International construction cost survey 2012
International construction cost survey 2012
International construction cost survey 2012
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Canada – hourly <strong>cost</strong> of labour (including overheads)<br />
Canada – major projects<br />
CAD<br />
Halton Region Hospital 1bn<br />
Humber River Regional Hospital 1bn<br />
Air Rail Link 310m<br />
Union Station Revitalisation 640m<br />
Toronto-York Spadina Subway Extension 2.6bn<br />
2010 2011 2011<br />
CAD CAD USD<br />
Group 1 tradesman – eg plumber, electrician 60 60 61<br />
Group 2 tradesman – eg carpenter, bricklayer 55 55 56<br />
Group 3 tradesman – eg carpet layer, tiler, plasterer 50 50 51<br />
General labourer 45 45 46<br />
Site foreman 75 75 76<br />
Canada – <strong>cost</strong>s of materials<br />
Concrete 30 mpa (m 3 ) (1,500m 3 job) 150 165 167<br />
Reinforcement bar 16mm (tonne) (120 tonne job) 1,200 1,350 1,368<br />
Concrete block (400 x 200) per 1,000 (>10,000 block job) 700 725 734<br />
Standard brick per 1,000 900 900 912<br />
Structural steel beams (tonne) (>100 tonne job) 2,000 2,100 2,127<br />
Glass pane 6mm (m 2 ) 165 165 167<br />
Softwood timber for framing 100mm x 50mm (m) 25 25 25<br />
Plasterboard 13mm (m 2 ) 10 10 10<br />
Emulsion paint (litre) 10 10 10<br />
Copper pipe 15mm (m) (>1,000m job) 6 10 10<br />
Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 4 7 7<br />
Canada – key trades (excluding preliminaries and builders’ margins)<br />
Excavate basement (m 3 ) (1,800m 3 job) 15 15 15<br />
Excavate footings (m) 20 20 20<br />
Concrete in slab (m 3 ) (1,500m 3 job) 190 190 192<br />
Reinforcement in beams (tonne) 1,800 1,900 1,925<br />
Formwork to soffit of slab (m 2 ) 140 140 142<br />
Blockwork in wall (m 2 ) (10,000 block job) 120 120 122<br />
Structural steel beams (tonne) 3,000 3,250 3,292<br />
Pre-cast concrete wall (m 2 ) 300 325 329<br />
Curtain wall glazing incl support system (m 2 ) (1,000m 2 job) 900 925 937<br />
Plasterboard 13mm thick to stud wall (m 2 ) (3,000m 2 job) 25 25 25<br />
Single solid core door incl frame and hardware (no) (50 door job) 1,500 1,600 1,621<br />
Painting to walls primer + 2 coats (m 2 ) 8 10 10<br />
Ceramic tiling (m 2 ) (1,000m 2 job) 85 85 86<br />
Vinyl flooring to wet areas (m 2 ) (500m 2 job) 60 65 66<br />
Carpet medium tufted (m 2 ) (4,500m 2 job) 55 55 56<br />
Lighting installation (m 2 ) (>5,000m 2 job) 50 50 51<br />
Copper pipe 15mm to wall (m) (>1,000m job) 65 65 66<br />
Fire sprinklers (per m 2 ) (5,000m 2 job) 35 35 35<br />
Air conditioning incl main plant (m 2 ) (>5,000m 2 job) 310 310 314<br />
making the difference 11<br />
This document is in the public domain and is shared here by RSS Construction Projects Ltd - www.rssprojects.com