DIRECTOR GENERAL NAVAL PROJECT, MUMBAI-23<br />
AUGMENTATION OF POWER SUPPLY AND FREQUENCY CONVERTER<br />
ARRANGEMENTS <strong>FOR</strong> BRAHMAPUTRA CLASS OF SHIPS<br />
Request for Proposal No.DGNP (MBI)/7564/B’PUTRA dated 14 Dec 12<br />
INSTRUCTIONS TO BIDDERS<br />
1. Bids <strong>in</strong> sealed cover are <strong>in</strong>vited from Orig<strong>in</strong>al Equipment Manufacturers<br />
(OEMs) or authorised dealers of OEMs for Augmentation of Power Supply and<br />
Frequency Converter Arrangements for Brahmaputra Class of Ships as listed <strong>in</strong> Part<br />
II of this RFP. Please super scribe the abovementioned Title, RFP number and date<br />
of open<strong>in</strong>g of the Bids on the sealed cover to avoid the Bid be<strong>in</strong>g declared <strong>in</strong>valid.<br />
2. Qualification Criteria: To qualify, an applicant must demonstrate to<br />
DGNP(MBI) that it substantially satisfies the requirements regard<strong>in</strong>g experience,<br />
design, personnel, f<strong>in</strong>ancial position and litigation history. The qualification will<br />
therefore be based on the applicant meet<strong>in</strong>g the m<strong>in</strong>imum criteria regard<strong>in</strong>g the<br />
applicant’s general and specific experience, personnel and equipment capabilities,<br />
and f<strong>in</strong>ancial position, specified <strong>in</strong> the Qualification criteria, as demonstrated by the<br />
applicant’s responses <strong>in</strong> the forms attached and other requested documentation.<br />
DGNP(MBI) reserves the right to waive off m<strong>in</strong>or deviations from the criteria if they<br />
do not materially affect the capability of an applicant to perform the contract. Any<br />
tender submitted without the necessary support<strong>in</strong>g documents is liable to be<br />
rejected. M<strong>in</strong>imum qualify<strong>in</strong>g criteria for the quot<strong>in</strong>g firms is as follows:-<br />
(a) Constitution, legal status and registration (class and type) with other<br />
government agencies and previous qualification for similar work <strong>in</strong>clud<strong>in</strong>g the<br />
grade awarded would be required.<br />
(b) OEM or authorised dealership certificate.<br />
(c) F<strong>in</strong>ancial Position. The Supplier should satisfy the follow<strong>in</strong>g<br />
requirements:-<br />
(i) Average f<strong>in</strong>ancial turnover (I.T.C.C, Annual Report, Balance<br />
sheet and profit & loss statement to be enclosed) of the quot<strong>in</strong>g<br />
firm/Pr<strong>in</strong>cipals for last 03 years of FY end<strong>in</strong>g 31 Mar 12 should be at<br />
least Rs. 5 Crores.<br />
(ii) F<strong>in</strong>ancial stand<strong>in</strong>g as certified by Banker, audited profit & loss<br />
and audited balance sheets for the last three years should be<br />
submitted and must demonstrate the soundness of the applicant’s<br />
f<strong>in</strong>ancial position, show<strong>in</strong>g long term profitability. Where necessary,<br />
DGNP(MBI) will make enquiries with the applicant’s bankers and/or<br />
other sources as applicable.<br />
Page 1 of 56
(iii) The applicant shall demonstrate that he has access to, or has<br />
available, liquid assets, unencumbered real assets, l<strong>in</strong>es of credit, and<br />
other f<strong>in</strong>ancial means sufficient to meet the construction cash flow for<br />
the contract, net of the applicant’s commitments for other contracts.<br />
The applicant must submit a solvency certificate to demonstrate that a<br />
level of work<strong>in</strong>g capital or credit is available to support the statement<br />
on f<strong>in</strong>anc<strong>in</strong>g of project.<br />
(d) Specific Experience. Firm/Pr<strong>in</strong>cipals should have experience <strong>in</strong><br />
design & manufacture of power supply and frequency converter arrangements<br />
and its associated system/sub systems.<br />
(e) Litigation History. The applicant shall provide accurate <strong>in</strong>formation<br />
on any current or past litigation or arbitration result<strong>in</strong>g from contracts<br />
completed or under execution by him over the last ten years. A history of<br />
awards aga<strong>in</strong>st the applicant can be a ground for disqualification of<br />
application. DGNP(MB) reserves the right to verify the facts wherever<br />
applicable and disqualify applicants on this account. In addition, an Affidavit<br />
on judicial stamp paper stat<strong>in</strong>g that the firm is not banned or blacklisted and<br />
no recovery outstand<strong>in</strong>g <strong>in</strong> any govt. department will be required.<br />
(f) Current Work Load and EDC. The applicants shall submit details of<br />
current orders with expected dates of completion (EDC) of work. Also, for<br />
works <strong>in</strong> progress, the percentage of work completed as on 31 Mar 12 is to be<br />
<strong>in</strong>cluded. Availability of qualified manpower with firm for the execution of the<br />
project and attend<strong>in</strong>g calls dur<strong>in</strong>g warranty period is to be confirmed by the<br />
applicant.<br />
(g) Open<strong>in</strong>g of ‘Q’ Bids.<br />
(i) ‘Q’ bids of only those firms that have been qualified dur<strong>in</strong>g<br />
Tech<strong>nic</strong>al evaluation would be opened. Submission or participation by<br />
a tenderer for more than one tender for the present RFP will result <strong>in</strong><br />
disqualification of all tenders submitted by him for this RFP.<br />
(ii) Failure to provide <strong>in</strong>formation which is essential to evaluate the<br />
applicant’s qualifications or to provide timely clarification or<br />
substantiation of the <strong>in</strong>formation supplied will result <strong>in</strong> disqualification of<br />
the applicant.<br />
(iii) DGNP(MB) reserves the right to:-<br />
-Amend the scope and value of the contract be<strong>in</strong>g tendered.<br />
-Reject or accept any application.<br />
-Cancel the qualification process and reject all applications<br />
without assign<strong>in</strong>g any reasons.<br />
(h) Language. The rul<strong>in</strong>g language of the application shall be English.<br />
Page 2 of 56
3. General Information about the tender:-<br />
(a) Tender reference No DGNP (MBI)/7564/B’PUTRA<br />
(b) Last date and time for receipt of tenders: 15 Jan 2013 / 1400 Hrs<br />
(c) Date and Time for open<strong>in</strong>g of tenders: 15 Jan 2013 / 1500 Hrs<br />
(d) Place of open<strong>in</strong>g of tenders: DGNP Build<strong>in</strong>g Naval Dockyard, Mumbai<br />
(e) Pre-Bid Conference between 07 Jan 2013 and 11 Jan 2013 at JPD(L)<br />
Office, DGNP(MBI) Tel No. 022-22751884/ 22751665 (The details of<br />
personnel attend<strong>in</strong>g is to be <strong>in</strong>timated one day prior to the pre-bid meet<strong>in</strong>g)<br />
(f) For clarification contact as follows:-<br />
Clarification on Tech<strong>nic</strong>al matters/Scope of Work<br />
The Director General Naval Project<br />
[for JPDL]<br />
Naval Dockyard<br />
Mumbai 400023<br />
Tele:- 022-22751884/22751665/22661144/22751937<br />
Fax:- 022-22661142<br />
e-mail : wncdgnp-navy@<strong>nic</strong>.<strong>in</strong><br />
4. This RFP is divided <strong>in</strong>to five parts as follows:-<br />
(a) Part I – Conta<strong>in</strong>s General Information and Instructions for the Bidders<br />
about the RFP such as the time, place of submission and open<strong>in</strong>g of tenders,<br />
Validity period of tenders, etc.<br />
(b) Part II – Conta<strong>in</strong>s essential details of the items/services required, such<br />
as the Schedule of Requirements (SOR), Tech<strong>nic</strong>al Specifications, Delivery<br />
Period, Mode of Delivery and Consignee details.<br />
(c) Part III – Conta<strong>in</strong>s Standard Conditions of RFP, which will form part of<br />
the Contract with the successful Bidder.<br />
(d) Part IV – Conta<strong>in</strong>s Special Conditions applicable to this RFP and which<br />
will also form part of the contract with the successful Bidder.<br />
(e) Part V – Conta<strong>in</strong>s Evaluation Criteria and Format for Price Bids.<br />
Page 3 of 56
Commercial Bid<br />
5. The Commercial bid is to be submitted strictly <strong>in</strong> accordance with Enclosure -<br />
V to this tender enquiry. This format is to be strictly adhered to for submission of<br />
commercial bid. Non compliance could result <strong>in</strong> disqualification of the firm. The<br />
Commercial bid once opened, will not be subjected to unilateral revision by the firm,<br />
unless the firm is called for price negotiations specifically and asked to justify the<br />
rates. (Total Nos of pages <strong>in</strong> the Q-bid are to be mentioned on the first page of<br />
the Q-bid. Further each page to be numbered. For example if there are 20<br />
pages <strong>in</strong> Q bid, first page to be numbered as 1/20 and last page to be<br />
numbered as 20/20.)<br />
Conditions under which this RFP is issued<br />
6 This RFP is be<strong>in</strong>g issued with no f<strong>in</strong>ancial commitment and Buyer reserves<br />
the right to change or vary any part thereof at any stage. The Buyer reserves the<br />
right to reject any or all of the offers without assign<strong>in</strong>g any reason whatsoever. The<br />
Buyer also reserves the right to withdraw the RFP should it be so necessary at any<br />
stage.<br />
Note: - The bids of vendors not qualify<strong>in</strong>g the m<strong>in</strong>imum aforesaid qualification criteria<br />
are liable to be rejected.<br />
Page 4 of 56
Part I – General Information<br />
1. Two Bid System. In this Two-bid system, the bidders are to forward their<br />
quotes for the complete scope of work <strong>in</strong> two parts as follows:-<br />
(a) Part I: Tech<strong>nic</strong>al Bid (‘T’ bid): The ‘T’ bid should cover the<br />
complete scope of supply, progress schedule / timel<strong>in</strong>es and delivery<br />
durations, etc. The specifications should be well documented and supported<br />
by draw<strong>in</strong>gs, manuals, relevant calculations and descriptive text as necessary<br />
for an evaluation to be made. A copy of unpriced ‘Q’ bid must be <strong>in</strong>cluded<br />
alongwith the ‘T’ bid. This will be identical to the sealed ‘Q’-bid, but<br />
without any <strong>in</strong>dication of the prices.<br />
(b) Part II: Commercial Bid (‘Q’ bid): The ‘Q’ bid should give the cost of<br />
each item as per format enclosed.<br />
2. The Tech<strong>nic</strong>al bid and the Commercial bid should be sealed by the bidder <strong>in</strong><br />
separate covers duly super scribed and both these sealed covers are to be put <strong>in</strong> a<br />
s<strong>in</strong>gle cover which should also be sealed and duly super scribed as under:-<br />
“Augmentation of Power Supply and Frequency Converter Arrangements for<br />
Brahmaputra Class of Ships”. [Part I (Tech<strong>nic</strong>al) / Part II (Commercial)] is also<br />
to be <strong>in</strong>dicated as applicable on <strong>in</strong>ner covers.<br />
3. Earnest Money Deposit (EMD) shall be kept with the cover conta<strong>in</strong><strong>in</strong>g ‘T’ bid.<br />
4. The bidders have to strictly furnish clause by clause compliance of<br />
specifications br<strong>in</strong>g<strong>in</strong>g out clearly the deviations from specifications, if any.<br />
The Bidders are advised to submit the compliance statement <strong>in</strong> the follow<strong>in</strong>g format<br />
along with ‘T’ bid. In case of non-compliance, deviation from RFP is to be specified <strong>in</strong><br />
unambiguous terms.<br />
Para of RFP<br />
Specifications<br />
Specification of<br />
Item offered<br />
Compliance to RFP<br />
specification – whether<br />
Yes or No<br />
Page 5 of 56<br />
In case of noncompliance,<br />
Deviation from<br />
RFP<br />
5. Last Date and Time for Deposit<strong>in</strong>g the Bids. 15 Jan 2013 by 1400 hrs.<br />
The sealed Bids (both Tech<strong>nic</strong>al and Commercial) should be deposited/reach by the<br />
due date and time. The responsibility to ensure this lies with the Bidder.<br />
6. Manner of deposit<strong>in</strong>g the Bids. Sealed Bids should be either dropped <strong>in</strong> the<br />
Tender Box marked as DGNP(MBI) or sent by registered post at the address given<br />
above so as to reach by the due date and time. Late tenders will not be considered.<br />
No responsibility will be taken for postal delay or non-delivery/ non-receipt of Bid<br />
documents. Bids sent by FAX or e-mail will not be considered. Hand written Bids will<br />
not be considered and will be rejected outright.
7. Time and date for open<strong>in</strong>g of Bids: 15 Jan 2013 at 1500 hrs If due to any<br />
exigency, the due date for open<strong>in</strong>g of the Bids is declared a closed holiday, the Bids<br />
will be opened on the next work<strong>in</strong>g day at the same time or on any other day/time, as<br />
<strong>in</strong>timated by the Buyer. The date of open<strong>in</strong>g of Commercial Bid will be <strong>in</strong>timated after<br />
acceptance of Tech<strong>nic</strong>al Bids.<br />
8. Location of the Tender Box. Muster Gate, Naval Dockyard, Mumbai<br />
Only those Bids that are found <strong>in</strong> the ‘DGNP’ tender box will be opened. Bids<br />
dropped <strong>in</strong> the wrong Tender Box will be rendered <strong>in</strong>valid.<br />
9. Place of open<strong>in</strong>g of the Bids. Office of Director General Naval Project,<br />
(Mumbai) Cruiser Grav<strong>in</strong>g Dock Accommodation Complex, 5 th floor,<br />
Conference Hall, Lion Gate, Naval Dockyard, Mumbai. The Bidders may depute<br />
their representatives, duly authorized <strong>in</strong> writ<strong>in</strong>g, to attend the open<strong>in</strong>g of Bids on the<br />
due date and time. Rates and important commercial/tech<strong>nic</strong>al clauses quoted by all<br />
Bidders will be read out <strong>in</strong> the presence of the representatives of all the Bidders. This<br />
event will not be postponed due to non-presence of your representative.<br />
10. Forward<strong>in</strong>g of Bids. Bids should be forwarded by Bidders under their orig<strong>in</strong>al<br />
memo / letter pad <strong>in</strong>ter alia furnish<strong>in</strong>g details like TIN number, VAT/CST number,<br />
PAN number, Bank address with EFT Account if applicable, etc and complete postal<br />
& e-mail address of their office.<br />
11. Pre-Bid meet<strong>in</strong>g. Pre-bid meet<strong>in</strong>g will be scheduled between 07 Jan 13 and<br />
11 Jan 13 for clarify<strong>in</strong>g issues and clear<strong>in</strong>g doubts, about the specification and other<br />
tech<strong>nic</strong>al details of the equipment projected <strong>in</strong> the RFP. Firms are required to take<br />
prior appo<strong>in</strong>tment for the same. It is advised to all the bidd<strong>in</strong>g firms should attend the<br />
pre-bid meet<strong>in</strong>g <strong>in</strong> their own <strong>in</strong>terest. Firms are also advised to visit the site to<br />
ascerta<strong>in</strong> the requirement and scope to avoid any change of scope <strong>in</strong> future.<br />
12. Modification and Withdrawal of Bids. A bidder may modify or withdraw his<br />
bid after submission provided that the written notice of modification or withdrawal is<br />
received by the Buyer prior to deadl<strong>in</strong>e prescribed for submission of bids. A<br />
withdrawal notice may be sent by fax but it should be followed by a signed<br />
confirmation copy to be sent by post and such signed confirmation should reach the<br />
purchaser not later than the deadl<strong>in</strong>e for submission of bids. No bid shall be modified<br />
after the deadl<strong>in</strong>e for submission of bids. No bid may be withdrawn <strong>in</strong> the <strong>in</strong>terval<br />
between the deadl<strong>in</strong>e for submission of bids and expiration of the period of bid<br />
validity specified. Withdrawal of a bid dur<strong>in</strong>g this period will result <strong>in</strong> Bidder’s<br />
forfeiture of bid security.<br />
13. Clarification Regard<strong>in</strong>g Contents of the Bids. Dur<strong>in</strong>g evaluation and<br />
comparison of bids, the Buyer may, at its discretion, ask the bidder for clarification of<br />
his bid. The request for clarification will be given <strong>in</strong> writ<strong>in</strong>g and no change <strong>in</strong> prices or<br />
substance of the bid will be sought, offered or permitted. No post-bid clarification on<br />
the <strong>in</strong>itiative of the bidder will be enterta<strong>in</strong>ed.<br />
14. Rejection of Bids. Canvass<strong>in</strong>g by the Bidder <strong>in</strong> any form, unsolicited letters<br />
and post-tender corrections may <strong>in</strong>voke summary rejection with forfeiture of EMD.<br />
Conditional tenders will be rejected.<br />
Page 6 of 56
15. Validity of Bids. The Bids should rema<strong>in</strong> valid till 120 days from the last date<br />
of submission of the Bids.<br />
16. Earnest Money Deposit. Bidders are required to submit Earnest Money<br />
Deposit (EMD) for amount of 30 Lakhs along with their bids. The EMD may be<br />
submitted <strong>in</strong> the form of an Account Payee Demand Draft, Fixed Deposit Receipt,<br />
Banker's Cheque or Bank Guarantee from any of the public sector banks or a private<br />
sector bank authorised to conduct government bus<strong>in</strong>ess as per Form DPM-13<br />
(Available <strong>in</strong> MoD website and placed at Enclosure to Part I). EMD is to rema<strong>in</strong><br />
valid for a period of forty five days beyond the f<strong>in</strong>al bid validity period. EMD of<br />
the unsuccessful bidders will be returned to them at the earliest after expiry of the<br />
f<strong>in</strong>al bid validity and latest on or before the 30th day after the award of the contract.<br />
EMD is not required to be submitted by those Bidders who are registered with the<br />
Central Purchase Organization (e.g. DGS&D), or any Department of MoD for the<br />
same items/ range of products or services for which the tenders have been<br />
issued. However, the firm has to submit the valid registration proof along with the<br />
