• Increm entII<br />

• SubstantialCompletion Jan 25,2009 (A)<br />

• InteriorS -Punch List/ Clean-up Jan 25,2010 (A)<br />

• FinalCompletion Feb 05,2010 (P)<br />

• Increm entI<br />

• Building S Earthwork Aug 03,2009 (A)<br />

• Parking LotSite Work Aug 03,2009 (A)<br />

• ModularRestroom s Utilities Aug 03,2009 (A)<br />

• Bldgs.B,E,T,L,G Fire Alarm Aug 10,2009 (A)<br />

• Bldgs.J & M Restroom s O ct02,2009 (A)<br />

• Bldg.Q 10 Demolition Dec 28,2009 (A)<br />

• Bldg.F South Modernization Jan 08,2010 (A)<br />

• Bldg.K Modernization May 07,2010 (P)<br />

• Bldg.R Modernization Jul30,2010 (P)<br />

• Bldg.R New Construction Jul30,2010 (P)<br />

• Bldgs.D,P,Q Fire Alarm Jul30,2010 (P)<br />

• Fire Alarm System Activation Jul30,2010 (P)<br />

• Bldgs.J5 & J6 Demolition Jul30,2010 (P)<br />

• FinalCompletion Jul30,2010 (P)<br />

• Building E (Re-Bid)<br />

• FirstAdvertisem entApr06,2010 (P)<br />

• Job Walks Apr13,2010 (P)<br />

• Bids Opening Apr28,2010 (P)<br />

• Board Award ofContracts May 05,2010 (P)<br />

• NTP Issuance May 14,2010 (P)<br />

• StartofConstruction May 14,2010 (P)<br />

• FinalCompletion Aug 12,2010 (P)<br />

• Site SewerLine Relocation<br />

• Job Walks Feb 11,2010 (A)<br />

• Bids Opening Mar02,2010 (A)<br />

• Board Award ofContracts Mar31,2010 (A)<br />

• StartofConstruction Jun 07,2010 (P)<br />

• SubstantialCompletion Jul30,2010 (P)<br />

• FinalCompletion Aug 04,2010 (P)<br />

• (A):Actual(P):Projected