RNAS Howden - The Airfield Research Group
RNAS Howden - The Airfield Research Group
RNAS Howden - The Airfield Research Group
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>The</strong> last two members of the main arch were then lifted, one by each crane, one slightly ahead of the<br />
other; the two were then lowered into position, connected up at the eaves, and the centre pin driven<br />
home. <strong>The</strong> first main arch was thus now completed and the second main arch was then erected and all<br />
wind girders and intermediate trusses, along with braces were inserted to complete the bay.<br />
A fine day was chosen for the elevation of the first bay and the stage was placed in such a position as to<br />
allow both main arch ribs to be raised without moving the stages. <strong>The</strong> stages were then moved<br />
backwards into position for the next bay, this process being repeated as the process proceeded.<br />
After the completion of the last bay the west end main doors were erected in a similar manner to those at<br />
the east end.<br />
4.3.4 Stage Removal<br />
A three-ton hand crane was installed on each stage for taking down the steam derrick cranes, and after<br />
removal of the cranes from the stages, a 110-foot jib crane was erected at ground level on bogies<br />
running on railway track, for the taking down of the staging steelwork.<br />
4.3.5 Sundry Work<br />
On completion of the steelwork, came the sheeting, glazing, painting and sundry work. <strong>The</strong> shed floor<br />
had been covered with hardcore, and this helped in keeping the site dry. <strong>The</strong> concreting of the floor and<br />
the construction of the hydrogen and heating trenches then followed, after the completion of the roof<br />
covering. <strong>The</strong> floor was concreted in-situ, using nine-foot square slabs.<br />
Plate 16: Twin Shed under construction 14-05-18<br />
17