bid. The Bid Security of the successful bidder would be returned, without any <strong>in</strong>terest<br />
whatsoever, after the receipt of Performance Security from them as called for <strong>in</strong> the<br />
contract. The EMD will be forfeited if the bidder withdraws or amends impairs or<br />
derogates from the tender <strong>in</strong> any respect with<strong>in</strong> the validity period of their tender.<br />
17. Unwill<strong>in</strong>gness to quote. Bidders unwill<strong>in</strong>g to quote should ensure that<br />
<strong>in</strong>timation to this effect reaches before the due date and time of open<strong>in</strong>g of the Bid,<br />
fail<strong>in</strong>g which the default<strong>in</strong>g Bidder may be de-listed for the given range of items as<br />
mentioned <strong>in</strong> this RFP.<br />
18. Independent Monitor. The buyer has appo<strong>in</strong>ted an <strong>in</strong>dependent monitor<br />
by way of Vigilance Officer to monitor this contract, whose name and address is<br />
given below. The vendor is at liberty to contact the under mentioned Officer directly if<br />
any case of undue <strong>in</strong>fluence is noticed or any unethical means by any party/official is<br />
employed to secure the contract/order or to disable/disqualify the vendor.<br />
Shri AK Bhagat<br />
Tel. No.: 022-22751257<br />
Office of the Director General<br />
Naval Project (MB)<br />
Shahid Bhagat S<strong>in</strong>gh Road<br />
Naval Dockyard<br />
Mumbai – 400 023<br />
Page 7 of 56
EMD BANK GUARANTEE <strong>FOR</strong>MAT<br />
Page 8 of 56<br />
Form DPM-13<br />
Whereas …………………………………… (here<strong>in</strong>after called the “Bidder”) has<br />
submitted their offer dated………………………………….for the supply of<br />
……………………………………… (here<strong>in</strong>after called the “Bid”) aga<strong>in</strong>st the Buyer’s<br />
Request for proposal No. ……………………………………………… KNOW ALL MEN<br />
by these presents that WE<br />
……………………………of………………………………………….. hav<strong>in</strong>g our<br />
registered office at ……………………………………………………………. are bound<br />
unto …………………. (here<strong>in</strong>after called the “Buyer) <strong>in</strong> the sum of<br />
………………………………………………………………………for which payment will<br />
and truly to be made to the said Buyer, the Bank b<strong>in</strong>ds itself, its successors and<br />
assigns by these presents.<br />
Sealed with the Common Seal of the said Bank this…………… day of<br />
………….20……<br />
The conditions of obligations are –<br />
(1) If the Bidder withdraws or amends, impairs or derogates from the Bid <strong>in</strong> any<br />
respect with<strong>in</strong> the period of validity of this tender.<br />
(2) If the Bidder hav<strong>in</strong>g been notified of the acceptance of his tender by the Buyer<br />
dur<strong>in</strong>g the period of its validity.<br />
a) If the Bidder fails to furnish the Performance Security for the due performance<br />
of the contract.<br />
b) Fails or refuses to accept/execute the contract. WE undertake to pay the<br />
Buyer up to the above amount upon receipt of its first written demand, without<br />
the Buyer hav<strong>in</strong>g to substantiate its demand, provided hat <strong>in</strong> its demand the<br />
Buyer will note that the amount claimed by it is due to it ow<strong>in</strong>g to the occurrence<br />
of one or both the two conditions, specify<strong>in</strong>g the occurred condition or<br />
conditions. This guarantee will rema<strong>in</strong> <strong>in</strong> force upto and <strong>in</strong>clud<strong>in</strong>g 45 days after<br />
the period of tender validity and any demand <strong>in</strong> respect thereof should reach the<br />
Bank not later than the above date.<br />
…………………………….<br />
(Signature of the authorized officer of the Bank)<br />
Name and designation of the officer<br />
Seal, name & address of the Bank and address of the Branch
GENERAL<br />
PART II – ESSENTIAL DETAILS OF ITEMS/SERVICES REQUIRED<br />
1. This specification is for creat<strong>in</strong>g a facility to provide 440V, 3PH, 60 Hz shore<br />
supply to ships at Naval Dockyard (Mumbai), which shall comprise ma<strong>in</strong>ly 02 Nos.<br />
1000 KW (1250kVA) Variable Frequency Drive (VFD) type frequency converter sets<br />
with a provision to parallel them, associated transformers, cabl<strong>in</strong>g, shore supply<br />
EBXL cable sets with cable drums, HT & LT panels, cope boxes, feeder pillars etc.<br />
SCOPE OF WORK<br />
2. Augmentation of Power supply and frequency converter arrangement at Naval<br />
Dockyard, Mumbai <strong>in</strong>volves supply, <strong>in</strong>stallation, test<strong>in</strong>g and commission<strong>in</strong>g of<br />
Frequency Converter sets, Control Panels, parallel<strong>in</strong>g arrangements, associated<br />
switch gear, remote <strong>in</strong>dication and monitor<strong>in</strong>g panel at operator’s cab<strong>in</strong>, cables –<br />
XLPE (permanently laid) and shore supply cables- EBXL (loose supply), cope<br />
boxes/pillar boxes. The entire work has to be completed on a turnkey basis. Any<br />
additional <strong>in</strong>stallation material essential to commission the facilities on turnkey basis<br />
is to be catered for by the vendor and no separate/additional charges will be paid to<br />
the vendor.<br />
3. The <strong>in</strong>dicative scope of supply is as follows:<br />
SI Item Rat<strong>in</strong>g Qty<br />
(a) MG Set, with necessary<br />
remote <strong>in</strong>dication panel.<br />
(b) Variable Frequency Drive<br />
Cum Controller (with<br />
<strong>in</strong>tegral dry type<br />
transformer if necessary)<br />
AC motor of 1200 kW, suitable HT/LT<br />
voltage (match<strong>in</strong>g with VFD drive),<br />
4 Pole, 50/60 Hz, design specification as<br />
per EED-Q-071 (R3).<br />
AC Generator of 1000KW, 380-480 V, 3<br />
Ph, 50/60 Hz (dual Frequency), 1800<br />
RPM (or as required by design), 4 pole<br />
(or as required by design), design<br />
specifications as per EED-Q-242(R2).<br />
Input Voltage 6.6 kV or 11 kV<br />
(selectable), Input frequency 50 Hz,<br />
suitable for above AC Induction Motor<br />
(c) Synchronization panel Synchroniz<strong>in</strong>g relay, meters, PTs, auto<br />
and manual synchronizer<br />
Page 9 of 56<br />
2<br />
2<br />
1
(d) Incom<strong>in</strong>g VCB, HT<br />
Breaker panel compris<strong>in</strong>g<br />
of two <strong>in</strong>com<strong>in</strong>g breakers<br />
and necessary<br />
<strong>in</strong>strumentation<br />
(e) Base frame, rail<strong>in</strong>g and<br />
wheels and coupl<strong>in</strong>g<br />
11kV, 630 Amps.<br />
Follow<strong>in</strong>g required:<br />
(a) 11/6.6 KV compatible VCB<br />
(b)Display meter should have<br />
multifunction Trivector meter(02 nos.)<br />
(c) Follow<strong>in</strong>g Relays required:<br />
(i) Earth fault – 02 nos.<br />
(ii) Over current – 02 nos.<br />
(iii) Under frequency – 02 nos.<br />
(iv) Under voltage – 02 nos.<br />
Page 10 of 56<br />
1set<br />
Suitable for above MG set 2 sets<br />
(f) Anti Vibration Mounts Suitable for the above MG Set 16<br />
(g) Indoor Power Distribution<br />
Board(FC Set Room)<br />
Follow<strong>in</strong>g required:<br />
(a) ACB – 11 nos.<br />
(Incom<strong>in</strong>g feeder ACB 2000 A: 02 nos.<br />
Bus coupler ACB 2000 A : 01 nos.<br />
Outgo<strong>in</strong>g feeder ACB 2000 A: 08 nos.)<br />
(b) Meters –<br />
Voltmeter(10 nos.) &<br />
Ammeter (10 nos.)<br />
(c) Insulation meter<br />
(d) Follow<strong>in</strong>g Relays required:<br />
(i) Earth fault – 10 nos.<br />
(ii)Overcurrent – 10 nos.<br />
(iii)Under frequency (<strong>in</strong>comer ACB)-<br />
02 nos.<br />
(iv)Reverse Power relay (Incomer<br />
(ACB) – 02 nos.<br />
(v) Differential(Incomer ACB) –<br />
02 nos.<br />
1set
(h) Feeder Pillars ACB 2000Amps, CTs<br />
(j) Outdoor Cope Boxes<br />
(should be rat/ pest<br />
<strong>in</strong>gress protected and<br />
should be IP 65)<br />
Meter – Voltmeter<br />
Page 11 of 56<br />
Ammeter<br />
MCCB 800 Amps, CTs<br />
Meter- Ammeter<br />
800A Copper Bus bars 8<br />
(k) HT Cables XLPE, 11kV, 3 core, armoured, AI cables As<br />
(l) LT Cables XLPE, 11kV, 3 core, armoured, AI cables<br />
(m) Shore Supply Cables EBXL, 1.1kV,Flexible, s<strong>in</strong>gle core,<br />
Copper 300sq mm Conductor, as per<br />
EED Q 50-12<br />
(n) All other items as required for a turnkey execution of the project<br />
SPECIFICATION <strong>FOR</strong> FREQUENCY CONVERTOR SETS<br />
System Description<br />
4<br />
4<br />
4<br />
8<br />
8<br />
listed<br />
at Para<br />
30<br />
4. The system shall comprise of two sets of Frequency converters produc<strong>in</strong>g<br />
380-480V, 50/60 Hz (dual frequency), 3 phase 1250 kVA (1000 kW at 0.8 lagg<strong>in</strong>g<br />
power factor) output. The system shall operate with an <strong>in</strong>com<strong>in</strong>g HT supply of 11kV /<br />
6.6 kV (should be designed for both), 3 Ph, and 50 Hz.<br />
5. In each set, the HT supply is fed to a step down Transformer of suitable<br />
rat<strong>in</strong>g. From the secondary of the transformer, supply is fed to a Variable Frequency<br />
Drives (VFD). The VFD output is fed to an AC cage motor rated suitably to drive an<br />
AC generator to produce 380-480 V, 50/60 Hz, 3 phase 1250 kVA ma<strong>in</strong>ta<strong>in</strong><strong>in</strong>g 440 V<br />
at 60 Hz and 380 & 415 V at 50 Hz at consumer end i.e., at the cope box.<br />
6. The speed of the motor shall be controlled by variable frequency drive with a<br />
provision to bypass the same <strong>in</strong> case of emergency operation. AC generator shall be<br />
directly coupled to AC motor and mounted on a common base plate. The generator<br />
shall be rated for 1250 kVA, 440 V at 60 Hz and 380 & 415 V at 50 Hz at consumer<br />
end, i.e., the cope box.
7. The term<strong>in</strong>al voltage of the generator shall be regulated by an automatic<br />
voltage regulator. A hand voltage regulator shall also be provided along with a hand /<br />
auto changeover switch. Both the regulators are to be housed <strong>in</strong> Excitation Control<br />
Panel.<br />
8. Two such Motor Generator (MG) sets shall be provided <strong>in</strong> this system with<br />
any one of them <strong>in</strong>tended to operate as ‘Ma<strong>in</strong>’ and the other as ‘standby’. The MG<br />
sets shall have facility to be synchronized or ‘paralleled’ for un<strong>in</strong>terrupted transfer of<br />
power to the load from one set to another. A synchroniz<strong>in</strong>g / parallel<strong>in</strong>g panel is to be<br />
provided for synchronization of two Generators. Though normally only one MG set is<br />
envisaged to run on load at any time, except dur<strong>in</strong>g parallel<strong>in</strong>g for load transfer, both<br />
generators are to be rated for cont<strong>in</strong>uous duty as they may be required to run<br />
simultaneously <strong>in</strong> <strong>in</strong>dependent mode. Provision is therefore to be made <strong>in</strong> the Power<br />
Panels etc. to allow such operation and feed required consumers separately from<br />
each FC set.<br />
9. The system shall be designed for outdoor application suitable to be housed <strong>in</strong><br />
a room with concrete structure close to the jetty. The system shall be suitable to be<br />
<strong>in</strong>stalled on a cement/suitable foundation normally without any special foundation<br />
arrangements. Indoor Power Distribution Board with suitable breakers shall be<br />
placed <strong>in</strong>side the room. The system will be located as follows:-<br />
(a) Incom<strong>in</strong>g HT Breaker panel associated HT to LT step down<br />
transformers, along with necessary <strong>in</strong>strumentation, to be fitted <strong>in</strong> proposed<br />
FC set station.<br />
(b) The VFDs with necessary <strong>in</strong>com<strong>in</strong>g LT supply panel(s), MG sets and<br />
<strong>in</strong>door outgo<strong>in</strong>g (440V 60Hz 3phase) power distribution panel <strong>in</strong> the proposed<br />
FC set station.<br />
(c) The LT distribution breakers (08 <strong>in</strong> nos.) along with the necessary<br />
<strong>in</strong>strumentation are to be located <strong>in</strong> the proposed FC set station.<br />
(d) The feeder pillars (04 <strong>in</strong> no.), each with one set of ACB and two sets of<br />
MCB are to be located on the jetty.<br />
10. The FC sets along with VFD drives, power panels and associated fitt<strong>in</strong>gs<br />
proposed to be <strong>in</strong>stalled <strong>in</strong> FC Room shall not take more than 20 m × 7 m × 7.5 m of<br />
space <strong>in</strong>clusive of ma<strong>in</strong>tenance envelope and free spaces / heights required. The<br />
bidders should provide proposed layout along with the T-bid.<br />
11. Necessary lay<strong>in</strong>g of cables with ACB and MCCB panels, feeder pillars and<br />
cope boxes suitable for outdoor <strong>in</strong>stallation shall also be provided and <strong>in</strong>stalled for<br />
load distribution, and protection. All <strong>in</strong>cidental civil work <strong>in</strong>clud<strong>in</strong>g cable supports /<br />
trays and their grout<strong>in</strong>g, foundations for cope/pillar boxes etc. will be with<strong>in</strong> the scope<br />
of <strong>in</strong>stallation. The metallic frames and all other parts of the foundation will be factory<br />
treated for protection aga<strong>in</strong>st corrosion with life of 40 years. The treatment can be of<br />
epoxy coats or other modern methods which need to be approved <strong>in</strong> advance.<br />
Page 12 of 56
12. If necessary, an auxiliary supply of 415 V, 30 amps, 50 Hz shall to be<br />
provided by Naval Dockyard, Mumbai, <strong>in</strong> addition to <strong>in</strong>com<strong>in</strong>g 6.6kV, for power<strong>in</strong>g<br />
space heaters, light<strong>in</strong>g and other auxiliary loads, dur<strong>in</strong>g non-operation of MG sets.<br />
The necessary switchgear and cabl<strong>in</strong>g from nearest supply po<strong>in</strong>t i.e. CW Sub Station<br />
will be with<strong>in</strong> the scope of <strong>in</strong>stallation, <strong>in</strong>clud<strong>in</strong>g all material necessary.<br />
13. The lay<strong>in</strong>g and term<strong>in</strong>ations of all necessary <strong>in</strong>com<strong>in</strong>g HT cables and any<br />
other necessary supply / control cables from the exist<strong>in</strong>g Cruiser Wharf Substation to<br />
the system (<strong>in</strong>clud<strong>in</strong>g transformers) will be done by the contractor <strong>in</strong>clud<strong>in</strong>g end<br />
term<strong>in</strong>ations, supply of necessary accessories like cables, lugs etc. and also<br />
carry<strong>in</strong>g-out some m<strong>in</strong>or civil work, as required.<br />
14. Indicative layout of the FC room at cruiser wharf entrance, Schematic layout<br />
of the system on Cruiser Wharf, <strong>in</strong>clud<strong>in</strong>g cabl<strong>in</strong>g and system s<strong>in</strong>gle l<strong>in</strong>e diagram are<br />
available at DGNP(MBI) and can be provided on request to Bidders.<br />
15. The system shall be designed, eng<strong>in</strong>eered, manufactured, <strong>in</strong>stalled,<br />
tested and commissioned as a turnkey project.<br />
System Specifications<br />
16. Ambient Conditions. The system shall be suitable to operate under the<br />
follow<strong>in</strong>g conditions:<br />
(a) Ambient Temperature : 45 deg. Cent.,<br />
(b) Atmosphere : Sal<strong>in</strong>e and corrosive.<br />
(c) Altitude : Less than 1000 m. Above MSL<br />
(d) Relative humidity : 95% (non-condens<strong>in</strong>g)<br />
17. Input and Output Supply.<br />
(a) Input.<br />
(i) 6.6 KV or 11 KV 3 Phase 50 Hz (To be selectable to cater for<br />
future migration to 11 kV)<br />
(ii) Voltage Tolerance - +/- 10%<br />
(iii) Frequency Tolerance - +/- 5%<br />
(iv) Comb<strong>in</strong>ed Tolerance - +/- 15%<br />
(v) Aux. Supply: 415 V, 50 Hz, 3 phase.<br />
(b) Output.<br />
(i) 380-480 V, 50/60 Hz, 3 phase 1250 kVA ma<strong>in</strong>ta<strong>in</strong><strong>in</strong>g 440 V at<br />
60 Hz and 380 & 415 V at 50 Hz at consumer end i.e. at the<br />
cope box.<br />
(ii) Voltage Tolerance - +/- 1% as at cope box<br />
(iii) Frequency Tolerance - +/- 1%<br />
Page 13 of 56
18. VCB INCOMING BREAKER PANEL<br />
(i) Breaker Type :VCB<br />
(ii) Rated Current :630 A<br />
(iii) Rated Frequency :50Hz<br />
(iv) Break<strong>in</strong>g capacity :25 KA for 3 sec<br />
(v) Rated Short circuit mak<strong>in</strong>g current (peak):66kA<br />
(vi) Rated Short Circuit break<strong>in</strong>g current rms : 25kA<br />
(vii) Rated Power Fr. :28kV With stand<br />
voltage<br />
(viii) Impulse withstand voltage :75kV<br />
(ix) No of poles :3<br />
(x) Voltage rat<strong>in</strong>g :11/6.6kV Compatible<br />
VCB Panel<br />
(xi) Protection :Over Current, Short<br />
circuit., Earth Fault<br />
(xii) Meter<strong>in</strong>g :Voltage and current<br />
(xiii) Accessories :Space heater<br />
(xiv) CTs and PT :Ct ratio-200/5 A, Pt<br />
ratio- 11 or 6.6kV/ 110V<br />
(xv) Enclosure :IP 43 or better<br />
(xvi) Cable Entry :From bottom<br />
(xvii) Draw out :Manual<br />
(xviii) Auxiliary contacts :As required<br />
(xix) Shunt trip coil :110 V A/C<br />
(xx) Make :Reputed makes like<br />
Siemens, Areva &<br />
Schneider, ABB etc.<br />
(xxi) Colour cod<strong>in</strong>g :CRCA/coated steels.<br />
Corrosion resistant<br />
powder coat<strong>in</strong>g light.<br />
(xxii) Busbar :Busbars rated to carry<br />
630 Amps, 6.6/11 kV,<br />
50Hz, copper materials,<br />
heat shr<strong>in</strong>kable PVC<br />
sleeve <strong>in</strong>sulation, all<br />
copper – to – copper<br />
jo<strong>in</strong>ts are t<strong>in</strong> or silver<br />
plated. The busbar is<br />
fully <strong>in</strong>sulated for 1<br />
m<strong>in</strong>ute. Colour code<br />
(RYB) & with<br />
temperature rise with<strong>in</strong><br />
specified limits.<br />
Page 14 of 56
(xxiii) Compartment Earth<strong>in</strong>g :Each compartment<br />
such as circuit<br />
breaker, relay/<br />
<strong>in</strong>strument, busbar<br />
CT/cable chambers<br />
should be earthed.<br />
(xxiv) Metal – to –metal jo<strong>in</strong>ts :Metal – to – metal<br />
jo<strong>in</strong>ts <strong>in</strong>side the panel<br />
to be design fitted to<br />
