature and extent of impacts on the<br />

environment on shore and in The Wadden Sea?<br />

• If unacceptable: can the impact be reduced or eliminated?<br />

• Will the construction and operation of the facilities <strong>af</strong>fect<br />

the infrastructure?<br />

• Will it <strong>af</strong>fect the visual, cultural and recreational values of<br />

the shoreline and/or the landscape?<br />

• Risk assesment and contingency planning?<br />

21


Public Hearing Phases<br />

1. A general hearing based on the announcement of intent,<br />

i.e. "we want to establish and operate such a facility"<br />

2. The Environmental Impact Assesment is presented along<br />

with the necessary adjustments of the regional plans for<br />

area use, encompassing ideas and arguments received at<br />

the hearing<br />

3. A second public hearing (8 weeks)<br />

4. The County adobts the plan and approves the<br />

environmental license for the facility<br />

22


Decommissioning in the Port of Esbjerg<br />

The focus is on:<br />

• Economy – always the cheapest and the best solution<br />

• Health<br />

• S<strong>af</strong>ety<br />

• Environment<br />

• Quality<br />

23


With regard to the decommissioning,<br />

Esbjerg – Denmarks Off-shore City No. 1 – offers<br />

the following:<br />

• Suitable locations and infrastructure<br />

• Capable companies<br />

• Knowledge and experience<br />

24


Read more and contact us on<br />

www.<strong>offshore</strong>center.dk<br />

www.decom2007.dk<br />