Project Management Consultancy Services for <strong>Sewerage</strong>, Storm, Surface Water Drains and Lake<br />

Protection Works For <strong>Raipur</strong> City<br />

Detailed Design Report - <strong>Sewerage</strong><br />

Chapter 9: Design of Sewage Treatment Plant<br />

The above costs are presented for two cases, namely ultimate requirement and intermediate<br />

requirement. ASP and SBR are almost identical in cost though the civil component is less in SBR.<br />

Operation & Maintenance cost: The technological options under consideration require various<br />

mechanical equipments (pumps, aerators) for aiding the biological process. These equipments or<br />

their parts are in continuous touch with sewage and due to corrosive nature / contents of<br />

sewage, they get clogged and/or are damaged. This needs periodic maintenance to upkeep their<br />

useful life and utility in the process. The piping, valves, gasholders, etc, need periodic<br />

maintenance for efficient working of the reactors. In ASP large machinery is at work that<br />

requires O&M. In mechanized processes category SBR requires minimum O&M because the<br />

plant is working under controlled processes. On the basis of literature and experience in Indian<br />

conditions, for various technologies, the annual O&M percentage cost with respect to capital<br />

cost (for intermediate stage of year 2027) is presented in Table 9.11.<br />

Table-9.11: O&M Cost for STPs with SBR & ASP<br />

O& M cost<br />

Rank Process % (Lakh Rs.)*<br />

1 Sequential Batch Reactor (SBR) 4 819.28<br />

2 Activated Sludge Process 8 1588.4<br />

* Intermediate year 2027<br />

For the intermediate stage of year 2027, a total of 209 Mld sewage would be available for<br />

treatment. The capital cost and annual O&M cost along with capitalized O&M cost (for 15 years<br />

with 12% interest) for ASP and SBR technologies is computed and presented in Table 9.12 below.<br />

Table-9.12: O&M Cost for ASP and SBR STPs (Intermediate Stage – 209 MLD)<br />

Rank Process<br />

Cost (Lakh Rs.)<br />

Capital O&M Capitalized Total<br />

Per O&M - 15<br />

year yrs<br />

(i) (ii) (iii) (i+iii)<br />

1 Sequential Batch Reactor (SBR) 19855 819.28 5580.01 26062.01<br />

2 Activated Sludge Process 20482 1588.40 10818.38 30673.38<br />

9.5.3 Total Cost of STP<br />

Using the computations of land cost, capital investment cost and annualized O&M cost for the<br />

selected options, a final ranking is presented in Table 9.13.<br />

Table 9.13 : Total Cost For STPs (Intermediate Stage)<br />

Rank Process<br />

Cost (Lakh Rs.)<br />

Land Capital Capitalized O&M<br />

for 15 yrs<br />

Total<br />

1 Sequential Batch Reactor (SBR) 31.65 19855.00 5580.01 25466.66<br />

2 Activated Sludge Process 79.12 20482.00 10818.38 31379.5<br />

As seen from the above comparison, SBR technology is cheaper than Activated Sludge Process<br />

and becomes the economical option considering cost of land, capital investment and annualized<br />

O&M for 15 years tenure. The life cycle analysis of ASP and SBR plants for all three zones is<br />

presented in Annexure – 6 and the hydraulic design of SBR plants is given in Volume – III.<br />

9.5.4 Recommendation on Treatment Technology<br />

On the basis of information presented in section 9.4, a summary of technical and economical<br />

comparison is presented in Table 9.14.<br />

Meinhardt Singapore Pte Ltd, (India Branch) Page 83 of 120