achieve zero gap.<br />
(xxv) Multi Function Tri vector Meter :Multifunction meter (Tri<br />
Vector Meter), with<br />
RS485-commu<strong>nic</strong>ation<br />
port with software as<br />
per the user<br />
requirement.<br />
(Make L&T/KAYCEE/<br />
CONZERV/MECO/<br />
KRYCARD<br />
19. Transformers for VFD (Preferred to be part of VFD panel):<br />
(i) Rat<strong>in</strong>g : As suitable<br />
(ii) Primary voltage :11kV / 6.6 kV (both needed,<br />
any one to be<br />
selectable/connectable), 50<br />
Hz., 3 ф<br />
(iii) Secondary -1 : As required<br />
(iv) Duty : Converter duty<br />
(v) Vector Group : Ddyn-11<br />
(vi) Impedance : 5%<br />
(vii) Installation : In door<br />
(viii) Accessories standard fitt<strong>in</strong>gs<br />
(ix) Tapp<strong>in</strong>gs :(±) 2.5%, :(±) 5% on HT side<br />
(x) Class of <strong>in</strong>sulation : B<br />
(xi) Size : To be compact to fit<br />
<strong>in</strong>to the available<br />
space of the room with<br />
all other equipment.<br />
(xii) Type- :Dry type, air cooled<br />
Page 15 of 56
20. Bus Coupler:<br />
(i) Bus coupler : As suitable<br />
(ii) Enclosure : IP 42 or better<br />
(iii) Cool<strong>in</strong>g : Air Natural<br />
(iv) Interlocks : Electrical suitable for<br />
synchronis<strong>in</strong>g<br />
(v) Meters : CT’s with Ammeter and PT’s<br />
with Voltmeter.<br />
(vi) Cable Entry : From Bottom<br />
21. Variable Frequency Drive (VFD) Module:<br />
(i) Input Voltage :LT, Value as required, 50 Hz,<br />
3Ph<br />
(ii) Incom<strong>in</strong>g Breaker :ACB, Rat<strong>in</strong>g as suitable<br />
(iii) Type of Breaker :Electrical Draw out, with<br />
Electro<strong>nic</strong> release<br />
(iv) Rated Output Voltage :Lt, Value as required, 3 Ph<br />
(v) Output Frequency :50 Hz<br />
(vi) Output Freq. Variation band :0-75 Hz (Cont<strong>in</strong>uously<br />
adjustable)<br />
(vii) Mode of operation :Constant (V/F) upto motor’s<br />
rated voltage, and, Constant<br />
V, variable f for f>50 Hz.<br />
(viii) Method of control :Microprocessor based digital<br />
control system.<br />
(ix) Motor rat<strong>in</strong>g : As per motor specifications<br />
(x) Duty :Cont<strong>in</strong>uous<br />
(xi) Range of Speed Control :0-Full range RPM.<br />
(xii) Ambient temperature :45-C<br />
(xiii) Power elements provided :3 phase L<strong>in</strong>e reactor<br />
(xiv) Meter<strong>in</strong>g :Voltage, Current, Speed<br />
(xv) L<strong>in</strong>e side switchgear :ACB of suitable rat<strong>in</strong>g<br />
(xvi) Protections :Over current, locked rotor,<br />
s<strong>in</strong>gle phas<strong>in</strong>g,<br />
motor protection relay.<br />
(xvii) Direction of rotation :Uni- Directional.<br />
(xviii) Controls :locally provided<br />
(xix) Cable entry :From bottom<br />
(xx) Enclosure :IP 42 or better<br />
Page 16 of 56
22. MG Set<br />
(a) AC Motor:<br />
(i) Rat<strong>in</strong>g : As required.<br />
(ii) Rated Voltage : HT/LT. Value as required.<br />
(iii) Rated frequency : 50/60 Hz (dual frequency),(4 Poles)<br />
(iv) Speed : 1800 RPM or as required by design<br />
(v) Range of Speed Control : 0-Full RPM<br />
(vi) Class of <strong>in</strong>sulation : F<br />
(vii) Temp rise : As per class B<br />
(viii) Cool<strong>in</strong>g : IC – 411 or better<br />
(ix) Enclosure : IP 23 or better<br />
(x) Max Ambient Temperature : 55°C at full Load<br />
(xi) Type : Cage<br />
(xii) Start<strong>in</strong>g : Suitable for VFD power source<br />
(xiii) Efficiency : Not less than 95% on full load.<br />
(xiv) Accessories : RTDs for w<strong>in</strong>d<strong>in</strong>gs and Bear<strong>in</strong>gs,<br />
Space Heater, etc.<br />
(xv) Design Specifications : As per EED-Q-071(R3)<br />
(b) AC Generator:<br />
(i) Rat<strong>in</strong>g : 1250 kVA, 3 Ph<br />
(ii) Voltage : 380-480 V,50/60 Hz (dual frequency),<br />
3phase 1250 kVA ma<strong>in</strong>ta<strong>in</strong><strong>in</strong>g 440 V<br />
at 60 Hz and 380 & 415 V at 50 Hz<br />
at consumer end i.e. at the cope box.<br />
Rated voltage at generator output<br />
term<strong>in</strong>als to be settable from 380V to<br />
480V<br />
(iii) Frequency : 50/60 Hz. (dual frequency), (4 Poles)<br />
(iv) Pf : 0.8 Pf (lag)<br />
(v) Speed : 1800 RPM<br />
(vi) Total Harmo<strong>nic</strong> Distortion: Distortion of the l<strong>in</strong>e voltage at no<br />
load must not exceed 2% of the<br />
amplitude of the fundamental.<br />
(vii) Transient Voltage Dip : less than 15% on application of100%<br />
step load.<br />
(viii) Exciter : Brushless<br />
(ix) Excitation control : AVR and hand voltage regulator<br />
(panel mounted)<br />
(x) Cool<strong>in</strong>g : IC 01 or better<br />
(xi) Enclosure : IP23 or better<br />
Page 17 of 56
(xii) Connection : Star<br />
(xiii) Efficiency : Not less than 94.5 % on full load<br />
(xiv) Max Ambient temperature: 55°C at full Load.<br />
(xv) Class of <strong>in</strong>sulation : F<br />
(xvi) Prime mover : AC motor as specified <strong>in</strong> sl(a) above<br />
(xvii) Application : To be suitable for naval duty<br />
(xviii) Duty : Cont<strong>in</strong>uous<br />
(xix) Temperature rise : Limited to class B<br />
(xx) Accessories : RTDs for w<strong>in</strong>d<strong>in</strong>gs and bear<strong>in</strong>gs,<br />
space heater.<br />
(xxi) Design Specifications : As per EED-Q-242 (R2)<br />
23. Excitation Control Panel:<br />
(i) Mount<strong>in</strong>g :On floor<br />
(ii) Cable entry :From bottom<br />
(iii) Controls provided :AVR & Manual Excitation<br />
controller with selector switch.<br />
(iv) Input supply :Transformer 6600/110V, 50<br />
Hz (rat<strong>in</strong>g suitable to provide<br />
control supply of 110V to all<br />
related panels)<br />
Note: controls of all the panels<br />
<strong>in</strong>clud<strong>in</strong>g VFD panel should<br />
be derived from this<br />
transformer only, <strong>in</strong>put supply<br />
to space heaters to be taken<br />
from 415V, 50 Hz 3 phase<br />
supply available at cruiser<br />
wharf S/stn.<br />
(v) Rat<strong>in</strong>g of excitation controller :To suit generator<br />
characteristics<br />
(vi) Power module :S<strong>in</strong>gle phase thyristor<br />
converter with digital Controls.<br />
(vii) Voltage control :Voltage <strong>in</strong>crease / decrease<br />
push buttons.<br />
(viii) Meter<strong>in</strong>g for Field :Field voltage – (Vf), Field<br />
current – (If)<br />
(ix) Relays :Over excitation, Rotat<strong>in</strong>g<br />
Diode Failure Indicator (DFI),<br />
(x) Control supply :110 V AC (to be <strong>in</strong>ternally<br />
derived)<br />
(xi) Frequency Control :Manual frequency control<br />
potentiometer be provided<br />
excitation control panel.<br />
Page 18 of 56
(xii) Insulation monitor<strong>in</strong>g :Onl<strong>in</strong>e <strong>in</strong>sulation monitor<strong>in</strong>g<br />
device be provided for<br />
monitor<strong>in</strong>g <strong>in</strong>sulation of MG<br />
sets, associated cables and<br />
other ACBs/MCCBs.<br />
(xiii) Local and remote controls :Provision is required to be<br />
made for both local and<br />
remote Control.<br />
(xiv) Breaker Tripp<strong>in</strong>g logic : Master trip relay contacts will<br />
be wired to TB for external<br />
connection to trip Coil to<br />
breaker<br />
(xv) Accessories :Annunciator, <strong>in</strong>dicat<strong>in</strong>g Lamp<br />
(LEDs), Push buttons.<br />
24. Synchronization Panel. The panel should permit automatic as well<br />
as manual parallel<strong>in</strong>g of the MG sets at generator ends. The follow<strong>in</strong>g specifications<br />
are guidel<strong>in</strong>es and can be altered as required for design.<br />
(i) Incomer voltage : As required<br />
(ii) Relays :Sync. check Relay<br />
(iii) Synchronizer :Auto synchronizer<br />
and manual<br />
synchronizer with<br />
selector switch.<br />
(iv) Meters :Double Volt meter,<br />
Double frequency<br />
Meter,Synchronizer<br />
with selector switch.<br />
(v) Generator selection :through selector<br />
switch.<br />
(vi) Speed control :Push buttons / pistol<br />
grip spr<strong>in</strong>g loaded<br />
switch provided for<br />
<strong>in</strong>crease / decrease.<br />
(vii) Voltage control :Push buttons provided<br />
for <strong>in</strong>crease / decrease.<br />
(viii) Breaker clos<strong>in</strong>g command :Through push button <strong>in</strong><br />
manual mode, and,<br />
automatically <strong>in</strong> auto mode<br />
(ix) Cable entry :From bottom<br />
(x) Enclosure :IP-43<br />
Page 19 of 56
25. Indoor Power Distribution Board –F/C Room [Incomer (02) , Bus<br />
coupler(01), Outgo<strong>in</strong>g(08)]:<br />
(i) Breaker :ACB 2000 Amps.<br />
(ii) Number :11<br />
(iii) Type :Electrical Draw out,<br />
with electro<strong>nic</strong> release<br />
(iv) CTs :Cast res<strong>in</strong> type, class<br />
1.0<br />
(v) Meters :AC Ammeter and<br />
Voltameter<br />
(vi) Protections :Standard<br />
(vii) Enclosure :Metallic treated for<br />
corrosion protection<br />
powder coated with<br />
dust protection<br />
(viii) Cable entry :from bottom<br />
(ix) Short Circuit Capacity :50 kA<br />
(x) Colour : Navy Grey<br />
26. Outdoors Feeder Pillars (each with 01 ACB- 2000A and 02 MCCB’s<br />
-800A):<br />
(i) Breaker :MCCB 800 Amps, non draw<br />
out, ACB 2000A drawout.<br />
(ii) CTs :Cast res<strong>in</strong> type, CTR: 1000/5<br />
MCCB, Class 1.0 and 2000/5<br />
A for ACB<br />
(iii) Meters :AC Ammeter and voltmeter<br />
(iv) Protections :Standard<br />
(v) Enclosure :Metallic treated for corrosion<br />
protection, with ra<strong>in</strong> and dust<br />
protection.<br />
(vi) Cable entry :from bottom<br />
(vii) Colour : Dark Blue<br />
27. Cope Boxes.<br />
(i) Bus Bars :T<strong>in</strong>ned Copper, 3 ph<br />
(ii) Enclosure :IP 54<br />
(iii) Mount<strong>in</strong>g :Floor mounted<br />
(iv) Cable Entry :Bottom<br />
(v) Doors : Detachable bolted Doors<br />
(vi) Pa<strong>in</strong>t :Powder coated epoxy pa<strong>in</strong>t<br />
(vii) Colour : Dark Blue<br />
Page 20 of 56
28. All meters <strong>in</strong> all panels shall be Digital except Ammeter and Voltmeters, which<br />
will be analogue (as they are more convenient to see load variations). Accuracy<br />
class shall be Class 1.5 and recommended makes are L&T/Rishabh/AE/Conzerve.<br />
Digital meters will have RS 485 port for network<strong>in</strong>g with SCADA system (SCADA<br />
system not <strong>in</strong> scope of current proposal).<br />
29. All cope and feeder pillars to have fibre glass or similar ma<strong>in</strong>tenance free with<br />
fluorescent pa<strong>in</strong>t lettered tallies <strong>in</strong>dicat<strong>in</strong>g source of supply and details of outgo<strong>in</strong>g<br />
feeders/ cope boxes connected, along with separate and prom<strong>in</strong>ent tallies “440 V 60<br />
Hz, 3 phase”<br />
30. Cables.<br />
(a) HT Cables between CWSS HT Panel &Transformer of VFD<br />
Drive<br />
(i) Grade :300 sq mm*2 runs, XLPE, 11kV<br />
Armoured, AI power cable<br />
(ii) Rat<strong>in</strong>g :300 Amps.<br />
(iii) Number of core :3 Core<br />
(iv) Runn<strong>in</strong>g Length :150 m (consolidated) approximate, to be<br />
verified on site before quot<strong>in</strong>g.<br />
(b) Cables between Indoor PDB and Outdoors Feeder Pillars<br />
(i) Grade :XLPE, 1.1kV Armoured, AI power cable<br />
(ii) Rat<strong>in</strong>g :2000 Amps.<br />
(iii) Number of core :3 Core<br />
(iv) Runn<strong>in</strong>g Length:1500 m (consolidated) approximate, to<br />
be verified on site before quot<strong>in</strong>g.<br />
(c) Cables between Outdoors Feeder Pillars and Cope Boxes<br />
(i) Grade :400 sqmm*2runs, XLPE, 1.1kV<br />
Armoured, AI power cable<br />
(ii) Rat<strong>in</strong>g :800 Amps.<br />
(iii) Number of core :3 Core<br />
(iv) Runn<strong>in</strong>g Length :500 m (consolidated) approximate, to be<br />
verified on site before quot<strong>in</strong>g.<br />
(d) Cables between Cope Boxes andShips(to be suppliedloose)<br />
(i) Grade :EBXL, 1.1 kV, Flexible, s<strong>in</strong>gle core,<br />
Copper 185sq mm Conductor, as per EED<br />
Q 50-12, 3 Core<br />
(ii) Rat<strong>in</strong>g :800 Amps, nom<strong>in</strong>al.<br />
(iii) Length :24 <strong>in</strong> no. pieces of 100 m length each and<br />
complete with suitable t<strong>in</strong>ned copper lugs<br />
crimped at both free ends of each cable.<br />
The total length will be 2500 mtrs.<br />
(Consolidated)<br />
Page 21 of 56
(e) In addition to all other LT / control cables required as per<br />
standard specifications of reputed make.<br />
31. Noise Level and Vibrations Standards - The maximum permissible sound<br />
pressure level for FC sets shall be not more than 90 dBA when both sets are runn<strong>in</strong>g<br />
at full load <strong>in</strong>side the room where the MG sets are fitted and <strong>in</strong> any case not more<br />
than 75 dBA per set at 1 meter under free field conditions, <strong>in</strong> accordance with latest<br />
norms of Noise pollution (Regulation & Control) Rules, 2000. Vibration Standards<br />
shall be as per IS 12075.<br />
32. Provision for Removal of MG Sets and Transformers for Repair. The MG<br />
sets and Transformer shall be fitted with suitable rails/guides and slid<strong>in</strong>g<br />
arrangement with castor wheels provided at the bottom of the base frame to facilitate<br />
their roll<strong>in</strong>g out horizontally to outside the FC Room when required for ma<strong>in</strong>tenance /<br />
overhaul and also refitt<strong>in</strong>g post such overhaul. The slid<strong>in</strong>g may be carried out on rails<br />
embedded <strong>in</strong> the floor<strong>in</strong>g. These wheels shall be easily removable by jack<strong>in</strong>g the MG<br />
sets and AVMs fitted for normal operations.<br />
33. Documentation. The follow<strong>in</strong>g documents shall be supplied:<br />
(a) Foot pr<strong>in</strong>t and Foundation layout<br />
(b) S<strong>in</strong>gle l<strong>in</strong>e diagram<br />
(c) Schematic diagram<br />
(d) Bill of material with OEM’s part identification list<br />
(e) Cable schedule<br />
(f) Instruction manuals<br />
(g) Tech<strong>nic</strong>al manuals for all equipment <strong>in</strong>clud<strong>in</strong>g circuit, cable connection<br />
diagrams and troubleshoot<strong>in</strong>g procedures<br />
(h) All test and calibration reports<br />
(j) OEM’s spare part list with draw<strong>in</strong>gs<br />
34. The above documents shall be submitted as follows:<br />
(a) Hard copy – 4 sets<br />
(b) Soft copy – 2 Nos. CDs. The soft copy of the documentation shall have<br />
the follow<strong>in</strong>g features:-<br />
(i) It should <strong>in</strong>clude complete contents as listed <strong>in</strong> para 33 above.<br />
` (ii) It should be <strong>in</strong> a searchable text document format like PDF or<br />
MS Word (and not scanned versions of hard copy) which should be<br />
open able on normal PC without any requirement of any special<br />
software / application.<br />
Page 22 of 56
35. Spares for Five years of Normal Operation: To be provided. An <strong>in</strong>dicative<br />
list is as follows:-<br />
(a) Automatic Voltage Regulator - 4 Nos<br />
(b) Revolv<strong>in</strong>g diode disc complete with diodes - 6 Nos.<br />
(c) Diodes for revolv<strong>in</strong>g diode disk<br />
(i) Anode - 4 Nos.<br />
(ii)Cathode - 4 Nos.<br />
(d) Bear<strong>in</strong>gs<br />
(i) DE side of Motor - 2 Nos.<br />
(ii)NDE side of Motor - 2 Nos.<br />
(iii)DE side of Generator - 2 Nos.<br />
(iv)NDE side of Generator - 2 Nos.<br />
(e) Power Card - 2 Nos.<br />
(f) Control Card - 2 Nos.<br />
(g) Display Card - 2 Nos.<br />
(h) Indicat<strong>in</strong>g lamps - 12 Nos.<br />
(j) HRC fuses - 12 Nos.<br />
(k) ACB 1600 Amps - 1 Nos.<br />
(l) MCCB 800 Amps - 3 Nos.<br />
(m) IGBT Module - 2 Nos.<br />
36. In addition to the above mentioned list of spares, follow<strong>in</strong>g spares are to be<br />
supplied per unit:-<br />
(a) A complete set of VFD spares <strong>in</strong>clud<strong>in</strong>g all important cards, contactors,<br />
<strong>in</strong>dication assembly, other sub assemblies, consumables like fuses, lamps,<br />
lamp covers, switches, knobs, etc.<br />
(b) Tools for system ma<strong>in</strong>tenance.<br />
(c) All test equipments necessary for ma<strong>in</strong>tenance.<br />
(d) One complete set of spares for HT and LT breakers, e.g. 1 Nos clos<strong>in</strong>g<br />
& tripp<strong>in</strong>g coil, 3 Nos. PT fuses, 3 Nos. Vacuum bottle, 3 Nos micro/limit<br />
switches, 25 Nos. <strong>in</strong>dication lamp.<br />
(e) One spare MCCB.<br />
37. Load Trials. The complete system shall be tested <strong>in</strong> factory as well as on<br />
site. While FATs schedule will be decided by OEM, onsite tests shall <strong>in</strong>clude both<br />
transient, static load and parallel<strong>in</strong>g tests. The procedure for the same will be as<br />
placed at Annexure A. The tests are to be carried out <strong>in</strong> the presence of the<br />
User/ND(MBI), on site i.e Naval Dockyard, Mumbai post <strong>in</strong>stallation. Inability to<br />
undertake any particular test by the bidder is to be <strong>in</strong>dicated dur<strong>in</strong>g the Pre-bid<br />
meet<strong>in</strong>g and a decision would be arrived then.<br />
Page 23 of 56
38. Tra<strong>in</strong><strong>in</strong>g of Personnel. The Supplier should, dur<strong>in</strong>g manufacture, erection<br />
and commission<strong>in</strong>g, <strong>in</strong>struct the User’s staff <strong>in</strong> the operation of the equipment to get<br />
conversant with the system operation. After all the systems have been completely<br />
erected at the site under the supervision of the Supplier’s representative and all<br />
necessary tests have been carried out, the Supplier’s representative shall rema<strong>in</strong><br />
available at site for further period of at least 1 week to <strong>in</strong>struct as required to enable<br />
successful operation and ma<strong>in</strong>tenance by the User.<br />
INSPECTION AND TESTING<br />
39. All equipment, assemblies, sub-assemblies, components <strong>in</strong>clud<strong>in</strong>g boughtouts<br />
and all material shall be subjected to third party <strong>in</strong>spection(IRS/LRS/BVQI)<br />
