CONSTRUCŢII <strong>SUB</strong>TERANE<br />
lungime de 3,00 m;<br />
Etapa 5 – Execuţia celui de al doilea tronson de boltă L=<br />
2,00 m şi a primului tronson de radier L= 3,00 m pentru un<br />
inel nou<br />
• Se armează, se cofrează şi se betonează al doilea tronson de<br />
boltă de 2,00 m al primului inel;<br />
• Se demolează structura existentă pe 3,50 m şi se sprijină<br />
provizoriu bolta existenta în front, cu cintre demontabile;<br />
• Se execută sapatura la cotele din proiect pentru realizarea<br />
radierului pe o lungime de 3,0m;<br />
• Se montează cintrele metalice pierdute la extradosul ţevilor;<br />
• Se montează tolele metalice sudate de cintre pe tronsonul<br />
pe care s-a betonat radierul;<br />
• Se realizează rostul total cu 2 foi de carton bitumat între<br />
bolţari la nivelul radierului;<br />
Fig. 7 Armare şi betonare boltă.<br />
• Se execută hidroizolaţia şi se petrece cu cea executată în<br />
etapa anterioară;<br />
• Se completează betonul de egalizare de 15 cm grosime;<br />
• Se armează, se cofrează şi se betonează tronsonul 1 de<br />
radier al urmatorului inel;<br />
Etapa 6 – Execuţia ultimului tronson de bolta al inelului 1<br />
• Se armează, se cofreaza şi se betonează al treilea tronson de<br />
2,00 m, al primului inel;<br />
• Se realizează rostul total cu 2 foi de carton bitumat între<br />
inele la nivelul bolţii;<br />
Se repetă etapele 2,3,4,5 si 6, pana se finalizează podeţul<br />
Fig. 8 Imagini finale timpan aval şi amonte<br />
meters length<br />
UNDERGROUND CONSTRUCTIONS<br />
Stage 5- Construction of the second arch section, L=2m, and<br />
the first invert section, L=3.00m for a new ring.<br />
• reinforcement and encasement are performed, then the<br />
second arch section L=2.00 m of the first ring is concreted;<br />
• existing structure is demolished on a 3.50 m length and the<br />
existing arch is temporarily supported by removable frame<br />
steelworks<br />
• an excavation is performed based on the blueprint in order<br />
to construct the invert on a 3.0 m length<br />
• frame steelworks are put in place at the pipes’ intrados<br />
• metallic end plates welded on frame steelworks are<br />
installed in the section where the invert was concreted<br />
• total joint is made using 2 asphalt board sheets in between<br />
the lining segments at the invert level.<br />
Figure 7 Arch reinforcement and concreting<br />
• waterproofing is performed and meets the one performed<br />
during the previous stage<br />
• the levelling concrete is completed up to a 15 cm thickness<br />
• invert section 1 of the next ring is reinforced, cased and<br />
concreted.<br />
Stage 6 – Construction of last arch section of ring 1<br />
• reinforcement and encasement are performed, then the third<br />
arch section of 2 m length of the first ring is concreted;<br />
• total joint is made using 2 asphalt board sheets in between<br />
the rings at the arch level<br />
Stages 2, 3, 4, 5 and 6 are repeated until the culvert is completed<br />
Fig. 8 Final images end element upstream and downstream<br />