CONSTRUCŢII <strong>SUB</strong>TERANE<br />

lungime de 3,00 m;<br />

Etapa 5 – Execuţia celui de al doilea tronson de boltă L=<br />

2,00 m şi a primului tronson de radier L= 3,00 m pentru un<br />

inel nou<br />

• Se armează, se cofrează şi se betonează al doilea tronson de<br />

boltă de 2,00 m al primului inel;<br />

• Se demolează structura existentă pe 3,50 m şi se sprijină<br />

provizoriu bolta existenta în front, cu cintre demontabile;<br />

• Se execută sapatura la cotele din proiect pentru realizarea<br />

radierului pe o lungime de 3,0m;<br />

• Se montează cintrele metalice pierdute la extradosul ţevilor;<br />

• Se montează tolele metalice sudate de cintre pe tronsonul<br />

pe care s-a betonat radierul;<br />

• Se realizează rostul total cu 2 foi de carton bitumat între<br />

bolţari la nivelul radierului;<br />

Fig. 7 Armare şi betonare boltă.<br />

• Se execută hidroizolaţia şi se petrece cu cea executată în<br />

etapa anterioară;<br />

• Se completează betonul de egalizare de 15 cm grosime;<br />

• Se armează, se cofrează şi se betonează tronsonul 1 de<br />

radier al urmatorului inel;<br />

Etapa 6 – Execuţia ultimului tronson de bolta al inelului 1<br />

• Se armează, se cofreaza şi se betonează al treilea tronson de<br />

2,00 m, al primului inel;<br />

• Se realizează rostul total cu 2 foi de carton bitumat între<br />

inele la nivelul bolţii;<br />

Se repetă etapele 2,3,4,5 si 6, pana se finalizează podeţul<br />

Fig. 8 Imagini finale timpan aval şi amonte<br />

meters length<br />

UNDERGROUND CONSTRUCTIONS<br />

Stage 5- Construction of the second arch section, L=2m, and<br />

the first invert section, L=3.00m for a new ring.<br />

• reinforcement and encasement are performed, then the<br />

second arch section L=2.00 m of the first ring is concreted;<br />

• existing structure is demolished on a 3.50 m length and the<br />

existing arch is temporarily supported by removable frame<br />

steelworks<br />

• an excavation is performed based on the blueprint in order<br />

to construct the invert on a 3.0 m length<br />

• frame steelworks are put in place at the pipes’ intrados<br />

• metallic end plates welded on frame steelworks are<br />

installed in the section where the invert was concreted<br />

• total joint is made using 2 asphalt board sheets in between<br />

the lining segments at the invert level.<br />

Figure 7 Arch reinforcement and concreting<br />

• waterproofing is performed and meets the one performed<br />

during the previous stage<br />

• the levelling concrete is completed up to a 15 cm thickness<br />

• invert section 1 of the next ring is reinforced, cased and<br />

concreted.<br />

Stage 6 – Construction of last arch section of ring 1<br />

• reinforcement and encasement are performed, then the third<br />

arch section of 2 m length of the first ring is concreted;<br />

• total joint is made using 2 asphalt board sheets in between<br />

the rings at the arch level<br />

Stages 2, 3, 4, 5 and 6 are repeated until the culvert is completed<br />

Fig. 8 Final images end element upstream and downstream<br />

Număr Special 2005<br />

Special Issue 34