test<strong>in</strong>g at the stages of manufacture and dur<strong>in</strong>g erection, test<strong>in</strong>g and commission<strong>in</strong>g<br />
at site as per approved QAP f<strong>in</strong>alized after award of Contract. The <strong>in</strong>spection would<br />
be carried out by the IRS(Indian Register of Shipp<strong>in</strong>g)/LRS(Lloyds Register<br />
Services)/ BVQI at the cost of the Seller. The tests, identifications, stamp<strong>in</strong>g and the<br />
like would be done as per the scope of work.<br />
40. The f<strong>in</strong>alization of design, submission of design and obta<strong>in</strong><strong>in</strong>g approval from<br />
third party <strong>in</strong>spection agency should be undertaken by the Supplier with<strong>in</strong> 03 months<br />
of Contract effective date. Any correction/improvement suggested by the third party<br />
<strong>in</strong>spector(IRS/LRS/BVQI) is to be <strong>in</strong>corporated without additional cost and time. The<br />
Supplier will be solely responsible for timely submission, follow-up and <strong>in</strong>spection by<br />
third party agency. Any delays on any of the stages would be on account of the<br />
Supplier. No extension of time for any activity will be permissible for delays on such<br />
counts.<br />
41. The Supplier is required to propose the <strong>in</strong>spection schedule to third party<br />
agency(IRS/LRS/BVQI) for approval. Once approved, the Supplier has to ensure that<br />
the approved <strong>in</strong>spection schedule is handed over to the Buyer with<strong>in</strong> one week.<br />
42. DGNP(MBI) reserves the right to visit OEM premises for any <strong>in</strong>spections<br />
carried out by third party agency(IRS/LRS/BVQI) 15 days notice is required to be<br />
given by the Supplier to DGNP(MBI) whenever the Supplier offers <strong>in</strong>spection to the<br />
third party agency(IRS/LRS/BVQI).<br />
43. Delivery Period - Delivery period for supply, <strong>in</strong>stallation and commission<strong>in</strong>g<br />
of the items would be 12 months from the effective date of contract, which is date of<br />
sign<strong>in</strong>g the contract by both the parties i.e. BUYER and SELLER. The delivery shall<br />
ONLY be considered complete after receipt of material/items at site, completion of<br />
<strong>in</strong>stallation, test/trials of equipments to the satisfaction of the End User and<br />
thereafter obta<strong>in</strong><strong>in</strong>g a work completion certificate from the End User. The<br />
commencement of this period will be from the effective date of sign<strong>in</strong>g the<br />
contract and the total duration of delivery will be accounted, till the date of<br />
Work Completion Certificate (WCC) issued from End User to the firm. Please<br />
note that Contract can be cancelled unilaterally by the Buyer <strong>in</strong> case items are<br />
not received and commissioned with<strong>in</strong> the contracted Delivery Period.<br />
Extension of contracted delivery period will be at the sole discretion of the Buyer,<br />
with applicability of LD clause.<br />
Page 24 of 56
44. Warranty The follow<strong>in</strong>g Warranty will form part of the contract placed on<br />
successful Bidder: –<br />
(a) The Seller warrants that the goods supplied under the contract conform<br />
to tech<strong>nic</strong>al specifications prescribed and shall perform accord<strong>in</strong>g to the said<br />
tech<strong>nic</strong>al specifications.<br />
(b) The Seller warrants for a period of 12 months from the date of<br />
acceptance of stores by Jo<strong>in</strong>t Receipt Inspection or date of <strong>in</strong>stallation and<br />
commission<strong>in</strong>g or date of obta<strong>in</strong><strong>in</strong>g work completion certificate from the user,<br />
whichever is later, that the goods/stores supplied under the contract and each<br />
component used <strong>in</strong> the manufacture thereof shall be free from all types of<br />
defects/failures.In case of defects with<strong>in</strong> the warrantee period, the same<br />
should be rectified free of cost for the defective parts.<br />
45. Compliance to Safety Rules The Supplier would be required to abide by all<br />
the safety rules & practices and Labour Rules applicable dur<strong>in</strong>g supply, <strong>in</strong>stallation,<br />
test<strong>in</strong>g and commission<strong>in</strong>g the facility at the site.<br />
46. The work is required to be undertaken <strong>in</strong>side defence area. The workers will<br />
be required to follow the security regulations as laid down / fresh security measures,<br />
if any as and when promulgated.<br />
47. Format of Schedules and Other Details The formats of different schedules<br />
and other details required to be submitted by the Supplier are given <strong>in</strong> the<br />
succeed<strong>in</strong>g pages.<br />
48. Consignee details –<br />
The Admiral Super<strong>in</strong>tendent<br />
Naval Dockyard<br />
Lion Gate<br />
Mumbai- 400 023<br />
Page 25 of 56
Throw<br />
On/off<br />
TRIAL SCHEDULE<br />
Page 26 of 56<br />
Annexure A<br />
1. Installation Inspection Will be carried out after completion of <strong>in</strong>stallation.<br />
(a) Load trials are to be carried out as per follow<strong>in</strong>g load conditions:-<br />
(i) 25% load for 30 m<strong>in</strong>utes.<br />
(ii) 50% load for 30 m<strong>in</strong>utes.<br />
(iii) 75% load for 60 m<strong>in</strong>utes.<br />
(iv) 100% load for 120 m<strong>in</strong>utes.<br />
(v) 110% load for 60 m<strong>in</strong>utes.<br />
(vi) total duration: 05 hours<br />
(b) Frequency and voltage control tests<br />
Load % % peak variation <strong>in</strong><br />
frequency<br />
Chan<br />
nge<br />
0-25 +25<br />
25-50 +25<br />
50-75 +25<br />
75-100 +25<br />
100-75 -25<br />
75-50 -25<br />
50-25 -25<br />
25- 0 -25<br />
Obser<br />
ved<br />
Permitted<br />
limits <strong>in</strong> %<br />
1.5<br />
Time of<br />
recovery(Sec)<br />
Obser<br />
ved<br />
Permitted<br />
limits <strong>in</strong> %<br />
2<br />
% peak variation <strong>in</strong><br />
voltage<br />
Obser<br />
ved<br />
0-70 +70 5 15<br />
100-0 -100 5 15<br />
Permitted<br />
limits <strong>in</strong> %<br />
7.5<br />
Time of<br />
recovery(Sec)<br />
Obser<br />
ved<br />
Permitted<br />
Limits <strong>in</strong> %<br />
1
2. Power Quality checks will be carried out as per the parameters mentioned at<br />
table below:-<br />
Note:-<br />
Parameters Acceptable Value<br />
Nom<strong>in</strong>al User Voltage 440V/415V/380V<br />
User Voltage Tolerances<br />
(a) Average of three l<strong>in</strong>e-to-l<strong>in</strong>e voltages<br />
(b) Any one l<strong>in</strong>e-to-l<strong>in</strong>e voltage <strong>in</strong>clud<strong>in</strong>g<br />
(a) Trial procedure & parameters are as per EED-Q-242(R2) for DGs.<br />
(b) Trials will be carried out <strong>in</strong> 0.8 lagg<strong>in</strong>g power factor.<br />
(c) Above trials will be carried out at output end i.e. at cope box.<br />
Page 27 of 56<br />
± 5%<br />
± 7%<br />
Voltage Modulation 2%<br />
L<strong>in</strong>e Voltage Unbalance Tolerance 2%<br />
Voltage Transient Recovery Time 01 Sec<br />
Waveform<br />
Total Harmo<strong>nic</strong> Distortion Tolerance 5%<br />
Individual Harmo<strong>nic</strong> 3%<br />
Deviation Factor 5%<br />
Frequency<br />
Nom<strong>in</strong>al Frequency 50/60 Hz<br />
Frequency Tolerance ± 3%<br />
Frequency Modulation 0.5%<br />
Frequency Transient Tolerance ± 4%<br />
Frequency Transient Recovery Time 02 seconds
SCHEUDLE “A”<br />
(To be prepared by vendor and submitted)<br />
TIME <strong>FOR</strong> COMMENCEMENT AND COMPLETION OF THE WORK<br />
We undertake to commence and complete all phases of construction,<br />
<strong>in</strong>stallation and commission<strong>in</strong>g activity with<strong>in</strong> the time periods mentioned <strong>in</strong> our offer.<br />
We further undertake to commence and complete the follow<strong>in</strong>g def<strong>in</strong>ed and itemized<br />
sections of the work with<strong>in</strong> the time stated below calculated from date of sign<strong>in</strong>g of<br />
contract.<br />
Page 28 of 56<br />
Commence <strong>in</strong>Complete <strong>in</strong><br />
1. Advance plann<strong>in</strong>g for design and<br />
Procurement and schedul<strong>in</strong>g ………days ………days<br />
2. Submission of design and draw<strong>in</strong>gs<br />
for structural and mecha<strong>nic</strong>al<br />
items for approval ………days ………days<br />
3. Submission of design and draw<strong>in</strong>gs<br />
for electrical items for approval ………days ………days<br />
4. Procurement of materials for –<br />
(a) Steel ………days ………days<br />
(b) Components ………days ………days<br />
(c) Controls ………days ………days<br />
5. Procurement of Import Licence<br />
if required ………days ………days<br />
6. Procurement of imported items ………days ………days<br />
7. Manufactur<strong>in</strong>g for –<br />
(a) Structurals ………days ………days<br />
(b) Drives ………days ………days<br />
(c) Electricals ………days ………days<br />
(d) Assembly ………days ………days<br />
8. Ready for shop test<strong>in</strong>g ………days ………days<br />
9. Transportation to site ………days ………days<br />
10. Installation at site ………days ………days<br />
11. Commission<strong>in</strong>g at site ………days ………days
12. Clean<strong>in</strong>g, pa<strong>in</strong>t<strong>in</strong>g and completion<br />
In all respects and hand<strong>in</strong>g over ………days ………days<br />
Detailed stage wise progress chart (CPM Diagram) (attach copy).<br />
Note : Total time for completion is 12 months from effective date of contract. This<br />
period will also <strong>in</strong>clude <strong>in</strong>spection, trials and hand<strong>in</strong>g over of all equipment / stores /<br />
documentation as contracted.<br />
Signature____________________<br />
For and on behalf of____________<br />
____________________________<br />
____________________________<br />
Date ___________________<br />
Page 29 of 56
SCHEUDLE ‘B’<br />
(To be prepared by vendor and submitted)<br />
LIST OF DRAWINGS / DOCUMENTS ACCOMPANYING THE TENDER<br />
<strong>FOR</strong> EQUIPMENT<br />
Description Draw<strong>in</strong>g Nos.<br />
The follow<strong>in</strong>g draw<strong>in</strong>gs are required to<br />
be submitted along with the Tender for<br />
each equipment :<br />
a) General Arrangement Draw<strong>in</strong>gs<br />
b) Layout of Mach<strong>in</strong>ery and Drives<br />
c) Control Circuit Diagram<br />
d) Load/speed curve for motors<br />
e) Stability calculations for major<br />
items like jibs, wheels, drums,<br />
slew bear<strong>in</strong>g, portals, etc.<br />
f) Any other enclosure for Hook<br />
Position <strong>in</strong>dicator, analog <strong>in</strong>di-<br />
cator, cable drum, etc.<br />
Signature<br />
For & On Behalf of<br />
Date<br />
Page 30 of 56
Part III – Standard Conditions of RFP<br />
The Bidder is required to give confirmation of their acceptance of the<br />
Standard Conditions of the Request for Proposal mentioned below which will<br />
automatically be considered as part of the Contract concluded with the successful<br />
Bidder (i.e. Seller <strong>in</strong> the Contract) as selected by the Buyer. Failure to do so may<br />
result <strong>in</strong> rejection of the Bid submitted by the Bidder.<br />
1. Law: The Contract shall be considered and made <strong>in</strong> accordance with the<br />
laws of the Republic of India. The contract shall be governed by and <strong>in</strong>terpreted <strong>in</strong><br />
accordance with the laws of the Republic of India.<br />
2. Effective Date of Contract: The contract shall come <strong>in</strong>to effect on the date of<br />
signatures of both the parties on the contract (Effective Date) and shall rema<strong>in</strong> valid<br />
until the completion of the obligations of the parties under the contract. The<br />
deliveries and supplies and performance of the services shall commence from the<br />
effective date of the contract.<br />
3. Arbitration: All disputes or differences aris<strong>in</strong>g out of or <strong>in</strong> connection with the<br />
Contract shall be settled by bilateral discussions. Any dispute, disagreement or<br />
question aris<strong>in</strong>g out of or relat<strong>in</strong>g to the Contract or relat<strong>in</strong>g to construction or<br />
performance, which cannot be settled amicably, may be resolved through arbitration.<br />
The standard clause of arbitration is as per Forms DPM-7, DPM-8 and DPM-9<br />
(Available <strong>in</strong> MoD website and can be provided on request).<br />
4. Penalty for Use of Undue Influence: The Seller undertakes that he has not<br />
given, offered or promised to give, directly or <strong>in</strong>directly, any gift, consideration,<br />
reward, commission, fees, brokerage or <strong>in</strong>ducement to any person <strong>in</strong> service of the<br />
Buyer or otherwise <strong>in</strong> procur<strong>in</strong>g the Contracts or forbear<strong>in</strong>g to do or for hav<strong>in</strong>g done<br />
or forborne to do any act <strong>in</strong> relation to the obta<strong>in</strong><strong>in</strong>g or execution of the present<br />
Contract or any other Contract with the Government of India for show<strong>in</strong>g or<br />
forbear<strong>in</strong>g to show favour or disfavour to any person <strong>in</strong> relation to the present<br />
Contract or any other Contract with the Government of India. Any breach of the<br />
aforesaid undertak<strong>in</strong>g by the Seller or any one employed by him or act<strong>in</strong>g on his<br />
behalf (whether with or without the knowledge of the Seller) or the commission of<br />
any offers by the Seller or anyone employed by him or act<strong>in</strong>g on his behalf, as<br />
def<strong>in</strong>ed <strong>in</strong> Chapter IX of the Indian Penal Code, 1860 or the Prevention of Corruption<br />
Act, 1986 or any other Act enacted for the prevention of corruption shall entitle the<br />
Buyer to cancel the contract and all or any other contracts with the Seller and<br />
recover from the Seller the amount of any loss aris<strong>in</strong>g from such cancellation. A<br />
decision of the Buyer or his nom<strong>in</strong>ee to the effect that a breach of the undertak<strong>in</strong>g<br />
had been committed shall be f<strong>in</strong>al and b<strong>in</strong>d<strong>in</strong>g on the Seller. Giv<strong>in</strong>g or offer<strong>in</strong>g of any<br />
gift, bribe or <strong>in</strong>ducement or any attempt at any such act on behalf of the Seller<br />
towards any officer/employee of the Buyer or to any other person <strong>in</strong> a position to<br />
<strong>in</strong>fluence any officer/employee of the Buyer for show<strong>in</strong>g any favour <strong>in</strong> relation to this<br />
or any other contract, shall render the Seller to such liability/ penalty as the Buyer<br />
may deem proper, <strong>in</strong>clud<strong>in</strong>g but not limited to term<strong>in</strong>ation of the contract, imposition<br />
of penal damages, forfeiture of the Bank Guarantee and refund of the amounts paid<br />
by the Buyer.<br />
Page 31 of 56
5. Agents / Agency Commission: The Seller confirms and declares to the<br />
Buyer that the Seller is the orig<strong>in</strong>al manufacturer of the stores/provider of the<br />
services referred to <strong>in</strong> this Contract and has not engaged any <strong>in</strong>dividual or firm,<br />
whether Indian or foreign whatsoever, to <strong>in</strong>tercede, facilitate or <strong>in</strong> any way to<br />
recommend to the Government of India or any of its functionaries, whether officially<br />
or unofficially, to the award of the contract to the Seller; nor has any amount been<br />
paid, promised or <strong>in</strong>tended to be paid to any such <strong>in</strong>dividual or firm <strong>in</strong> respect of any<br />
such <strong>in</strong>tercession, facilitation or recommendation. The Seller agrees that if it is<br />
established at any time to the satisfaction of the Buyer that the present declaration is<br />
<strong>in</strong> any way <strong>in</strong>correct or if at a later stage it is discovered by the Buyer that the Seller<br />
has engaged any such <strong>in</strong>dividual/firm, and paid or <strong>in</strong>tended to pay any amount, gift,<br />
reward, fees, commission or consideration to such person, party, firm or <strong>in</strong>stitution,<br />
whether before or after the sign<strong>in</strong>g of this contract, the Seller will be liable to refund<br />
that amount to the Buyer. The Seller will also be debarred from enter<strong>in</strong>g <strong>in</strong>to any<br />
supply Contract with the Government of India for a m<strong>in</strong>imum period of five years.<br />
The Buyer will also have a right to consider cancellation of the Contract either wholly<br />
or <strong>in</strong> part, without any entitlement or compensation to the Seller who shall <strong>in</strong> such an<br />
event be liable to refund all payments made by the Buyer <strong>in</strong> terms of the Contract<br />
along with <strong>in</strong>terest at the rate of 2% per annum above LIBOR rate. The Buyer will<br />
also have the right to recover any such amount from any contracts concluded earlier<br />
with the Government of India.<br />
6. Access to Books of Accounts: In case it is found to the satisfaction of the<br />
Buyer that the Seller has engaged an Agent or paid commission or <strong>in</strong>fluenced any<br />
person to obta<strong>in</strong> the contract as described <strong>in</strong> clauses relat<strong>in</strong>g to Agents/Agency<br />
Commission and penalty for use of undue <strong>in</strong>fluence, the Seller, on a specific request<br />
of the Buyer, shall provide necessary <strong>in</strong>formation/ <strong>in</strong>spection of the relevant f<strong>in</strong>ancial<br />
documents/<strong>in</strong>formation.<br />
7. Non-disclosure of Contract Documents: Except with the written consent of<br />
the Buyer/ Seller, other party shall not disclose the contract or any provision,<br />
specification, plan, design, pattern, sample or <strong>in</strong>formation thereof to any third party.<br />
8. Liquidated Damages: In the event of the Seller's failure to submit the Bonds,<br />
