Drilling at the Mango Prospect has confirmed a new discovery of copper‐silver mineralisation<br />
at both ends of what is believed <strong>to</strong> be a 36 kilometre prospective horizon.<br />
<br />
Mid Kalahari Zone (targeting new standalone mining operation)<br />
o<br />
The seven Ghanzi district prospecting licences (first granted in 2008) have been renewed for<br />
two years.<br />
o Initial drill testing of Ourea, Kronos, Notus and Hemera Prospects was completed. Assay<br />
results are anticipated <strong>to</strong> be available for release in the December quarter.<br />
<br />
South‐west Kalahari Zone (targeting new standalone mining operations)<br />
o<br />
Corporate<br />
Soil sampling continued at the Hermes target.<br />
<br />
The project finance package was completed and US$115 million of $205 million available drawn down<br />
in three tranches during the quarter <strong>to</strong> meet expected payments until the end of Oc<strong>to</strong>ber.<br />
<br />
The Company entered in<strong>to</strong> a commodity price protection strategy by hedging 40% of forecast copper<br />
income and 65% of forecast silver income for the period from <strong>July</strong> 2012 <strong>to</strong> March 2015 at average<br />
future strike prices of US$4.01/lb for copper and US$36.07 for silver.<br />
<br />
<strong>Discovery</strong> Metals had US$118 million in cash and had drawn down US$115 million of Bose<strong>to</strong> project<br />
financing at <strong>30</strong> <strong>September</strong>.<br />
1. Bose<strong>to</strong> Copper Project Development Progress (‘Bose<strong>to</strong>’ or ‘the<br />
Project’)<br />
The Engineering Procurement and Construction (EPC) contract <strong>to</strong> construct the 3 million <strong>to</strong>nnes per annum<br />
Bose<strong>to</strong> processing plant and related works commenced in <strong>September</strong> 2010. <strong>Activities</strong> in the <strong>September</strong> <strong>2011</strong><br />
quarter included finalisation of off‐site engineering and procurement with most items delivered <strong>to</strong> site. Onsite<br />
works included erection of structural steelwork, installation of plant, equipment, piping and electrical<br />
works. The construction timeline remains on schedule <strong>to</strong> allow commencement of commissioning of the<br />
process plant in first half of 2012. Bose<strong>to</strong> project progress for the quarter was:<br />
o Engineering and procurement neared completion;<br />
o Toteng housing contracts awarded and works commenced;<br />
o Delivery of mine mobile equipment (including spare parts and tyres) commenced <strong>to</strong> enable ontime<br />
commencement of mining operations;<br />
o Structural concrete for the process plant has been completed;<br />
o Erection of structural steelwork for the process plant continued;<br />
o Installation of plant, equipment, piping and electrical commenced;<br />
o Construction of the mine offices & workshops continued;<br />
o Pipe and power lines for the Project’s water supply progressed;<br />