12.03.2014 Views

Volume-IF - JantERmantER

Volume-IF - JantERmantER

Volume-IF - JantERmantER

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

TENDER NO<br />

VOLUME<br />

PSER:SCT:DPL-C1154:10<br />

<strong>IF</strong> TECHNICAL CONDITIONS OF CONTRACT<br />

&<br />

SCOPE, DRAWINGS, ETC<br />

JOB CONSTRUCTION OF 220M HIGH RCC SINGLE<br />

FLUE BRICK LINED CHIMNEY INCLUDING<br />

SUPPLY, ERECTION, COMMISSIONING ETC OF<br />

EQUIPMENTS/ MATERIAL, COMPLETE.<br />

CAPACITY 1x250 MW<br />

PROJECT DPL, DURGAPUR, WEST BENGAL.<br />

BHARAT HEAVY ELECTRICALS LIMITED<br />

(A Govt Of India Undertaking)<br />

POWER SECTOR – EASTERN REGION<br />

PLOT – DJ 9/1, SECTOR II, SALT LAKE<br />

KOLKATA – 700 091


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 1 OF 7<br />

INDEX<br />

CLAUSE DESCRIPTION<br />

NO<br />

1.0 BROAD SCOPE OF WORK<br />

2.0 SITE VISIT<br />

3.0 INSURANCE<br />

4.0 TAXES, DUTIES ETC<br />

5.0 SECURITY DEPOSIT<br />

6.0 PERFORMANCE BOND<br />

7.0 COMPLETION PERIOD<br />

8.0 SCHEDULE OF SUPPLY<br />

9.0 INTEREST BEARING RECOVERABLE ADVANCE<br />

10.0 PAYMENT TERMS<br />

11.0 PRICE VARIATION COMPENSATION (PVC)<br />

12.0 OVER RUN CHARGE<br />

13.0 GUARANTEE<br />

14.0 LIQUIDATED DAMAGE/ COMPENSATION FOR DELAY<br />

15.0 CONTRACT PRICE<br />

16.0 MATERIAL DESPATCH CLEARANCE CER<strong>IF</strong>ICATE (MDCC)<br />

17.0 MATERIAL RECEIPT CERT<strong>IF</strong>ICATE (MRC)<br />

18.0 CONSIGNEE<br />

19.0 DESPATCH<br />

20.0 INSPECTION & JOINT VER<strong>IF</strong>ICATION(AT CONTRACTOR’S WORKS)<br />

21.0 INSPECTION & JOINT VER<strong>IF</strong>ICATION (AT SITE)<br />

22.0 QUALITY PLAN<br />

23.0 DIVISIBLE CONTRACT<br />

24.0 OTHER TERMS


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 2 OF 7<br />

This volume shall be construed as part of tender document and shall be read along-with others<br />

volumes of tender. In case of any conflict or inconsistency between the general and technical<br />

conditions, the same shall be brought out by the bidder in writing to BHEL for clarification during<br />

pre-bid discussions; failing which most stringent interpretation/ clause in favour of BHEL shall be<br />

adopted and the same shall be binding to the bidder.<br />

CLAUSE DESCRIPTION<br />

NO<br />

1.0 BROAD SCOPE OF WORK<br />

The work to be done broadly under this specification comprises of design,<br />

engineering, manufacturing, assembly, inspection, testing at manufacturer’s/ subvendor’s<br />

works, painting, proper packing, transportation, delivery, handing over at<br />

site of materials as detailed in the specification and elsewhere in the tender<br />

document (as covered in Part-2 of price schedule, <strong>Volume</strong>-IIIA). However,<br />

completeness of the supply for completion of the package is to be ensured by the<br />

bidder.<br />

2.0 SITE VISIT<br />

Bidder should visit site and acquire full knowledge & information about site<br />

conditions prevailing at site and in and around the plant premises at together with<br />

all the statutory, obligatory, mandatory requirements of various authorities before<br />

submission of the bid.<br />

3.0 INSURANCE<br />

3.1 BHEL shall arrange comprehensive MCE insurance policy covering transit risk &<br />

loss. Bidder shall be responsible for timely intimation of loss/ damage/ theft to the<br />

underwriter, assistance in lodging & settlement of claim for losses/ damages/ theft.<br />

