13.08.2013 Views

Abstracts of Remediation Case Studies, Volume 7 - Federal ...

Abstracts of Remediation Case Studies, Volume 7 - Federal ...

Abstracts of Remediation Case Studies, Volume 7 - Federal ...

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Electrical Resistive Heating at the Avery Dennison Site,<br />

Waukegan, Illinois (continued)<br />

Description:<br />

The Avery Dennison site is located in the Waukegan-Gurnee Industrial Park in Waukegan, Illinois. From 1975 through<br />

1992 film coating operations were performed at the site. Methylene chloride (MeCl) used in these operations was<br />

unloaded in the northeast corner <strong>of</strong> the building, and transferred by underground piping to above-ground storage tanks in<br />

the northwest corner <strong>of</strong> the building. In May 1985, an inventory check indicated that approximately 1,585 gallons <strong>of</strong> MeCl<br />

was released from the underground pipe. Site investigations indicated that the released MeCl was present in the soil and<br />

groundwater beneath the loading area, the bulk storage tank area, the underground transfer pipe, and a former stormwater<br />

drainage system. Cleanup activities at the site performed from 1985 through 1998 included excavation, soil vapor<br />

extraction, groundwater pump and treat, and air sparging. The results <strong>of</strong> additional investigations indicated that DNAPL<br />

was present in soil at the site. ERH was used from December 1999 through November 2000 to address the DNAPL source<br />

in the unsaturated zone.<br />

The ERH system included 95 copper electrodes installed around the perimeter <strong>of</strong> 20 treatment cells, including six<br />

electrodes installed below an active street, and sixteen installed inside the existing building. Thirty four recovery wells<br />

were installed to extract <strong>of</strong> soil vapor and steam. Two thermocouples were installed in the center <strong>of</strong> each treatment cell, at<br />

the shallowest (4 ft) and deepest (24 ft) levels <strong>of</strong> contamination. ERH was performed in the western portion <strong>of</strong> the<br />

treatment zone starting in December 1999 and in the eastern portion <strong>of</strong> the treatment zone starting in June 2000. During<br />

the first four weeks <strong>of</strong> operation, the system did not achieve the target heating rate and power input to the subsurface. The<br />

vendor found that the electrodes had oxidized and that the down hole power cables had been damaged. System<br />

modifications included installing galvanized steel pipes around the electrodes and using above-ground power cables. The<br />

system was restarted and achieved the target heating rate and soil temperature, though the power input remained below the<br />

design level. With the exception <strong>of</strong> four treatment cells, the concentrations <strong>of</strong> methylene chloride were reduced to below<br />

cleanup goals by October 2000. Additional electrodes were added to these cells and the system was operated another<br />

month to meet the cleanup goals. No cost data were available for this application.<br />

25

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!