2ub8Xn
2ub8Xn
2ub8Xn
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
Allana Potash Corp.<br />
Management’s Discussion and Analysis<br />
For the three months ended October 31, 2012<br />
Estimated OPEX were also calculated for Production, Transportation/Handling, and Port. The OPEX costs<br />
in US$ per tonne are outlined in the table below:<br />
Estimated Production OPEX $70.24/tonne<br />
Estimated Transportation/Handling OPEX $8.85/tonne<br />
Estimated Port OPEX $2.88/tonne<br />
Estimated general & administrative and contingency costs were also calculated in US$ per tonne and are<br />
outlined in the table below:<br />
Estimated G&A $5.70/tonne<br />
Estimated Contingency $2.87/tonne<br />
The main assumptions used in the PEA are as follows:<br />
Production: One million tonnes MOP per year<br />
Mine life: 30 years<br />
Mining method: Solution mining<br />
Processing: Solar evaporation and flotation<br />
Transport: Trucking to Djibouti<br />
Power: Diesel generation with fuel shipped to site<br />
Water: Water on site<br />
Potash Price: US$500 per tonne in 2013<br />
Sustaining CAPEX: US$44 million (before cavern or process design optimization)<br />
Feasibility Study work is ongoing and on schedule for completion in yearly 2013. In the PEA, Ercosplan<br />
recommends hydro-geological studies to identify large water sources, dissolution testwork, rock<br />
mechanical testwork, a pilot solution mining operation and solar evaporation ponds tests. Allana initiated<br />
these studies in November 2011 and the work is proceeding. Five geotechnical drill holes have been<br />
completed to supply large diameter (PQ) core for rock mechanic testwork which is underway in Germany.<br />
Pilot solar evaporation ponds are complete and preliminary evaporation tests on synthetic brine indicate<br />
evaporation rates of approximately 1 cm per day. The crystal crop from this brine serves as preliminary<br />
test material and 1000 kg were shipped to Germany for flotation studies to prepare the processing flow<br />
sheets.<br />
Pilot solution mining is also underway on the project. A trial well has completed sump leaching and<br />
undercut leaching. Production leaching of the Sylvinite Zone was initiated in December and the resulting<br />
crystal crop will be utilized to optimize processing.<br />
In addition, hydrogeological studies are underway throughout the Allana license. To date, 18 holes have<br />
been drilled and all have encountered water. Pump down tests and recharge tests are ongoing but<br />
preliminary data indicated flow rates of up to 150 m 3 per hour from some wells. .<br />
Ercosplan is evaluating the costs and benefits of increasing production of MOP to two MTPY after the third<br />
year of full production. The potential increase would coincide with the planned completion of rail capacity<br />
for potash transport in the area.<br />
The PEA, with a target accuracy of +/- 35%, was completed as an initial scope within Allana’s full<br />
Feasibility Study program currently being undertaken by Ercosplan, a widely recognized world leader in<br />
potash exploration techniques and potash mining and processing.<br />
20