3.2 Other provisions of insurance shall be as stipulated under relevant clauses of GCC.<br />

4.0 TAXES, DUTIES ETC<br />

4.1 EXCISE DUTY<br />

4.1.1 Excise duty actually incurred by seller/ contractor on self manufactured items<br />

against the despatch made from his factory/ works constituting a sale under the<br />

order/ contract, alone shall be reimbursed at actual against requisite documentary<br />

evidence limited to the quoted value.<br />

4.1.2 The invoice cum Excise Duty gate pass (Excise Invoice) should contain the name<br />

of ultimate consignee as specified in the order/ contract.<br />

4.1.3 No excise duty shall be payable by purchaser on inputs, bought out items, raw<br />

materials and components consigned directly to site from sources other than seller/<br />

contractor's factory/ works.<br />

4.1.4 The seller/ contractor is required to ensure that excise duty is properly calculated<br />

and paid and exemption and benefits are fully availed of.<br />

4.1.5 Bidder to consider the benefit of CENVAT in their quoted basic price.<br />

4.1.6 If the seller/ contractor claims/ obtains any refund of the excise duty paid and gets<br />

reimbursed, the same shall be refunded to the purchases immediately.<br />

4.1.7 Excise duty shall be paid at actual but restricted to the amount and percentage<br />

shown in the order/ contract. Additional excise duty due to statutory variation, if<br />

imposed after due date of submission of latest price offer and within contract period<br />

including extension, if any (provided reason for extension is not attributable to<br />

vendor), will be reimbursed at actual by BHEL.<br />

4.1.8 No statutory variations shall be permissible beyond the contractual period.<br />

4.2 CENTRAL SALES TAX<br />

4.2.1 Central Sales tax shall be payable extra, limited to the quoted value on submission<br />

of invoice, if the same is payable by the bidder to the respective Government<br />

Authorities meeting all statutory requirements and availing all exemption/<br />

concessions under the Central Sales Tax Act, 1956. Bidder shall show CST<br />

separately in the invoice for inter-state sales at prevailing rate.<br />

4.2.2 Sales tax on bought out items paid/ payable by bidder to the sub-vendors shall be<br />

borne by bidder and shall not be invoiced to/ paid extra by BHEL.<br />

4.2.3 BHEL proposes to make sale in transit as per Sec 6(2) (b) of the CST Act, 1956


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 3 OF 7<br />

where goods are moving inter-state. “C” Form shall be issued and exchanged<br />

against E-I/II Certificates based on quarterly transaction. The bidder is required to<br />

submit his request within 10 (ten) days from the end of the quarter in the specified<br />

format. No concessional forms shall be issued for goods moving within the state.<br />

4.2.4 In order to obtain the benefit of Transit Sale exemption U/S 6(2), following mode of<br />

documentation shall be followed.<br />

4.2.4.1 FOR SELF MANUFACTURED ITEMS OF VENDORS<br />

In case of BOP, steel & cement, vendor’s LR/ RR/ GR/ CN must the bear the name<br />

of BHEL as `Consignee’. BHEL will endorse the following words on the back of<br />

despatch documents, ie LR/ RR/ GR/ CN prior to the date of receipt of materials by<br />

BHEL at site, ie after movement commences and before it terminate.<br />

`Please deliver the goods to (State customer’s name & address), (State customer’s<br />

CST No)’.<br />

Name of authorized signatory of BHEL’s MM department: ____________<br />

Date:<br />

Signature:<br />

____________<br />

____________<br />

4.2.4.2 FOR BOUGHT-OUT ITEMS OF VENDORS:<br />

4.2.4.2.1 STEP-1<br />

Sub-vendors’ LR/ RR/ GR/ CN must the bear the name of vendor as `Consignee’.<br />

Vendor must endorse the following words on the back of despatch documents, ie<br />

LR/ RR/ GR/ CN prior to the date of receipt of materials by vendor, ie after<br />

movement commences and before it terminates.<br />

`Please deliver the goods to (State BHEL’s site’s name & address), (State BHEL’s<br />

