preliminary interconnection feasibility assessment. This study showed that a system redispatch<br />

would solve any post-contingency overloads in the 138kv circuits created by the<br />

interconnection of the Project. <strong>Deepwater</strong> also commissioned Siemens PTI to prepare an<br />

interface analysis, which shows that the Project does not violate any of the major<br />

interfaces. Accordingly, <strong>Deepwater</strong> has a high degree of confidence in the technical<br />

ability to interconnect and deliver power from the Project.<br />

<strong>Deepwater</strong> has been working with LIPA on two interconnection requests since 2008 and<br />

is committed to complying with the capacity deliverability requirements, both those of<br />

the NYISO and LIPA itself. <strong>Deepwater</strong> is preparing to submit an interconnection<br />

request to the NYISO for the Shoreham 138 kV substation and will seek to obtain<br />

Capacity Resource Interconnection Service.<br />

!<br />

20