shall not be accepted by <strong>the</strong> OWNER as basis for any claims for compensation.<br />

39.0 Work covered under this specification shall be completed in all respects, as stipulated<br />

under scope of work.<br />

40.0 ACCEPTANCE / REJECTION OF BID<br />

40.1 GSECL reserves <strong>the</strong> right to accept or reject any bid in whole or part and/or accept o<strong>the</strong>r<br />

than <strong>the</strong> lowest bid without assigning any reasons.<br />

40.2 The bid is liable for rejection prima facie, if it is:<br />

a. Not in <strong>the</strong> prescribed form.<br />

b. Not properly signed by <strong>the</strong> BIDDER.<br />

c. Not conforming to TENDER specification.<br />

d. Received after expiry of <strong>the</strong> due date and time.<br />

e. Received by telex or telegram or fax.<br />

41.0 SUBMISSION OF TENDER<br />

41.1 The tender must reach to <strong>the</strong> office of I/C Chief Engineer, GSECL, GBPS, Utran, Dist.<br />

Surat on or before due date and time of submission mentioned in tender notice. No<br />

tender shall be accepted/opened in any case received after due date and time of receipt<br />

of tender, irrespective of delay due to postal services or any o<strong>the</strong>r reasons, and <strong>the</strong><br />

GSECL shall not take any responsibility for late receipt of tender. Any tender received<br />

after <strong>the</strong> due date and time of submission shall not be considered.<br />

41.2 GSECL reserves <strong>the</strong> right to delete any item of schedule-B for which contractor shall not<br />

Have any right to claim on this account.<br />

42.0 During <strong>the</strong> execution of <strong>the</strong> work if it is found that <strong>the</strong> work is not progressing as per<br />

<strong>the</strong> scheduled programme, approved by <strong>the</strong> GSECL & planned by <strong>the</strong> contractor, due to<br />

<strong>the</strong> reasons attributable to <strong>the</strong> contractor, suitable action shall be taken as per Clause No.<br />

2, 3 & o<strong>the</strong>r relevant clauses appearing in <strong>the</strong> section of “Tender and Contract for<br />

works” of tender document. And <strong>the</strong> GSECL may also take such action as it may deem<br />

fit to ensure that <strong>the</strong> work is completed in time at Risk and cost of <strong>the</strong> contractor.<br />

I/c Addl.Chief Engineer<br />

GSECL, GBPS, UTRAN.<br />