o Delivery and commissioning of mobile equipment commenced; and<br />
o The first two of the eight 2.5 megawatt diesel powered genera<strong>to</strong>rs arrived on site in early<br />
Oc<strong>to</strong>ber.<br />
Construction of the project has been significantly advanced over the quarter. Pho<strong>to</strong>graphs included in this<br />
release show that the primary, secondary and tertiary crushers have been installed, the screening plant is<br />
erected, the ball mill is in place and float cells have been placed upon their concrete support structures. All<br />
major components are on site and work has commenced on the electrical and piping packages of work.<br />
Work continues <strong>to</strong> complete erection of the fine ore bin and the concentrate shed and work has<br />
commenced <strong>to</strong> construct the Run Of Mine (ROM) ore pad adjacent <strong>to</strong> the primary crusher.<br />
The latest estimate <strong>to</strong> complete the Bose<strong>to</strong> capital works project show that the project is expected <strong>to</strong> be<br />
completed within the US$175 million approved budget. The separate estimate of US$75 million for the<br />
procurement and delivery of the mobile mine equipment is also in line with budget estimates. The<br />
Company has maintained progress in line with the schedule set in August 2010.<br />
Monthly progress of the Bose<strong>to</strong> construction can be tracked pic<strong>to</strong>rially on the Company’s website.<br />
Aerial view of construction site – plant site (lower), infrastructure area (middle).<br />