CST No)’.<br />

Name of authorized signatory of vendor: _________________________<br />

Date:<br />

Signature:<br />

_________________________<br />

_________________________<br />

4.2.4.2.2 STEP-2<br />

BHEL must endorse the following words on the back of despatch documents, ie LR/<br />

RR/ GR/ CN prior to the date of receipt of materials by BHEL at site, ie after<br />

movement commences and before it terminates.<br />

`Please deliver the goods to (State customer’s name & address), (State customer’s<br />

CST No)’.<br />

Name of authorized signatory of BHEL’s MM department: ____________<br />

Date:<br />

Signature:<br />

____________<br />

____________<br />

4.2.5 If documents are submitted through bank, issuance of “C” Form shall not be<br />

insisted upon at the time of retirement of document(s).<br />

4.2.6 BHEL, PSER is registered with the Sales Tax authority in the state under the<br />

Central Sales Tax Act, 1956.<br />

4.3 VALUE ADDED TAX<br />

4.3.1 The bidder must be registered with the sales tax authority in the state for supply<br />

from the state. The bidder must produce copy of the Registration Certificate issued


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 4 OF 7<br />

by the Sales Tax Authority. The bidder must issue “TAX INVOICE” showing VAT<br />

charged separately in case of supply from the state.<br />

4.3.2 Bidder to consider the benefit of Input Credit of VAT in their offer.<br />

4.3.3 VAT shall be payable extra, limited to the quoted value on all items supplied from<br />

the state on submission of Invoice & as per tariff applicable, if the same is payable<br />

by bidder to the respective Government authorities meeting all statutory<br />

requirements and availing all exemption/ concessions under the state Value Added<br />

Tax Act, 2003.The tax invoice pertaining to supplies made in a quarter must be<br />

presented within that quarter so as to enable BHEL to take input credit within that<br />

quarter. If BHEL is denied of the benefit of Input Credit due to late/ non submission<br />

of “TAX INVOICE”, VAT shall not be paid at all.<br />

4.3.4 BHEL is registered with Sales Tax authority in the state under the state Value<br />

Added Tax Act, 2003 have the Registration Certificate.<br />

4.4 COMMON FOR CST AND VAT<br />

Any variation on ST/ VAT, if imposed subsequently by statutory authority, after due<br />

date of submission of latest price offer as per NIT & TCN, as applicable, and within<br />

the contract period including extension, if any, (provided reason for extension is not<br />

attributable to vendor) shall be paid by BHEL on production of relevant supporting<br />

document to the satisfaction of BHEL.<br />

4.5 CUSTOMS DUTY<br />

4.5.1 Customs Duty element for imported items shall be included in basic prices. No<br />

variation in customs duty and exchange rate for imported items shall be payable by<br />

purchaser.<br />

4.5.2 Seller/ contractor shall arrange for his own import license, if required, since<br />

purchaser will not provide any import license since purchaser will not provide any<br />

import license. Therefore, seller/ contractor alone shall be responsible for any delay<br />

in getting import license or non-availability of the same or completion of other<br />

related formalities. Purchaser shall not be responsible for any financial liability,<br />

whatsoever, on this account.<br />

4.6 DIRECT TAX<br />

Purchaser shall not be liable towards income tax of whatever nature including<br />

variations thereof, arising out of this order/ contract, as well as tax liability of the<br />

seller/ contractor and his personnel.<br />

4.7 New tax & duties, if imposed subsequent to latest due date of offer submission, as<br />

per NIT & TCN, as applicable, by statutory authority after due date of submission of<br />

latest price offer and within the contract period including extension, if any (provided<br />

reason for extension is not attributable to vendor), shall be reimbursed by BHEL at<br />

actual on production of relevant supporting document to the satisfaction of BHEL.<br />

