24.09.2021 Views

WPNL 202101

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

Wind Energy Magazine is now Windpowernl. Informing on the developments in the Dutch wind energy sector and its players.

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

responsibilities that come with that.” Zeewolde Wind Farm is not

unique in this, by the way, explains Sieburgh. The same goes for the

Windplanblauw, Windplangroen and Krammer wind farms. “You

have to ask yourself, is this desirable? Just add up all those grids and

ask former minister Brinkhorst, who was in favour of public grids,

what he thinks about all those gigawatts of private grids being

created. At the same time, all the grid operators are complaining

that they have no connection capacity for solar.”

But for now, Windpark Zeewolde BV remains responsible for the

connection. Meanwhile, construction continues apace at the wind

farm. Building the largest onshore wind farm in the Netherlands is

a major logistical puzzle. In total, 700 heavy transports are required,

says Sieburgh. The components are manufactured all over the

world. The largest components arrive in Flevohaven by water and

are transported from there to the construction site. This often

happens at night, via special transports. A private exit from the

motorway has been built specifically for this purpose. Several crane

crews work simultaneously on the installation, otherwise the project

would take too long. Because of the different sizes of the turbines,

different crane sizes are also used.

Completion in autumn 2022

At the time this edition went to the printer, about 25 wind turbines

had been installed. On June 21, the first wind turbine was already

officially connected to the grid. By mid-July, all foundations were

completed, three months ahead of schedule. The wind farm is

planned to be fully operational in the fall of 2022 and is then

expected to generate around 850,000 megawatt hours annually. A

long-term contract has been signed with energy company Vattenfall

for the purchase of the power.•

Installation of a V136 along the A27

currently installed on land in the Netherlands – if you do not

include GE’s Haliade-X prototype at Maasvlakte 2. This will be

short-lived, however, because the wind turbines in the future

Windplangroen en Windplanblauw wind farms will be even larger,

says Sieburgh.

Windpark Zeewolde BV does not own any land itself, except for the

site where the substation for the wind farm is located. For the

placement of the new wind turbines, building contracts have been

set up with the relevant landowners. All in all more than a thousand

contracts were signed during this whole process, Sieburgh tells.

Network manager against all odds

That substation, to which all the wind turbines will be connected, is

a private substation. This wasn’t a conscious decision, Sieburgh

says. The law states that all projects over 100 MW must be

connected to grid operator TenneT via their own substation.

Sieburgh: “I’d rather hand it over to the grid managers. We’re now a

private party filling a public function. What’s more, Eneco and Pure

Energie’s eight wind turbines will also be connected to this

substation, which means we’re also taking on the role of grid

manager. With all the regulations, tariffs and all the installation

WIND FARM FACTS

Owner: Windpark Zeewolde BV

Installed capacity: 320 MW

Number of wind turbines: 83

Turbine type: Vestas V136, V126, V117, V110

Turbine power: Between 2.2 MW and 4.3 MW

Substation: 2 x 240 MWA transformers converting 33 kV

to 150 kV

Connection to national grid: TenneT’s station at the

Bloesemlaan

Companies involved:

Civil works: Windcombinatie Dura Vermeer–GMB

Cabling: Van den Heuvel

Substation construction: Hitachi ABB

Substation maintenance: Volker Energy Solutions

Asset Management: OutSmart

Crane hire: M Verschoor

01-2021 | 9

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!