MAJOR ACCOMPLISHMENTS

Automotive Repairs:

The city has a fleet of 160 pieces of rolling stock

Public Works / CIP

Last year request for repairs totaled 129, compared to 769 the previous year of which 117 were

successfully repaired. This demonstrates a vast improvement in our repairs and maintenance

operations.

Our challenge is the 60% of our fleet is beyond economical repair, and with three technicians these

tasks is overwhelming.

Pump Stations:

We relined six (6) linier miles of our gravity sewer system, I service areas 4, 5, 7, and 8.

Our goal is to be at 100% compliant by November 2020.

Our challenge is to stick relining of our gravity mains which is plagued with excessive inflow/

infiltration due to aged infrastructure this takes a toll on the longevity of pump stations.

Utility Billing Transition:

We have transitioned 98% of our utility billing to Miami-Dade County.

Of the 5,603 water meters in the distribution system, 332, are left to be replaced at an estimated

cost of $68,000.

Total number of meters in our system = 5,603

Total number of meters remaining to be replaced = 332 at a cost of $68,000.

Total number of meters replaced to date= 5,271.