FITT Resources recently completed a series of repair works on the Mangrove Creek Dam in NSW, on behalf of the Central Coast Council. The scope of works, which were completed between October 2019 and April 2020, included a series of joint repairs on the spillway chute wall, along with repairs to the slab floor, plus concrete repairs to cracks in the spillway wall, the dam face joint, and the interface between the dam wall and the toe slab.

FITT Resources recently completed a series of repair works on the Mangrove Creek Dam in NSW, on behalf of the Central Coast Council. The scope of works, which were completed between October 2019 and April 2020, included a series of joint repairs on the spillway chute wall, along with repairs to the slab floor, plus concrete repairs to cracks in the spillway wall, the dam face joint, and the interface between the dam wall and the toe slab.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Spillway Chute Floor Slab Repair

• 4 joints of varying length

(Avg 15 Lm per joint) to be

repaired

• Concrete cutting 1 m on

either side of the joint upto

avg. depth of 125 mm

• Expose and treat corroded

reo bars with anti-corrosive

coating

• Install SL 81 Mesh and

Anchor bars

• Pour 5 mm aggr. Concrete

upto slab level

SPILLWAY FLOOR SLAB REPAIR - SCOPE