• Increm entII • SubstantialCompletion Jan 25,2009 (A) • InteriorS -Punch List/ Clean-up Jan 25,2010 (A) • FinalCompletion Feb 05,2010 (P) • Increm entI • Building S Earthwork Aug 03,2009 (A) • Parking LotSite Work Aug 03,2009 (A) • ModularRestroom s Utilities Aug 03,2009 (A) • Bldgs.B,E,T,L,G Fire Alarm Aug 10,2009 (A) • Bldgs.J & M Restroom s O ct02,2009 (A) • Bldg.Q 10 Demolition Dec 28,2009 (A) • Bldg.F South Modernization Jan 08,2010 (A) • Bldg.K Modernization May 07,2010 (P) • Bldg.R Modernization Jul30,2010 (P) • Bldg.R New Construction Jul30,2010 (P) • Bldgs.D,P,Q Fire Alarm Jul30,2010 (P) • Fire Alarm System Activation Jul30,2010 (P) • Bldgs.J5 & J6 Demolition Jul30,2010 (P) • FinalCompletion Jul30,2010 (P) • Building E (Re-Bid) • FirstAdvertisem entApr06,2010 (P) • Job Walks Apr13,2010 (P) • Bids Opening Apr28,2010 (P) • Board Award ofContracts May 05,2010 (P) • NTP Issuance May 14,2010 (P) • StartofConstruction May 14,2010 (P) • FinalCompletion Aug 12,2010 (P) • Site SewerLine Relocation • Job Walks Feb 11,2010 (A) • Bids Opening Mar02,2010 (A) • Board Award ofContracts Mar31,2010 (A) • StartofConstruction Jun 07,2010 (P) • SubstantialCompletion Jul30,2010 (P) • FinalCompletion Aug 04,2010 (P) • (A):Actual(P):Projected
<strong>William</strong> S. <strong>Hart</strong> <strong>Union</strong> <strong>High</strong> <strong>School</strong> <strong>District</strong> Modernization Update May 19, 2010