However, the vendor shall obtain prior approval from BHEL before depositing new<br />

taxes & duties.<br />

4.8 Benefits of abolition and reduction of ED, CST & VAT on self manufactured items<br />

will be passed on to BHEL.<br />

4.9 All taxes & duties shall be paid, as applicable, limited to amounts indicated in the<br />

break up prices as indicated above. These shall be directly paid by contractor to the<br />

respective statutory authorities. Taxes and duties paid by sub vendors of contractor<br />

will not be reimbursed by BHEL.<br />

4.10 The seller/ contractor is required to ensure that taxes, duties etc, as applicable, are<br />

properly calculated & paid and exemption and benefits, as applicable, are fully<br />

availed of. BHEL shall not be held responsible on account of any fault on the part of<br />

vendor in this regard.<br />

4.11 Other than above, no taxes & duties are payable.<br />

5.0 SECURITY DEPOSIT<br />

Security deposit for this part of specification shall also be governed by the provision<br />

of GCC. Alternately, bidder may submit bank guarantee equivalent to 100 % of<br />

security deposit as per provision of GCC.<br />

6.0 PERFORMANCE BOND<br />

6.1 The bidder will have to execute a performance bond covering his entire scope of


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 5 OF 7<br />

supply (Part-2 of the price schedule) to be kept valid as per terms of tender.<br />

6.2 Performance bond shall be submitted as per tender provision.<br />

7.0 COMPLETION PERIOD<br />

Entire materials under the scope shall be dispatched to reach site within 29 (Twenty<br />

nine) months from the date of confirmation/ intimation from BHEL in writing.<br />

8.0 SCHEDULE OF SUPPLY<br />

The vendor shall furnish the L-1, L-2/ L-3 schedule indicating break-up of supply of<br />

various items under the specification matching with project schedule as referred in<br />

the tender within the stipulated completion period.<br />

9.0 INTEREST BEARING RECOVERABLE ADVANCE<br />

Not applicable for this tender.<br />

10.0 PAYMENT TERMS<br />

10.1 For all items of work as per price schedule of main supply (Part-2), <strong>Volume</strong>-IIIA,<br />

payment shall be made as per following break-up.<br />

10.1.1 5 % of basic price against submission and approval of all design document, such as<br />

data sheet, quality plan etc. Documents (required sets) required for such payment<br />

are as follows.<br />

10.1.1.1 Invoice in original.<br />

10.1.1.2 Certificate of BHEL as regard to completion of activity.<br />

10.1.2 80 % of basic price of materials supplied along with 100 % ED, CST & VAT, as<br />

applicable, against dispatch document on pro-rat basis. Documents (required sets)<br />

required for such payment are as follows.<br />

10.1.2.1 Invoice/ excisable invoice in original.<br />

10.1.2.2 LR/ RR (consignee copy).<br />

10.1.2.3 Packing list.<br />

10.1.2.4 MDCC enclosing QS note, test certificate.<br />

10.1.2.5 Copy of letter, addressed to insurance company intimating dispatch.<br />

10.1.3 15 % of basic price along with 100 % freight & other charge shall be released on<br />

pro-rata basis against receipt of material at site. Documents (required sets)<br />

required for such payment are as follows.<br />

10.1.3.1 Invoice in original.<br />

10.1.3.2 MRC issued by BHEL site.<br />

10.2 10 % of gross bill amount except taxes & duties shall be retained from each bill<br />

which shall be released along with final bill on completion of total chimney work.<br />

Documents (required sets) required for such payment are as follows.<br />

10.2.1 Invoice in original.<br />

10.2.2 Certificate of BHEL site as regard to completion of activity.<br />

10.3 In case freight component is not indicated by bidder in the price offer separately, 2<br />

% of basic amount shall be taken into account as freight component and payment<br />

will be made accordingly as per the payment terms.<br />

10.4 Payment shall be made by BHEL site offices within 30 days of receipt of invoice<br />

subject to its completeness in all respects as per BHEL’s procedure. All admissible<br />

recovered/ adjustments etc shall be made from the interim payable amount.<br />

10.5 BHEL, at discretion, any further split up the above percentages and effect payment<br />

to suit the site condition, cash flow requirement, according to the progress of work.<br />

