06.02.2024 Views

CC4201

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

CASEstudy<br />

Skipping ahead<br />

BIM software has been used on the temporary works for HS2's Colne Valley Viaduct, which has been<br />

designed to mimic the skipping of stones across a lake<br />

With a tight programme schedule,<br />

the use of Tekla custom<br />

components proved essential<br />

on the construction of HS2's Colne Valley<br />

Viaduct temporary works, enabling<br />

Taziker to navigate design changes and<br />

modifications timely and efficiently.<br />

Stretching for over two miles (3.4km)<br />

between Hillingdon and the M25, the<br />

Colne Valley Viaduct forms a critical part<br />

of the HS2 network. Carrying the railway<br />

around 10 metres high above a series of<br />

lakes, the River Colne and Grand Union<br />

Canal, the viaduct will be the longest<br />

railway bridge of its kind in the UK once<br />

completed. The design of the structure<br />

was inspired by the flight of a stone<br />

skipping across water, with a series of<br />

elegant spans making up its<br />

construction. The project is being led by<br />

HS2's main works contractor Align JV - a<br />

team made up of Bouygues Travaux<br />

Publics, Sir Robert McAlpine and<br />

VolkerFitzpatrick.<br />

The construction of the momentous<br />

structure has understandably come up<br />

against various logistical and engineering<br />

challenges, not least the location and<br />

tricky terrain. One of those challenges<br />

was to construct 292 bored piles,<br />

required to support the piers and<br />

abutments of the bridge. In order to<br />

enable these works and provide safe<br />

access for plant equipment and materials<br />

operating over the lakes, a series of<br />

temporary steel jetties were required.<br />

Spanning over four lakes in the South<br />

Harefield region, this temporary<br />

causeway was detailed, fabricated and<br />

installed by Taziker.<br />

Measuring at over 3,000 km in length,<br />

the temporary jetties were constructed<br />

from circa 3600 tonnes of steelwork. At<br />

each pier location, the jetty was further<br />

widened to include the whole working<br />

area, with modular decking sections<br />

removed as required for permanent piling<br />

and to construct cofferdams.<br />

18<br />

January/February 2024

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!