Guarantees and Documents, supply the stores/goods and conduct trials, <strong>in</strong>stallation<br />
of equipment, tra<strong>in</strong><strong>in</strong>g, etc as specified <strong>in</strong> this contract, the Buyer may, at his<br />
discretion, withhold any payment until the completion of the contract. The BUYER<br />
may also deduct from the seller as agreed, liquidated damages to the sum of 0.5% of<br />
the contract price of the delayed/undelivered stores/services mentioned above for<br />
every week of delay or part of a week, subject to the maximum value of the<br />
Liquidated Damages be<strong>in</strong>g not higher than 10% of the value of delayed stores.<br />
9. Term<strong>in</strong>ation of Contract: The Buyer shall have the right to term<strong>in</strong>ate this<br />
Contract <strong>in</strong> part or <strong>in</strong> full <strong>in</strong> any of the follow<strong>in</strong>g cases :-<br />
(a) Failure to submit PBG as per Clause 1, Part IV of this RFP.<br />
(b) When the supplier has failed to honour any part of the contract<br />
<strong>in</strong>clud<strong>in</strong>g failure to deliver the contracted stores/render services <strong>in</strong> time.<br />
Page 32 of 56
(c) When the contractor is found to have made false or fraudulent<br />
declaration or statement to get the contract or he is found to be <strong>in</strong>dulg<strong>in</strong>g <strong>in</strong><br />
unethical or unfair trade practices.<br />
(d) The Buyer has noticed that the Seller has utilised the services of any<br />
Indian/Foreign agent <strong>in</strong> gett<strong>in</strong>g this contract and paid any commission to such<br />
<strong>in</strong>dividual/company etc.<br />
(e) The delivery of the material is delayed for causes not attributable to<br />
Force Majeure for more than 06 months after the scheduled date of delivery.<br />
(f) The delivery of material is delayed due to causes of Force Majeure by<br />
more than12 months.<br />
(g) When the item offered by the supplier repeatedly fails <strong>in</strong> the <strong>in</strong>spection<br />
and /or the supplier is not <strong>in</strong> the position to either rectify the defects or offer<br />
items confirm<strong>in</strong>g to the contracted quality standards.<br />
(h) When both parties agree mutually to term<strong>in</strong>ate the contract.<br />
(j) The Seller is declared bankrupt or becomes <strong>in</strong>solvent.<br />
(k) Any special circumstances to justify the cancellation or term<strong>in</strong>ation of a<br />
contract.<br />
(l) As per decision of the Arbitration Tribunal.<br />
10. Notices: Any notice required or permitted by the contract shall be written <strong>in</strong><br />
the English language and may be delivered personally or may be sent by FAX or<br />
registered pre-paid mail/airmail, addressed to the last known address of the party to<br />
whom it is sent.<br />
11. Transfer and Sub-lett<strong>in</strong>g: The Seller has no right to give, barga<strong>in</strong>, sell,<br />
assign or sublet or otherwise dispose of the Contract or any part thereof, as well as<br />
to give or to let a third party take benefit or advantage of the present Contract or any<br />
part thereof.<br />
12. Patents and Other Industrial Property Rights: The prices stated <strong>in</strong> the<br />
present Contract shall be deemed to <strong>in</strong>clude all amounts payable for the use of<br />
patents, copyrights, registered charges, trademarks and payments for any other<br />
<strong>in</strong>dustrial property rights. The Seller shall <strong>in</strong>demnify the Buyer aga<strong>in</strong>st all claims from<br />
a third party at any time on account of the <strong>in</strong>fr<strong>in</strong>gement of any or all the rights<br />
mentioned <strong>in</strong> the previous paragraphs, whether such claims arise <strong>in</strong> respect of<br />
manufacture or use. The Seller shall be responsible for the completion of the<br />
supplies <strong>in</strong>clud<strong>in</strong>g spares, tools, tech<strong>nic</strong>al literature and tra<strong>in</strong><strong>in</strong>g aggregates<br />
irrespective of the fact of <strong>in</strong>fr<strong>in</strong>gement of the supplies, irrespective of the fact of<br />
<strong>in</strong>fr<strong>in</strong>gement of any or all the rights mentioned above.<br />
Page 33 of 56
13. Amendments: No provision of present Contract shall be changed or modified<br />
<strong>in</strong> any way (<strong>in</strong>clud<strong>in</strong>g this provision) either <strong>in</strong> whole or <strong>in</strong> part except by an <strong>in</strong>strument<br />
<strong>in</strong> writ<strong>in</strong>g made after the date of this Contract and signed on behalf of both the<br />
parties and which expressly states to amend the present Contract.<br />
14. Taxes and Duties<br />
(a) General.<br />
(i) If Bidder desires to ask for excise duty or Sales Tax / VAT extra,<br />
the same must be specifically stated. In the absence of any such<br />
stipulation, it will be presumed that the prices <strong>in</strong>clude all such charges<br />
and no claim for the same will be enterta<strong>in</strong>ed.<br />
(ii) If reimbursement of any Duty/Tax is <strong>in</strong>tended as extra over the<br />
quoted prices, the Bidder must specifically say so. In the absence of<br />
any such stipulation it will be presumed that the prices quoted are firm<br />
and f<strong>in</strong>al and no claim on account of such duty/tax will be entra<strong>in</strong>ed<br />
after the open<strong>in</strong>g of tenders.<br />
(iii) If a Bidder chooses to quote a price <strong>in</strong>clusive of any duty/tax and<br />
does not confirm <strong>in</strong>clusive of such duty/tax so <strong>in</strong>cluded is firm and f<strong>in</strong>al,<br />
he should clearly <strong>in</strong>dicate the rate of such duty/tax and quantum of<br />
such duty/tax <strong>in</strong>cluded <strong>in</strong> the price. Failure to do so may result <strong>in</strong><br />
ignor<strong>in</strong>g of such offers summarily.<br />
(iv) If a Bidder is exempted from payment of any duty/tax up to any<br />
value of supplies from them, he should clearly state that no such<br />
duty/tax will be charged by him up to the limit of exemption which he<br />
may have. If any concession is available <strong>in</strong> regard to rate/quantum of<br />
any Duty/tax, it should be brought out clearly. Stipulations like, the said<br />
duty/tax was presently not applicable but the same will be charged if it<br />
becomes leviable later on, will not be accepted unless <strong>in</strong> such cases it<br />
is clearly stated by a Bidder that such duty/tax will not be charged by<br />
him even if the same becomes applicable later on. In respect of the<br />
Bidders, who fail to comply with this requirement, their quoted prices<br />
shall be loaded with the quantum of such duty/tax which is normally<br />
applicable on the item <strong>in</strong> question for the purpose of compar<strong>in</strong>g their<br />
prices with other Bidders.<br />
(v) Any change <strong>in</strong> any duty/tax upward/downward as a result of any<br />
statutory variation <strong>in</strong> excise tak<strong>in</strong>g place with<strong>in</strong> contract terms shall be<br />
allowed to the extent of actual quantum of such duty/tax paid by the<br />
supplier, provided the supplies are made dur<strong>in</strong>g the orig<strong>in</strong>al delivery<br />
period. Similarly, <strong>in</strong> case of downward revision <strong>in</strong> any duty/tax, the<br />
actual quantum of reduction of such duty/tax shall be reimbursed to the<br />
Buyer by the Seller. All such adjustments shall <strong>in</strong>clude all reliefs,<br />
exemptions, rebates, concession etc. if any obta<strong>in</strong>ed by the Seller.<br />
Page 34 of 56
(b) Customs Duty<br />
(i) For imported stores offered aga<strong>in</strong>st forward delivery, the Bidder<br />
shall quote prices thereof exclusive of customs duty. The Bidder shall<br />
specify separately the C.I.F. prices and total amount of customs duty<br />
payable. They will also <strong>in</strong>dicate correctly the rate of customs duty<br />
applicable along with Indian Customs Tariff Number. Customs duty as<br />
actually paid will be reimbursed on production of necessary documents<br />
i.e.<br />
(aa) Triplicate copy of the bill of entry;<br />
(ab) Copy of bill of lad<strong>in</strong>g;<br />
(ac) A copy of foreign pr<strong>in</strong>cipal’s <strong>in</strong>voice. However, if the<br />
Bidder imports the stores <strong>in</strong> question aga<strong>in</strong>st his own<br />
commercial quota Import Licences, he will also be required to<br />
submit <strong>in</strong> addition the triplicate copy of bills of entry etc. a<br />
certificate from his Internal Auditor on the bill itself, to the effect<br />
that the follow<strong>in</strong>g items/quantity <strong>in</strong> the bill of entry related to the<br />
stores imported aga<strong>in</strong>st Defence Buyer contract<br />
number…………………………….. dated…………..<br />
(ii) Subsequent to the reimbursement of customs duty, the Bidder<br />
will submit to the concerned Payment Authority a certificate to the<br />
effect that he has not obta<strong>in</strong>ed any refund of customs duty subsequent<br />
to the payment of duty to the Customs authority by him. In addition, he<br />
shall also submit to the Pay<strong>in</strong>g Authority concerned a certificate<br />
immediately after a period of three months from the date of payment of<br />
the duty to customs authorities to the effect that he has not applied for<br />
refund of the customs duty subsequent to the payment of duty to the<br />
customs authorities by him.<br />
(iii) In case the Bidder obta<strong>in</strong>s any refund of customs duty,<br />
subsequently to the payment of the same by him to the customs<br />
authorities and reimbursement of the customs duty to him by the<br />
Payment Authority, he should forthwith furnish the details of the refund<br />
obta<strong>in</strong>ed and afford full credit of the same to the Buyer.<br />
(c) Excise Duty<br />
(i) Where the excise duty is payable on advalorem basis, the<br />
Bidder should submit along with the tender, the relevant form and the<br />
Manufacturer’s price list show<strong>in</strong>g the actual assessable value of the<br />
stores as approved by the Excise authorities.<br />
(ii) Bidders should note that <strong>in</strong> case any refund of excise duty is<br />
granted to them by Excise authorities <strong>in</strong> respect of Stores supplied<br />
under the contract, they will pass on the credit to the Buyer<br />
Page 35 of 56
immediately along with a certificate that the credit so passed on relates<br />
to the Excise Duty, orig<strong>in</strong>ally paid for the stores supplied under the<br />
contract. In case of their failure to do so, with<strong>in</strong> 10 days of the issue of<br />
the excise duty refund orders to them by the Excise Authorities the<br />
Buyer would be empowered to deduct a sum equivalent to the amount<br />
refunded by the Excise Authorities without any further reference to<br />
them from any of their outstand<strong>in</strong>g bills aga<strong>in</strong>st the contract or any<br />
other pend<strong>in</strong>g Government Contract and that no disputes on this<br />
account would be raised by them.<br />
(iii) The Seller is also required to furnish to the Pay<strong>in</strong>g Authority the<br />
follow<strong>in</strong>g certificates:<br />
(aa) Certificate with each bill to the effect that no refund has<br />
been obta<strong>in</strong>ed <strong>in</strong> respect of the reimbursement of excise duty<br />
made to the Seller dur<strong>in</strong>g three months immediately preced<strong>in</strong>g<br />
the date of the claim covered by the relevant bill.<br />
(ab) Certificate as to whether refunds have been obta<strong>in</strong>ed or<br />
applied for by them or not <strong>in</strong> the preced<strong>in</strong>g f<strong>in</strong>ancial year after<br />
the annual Audit of their accounts also <strong>in</strong>dicat<strong>in</strong>g details of such<br />
refunds/applications, if any.<br />
(ac) A certificate along with the f<strong>in</strong>al payment bills of the Seller<br />
to the effect whether or not they have any pend<strong>in</strong>g<br />
appeal/protest for refund or partial refund of excise duties<br />
already reimbursed to the Seller by the Government pend<strong>in</strong>g<br />
with the Excise authorities and if so, the nature, the amount<br />
<strong>in</strong>volved, and the position of such appeals.<br />
(ad) An undertak<strong>in</strong>g to the effect that <strong>in</strong> case it is detected by<br />
the Government that any refund from Excise Authority was<br />
obta<strong>in</strong>ed by the Seller after obta<strong>in</strong><strong>in</strong>g reimbursement from the<br />
Pay<strong>in</strong>g Authority, and if the same is not immediately refunded by<br />
the Seller to the Pay<strong>in</strong>g Authority giv<strong>in</strong>g details and particulars of<br />
the transactions, Pay<strong>in</strong>g Authority will have full authority to<br />
recover such amounts from the Seller’s outstand<strong>in</strong>g bills aga<strong>in</strong>st<br />
that particular contract or any other pend<strong>in</strong>g Government<br />
contracts and that no dispute on this account would be raised by<br />
the Seller.<br />
(iv) Unless otherwise specifically agreed to <strong>in</strong> terms of the contract,<br />
the Buyer shall not be liable for any claim on account of fresh<br />
imposition and/or <strong>in</strong>crease of Excise Duty on raw materials and/or<br />
components used directly <strong>in</strong> the manufacture of the contracted stores<br />
tak<strong>in</strong>g place dur<strong>in</strong>g the pendency of the contract.<br />
Page 36 of 56
(d) Sales Tax / VAT<br />
(i) If it is desired by the Bidder to ask for Sales tax / VAT to be paid<br />
as extra, the same must be specifically stated. In the absence of any<br />
such stipulation <strong>in</strong> the bid, it will be presumed that the prices quoted by<br />
the Bidder are <strong>in</strong>clusive of sales tax and no liability of sales tax will be<br />
developed upon the Buyer.<br />
(ii) On the Bids quot<strong>in</strong>g sales tax extra, the rate and the nature of<br />
Sales Tax applicable at the time of supply should be shown separately.<br />
Sales tax will be paid to the Seller at the rate at which it is liable to be<br />
assessed or has actually been assessed provided the transaction of<br />
sale is legally liable to sales tax and the same is payable as per the<br />
terms of the contract.<br />
(e) Octroi Duty & Local Taxes<br />
(i) Normally, materials to be supplied to Government Departments<br />
aga<strong>in</strong>st Government Contracts are exempted from levy of town duty,<br />
Octroi Duty, Term<strong>in</strong>al Tax and other levies of local bodies. The local<br />
Town/Mu<strong>nic</strong>ipal Body regulations at times, however, provide for such<br />
Exemption only on production of such exemption certificate from any<br />
authorised officer. Seller should ensure that stores ordered aga<strong>in</strong>st<br />
contracts placed by this office are exempted from levy of Town<br />
Duty/Octroi Duty, Term<strong>in</strong>al Tax or other local taxes and duties.<br />
Wherever required, they should obta<strong>in</strong> the exemption certificate from<br />
the Buyer, to avoid payment of such local taxes or duties.<br />
(ii) In case where the Mu<strong>nic</strong>ipality or other local body <strong>in</strong>sists upon<br />
payment of these duties or taxes the same should be paid by the Seller<br />
to avoid delay <strong>in</strong> supplies and possible demurrage charges. The receipt<br />
obta<strong>in</strong>ed for such payment should be forwarded to the Buyer without<br />
delay together with a copy of the relevant act or bylaws / notifications of<br />
the Mu<strong>nic</strong>ipality of the local body concerned to enable him to take up<br />
the question of refund with the concerned bodies if admissible under<br />
the said acts or rules.<br />
Page 37 of 56
Part IV – Special Conditions of RFP<br />
The Bidder is required to give confirmation of their acceptance of Special<br />
Conditions of the RFP mentioned below which will automatically be considered as<br />
part of the Contract concluded with the successful Bidder (i.e. Seller <strong>in</strong> the Contract)<br />
as selected by the Buyer. Failure to do so may result <strong>in</strong> rejection of Bid submitted by<br />
the Bidder.<br />
1. Performance Guarantee. The Bidder will be required to furnish a<br />
Performance Guarantee by way of Bank Guarantee through a public sector bank or<br />
a private sector bank authorized to conduct government bus<strong>in</strong>ess (ICICI Bank Ltd.,<br />
Axis Bank Ltd or HDFC Bank Ltd.) for a sum equal to 10% of the contract value<br />
with<strong>in</strong> 30 days of date of sign<strong>in</strong>g of contract.Performance Bank Guarantee should be<br />
valid up to 60 days beyond the date of warranty. The specimen of PBG is given <strong>in</strong><br />
Form DPM-15. Format Placed at enclosure.<br />
2. Tolerance Clause. To take care of any change <strong>in</strong> the requirement dur<strong>in</strong>g the<br />
period start<strong>in</strong>g from issue of RFP till placement of the contract, Buyer reserves the<br />
right to 50 % plus/m<strong>in</strong>us <strong>in</strong>crease or decrease the quantity of the required goods<br />
upto that limit without any change <strong>in</strong> the terms & conditions and prices quoted by the<br />
Seller. While award<strong>in</strong>g the contract, the quantity ordered can be <strong>in</strong>creased or<br />
decreased by the Buyer with<strong>in</strong> this tolerance limit.<br />
3. Payment Terms. It will be mandatory for the Bidders to <strong>in</strong>dicate their bank<br />
account numbers and other relevant e-payment details so that payments could be<br />
made through ECS/EFT mechanism <strong>in</strong>stead of payment through cheques, wherever<br />
feasible. A copy of the model mandate form prescribed by RBI to be submitted by<br />
Bidders for receiv<strong>in</strong>g payments through ECS is at Form DPM-11 (Available <strong>in</strong> MoD<br />