10.6 No bills including RA bills will be paid to individual consortium partners in case of<br />

consortium arrangement.<br />

11.0 PRICE VARIATION COMPENSATION (PVC)<br />

Not applicable for this part of tender.<br />

12.0 OVER RUN CHARGE<br />

No over run charge shall be applicable for this tender.<br />

13.0 GUARANTEE<br />

13.1 The contractor shall warrant that the (shall mean the goods and machinery/<br />

components/ parts and spares etc specified in the contract/ order which the<br />

contractor agreed to supply with the contract/ order to complete the jobs for<br />

satisfactory working of stores, generating the parameters stipulated in the tender<br />

document) supplied shall be free from all defects and faults in design, material,


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 6 OF 7<br />

workmanship and manufacture and shall be of highest grade and consistent with<br />

the established and generally accepted standards form the stores of the type<br />

ordered in full conformity with the order/ contract, specification, drawing or samples,<br />

if any.<br />

13.2 The guarantee shall be valid for a period of 12 calendar months from the date of<br />

completion of PG test of unit. Any approval or acceptance by BHEL/ owner therein,<br />

shall not in any way limit the contractor’s liability. The contract’s liability in respect of<br />

any complaints, defects and/ or claims shall be limited to be the furnishing and<br />

installation of the replaced part free of charges, or the repair of the defective parts<br />

only to the extent that such replacement or replacements are attributable to or arise<br />

from faulty workmanship, material or design in the manufacture of the stores or at<br />

the option of BHEL/ owner, to the payment of the value, expenditure and damages<br />

as hereunder mentioned provided defect are brought to the notice of the contractor<br />

within 3 months of their being first discovered during the guarantee period 3 months<br />

from the date of expiry of the guarantee period.<br />

13.3 The contractor shall, if required, replace, or repair the stores of such portion<br />

thereof, as is rejected by BHEL/ owner free of cost at the site or at the option of<br />

BHEL/ owner the contractor shall pay to BHEL/ owner value thereof at the order/<br />

contract price and such other expenditure and damages, as may arise by reason of<br />

the condition therein specified.<br />

13.4 All replacement and repairs that BHEL/ owner shall call upon the contractor to<br />

deliver or perform under the guarantee shall be delivered free of cost and<br />

performed promptly and satisfactorily by the contractor within 3 months, if the<br />

contractor so desires and BHEL/ owner agrees subject to import contract<br />

regulation, the replaced parts can be taken over by him or his representative or the<br />

same can be arranged to be dispatched by the contractor or his representative at<br />

the contractor’s cost as he deems fit within a period of 3 months from the date of<br />

replacement of stores/parts. At the expiry of this period no claim whatsoever, shall<br />

be with BHEL/owner.<br />

13.5 All replacement stores shall also be guaranteed as per above clause.<br />

13.6 The decision of BHEL/ owner in this regard to contractor’s liability and the amount,<br />

if any, payable under this guarantee shall be final and conclusive.<br />

14.0 LIQUIDATED DAMAGE/ COMPENSATION FOR DELAY<br />

As per the provision of GCC.<br />

15.0 CONTRACT PRICE<br />

Bidder shall quote rates/ price as per the format of <strong>Volume</strong>-IIIA. Separate order will<br />

be placed for supply part as per the price components of respective schedules.<br />

16.0 MATERIAL DESPATCH CLEARANCE CER<strong>IF</strong>ICATE (MDCC)<br />

16.1 MDCC shall be issued by BHEL/ owner or their authorized representative prior to<br />

dispatch. In case the tests are not witnessed by BHEL/ owner/ owner’s<br />

representative, the test certificates shall be submitted to owner through BHEL and<br />

MDCC will be issued thereafter.<br />

16.2 Copy of MDCC and other dispatch document shall accompany with every dispatch,<br />

failing which the consignment shall not be allowed to enter the project premises.<br />

