24.09.2021 Views

WPNL 202101

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Transport & Installation

Jan-Mark Meeuwisse

Q/A with Jan-Mark Meeuwisse, Commercial Director GustoMSC

A look at future offshore

wind turbine installation

In 2002, the first GustoMSC designed jack-up barge, ‘Buzzard’, worked on the

construction of Horns Rev1, Denmark’s first large offshore wind farm. Since

then, over thirty GustoMSC designed Jack-ups (barges and vessels) have been

operating in the offshore wind installation and maintenance.

How many GustoMSC designs have been

developed over time?

“Since 2007 over seven dedicated WTI-JU (Wind Turbine

Installation Jack-Up) designs have been designed and are

operational. These last four years we have developed 4 new future

proof WTI-JU designs. All of them are under construction at

shipyards in the US, Japan, Singapore, South Korea and China

and each design has its owner specific requirements incorporated.”

What design has been the most challenging

and why?

“For me personally that will be the first NG-9000C designs, being

the Sea Installer and Sea Challenger for A2SEA and the Brave and

Bold Tern for Fred. Olsen Windcarrier. These where the first

dedicated new generation WTI-JUs and in time the most copied

designs. Here we enabled the installation market to install faster,

carry more than 8 WTG (Wind Turbine Generator) sets with full

length towers, integrated leg encircling cranes and operate in a

deep water range of 45 to 50 meters. The market required

dedicated installation vessels for faster, safer installations and these

NG-9000C’s installed most of the WTG’s to date.”

What have been the main developments in

design since the first vessel?

“There have been many developments in the design, for example,

when it comes to the operational window, like significant wave

height (Hs) ability, crane capacity, payload, deck area, number of

components in one go, installation speed and safety. In particular

in the jacking system, in combination with the design of the hull,

leg, leg guides and footing.

Our success is that we supply the design and jacking system as an

integrated solution, therefore reducing the risk of the shipyard and

eventually the owner. These jack-ups are supported on four hard

points (legs). The complete hull needs to be lifted daily, meaning

the number of jacking moves are far more compared to the jackups

used in the Oil&Gas sector. We have managed to achieve high

jacking cycles and less wear & tear on the legs and system,

reducing OPEX during the life time of the WTI-JU. There is no

other supplier in the market that provides an optimized design and

system fully integrated.“

“We are able to integrate all these disciplines like the jacking

system, legs, crane, and more, in one design without

compromising on the safety, capacity, operability and strength.”

Over time, what have been the main changes

in requirements for vessels?

“The main challenges have been in crane capacity and outreach,

hoisting height and carrying capacity, resulting in larger and wider

vessels. And installing WTG’s and foundations in deep waters. All

due to the growing WTG sizes.”

Can conventional installation vessels still

install the future turbines or do you expect

completely different concepts?

“Over time we have been able to upgrade the NG-9000C with

minimal investments for the owner. Designed in 2008 for installing

3.6 to 5 MW WTG’s, we have been able to upgrade the designs to

install the 8 and 9.5 MW WTG’s. These owners recently

announced major upgrades. We already executed serious

engineering work to upgrade these NG-9000C’s, enabling to carry

1,600 ton cranes with longer booms.”

“Larger cranes are heavier and weight on a jack-up is a major

issue, therefore upgrades of the jacking system will be required

and one should accept the reduction of carrying capacity. New

innovations in these upgrades is mainly the Operating Support

System (our OSS - a Smart App) in order to maintain and control

safety of the overall Jack-up.”

Can existing vessels still be upgraded/refitted

to future standards?

“Only a few WTI-JUs can be upgraded. There is a limit to

upgrades and payload capacity will eventually be insufficient to

carry sufficient WTG sets. In addition some of these jack-ups are

restricted in water depths. Therefore the ‘shelf-life’ will be limited

and these jack-ups will end up executing maintenance work.”

28 | 01-2021

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!