website and can be given on request). The payment will be made as per the<br />
follow<strong>in</strong>g terms, on production of the requisite documents:-<br />
S.No. Stage Payment Details Payment<br />
Amount<br />
(a) Stage Payment 1 On Approval of QAP and Design by<br />
Inspection agency aga<strong>in</strong>st BG of equivalent amount<br />
valid up to Stage Payment 2.<br />
10 %<br />
(b) Stage Payment 2 Receipt of <strong>in</strong>spection notes of all<br />
equipment /systems duly certified by Inspection agency<br />
aga<strong>in</strong>st BG of equivalent amount valid up to Stage<br />
Payment 3.<br />
(c) Stage Payment 3 Receipt of all equipments/systems<br />
<strong>in</strong>stallation material etc at ND(MBI) and issue of<br />
<strong>in</strong>spection note by Inspection agency/User.<br />
(d) F<strong>in</strong>al Payment On completion of commission<strong>in</strong>g of<br />
entire system and successful tak<strong>in</strong>g over by User.<br />
Page 38 of 56<br />
20 %<br />
50 %<br />
20 %
4. Pay<strong>in</strong>g Authority. Director General Naval Project, Mumbai. The payment<br />
of bills will be made on submission of the follow<strong>in</strong>g documents by the Seller to the<br />
Pay<strong>in</strong>g Authority along with the bill:<br />
(a) Ink-signed copy of cont<strong>in</strong>gent bill / Seller’s bill.<br />
(b) Ink-signed copy of Commercial <strong>in</strong>voice / Seller’s bill.<br />
(c) Copy of Contract with U.O. number and date of IFA’s concurrence,<br />
where required under delegation of powers.<br />
(d) CRVs <strong>in</strong> duplicate<br />
(e) Inspection note.<br />
(f) Claim for statutory and other levies to be supported with requisite<br />
documents / proof of payment such as Excise duty challan, Customs duty<br />
clearance certificate, Octroi receipt, proof of payment for EPF/ESIC<br />
contribution with nom<strong>in</strong>al roll of beneficiaries, etc as applicable.<br />
(g) Exemption certificate for Excise duty / Customs duty, if applicable.<br />
(h) Bank Guarantee from nationalized bank for advance, if any <strong>in</strong><br />
prescribed format.<br />
(i) Guarantee / Warranty certificate.<br />
(j) Performance Bank guarantee from public sector bank or<br />
ICICI/AXIS/HDFC Bank/Indemnity Bond where applicable.<br />
(k) DP extension letter with CFA’s sanction, U.O. number and date of<br />
IFA’s concurrence, where required under delegation of powers, <strong>in</strong>dicat<strong>in</strong>g<br />
whether extension is with or without LD.<br />
(l) Details for electro<strong>nic</strong> payment viz Account holder’s name, Bank name,<br />
Branch name and address, Account type, Account number, IFSC code, MICR<br />
code (if these details are not <strong>in</strong>corporated <strong>in</strong> contract).<br />
(m) Any other document / certificate that may be provided for <strong>in</strong> the<br />
contract.<br />
(n) User Acceptance.<br />
(o) Xerox copy of PBG.<br />
5. Fall clause. The follow<strong>in</strong>g Fall Clause will form part of the contract placed on<br />
successful Bidder:-<br />
(a) The price charged for the stores supplied under the contract by the<br />
Seller shall <strong>in</strong> no event exceed the lowest prices at which the Seller sells the<br />
stores or offer to sell stores of identical description to any<br />
persons/Organisation <strong>in</strong>clud<strong>in</strong>g the purchaser or any department of the<br />
Central government or any Department of state government or any statutory<br />
undertak<strong>in</strong>g the central or state government as the case may be dur<strong>in</strong>g the<br />
period till performance of all supply Orders placed dur<strong>in</strong>g the currency of the<br />
rate contract is completed.<br />
(b) If at any time, dur<strong>in</strong>g the said period the Seller reduces the sale price,<br />
sells or offer to sell such stores to any person/organisation <strong>in</strong>clud<strong>in</strong>g the Buyer<br />
or any Deptt, of central Govt. or any Department of the State Government or<br />
any Statutory undertak<strong>in</strong>g of the Central or state Government as the case<br />
may be at a price lower than the price chargeable under the contract, the<br />
Seller shall forthwith notify such reduction or sale or offer of sale to the<br />
Director general of Supplies & Disposals and the price payable under the<br />
Page 39 of 56
contract for the stores of such reduction of sale or offer of the sale shall stand<br />
correspond<strong>in</strong>gly reduced. The above stipulation will, however, not apply to:-<br />
(i) Exports by the Seller.<br />
(ii) Sale of goods as orig<strong>in</strong>al equipment at price lower than the<br />
prices charged for normal replacement.<br />
(iii) Sale of goods such as drugs which have expiry dates.<br />
(iv) Sale of goods at lower price on or after the date of completion of<br />
the Contract sale/placement of the order of goods by the authority<br />
concerned under the exist<strong>in</strong>g or previous Rate Contracts as also under<br />
any previous contracts entered <strong>in</strong>to with the Central or State Govt.<br />
Depts, <strong>in</strong>clud<strong>in</strong>g their undertak<strong>in</strong>gs exclud<strong>in</strong>g jo<strong>in</strong>t sector companies<br />
and/or private parties and bodies.<br />
(c) The Seller shall furnish the follow<strong>in</strong>g certificate to the Pay<strong>in</strong>g Authority<br />
along with each bill for payment for supplies made aga<strong>in</strong>st the Contract – “We<br />
certify that there has been no reduction <strong>in</strong> sale price of the stores of<br />
description identical to the stores supplied to the Government under the<br />
Contract here<strong>in</strong> and such stores have not been offered/sold by me/us to any<br />
person/organisation <strong>in</strong>clud<strong>in</strong>g the purchaser or any department of Central<br />
Government or any Department of a state Government or any Statutory<br />
Undertak<strong>in</strong>g of the Central or state Government as the case may be upto the<br />
date of bill/the date of completion of supplies aga<strong>in</strong>st all supply orders placed<br />
dur<strong>in</strong>g the currency of the Contract at price lower than the price charged to<br />
the government under the contract except for quantity of stores categories<br />
under sub-clauses (a),(b) and (c) of sub-para (ii) above details of which are<br />
given below - ........”.<br />
6. Exchange Rate Variation Clause. No adjustment of prices shall be<br />
enterta<strong>in</strong>able on account of any variation <strong>in</strong> exchange rate.<br />
7. Risk & Expense Clause<br />
(a) Should the stores or any <strong>in</strong>stallment thereof not be delivered with<strong>in</strong> the<br />
time or times specified <strong>in</strong> the contract documents, or if defective delivery is<br />
made <strong>in</strong> respect of the stores or any <strong>in</strong>stallment thereof, the Buyer shall after<br />
grant<strong>in</strong>g the Seller 45 days to cure the breach, be at liberty, without prejudice<br />
to the right to recover liquidated damages as a remedy for breach of contract,<br />
to declare the contract as cancelled either wholly or to the extent of such<br />
default.<br />
(b) Should the stores or any <strong>in</strong>stallment thereof not perform <strong>in</strong> accordance<br />
with the specifications / parameters provided by the SELLER dur<strong>in</strong>g the check<br />
proof tests to be done <strong>in</strong> the BUYER’s country, the BUYER shall be at liberty,<br />
without prejudice to any other remedies for breach of contract, to cancel the<br />
contract wholly or to the extent of such default.<br />
(c) In case of a material breach that was not remedied with<strong>in</strong> 45 days, the<br />
BUYER shall, hav<strong>in</strong>g given the right of first refusal to the SELLER be at liberty<br />
Page 40 of 56
to purchase, manufacture, or procure from any other source as he th<strong>in</strong>ks fit,<br />
other stores of the same or similar description to make good:-<br />
(i) Such default.<br />
(ii) In the event of the contract be<strong>in</strong>g wholly determ<strong>in</strong>ed the balance<br />
of the stores rema<strong>in</strong><strong>in</strong>g to be delivered thereunder.<br />
(d) Any excess of the purchase price, cost of manufacturer, or value of any<br />
stores procured from any other supplier as the case may be, over the contract<br />
price appropriate to such default or balance shall be recoverable from the<br />
Seller. Such recoveries shall not exceed 100% of the value of the Contract.<br />
8. Force Majeure Clause<br />
(a) Neither party shall bear responsibility for the complete or partial<br />
nonperformance of any of its obligations (except for failure to pay any sum<br />
which has become due on account of receipt of goods under the provisions of<br />
the present contract), if the non-performance results from such Force Majeure<br />
circumstances as Flood, Fire, Earth Quake and other acts of God as well as<br />
War, Military operation, blockade, Acts or Actions of State Authorities or any<br />
other circumstances beyond the parties control that have arisen after the<br />
conclusion of the present contract.<br />
(b) In such circumstances the time stipulated for the performance of an<br />
obligation under the present contract is extended correspond<strong>in</strong>gly for the<br />
period of time of action of these circumstances and their consequences.<br />
(c) The party for which it becomes impossible to meet obligations under<br />
this contract due to Force Majeure conditions, is to notify <strong>in</strong> written form the<br />
other party of the beg<strong>in</strong>n<strong>in</strong>g and cessation of the above circumstances<br />
immediately, but <strong>in</strong> any case not later than 10 (Ten) days from the moment of<br />
their beg<strong>in</strong>n<strong>in</strong>g.<br />
(d) Certificate of a Chamber of Commerce (Commerce and Industry) or<br />
other competent authority or organization of the respective country shall be a<br />
sufficient proof of commencement and cessation of the above circumstances.<br />
(e) If the impossibility of complete or partial performance of an obligation<br />
lasts for more than 12 (twelve) months, either party hereto reserves the right<br />
to term<strong>in</strong>ate the contract totally or partially upon giv<strong>in</strong>g prior written notice of<br />
30 (thirty) days to the other party of the <strong>in</strong>tention to term<strong>in</strong>ate without any<br />
liability other than reimbursement on the terms provided <strong>in</strong> the agreement for<br />
the goods received.<br />
9. Specification. The follow<strong>in</strong>g Specification clause will form part of the contract<br />
placed on successful Bidder - The Seller guarantees to meet the specifications as<br />
per Part-II of RFP and to <strong>in</strong>corporate the modifications to the exist<strong>in</strong>g design<br />
configuration to meet the specific requirement of the Buyer Services as per<br />
modifications/requirements recommended after the Ma<strong>in</strong>tenance Evaluation Trials.<br />
All tech<strong>nic</strong>al literature and draw<strong>in</strong>gs shall be amended as the modifications by the<br />
Page 41 of 56
Seller before supply to the Buyer. The Seller, <strong>in</strong> consultation with the Buyer, may<br />
carry out tech<strong>nic</strong>al upgradation/alterations <strong>in</strong> the design, draw<strong>in</strong>gs and specifications<br />
due to change <strong>in</strong> manufactur<strong>in</strong>g procedures, <strong>in</strong>digenisation or obsolescence. This<br />
will, however, not <strong>in</strong> any way, adversely affect the end specifications of the<br />
equipment. Changes <strong>in</strong> tech<strong>nic</strong>al details, draw<strong>in</strong>gs repair and ma<strong>in</strong>tenance<br />
techniques along with necessary tools as a result of upgradation/alterations will be<br />
provided to the Buyer free of cost with<strong>in</strong> 15 days of affect<strong>in</strong>g such<br />
upgradation/alterations.<br />
10. OEM Certificate. In case the Bidder is not the OEM, the agreement certificate<br />
with the OEM for sourc<strong>in</strong>g the spares shall be mandatory. However, where OEMs do<br />
not exist, m<strong>in</strong>or aggregates and spares can be sourced from authorized vendors<br />
subject to quality certification.<br />
11. Earliest Acceptable Year of Manufacture. 2012 Quality / Life certificate will<br />
need to be enclosed with the Bill.<br />
12. Buyer Furnished Equipment. No equipment will be provided by the Buyer at his<br />
expense to the Seller:<br />
13. Transportation. The follow<strong>in</strong>g Transportation clause will form part of the contract<br />
placed on successful Bidder<br />
(a) CIF/CIP – The stores shall be delivered CIF/CIP at Naval Dockyard,<br />
Mumbai. Seller will bear the costs and freight necessary to br<strong>in</strong>g the goods to<br />
the port of dest<strong>in</strong>ation. The Seller also has to procure mar<strong>in</strong>e/other <strong>in</strong>surance<br />
aga<strong>in</strong>st the Buyer’s risk of loss of or damage to goods dur<strong>in</strong>g the carriage.<br />
The Seller will contract for <strong>in</strong>surance and pay the <strong>in</strong>surance premium. Seller is<br />
also required to clear the goods for export. The stores shall be delivered to<br />
the Buyer by Indian ships only. The date of issue of the Bill of Lad<strong>in</strong>g shall be<br />
considered as the date of delivery. No part shipment of goods would be<br />
permitted. Trans-shipment of goods would not be permitted. In case it<br />
becomes <strong>in</strong>evitable to do so, the Seller shall not arrange part-shipments<br />
and/or transshipment without the express/prior written consent of the Buyer.<br />
The goods should be shipped by Indian vessels only. However, the Seller can<br />
still utilize the services of the MoD, Govt of India Freight Forward<strong>in</strong>g Agent<br />
details for which will be provided by the Buyer. Seller will be required to<br />
commu<strong>nic</strong>ate the follow<strong>in</strong>g <strong>in</strong>formation <strong>in</strong>variably by telex/signed <strong>in</strong> case of<br />
import of Defence Stores be<strong>in</strong>g brought <strong>in</strong> commercial ships to Embarkation<br />
Head Quarters concerned well <strong>in</strong> advance before the Ship sails the port of<br />
load<strong>in</strong>g:<br />
(i) Name of the Ship<br />
(ii) Port of Load<strong>in</strong>g and name of Country.<br />
(iii) ETA at port of Discharge i.e. Mumbai, Kolkatta, Chennai and<br />
Kochi.<br />
(iv) Number of Packages and weight.<br />
(v) Nomenclature and details of major equipment.<br />
(vi) Special <strong>in</strong>structions, if any stores of sensitive nature requir<strong>in</strong>g<br />
special attention.<br />
Page 42 of 56
14. Air lift. The follow<strong>in</strong>g Airlift clause will form part of the contract placed on<br />
successful Bidder - Should the Buyer <strong>in</strong>tend to airlift all or some of the stores, the<br />
Seller shall pack the stores accord<strong>in</strong>gly on receipt of an <strong>in</strong>timation to that effect from<br />
the Buyer. Such deliveries will be agreed upon well <strong>in</strong> advance and paid for as may<br />
be mutually agreed.<br />
15. Pack<strong>in</strong>g and Mark<strong>in</strong>g. The follow<strong>in</strong>g Pack<strong>in</strong>g and Mark<strong>in</strong>g clause will form part<br />
of the contract placed on successful Bidder<br />
(a) The Seller shall provide pack<strong>in</strong>g and preservation of the equipment and<br />
spares/goods contracted so as to ensure their safety aga<strong>in</strong>st damage <strong>in</strong> the<br />
conditions of land, sea and air transportation, transshipment, storage and<br />
weather hazards dur<strong>in</strong>g transportation, subject to proper cargo handl<strong>in</strong>g. The<br />
Seller shall ensure that the stores are packed <strong>in</strong> conta<strong>in</strong>ers, which are made<br />
sufficiently strong, and with seasoned wood. The pack<strong>in</strong>g cases should have<br />
hooks for lift<strong>in</strong>g by crane/fork lift truck. Tags with proper mark<strong>in</strong>g shall be<br />
fastened to the special equipment, which cannot be packed.<br />
(b) The pack<strong>in</strong>g of the equipment and spares/goods shall conform to the<br />
requirements of specifications and standards <strong>in</strong> force <strong>in</strong> the territory of the<br />
Seller’s country.<br />
(c) Each spare, tool and accessory shall be packed <strong>in</strong> separate cartons. A<br />
label <strong>in</strong> English shall be pasted on the carton <strong>in</strong>dicat<strong>in</strong>g the under mentioned<br />
details of the item conta<strong>in</strong>ed <strong>in</strong> the carton. A tag <strong>in</strong> English with said<br />
<strong>in</strong>formation shall also be attached to six samples of the item. If quantity<br />
contracted is less than six then tag shall be affixed to complete quantity<br />
contracted of the item. The cartons shall then be packed <strong>in</strong> pack<strong>in</strong>g cases as<br />
required.<br />
(i) Part Number:<br />
(ii) Nomenclature:<br />
(iii) Contract annex number:<br />
(iv) Annex serial number:<br />
(v) Quantity contracted:<br />
(d) One copy of the pack<strong>in</strong>g list <strong>in</strong> English shall be <strong>in</strong>serted <strong>in</strong> each cargo<br />
package, and the full set of the pack<strong>in</strong>g lists shall be placed <strong>in</strong> Case No.1<br />
pa<strong>in</strong>ted <strong>in</strong> a yellow colour.<br />
(e) The Seller shall mark each package with <strong>in</strong>delible pa<strong>in</strong>t <strong>in</strong> the English<br />
language as follows:-<br />
(i) EXPORT<br />
(ii) Contract No. ------------------------------------------<br />
(iii) Consignee ---------------------------------------------<br />
(iv) Port / airport of dest<strong>in</strong>ation ------------------------<br />