17.0 MATERIAL RECEIPT CERT<strong>IF</strong>ICATE (MRC)<br />

MRC shall be issued by BHEL/ owner or their authorized representative after the<br />

material is received at site in good condition.<br />

18.0 CONSIGNEE<br />

Shall be intimated to bidder on later date.<br />

19.0 DESPATCH<br />

19.1 Despatch shall only be made only by road transport after inspection and issue of<br />

MDCC by BHEL/ owner.<br />

19.2 Each package should carry the packing slip/ details of contents and should be put<br />

inside a metal enclosure, properly fixed to the packing from outside.<br />

19.3 No consignment shall be dispatched on SELF basis. Material shall be despatched<br />

on pre-paid, door delivery basis.<br />

19.4 The packing shall be in such as to ensure prevention of damage, corrosion,


VOLUME-<strong>IF</strong><br />

(SUP)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SUPPLY)<br />

PAGE 7 OF 7<br />

pilferage, deterioration, loss in transit or storage and road-worthy.<br />

20.0 INSPECTION & JOINT VER<strong>IF</strong>ICATION (AT CONTRACTOR’S WORKS)<br />

Prior to dispatch, the materials would be offered by the contractor for joint<br />

inspection at the contractor’s works as detailed in this tender specification for which<br />

the contractor would serve the advance notice of 15 days for inspection call to<br />

BHEL.<br />

21.0 INSPECTION & JOINT VER<strong>IF</strong>ICATION (AT SITE)<br />

The contractor shall be intimated within 7 days from the date of receipt of each<br />

consignment at site to depute their representative for joint inspection and<br />

verification of the equipment/materials received at site. The contractor shall depute<br />

their representative within 7 days from receipt of such intimation failing which BHEL<br />

shall proceed with the inspection and verification of equipment/materials and<br />

BHEL’s decision in this regard shall be final and binding to the contractor.<br />

22.0 QUALITY PLAN<br />

The bidder shall furnish the quality assurance plan for approval of BHEL/ owner.<br />

23.0 DIVISIBLE CONTRACT<br />

Notwithstanding anything stated elsewhere in this tender, the contract to be<br />

awarded shall be on the basis of supply & erection contract (divisible contract) on<br />

single source responsibility. In the mode of contracting on the basis of supply &<br />

erection, the civil & erection portion of the contract will relate to the BOQ cum price<br />

schedule of (1) Part-1 and supply portion of the contract will relate to the BOQ cum<br />

price schedules of (1) Part-2.<br />

But the two contract shall not in any way dilute the responsibility of the bidder for<br />

the successful completion of the job as per tender specification and both the<br />

contracts shall contain a cross-fall breach clause, namely that a breach in one<br />

contract shall automatically be classified as a breach on the other contract which<br />

will confer a right on BHEL to terminate the other contract at the risk and cost of the<br />

bidder.<br />

The title of the ownership of goods to be supplied shall pass on to the owner on<br />

dispatch ex-works/ FOR destination. However till the scope is completed in all<br />

respect and the plant/ equipment is taken over by the owner the goods shall remain<br />

with the custody of the bidder.<br />

24.0 OTHER TERMS<br />

All other term & conditions of this specification shall be governed by the pertinent<br />

provisions of GCC, as applicable.


