International construction cost survey 2012
International construction cost survey 2012
International construction cost survey 2012
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
Vietnam – hourly <strong>cost</strong> of labour (including overheads)<br />
Vietnam – major projects<br />
USD<br />
Saigon <strong>International</strong> Terminal, Phu My 1 163m<br />
Urban Railway Line 1, Hanoi 1.1bn<br />
Mass Rapid Transit Line 1, Ho Chi Minh City 1.2bn<br />
Monorail Line 2, Ho Chi Minh City 350m<br />
Da Nang–Quang Ngai Expressway 1.5bn<br />
2010 2011 2011<br />
VND VND USD<br />
Group 1 tradesman – eg plumber, electrician 180,000 216,000 11<br />
Group 2 tradesman – eg carpenter, bricklayer 155,000 186,000 9<br />
Group 3 tradesman – eg carpet layer, tiler, plasterer 125,000 150,000 7<br />
General labourer 100,000 120,000 6<br />
Site foreman 90,000 200,000 10<br />
Vietnam – <strong>cost</strong>s of materials<br />
Concrete 30 mpa (m 3 ) (1,500m 3 job) 1,100,000 1,125,720 55<br />
Reinforcement bar 16mm (tonne) (120 tonne job) 16,575,000 17,311,000 849<br />
Concrete block (400 x 200) per 1,000 (>10,000 block job) 5,301,000 5,725,000 281<br />
Standard brick per 1,000 1,400,300 1,450,000 71<br />
Structural steel beams (tonne) (>100 tonne job) 17,500,000 20,178,000 989<br />
Glass pane 6mm (m 2 ) 247,000 265,000 13<br />
Softwood timber for framing 100mm x 50mm (m) 46,000 50,000 2<br />
Plasterboard 13mm (m 2 ) 45,000 50,000 2<br />
Emulsion paint (litre) 42,000 47,790 2<br />
Copper pipe 15mm (m) (>1,000m job) 350,000 379,140 19<br />
Copper cable (m) (3C + E, 2.5mm PVC) (>100,000m job) 29,000 35,000 2<br />
Vietnam – key trades (excluding preliminaries and builders’ margins)<br />
Excavate basement (m 3 ) (1,800m 3 job) 75,000 67,000 3<br />
Excavate footings (m) 76,000 80,000 4<br />
Concrete in slab (m 3 ) (1,500m 3 job) 1,600,000 1,440,000 71<br />
Reinforcement in beams (tonne) 19,500,000 22,038,000 1,080<br />
Formwork to soffit of slab (m 2 ) 380,000 208,000 10<br />
Blockwork in wall (m 2 ) (10,000 block job) 350,000 260,000 13<br />
Structural steel beams (tonne) 22,000,000 28,652,000 1,405<br />
Pre-cast concrete wall (m 2 ) 450,000 518,300 25<br />
Curtain wall glazing incl support system (m 2 ) (1,000m 2 job) 8,550,000 9,000,000 441<br />
Plasterboard 13mm thick to stud wall (m 2 ) (3,000m 2 job) 150,000 161,200 8<br />
Single solid core door incl frame and hardware (no) (50 door job) 4,750,000 5,241,600 257<br />
Painting to walls primer + 2 coats (m 2 ) 75,000 83,000 4<br />
Ceramic tiling (m 2 ) (1,000m 2 job) 650,000 405,600 20<br />
Vinyl flooring to wet areas (m 2 ) (500m 2 job) 300,000 322,400 16<br />
Carpet medium tufted (m 2 ) (4,500m 2 job) 650,000 660,000 32<br />
Lighting installation (m 2 ) (>5,000m 2 job) – 360,000 18<br />
Copper pipe 15mm to wall (m) (>1,000m job) 650,000 670,000 33<br />
Fire sprinklers (per m 2 ) (5,000m 2 job) – 600,000 29<br />
Air conditioning incl main plant (m 2 ) (>5,000m 2 job) – 800,000 39<br />
making the difference 39<br />
This document is in the public domain and is shared here by RSS Construction Projects Ltd - www.rssprojects.com