8301 – RGRTA Suburban Transit Station Study<br />
Objective:<br />
To assess the performance and effectiveness of the current RTS park-and-ride route<br />
structure and further refine and define the suburban transfer center concept.<br />
Classification: Planning/Policy (Anticipated)<br />
Participants: RGRTA (Lead Agency), GTC staff<br />
Budget:<br />
Sources of Funds<br />
Uses of Funds<br />
<strong>FY</strong> <strong>2010</strong>-11 <strong>FY</strong> <strong>2010</strong>-11<br />
Federal Funds<br />
GTC<br />
FHWA $0 Staff $0<br />
FTA 75,000 Contractual 0<br />
Subtotal $75,000 Subtotal $0<br />
Matching Funds<br />
Other Agency<br />
State (In-kind) $0 Staff $0<br />
Local (In-kind) 10,000 Contractual 75,000<br />
Local (Cash) 0 In-kind Exp. 10,000<br />
Subtotal $10,000 Subtotal $85,000<br />
Total $85,000 Total $85,000<br />
(This <strong>Task</strong> is carried over from the <strong>FY</strong> 2009-<strong>2010</strong> <strong>UPWP</strong> for completion in <strong>FY</strong> <strong>2010</strong>-<strong>2011</strong>; federal funds<br />
reflect amount carried over from original allocation of $75,000.)<br />
Process:<br />
Conduct an assessment of existing park-and-ride route structure and develop alternative<br />
concepts and strategies for serving suburban locations. Assess an enhanced route structure<br />
that includes express routes between major trip generators (i.e. downtown, U of R Medical<br />
Center). Develop projected ridership impacts, operational impacts, revenue vehicle<br />
requirements, capital costs and operating costs. Investigate the feasibility of developing<br />
multi-use satellite transit centers that would include tenants (i.e. daycare centers and<br />
convenience stores) and development partners (housing, retail, commercial).<br />
Schedule: 1. Scope of work approved April/May <strong>2010</strong><br />
2. Consultant selection completed September/October <strong>2010</strong><br />
3. Project initiation meeting November/December <strong>2010</strong><br />
4. Inventory of conditions completed March/April <strong>2011</strong><br />
5. Needs assessment completed May/June <strong>2011</strong><br />
6. First public meeting May/June <strong>2011</strong><br />
7. Alternatives developed July/August <strong>2011</strong><br />
8. Recommendations selected September/October <strong>2011</strong><br />
9. Second public meeting November/December <strong>2011</strong><br />
10. Draft report completed January/February 2012<br />
11. Final report completed January/February 2012<br />
Products:<br />
1. Final Report and Executive Summary on findings and recommendations<br />
2. Project steering committee and public meeting material<br />
83