IMAX Cinema, Waterloo<br />
This high-tech auditorium is located in a<br />
very difficult urban site: in the middle of a<br />
roundabout with tunnels below.<br />
The IMAX Cinema is the latest large<br />
screen format movie theatre for the British<br />
Film Institute located within the Bullring<br />
Roundabout, adjacent to Waterloo Station,<br />
and will be an addition to the South Bank<br />
Arts Centre. The cinema will be Europe's<br />
largest venue showing extra-high<br />
resolution IMAX films.<br />
The building consists of a circular drum<br />
approximately 40m in diameter and six<br />
storeys high providing an enclosure to<br />
house the auditorium. The perimeter<br />
structure is circular on plan and provides a<br />
gallery behind the glass cladding.<br />
Internally the majority of the space is<br />
devoted to the auditorium with other areas<br />
providing circulation, reception and plant<br />
- 34 -<br />
areas. The site is in a well in the middle of<br />
one of London's busiest roundabouts and<br />
as if the headache of site deliveries was not<br />
enough, a network of tunnels beneath the<br />
site made the foundation design a<br />
nightmare. Two Waterloo and City Line<br />
Underground tunnels run through the<br />
centre of the site at a depth of<br />
approximately 4.5m. At the south end of<br />
the site a main sewer and a BT duct<br />
infringe on the building's footprint<br />
requiring the foundations to span up to<br />
23m to avoid the obstructions. The solution<br />
was to provide a thick concrete slab<br />
supported on piles located where there was<br />
space to locate them.<br />
As there was no direct access by road to<br />
the site an elevated steel gantry was<br />
provided at road level which allowed<br />
traffic to enter from the roundabout to<br />
deliver materials. The gantry was designed<br />
to accept only a single wagon and there<br />
were restrictions on the hours during which<br />
deliveries could be made.<br />
In order to provide acoustic isolation of the<br />
auditorium from ground-borne vibration,<br />
spring mounts have been installed between<br />
the soffit of the first floor and the heads of<br />
the ground floor columns.<br />
The structure above the first floor podium<br />
slab is a structural steel frame. The upper<br />
floor areas are constructed using<br />
lightweight concrete cast onto profile steel<br />
sheeting. The floor beams are designed to