JOB SHOTS<br />

T-Bar Water Supply System<br />

Chlorination Facility<br />

(Midland County Fresh Water<br />

Supply District No. 1)<br />

Job 4401—$6.3 million<br />

Project Manager: Joey Perell<br />

Superintendent: Joe Ross<br />

Assistant Supt.: Charley Senne<br />

Project Engineer: Luke Messer<br />

Project Coordinator: Sally Miller<br />

Foreman: Sean Bryson<br />

Top Left: Completed footing and<br />

standing of the tower crane.<br />

Bottom Left: Placing the second lift of<br />

the water tower.<br />

Far Right: Placing the last ring on the<br />

water tower to complete the concrete<br />

work and allow for the metal tank to<br />

begin.<br />

Submitted by Joey Perell<br />

JOB SHOTS<br />

Hialeah Reverse Osmosis<br />

Water Treatment Plant<br />

(Hialeah Water LLP)<br />

Job 3016—$7.3 million<br />

Sr. Project Manager: Mark Abram<br />

Project Manager: Josh Petro<br />

Crew: Tyler Boehning, Ronald Mays,<br />

Duane Dennis, Jeff Griffin<br />

Top: Hydro tank change order work.<br />

Bottom: The project is coming to an end<br />

and waiting for start up.<br />

Submitted by Josh Petro<br />

Page 8<br />

MIDLAND, TEXAS<br />

HIALEAH, FLORIDA