(v) Ultimate consignee ----------------------------------<br />
(vi) SELLER ------------------------------------------------<br />
(vii) Package No. ------------------------------------------<br />
Page 43 of 56
(viii) Gross/net weight : -----------------------------------<br />
(ix) Overall dimensions/volume : ---------------------<br />
(x) The Seller’s mark<strong>in</strong>g.<br />
(f) If necessary, each package shall be marked with warn<strong>in</strong>g<br />
<strong>in</strong>scriptions:, “Do not turn over”, category of cargo etc.<br />
(g) Should any special equipment be returned to the Seller by the Buyer,<br />
the latter shall provide normal pack<strong>in</strong>g, which protects the equipment and<br />
spares/goods from the damage of deterioration dur<strong>in</strong>g transportation by land,<br />
air or sea. In this case the Buyer shall f<strong>in</strong>alize the mark<strong>in</strong>g with the Seller.<br />
16. Quality. The quality of the stores delivered accord<strong>in</strong>g to the present Contract<br />
shall correspond to the tech<strong>nic</strong>al conditions and standards valid for the deliveries of<br />
the same stores for <strong>in</strong> Seller’s country or specifications enumerated as per RFP and<br />
shall also <strong>in</strong>clude there<strong>in</strong> modification to the stores suggested by the Buyer. Such<br />
modifications will be mutually agreed to. The Seller confirms that the stores to be<br />
supplied under this Contract shall be new i.e. not manufactured before (Year of<br />
Contract),and shall <strong>in</strong>corporate all the latest improvements and modifications thereto<br />
and spares of improved and modified equipment are backward <strong>in</strong>tegrated and<br />
<strong>in</strong>terchangeable with same equipment supplied by the Seller <strong>in</strong> the past if any. The<br />
Seller shall supply an <strong>in</strong>terchangeability certificate along with the changed part<br />
numbers where<strong>in</strong> it should be mentioned that item would provide as much life as the<br />
orig<strong>in</strong>al item.<br />
17. Quality Assurance. Seller would provide the QAP with<strong>in</strong> 03 months of the date<br />
of sign<strong>in</strong>g of the Contract to the third party <strong>in</strong>spection agency. Buyer reserves the<br />
right to modify the QAP. Seller would be required to provide all test facilities at his<br />
premises for acceptance and <strong>in</strong>spection by the . The details <strong>in</strong> this regard will be<br />
coord<strong>in</strong>ated dur<strong>in</strong>g the negotiation of the contract. The item should be of the latest<br />
manufacture, conform<strong>in</strong>g to the current production standard and hav<strong>in</strong>g 100%<br />
def<strong>in</strong>ed life at the time of delivery.<br />
18. Inspection Authority. The Inspection will be carried out by the third party<br />
agency(IRS/LRS/BVQI) as mentioned at Part II of this RFP.<br />
19. Pre-Dispatch Inspection. The follow<strong>in</strong>g Pre-dispatch Inspection clause will form<br />
part of the contract placed on successful Bidder<br />
(a) The Buyer’s representatives may carry out Pre-Dispatch Inspection<br />
(PDI) of the stores/equipment <strong>in</strong> addition to the third party <strong>in</strong>spector, <strong>in</strong> order<br />
to check their compliance with specifications <strong>in</strong> accordance with its usual<br />
standard procedures. Upon successful completion of such PDI, the Seller and<br />
third party <strong>in</strong>spector will issue and sign a Certificate of Conformity as per the<br />
specimen at Form DPM-21(Available <strong>in</strong> MoD website and can be given on<br />
request).Same will be forwarded to DGNP(MBI) prior dispatch of items.<br />
(b) The Seller shall <strong>in</strong>timate the third party <strong>in</strong>spector/Buyer at least 45 days<br />
before the scheduled date of PDI. The Buyer may send his authorised<br />
representative(s) to attend the PDI.<br />
Page 44 of 56
(c) The Seller shall provide all reasonable facilities, access and assistance<br />
to the Buyer’s representative for safety and convenience <strong>in</strong> the performance<br />
of their duties <strong>in</strong> the Seller’s country.<br />
20. Jo<strong>in</strong>t Receipt Inspection. The follow<strong>in</strong>g Jo<strong>in</strong>t Receipt Inspection clause will form<br />
part of the contract placed on successful Bidder –<br />
(a) The Parties agree that the Jo<strong>in</strong>t Receipt Inspection (JRI) of delivered<br />
goods shall be conducted on arrival at ND(MBI). JRI will consist of<br />
(i) Quantitative check<strong>in</strong>g to verify that the quantities of the<br />
delivered goods correspond to the quantities def<strong>in</strong>ed <strong>in</strong> this contract<br />
and the <strong>in</strong>voices.<br />
(ii) Complete functional check<strong>in</strong>g of the stores/equipment as per<br />
specifications <strong>in</strong> the contract and as per procedures and tests laid<br />
down by Buyer but functional check<strong>in</strong>g of spares shall not be done.<br />
(b) JRI will be carried out by the User and Buyer’s representative(s). The<br />
Buyer will <strong>in</strong>vite the Seller with a prior notice of a m<strong>in</strong>imum of fifteen (15) days<br />
to attend the JRI for the delivered goods. The Seller shall have the right not to<br />
attend the JRI. The bio data of the Seller’s representative will need to be<br />
commu<strong>nic</strong>ated fifteen (15) days prior to the dispatch of goods to the Buyer for<br />
obta<strong>in</strong><strong>in</strong>g necessary security clearance <strong>in</strong> accordance with the rules<br />
applicable <strong>in</strong> the Buyer’s country.<br />
(c) Upon completion of each JRI, JRI proceed<strong>in</strong>gs and Acceptance<br />
Certificate will be signed by the Seller and the User. In case the Seller’s<br />
representative is not present, the JRI proceed<strong>in</strong>gs and Acceptance Certificate<br />
shall be signed by the User only and the same shall be b<strong>in</strong>d<strong>in</strong>g on the Seller.<br />
Copy of JRI proceed<strong>in</strong>gs and Acceptance Certificate shall be dispatched to<br />
the Seller with<strong>in</strong> 30 days of completion of the JRI. In case of deficiencies <strong>in</strong><br />
quantity and quality or defects, details of these shall be recorded <strong>in</strong> the JRI<br />
proceed<strong>in</strong>gs, Acceptance Certificate shall not be issued and claims raised as<br />
per the Article on Claims <strong>in</strong> the contract.<br />
21. Frank<strong>in</strong>g Clause. The follow<strong>in</strong>g Frank<strong>in</strong>g Clause will form part of the contract<br />
placed on successful Bidder:-<br />
(a) Frank<strong>in</strong>g Clause <strong>in</strong> the case of Acceptance of Goods “The fact that<br />
the goods have been <strong>in</strong>spected after the delivery period and passed by the<br />
Inspect<strong>in</strong>g Officer will not have the effect of keep<strong>in</strong>g the contract alive. The<br />
goods are be<strong>in</strong>g passed without prejudice to the rights of the Buyer under the<br />
terms and conditions of the contract”.<br />
(b) Frank<strong>in</strong>g Clause <strong>in</strong> the case of Rejection of Goods “The fact that<br />
the goods have been <strong>in</strong>spected after the delivery period and rejected by the<br />
Inspect<strong>in</strong>g Officer will not b<strong>in</strong>d the Buyer <strong>in</strong> any manner. The goods are be<strong>in</strong>g<br />
Page 45 of 56
ejected without prejudice to the rights of the Buyer under the terms and<br />
conditions of the contract.”<br />
22. Claims. The follow<strong>in</strong>g Claims clause will form part of the contract placed on<br />
successful Bidder:–<br />
(a) The claims may be presented either: (i) on quantity of the stores, where<br />
the quantity does not correspond to the quantity shown <strong>in</strong> the Pack<strong>in</strong>g<br />
List/Insufficiency <strong>in</strong> pack<strong>in</strong>g, or (ii) on quality of the stores, where quality does<br />
not correspond to the quality mentioned <strong>in</strong> the contract.<br />
(b) The quantity claims for deficiency of quantity shall be presented with<strong>in</strong><br />
45 days of completion of JRI and acceptance of goods. The quantity claim<br />
shall be submitted to the Seller as per Form DPM-22 (Available <strong>in</strong> MoD<br />
website and can be given on request).<br />
(c) The quality claims for defects or deficiencies <strong>in</strong> quality noticed dur<strong>in</strong>g<br />
the JRI shall be presented with<strong>in</strong> 45 days of completion of JRI and<br />
acceptance of goods. Quality claims shall be presented for defects or<br />
deficiencies <strong>in</strong> quality noticed dur<strong>in</strong>g warranty period earliest but not later than<br />
45 days after expiry of the guarantee period. The quality claims shall be<br />
submitted to the Seller as per Form DPM-23 (Available <strong>in</strong> MoD website and<br />
can be given on request).<br />
(d) The description and quantity of the stores are to be furnished to the<br />
Seller along with concrete reasons for mak<strong>in</strong>g the claims. Copies of all the<br />
justify<strong>in</strong>g documents shall be enclosed to the presented claim. The Seller will<br />
settle the claims with<strong>in</strong> 45 days from the date of the receipt of the claim at the<br />
Seller’s office, subject to acceptance of the claim by the Seller. In case no<br />
response is received dur<strong>in</strong>g this period the claim will be deemed to have been<br />
accepted.<br />
(e) The Seller shall collect the defective or rejected goods from the<br />
location nom<strong>in</strong>ated by the Buyer and deliver the repaired or replaced goods at<br />
the same location under Seller’s arrangement.<br />
(f) Claims may also be settled by reduction of cost of goods under claim<br />
from bonds submitted by the Seller or payment of claim amount by Seller<br />
through demand draft drawn on an Indian Bank, <strong>in</strong> favour of Pr<strong>in</strong>cipal<br />
Controller/Controller of Defence Accounts concerned.<br />
(g) The quality claims will be raised solely by the Buyer and without any<br />
certification/countersignature by the Seller’s representative stationed <strong>in</strong> India.<br />
23. Warranty<br />
The follow<strong>in</strong>g Warranty will form part of the contract placed on successful<br />
Bidder:–<br />
Page 46 of 56
(a) The Seller warrants that the goods supplied under the contract conform<br />
to tech<strong>nic</strong>al specifications prescribed and shall perform accord<strong>in</strong>g to the said<br />
tech<strong>nic</strong>al specifications.<br />
(b) The Seller warrants for a period of 12 months from the date of<br />
acceptance of stores by Jo<strong>in</strong>t Receipt Inspection or date of <strong>in</strong>stallation and<br />
commission<strong>in</strong>g, whichever is later, that the goods/stores supplied under the<br />
contract and each component used <strong>in</strong> the manufacture thereof shall be free<br />
from all types of defects/failures.<br />
(c) If with<strong>in</strong> the period of warranty, the goods are reported by the Buyer to<br />
have failed to perform as per the specifications, the Seller shall either replace<br />
or rectify the same free of charge, with<strong>in</strong> a maximum period of 45 days of<br />
notification of such defect received by the Seller, provided that the goods are<br />
used and ma<strong>in</strong>ta<strong>in</strong>ed by the Buyer as per <strong>in</strong>structions conta<strong>in</strong>ed <strong>in</strong> the<br />
Operat<strong>in</strong>g Manual. Warranty of the equipment would be extended by such<br />
duration of downtime. Record of the down time would be ma<strong>in</strong>ta<strong>in</strong>ed by the<br />
user <strong>in</strong> the logbook. Spares required for warranty repairs shall be provided<br />
free of cost by the Seller. The Seller also undertakes to diagnose, test, adjust,<br />
calibrate and repair/replace the goods/equipment aris<strong>in</strong>g due to accidents by<br />
neglect or misuse by the operator or damage due to transportation of the<br />
goods dur<strong>in</strong>g the warranty period, at the cost mutually agreed to between the<br />
Buyer and the Seller.<br />
(d) The Seller also warrants that necessary service and repair back up<br />
dur<strong>in</strong>g the warranty period of the equipment shall be provided by the Seller<br />
and he will ensure that the downtime is with<strong>in</strong> 0.5 % of the warranty period.<br />
(e) The Seller shall associate tech<strong>nic</strong>al personnel of the Ma<strong>in</strong>tenance<br />
agency and Quality Assurance Agency of the Buyer dur<strong>in</strong>g warranty repair<br />
and shall also provide the details of complete defects, reasons and remedial<br />
actions for defects.<br />
(f) If a particular equipment/goods fails frequently and/or, the cumulative<br />
down time exceeds 20 % of the warranty period, the complete equipment<br />
shall be replaced free of cost by the Seller with<strong>in</strong> a stipulated period of 60<br />
days of receipt of the notification from the Buyer. Warranty of the replaced<br />
equipment would start from the date of acceptance after Jo<strong>in</strong>t Receipt<br />
Inspection by the Buyer/date of <strong>in</strong>stallation and commission<strong>in</strong>g.<br />
(g) In case the complete delivery of Eng<strong>in</strong>eer<strong>in</strong>g Support Package is<br />
delayed beyond the period stipulated <strong>in</strong> this contract, the Seller undertakes<br />
that the warranty period for the goods/stores shall be extended to that extent.<br />
(h) The Seller will guarantee the shelf life of (10) years under the Indian<br />
tropical condition as given below:<br />
(i) M<strong>in</strong>imum temperature – 10ºC<br />
(ii) Maximum temperature - 50ºC<br />
(iii)Average Humidity – 90%<br />
Page 47 of 56
(j) For procurement of oils and lubricants, the follow<strong>in</strong>g will be applicable:–<br />
(i) The Seller warrants that the special oils and lubricants required<br />
dur<strong>in</strong>g the warranty period of the equipment shall be provided by the<br />
Seller himself.<br />
(ii) The penalty amount<strong>in</strong>g to (20 %) of the value of the equipment<br />
shall be imposed on the Seller <strong>in</strong> case the Seller refuses or fails to<br />
meet the requirement of oils and lubricants dur<strong>in</strong>g the warranty period<br />
of the equipment.<br />
(iii) The Seller shall make available the detailed specifications of all<br />
oils and lubricants required to be used <strong>in</strong> the equipment at the l<strong>in</strong>e of<br />
<strong>in</strong>itial delivery of equipment to facilitate identification and development<br />
of <strong>in</strong>digenous equivalents to be used after the expiry of the warranty<br />
period.<br />
24. Product Support. The follow<strong>in</strong>g Product Support clause will form part of the<br />
contract placed on successful Bidder:-<br />
(a) The Seller agrees to provide Product Support for the stores,<br />
assemblies/sub-, fitment items and consumables, Special Ma<strong>in</strong>tenance<br />
Tools(SMT)/Special Test Equipments (STE) subcontracted from other<br />
agencies/ manufacturer by the Seller for a maximum period of 20 years<br />
<strong>in</strong>clud<strong>in</strong>g 01 year of warranty period after the delivery of equipment.<br />
(b) In the event of any obsolescence dur<strong>in</strong>g the above mentioned period of<br />
product support <strong>in</strong> respect of any component or sub-system, mutual<br />
consultation between the Seller and Buyer will be undertaken to arrive at an<br />
acceptable solution <strong>in</strong>clud<strong>in</strong>g additional cost, if any.<br />
(c) Any improvement/modification/ up gradation be<strong>in</strong>g undertaken by the<br />
Seller or their sub suppliers on the stores/equipment be<strong>in</strong>g purchased under<br />
the Contract will be commu<strong>nic</strong>ated by the Seller to the Buyer and, if required<br />
by the Buyer, these will be carried out by the Seller at Buyer's cost.<br />
25. Eng<strong>in</strong>eer<strong>in</strong>g Support Package (ESP) clause. The follow<strong>in</strong>g ESP clause will<br />
form part of the contract placed on successful Bidder –<br />
(a) Repair Philosophy. The Eng<strong>in</strong>eer<strong>in</strong>g Support Philosophy shall<br />
conform to the repair philosophy as follows:<br />
(i) Unit level repairs. These are repairs carried out with<strong>in</strong> the unit<br />
hold<strong>in</strong>g this equipment with tools generally held with<strong>in</strong> the unit or<br />
supplied by the manufacturer with each equipment or as per scal<strong>in</strong>g of<br />
1:10 or any other scal<strong>in</strong>g recommended by the manufacturer as per<br />
population held <strong>in</strong> the unit. These perta<strong>in</strong> to clean<strong>in</strong>g, lubrications,<br />
m<strong>in</strong>or repairs and replacement of components and m<strong>in</strong>or assemblies<br />
that can be carried out <strong>in</strong> field without any sophisticated tools or test<br />
Page 48 of 56
equipment. For carry<strong>in</strong>g out such repairs, the manufacturer is required<br />
to provide the follow<strong>in</strong>g:-<br />
(aa) Table of Tools and Equipment (TOTE) with each<br />
equipment <strong>in</strong>clud<strong>in</strong>g operators manual.<br />
(ab) Scal<strong>in</strong>g of special tools and spares as mentioned above<br />
<strong>in</strong>clud<strong>in</strong>g Ma<strong>in</strong>tenance manual.<br />
(ii) Field Repairs. These are repairs carried out <strong>in</strong> the field by<br />
tech<strong>nic</strong>ians specially tra<strong>in</strong>ed for this purpose and where the required<br />
special tools and spares have to be provided. These repairs comprise<br />
replacement of major assemblies and other components beyond the<br />
scope of unit level repairs. Normally a field work shop that carries out<br />
such repairs looks after three to four units hold<strong>in</strong>g the said equipment.<br />
The manufacturer is required to provide the follow<strong>in</strong>g:-<br />
(aa) Quantity and specification of spares that need to be<br />
stocked for a population of ordered equipment.<br />
(ab) Special Ma<strong>in</strong>tenance Tools and Test Equipment that need<br />
to be provided to each such field work shop. (The total number<br />
of such facilities would also have to be stated based on<br />
deployment pattern of the concerned equipment to carryout total<br />
cost<strong>in</strong>g).<br />
(iii) Base overhaul. All repairs <strong>in</strong>clud<strong>in</strong>g repairs to components,<br />
subassemblies and overhaul of the complete equipment are carried out<br />
by this facility. Depend<strong>in</strong>g on the population of the equipment, one to<br />
five such facilities may be established <strong>in</strong> India for this purpose (The<br />
actual No would have to be stated for cost<strong>in</strong>g).The manufacturer is<br />
required to provide the follow<strong>in</strong>g:-<br />
(aa) All Special Ma<strong>in</strong>tenance Tools, jigs, fixtures and test<br />
equipment for carry<strong>in</strong>g out repairs up to component level.<br />
(ab) Quantity and specification of spares, sub assemblies as<br />
per population expected to be ma<strong>in</strong>ta<strong>in</strong>ed.<br />
(ac) Oils and lubricants necessary for overhaul.<br />
(ad) All necessary tech<strong>nic</strong>al literature.<br />
(ae) Calibration facilities for test equipment. This level of<br />
repair def<strong>in</strong>es stripp<strong>in</strong>g and rebuild<strong>in</strong>g of equipment <strong>in</strong> a Base<br />
workshop.<br />
(b) Manufacturers Recommended List of Spares (MRLS). Based on the<br />
explanation given above, Bidders are requested to provide MRLS to susta<strong>in</strong><br />
the equipment for a period of 05 years for various levels of repair as per<br />
format given at Form DPM-19 (Available <strong>in</strong> MoD website and can be given on<br />
request). Bidders will be required to provide these both with Tech<strong>nic</strong>al and<br />
Commercial proposals. (In case where the equipment has been <strong>in</strong> usage the<br />
spares would be sought by Buyer, on the recommended list to be furnished by<br />
the ma<strong>in</strong>tenance agency, based on the exploitation of the equipment, and<br />
Page 49 of 56
NOT as per MRLS). While with the commercial proposal, the actual costs of<br />
each component/spare will be provided, <strong>in</strong> the case of Tech<strong>nic</strong>al Proposal<br />
these will be reflected as Low Cost/ Medium Cost/High Cost. A guidel<strong>in</strong>e for<br />
this purpose is as under:-<br />
(i) Low Cost. Less than 2 % of the unit cost of the equipment/sub<br />
system.<br />
(ii) Medium Cost. 2 to 10% of the unit cost of the equipment/sub<br />
system.<br />
(iii) High Cost. Greater than 10 % of the unit cost of<br />
equipment/subsystem. If the complete equipment comprises a number<br />
of different sub systems, for e.g. it is com<strong>in</strong>g mounted on a vehicle or is<br />
provided with a stand for mount<strong>in</strong>g or is <strong>in</strong>clusive of a generator or an<br />
air conditioner or has a sight, the MRLS must be provided separately<br />
for each such sub system.<br />
(c) Special Ma<strong>in</strong>tenance Tools and Test Equipment. This is to be<br />
formulated <strong>in</strong> a similar manner as expla<strong>in</strong>ed for MRLS. A suggested format is<br />
given at Form DPM-17 (Available <strong>in</strong> MoD website and can be given on<br />
request) and is to be <strong>in</strong>cluded <strong>in</strong> both Tech<strong>nic</strong>al and Commercial Proposals.<br />
The cost column may be left blank <strong>in</strong> the Tech<strong>nic</strong>al Proposal.<br />
(d) Tech<strong>nic</strong>al Literature. The details of tech<strong>nic</strong>al literature to be supplied<br />
with the system should be listed as per the suggested format at Form DPM-18<br />
(Available <strong>in</strong> MoD website and can be given on request). This should be<br />
provided with both Tech<strong>nic</strong>al and Commercial Proposals. The cost column<br />
may be left blank <strong>in</strong> the Tech<strong>nic</strong>al Proposal.<br />
(e) Miscellaneous Aspects. (Applicable only when trials are required) –<br />
In cases where the equipment is required to undergo trials, the equipment will<br />
also be put through Ma<strong>in</strong>tenance Evaluation Test. Based on this evaluation<br />
and <strong>in</strong> consultation with the supplier, the MRLS may be ref<strong>in</strong>ed. Dur<strong>in</strong>g user<br />
trials it may be brought out that the equipment is acceptable subject to<br />
carry<strong>in</strong>g out certa<strong>in</strong> modifications / improvements.<br />
(f) Ma<strong>in</strong>ta<strong>in</strong>ability Evaluation Trials (MET). This is carried with a view to<br />
facilitate provision<strong>in</strong>g of effective eng<strong>in</strong>eer<strong>in</strong>g support dur<strong>in</strong>g life cycle of the<br />
equipment. This would <strong>in</strong>volve stripp<strong>in</strong>g of the equipment and carry<strong>in</strong>g out<br />
recommended tests and adjustments and establish<strong>in</strong>g adequacy of<br />
ma<strong>in</strong>tenance tools, test equipment and tech<strong>nic</strong>al literature. MET details will be<br />
given as per format given at Form DPM-20 (Available <strong>in</strong> MoD website and can<br />
be given on request). To facilitate this process the Bidder is required to<br />
provide the follow<strong>in</strong>g :-<br />
(i) Tech<strong>nic</strong>al Literature.<br />
(aa) User Handbook/Operators Manual <strong>in</strong> English and H<strong>in</strong>di.<br />
(ab) Design Specifications.<br />
Page 50 of 56
(ac) Tech<strong>nic</strong>al Manuals.<br />
-Part I Tech description, specifications, function<strong>in</strong>g of<br />
various systems.<br />
-Part II Inspection/Ma<strong>in</strong>tenance tasks repair procedures,<br />
materials used, fault diagnosis and use of Special<br />
Ma<strong>in</strong>tenance Tools (SMTs)/Special Test Equipment<br />
(STEs).<br />
-Part III Procedure for assembly/disassembly, repair up to<br />
component level, safety precautions.<br />
-Part IV Part list with draw<strong>in</strong>g reference and List of<br />
SMTs/STEs Test Bench.<br />
(ad) Manufacturers Recommended List of Spares (MRLS).<br />
(ae) Illustrated Spare Parts List (ISPL) and along with the<br />
prices <strong>in</strong> the Commercial offer.<br />
(af) Tech<strong>nic</strong>al Manual on STE with draw<strong>in</strong>g reference.<br />
(ag) Complete Equipment Schedule.<br />
(ah) Table of Tools & Equipment (TOTE) & carried spares.<br />
(ai) Rotable list, norms of consumption, mandatory/ non<br />
mandatory spares list for each system.<br />
(ii) One set of Gauges<br />
(iii) One set of Special Ma<strong>in</strong>tenance Tools (SMTs).<br />
(iv) One set of Special Test Equipment (STEs).<br />
(v) Servic<strong>in</strong>g Schedule.<br />
(vi) Condemnation limits.<br />
(vii) Permissive repair schedule.<br />
(viii) Pack<strong>in</strong>g specifications /<strong>in</strong>structions.<br />
(ix) Design Specifications.<br />
(x) Any additional <strong>in</strong>formation suggested by the OEM.<br />
(g) Vendors quot<strong>in</strong>g lesser ESP / MRLS <strong>in</strong> terms of range and depth will<br />
have to make good the deficiency. The vendors quot<strong>in</strong>g surplus items <strong>in</strong> ESP<br />
/ MRLS should agree to buy back the surplus spares.<br />
26. Price Variation (PV) Clause. This is a firm and fixed price contract and will not<br />
be subject to any adjustment dur<strong>in</strong>g the performance of contract for any reason<br />
whatsoever. However, taxes and levies, as per current rates will be applicable,<br />
provided the supplies are made dur<strong>in</strong>g the orig<strong>in</strong>al delivery period.<br />
Page 51 of 56
From:<br />
Bank _______________<br />
To,<br />
The President of India<br />
M<strong>in</strong>istry of Defence,<br />
Government of India<br />
New Delhi<br />
Dear Sir,<br />
DPM-15<br />
Performance Bank Guarantee Format<br />
Page 52 of 56<br />
Enclosure to Part-IV<br />
Whereas you have entered <strong>in</strong>to a contract No._______ dated_________ (here<strong>in</strong>after<br />
referred to as the said Contract) with M/s__________________________,<br />
here<strong>in</strong>after referred to as the “seller” for supply of goods as per Part-II of the said<br />
contract to the said seller and whereas the Seller has undertaken to produce a bank<br />
guarantee for( % ) of total Contract value amount<strong>in</strong>g to _________ to secure its<br />
obligations to the President of India. We the _______________ bank hereby<br />
expressly, irrevocably and unreservedly undertake and guarantee as pr<strong>in</strong>cipal<br />
obligors on behalf of the seller that, <strong>in</strong> the event that the President of India declares<br />
to us that the goods have not been supplied accord<strong>in</strong>g to the Contractual obligations<br />
under the aforementioned contract, we will pay you, on demand and without demur,<br />
all and any sum up to a maximum of ____________Rupees _____________ only.<br />
Your written demand shall be conclusive evidence to us that such repayment is due<br />
under the terms of the said contract. We undertake to effect payment upon receipt of<br />
such written demand.<br />
2. We shall not be discharged or released from this undertak<strong>in</strong>g and guarantee by<br />
any arrangements, variations made between you and the Seller, <strong>in</strong>dulgence to the<br />
Seller by you, or by any alterations <strong>in</strong> the obligations of the Seller or by any<br />
forbearance whether as to payment, time performance or otherwise.<br />
3. In no case shall the amount of this guarantee be <strong>in</strong>creased.<br />
4. This guarantee shall rema<strong>in</strong> valid for …… months from the date of JRI acceptance<br />
of test consignment <strong>in</strong> India or until all the store, spares and documentation have<br />
been supplied accord<strong>in</strong>g to the contractual obligations under the said contract.<br />
5. Unless a demand or claim under this guarantee is made on us <strong>in</strong> writ<strong>in</strong>g or on<br />
before the aforesaid expiry date as provided <strong>in</strong> the above referred contract or unless<br />
this guarantee is extended by us, all your rights under this guarantee shall be<br />
forfeited and we shall be discharged from the liabilities hereunder.<br />
6. This guarantee shall be a cont<strong>in</strong>u<strong>in</strong>g guarantee and shall not be discharged by<br />
and change <strong>in</strong> the constitution of the Bank or <strong>in</strong> the constitution of<br />
M/s______________________________.
Notwithstand<strong>in</strong>g anyth<strong>in</strong>g conta<strong>in</strong>ed here<strong>in</strong> above:-<br />
(a) Our liability under this guarantee is restricted to Rs.<br />
______________________________________.<br />
(b) The guarantee is valid up to ____________________(Date).<br />
(c) We are liable to pay guarantee amount or part thereof, if and only if ,<br />
we receive a written claim or demand on or before ________(Date).<br />
Place: ________________<br />
Date: _________________<br />
Page 53 of 56<br />
Yours faithfully,<br />
For_____________Bank<br />
(Authorized Signatory / Attorney)
Part V – Evaluation Criteria & Price Bid<br />
1. Evaluation Criteria. The broad guidel<strong>in</strong>es for evaluation of Bids will be as<br />
follows:<br />
(a) Only those Bids will be evaluated which are found to be fulfill<strong>in</strong>g all the<br />
eligibility and qualify<strong>in</strong>g requirements of the RFP, both tech<strong>nic</strong>ally and<br />
commercially.<br />
(b) If bidder is non OEM of either frequency converter or the VFD drive<br />
then the bidder should provide a certificate from all OEMs clearly authoriz<strong>in</strong>g<br />
him to quote on their behalf for this tender and express<strong>in</strong>g unequivocal<br />
support and back<strong>in</strong>g for supply, <strong>in</strong>stallation, test<strong>in</strong>g and commission<strong>in</strong>g<br />
<strong>in</strong>clud<strong>in</strong>g required quality assurance cover for the system as whole and also<br />
undertak<strong>in</strong>g to provide all necessary after sales support to Naval Dockyard,<br />
Mumbai for at least 10 years after the date of commission<strong>in</strong>g. Further such<br />
bidder should have sufficient experience <strong>in</strong> execution of turnkey work of<br />
similar nature and similar cost <strong>in</strong> last three years. Order copies and work<br />
completion certificates must be submitted along with the bid to support the<br />
same.<br />
(c) In respect of Two-Bid system, the Tech<strong>nic</strong>al Bid (‘T’ bid) forwarded by<br />
the Bidders will be evaluated by the Buyer with reference to the tech<strong>nic</strong>al<br />
characteristics of the equipment as mentioned <strong>in</strong> the RFP. The compliance of<br />
‘T’bid would be determ<strong>in</strong>ed on the basis of the parameters specified <strong>in</strong> Part II<br />
of the RFP. The unpriced ‘Q’ bids will be evaluated along with the ‘T’ bid to<br />
ensure uniform compliance with required taxes and terms of payment<br />
amongst various bidders.<br />
(d) The ‘Q’bids of only those Bidders will be opened whose ‘T’ bid would<br />
clear the tech<strong>nic</strong>al evaluation. The Lowest Bid will be decided upon the lowest<br />
price quoted by the particular Bidder as per the Price Format given at Para 2<br />
below. The consideration of taxes and duties <strong>in</strong> evaluation process will be<br />
such that all taxes and duties (<strong>in</strong>clud<strong>in</strong>g those for which exemption certificates<br />
are issued) quoted by the Bidders will be considered. The ultimate cost to the<br />
Buyer would be the decid<strong>in</strong>g factor for rank<strong>in</strong>g of Bids.<br />
(e) The Bidders are required to spell out the rates of Customs duty, Excise<br />
duty, VAT, Service Tax, etc <strong>in</strong> unambiguous terms; otherwise their offers will<br />
be loaded with the maximum rates of duties and taxes for the purpose of<br />
comparison of prices. If reimbursement of Customs duty / Excise Duty / VAT<br />
is <strong>in</strong>tended as extra, over the quoted prices, the Bidder must specifically say<br />
so. In the absence of any such stipulation it will be presumed that the prices<br />
quoted are firm and f<strong>in</strong>al and no claim on account of such duties will be<br />
entra<strong>in</strong>ed after the open<strong>in</strong>g of tenders. If a Bidder chooses to quote a price<br />
<strong>in</strong>clusive of any duty and does not confirm <strong>in</strong>clusive of such duty so <strong>in</strong>cluded<br />
is firm and f<strong>in</strong>al, he should clearly <strong>in</strong>dicate the rate of such duty and quantum<br />
of excise duty <strong>in</strong>cluded <strong>in</strong> the price. Failure to do so may result <strong>in</strong> ignor<strong>in</strong>g of<br />
such offers summarily. If a Bidder is exempted from payment of Customs duty<br />
/ Excise Duty / VAT duty up to any value of supplies from them, they should<br />
Page 54 of 56
clearly state that no excise duty will be charged by them up to the limit of<br />
exemption which they may have. If any concession is available <strong>in</strong> regard to<br />
rate/quantum of Customs duty / Excise Duty / VAT, it should be brought out<br />
clearly. Stipulations like, excise duty was presently not applicable but the<br />
same will be charged if it becomes leviable later on, will not be accepted<br />
unless <strong>in</strong> such cases it is clearly stated by a Bidder that excise duty will not be<br />
charged by him even if the same becomes applicable later on. In respect of<br />
the Bidders who fail to comply with this requirement, their quoted prices shall<br />
be loaded with the quantum of excise duty which is normally applicable on the<br />
item <strong>in</strong> question for the purpose of compar<strong>in</strong>g their prices with other Bidders.<br />
The same logic applies to Customs duty and VAT also.<br />
(f) All Payments will be made <strong>in</strong> Indian Rupees only.<br />
(g) If there is a discrepancy between the unit price and the total price that<br />
is obta<strong>in</strong>ed by multiply<strong>in</strong>g the unit price and quantity, the unit price will prevail<br />
and the total price will be corrected. If there is a discrepancy between words<br />
and figures, the amount <strong>in</strong> words will prevail for calculation of price.<br />
(h) The Lowest Bid which is acceptable will be considered further for<br />
placement of contract / Supply Order after complete clarification and price<br />
negotiations as decided by the Buyer.<br />
2. Price Bid Format. The Price Bid Format is given below and Bidders are<br />
required to fill this up correctly with full details. Detailed breakdown of Sl. No.(a), (b),<br />
(f) and (g) are to be <strong>in</strong>dicated.<br />
Sl. No. Description UOM Unit<br />
Price<br />
(a) Basic cost of<br />
(b)<br />
item/items(Itemwise)<br />
Accessories<br />
(c) Installation / Commission<strong>in</strong>g<br />
charges<br />
(d) Tra<strong>in</strong><strong>in</strong>g<br />
(e) Tech<strong>nic</strong>al literature<br />
(f) Tools<br />
(g) Spares<br />
(h) Any other item<br />
(i) Excise Duty @ -- %<br />
(j) VAT @ -- %<br />
(k) Octroi / Entry taxes (Octroi<br />
exemption can be issued if<br />
required)<br />
Page 55 of 56<br />
Qty Total
(l) Any other Tax or duty<br />
(m) Grand Total<br />
(n) Grand Total R/Off<br />
(o) Terms of payment Accepted / Not Accepted<br />
3. The bidders are also required to provide a budgetary estimate for undertak<strong>in</strong>g AMC on<br />
expiry of warranty period. This figure will not be used for evaluation of lowest bid s<strong>in</strong>ce AMC will<br />
be conducted separately.<br />
Page 56 of 56