TENDER NO<br />

VOLUME<br />

PSER:SCT:DPL-C1154:10<br />

<strong>IF</strong> TECHNICAL CONDITIONS OF CONTRACT<br />

(SERVICE)<br />

JOB CONSTRUCTION OF 220M HIGH RCC SINGLE<br />

FLUE BRICK LINED CHIMNEY INCLUDING<br />

SUPPLY, ERECTION, COMMISSIONING ETC OF<br />

EQUIPMENTS/ MATERIAL, COMPLETE.<br />

CAPACITY 1x250 MW<br />

PROJECT DPL, DURGAPUR, WEST BENGAL.<br />

BHARAT HEAVY ELECTRICALS LIMITED<br />

(A Govt Of India Undertaking)<br />

POWER SECTOR – EASTERN REGION<br />

PLOT – DJ 9/1, SECTOR II, SALT LAKE<br />

KOLKATA – 700 091


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 1 OF 35<br />

CONTENTS<br />

CLAUSE DESCRIPTION<br />

NO<br />

1.0 PROJECT SYNOPSIS AND GENERAL INFORMATION<br />

2.0 SITE VISIT<br />

3.0 SCOPE OF WORK<br />

4.0 DEVIATIONS<br />

5.0 DEWATERING<br />

6.0 LAND<br />

7.0 WATER<br />

8.0 ELECTRICITY<br />

9.0 GENERAL TECHNICAL REQUIREMENTS (CODES AND STANDARDS)<br />

10.0 SERVICES TO BE RENDERED BY THE BIDDER<br />

11.0 PROTECTION<br />

12.0 QUALITY CONTROL & QUALITY ASSURANCE<br />

13.0 QUALITY ASSURANCE PROGRAMME<br />

14.0 HSE REQUIREMENTS (HEALTH, SAFETY AND ENVIRONMENT)<br />

15.0 SPEC<strong>IF</strong>IC REQUIREMENTS FOR ISO 9002<br />

16.0 GENERAL REQUIREMENTS<br />

17.0 GENERAL GUIDELINES FOR FIELD ACTIVITIES<br />

18.0 PROJECT MANAGEMENT/ CONSTRUCTION MANAGEMENT<br />

19.0 RESPONSIBILITY OF CONTRACTOR<br />

20.0 TOOLS & PLANTS (TO BE PROVIDED BY CONTRACTOR)<br />

21.0 INSURANCE<br />

22.0 MATERIAL HANDLING OF CEMENT & STEEL<br />

23.0 ISSUE OF MATERIALS<br />

24.0 RETURN OF MATERIALS<br />

25.0 CEMENT AND STEEL CONSUMPTION AND WASTAGE<br />

26.0 RECONCILIATION OF BHEL ISSUED MATERIALS<br />

27.0 RECOVERY OF MATERIAL<br />

28.0 CONSTRUCTION OF TEMPORARY OFFICE, STORES ETC<br />

29.0 CIVIL LABORATORY AT SITE<br />

30.0 CONSTRUCTION SCHEDULE<br />

31.0 COMPLETION PERIOD<br />

32.0 LIQUIDATED DAMAGE<br />

33.0 CERT<strong>IF</strong>ICATE TOWARDS COMPLETION<br />

34.0 GUARANTEE<br />

35.0 INTEREST BEARING RECOVERABLE ADVANCE<br />

36.0 OVER RUN CHARGES<br />

37.0 REVISION ON ACCEPTED CONTRACT RATE<br />

38.0 PRICE VARIATION CLAUSE<br />

39.0 SECURITY DEPOSIT & PERFORMANCE BOND<br />

40.0 CONTRACT PRICE<br />

41.0 TAXES AND DUTIES<br />

42.0 INTERIM PAYMENTS<br />

43.0 METHOD OF MEASUREMENT<br />

44.0 EXTRA/ ADDITIONAL ITEMS OF WORK<br />

45.0 DESIGN OFFICE AND FABRICATION DRAWING<br />

46.0 FABRICATION / GALVANISING<br />

47.0 DIVISIBLE CONTRACT<br />

48.0 OTHER TERMS<br />

49.0 ANNEXURE-A


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 2 OF 35<br />

This volume shall be construed as part of tender document and shall be read along-with others<br />

volumes of tender. In case of any conflict or inconsistency between the general and technical<br />

conditions, the same shall be brought out by the bidder in writing to BHEL for clarification during<br />

pre-bid discussions; failing which most stringent interpretation/ clause in favour of BHEL shall be<br />

adopted and the same shall be binding to the bidder.<br />

CLAUSE DESCRIPTION<br />

NO<br />

1.0 PROJECT SYNOPSIS AND GENERAL INFORMATION<br />

1.1 1 x 250 MW Thermal Power Plant is being set up at Durgapur by Durgapur Projects<br />

Limited, using pulverised coal as the main fuel, to work as a peak load station<br />

capable of two shift operation. The power plant will be installed as unit # 8 at<br />

Durgapur Projects Power Station, Durgapur in Burdwan district, West Bengal, India,<br />

as extension unit.<br />

Durgapur city is disposed at 28048’ N latitude and 85033’45” E longitude located at<br />

left bank of river Damodar, in the district of Burdwan at a distance of about 160 KM<br />

from Kolkata. The plant site is 6 KM away from Durgapur Barrage located on the<br />

river Damodar. The site is well connected by roads with important industrial centres<br />

in the area. Broad gauge railway line of the Eastern Railway and good all-weather<br />

roads connect Durgapur with Kolkata and nearby collieries.<br />

Owner of the project: Durgapur Projects Limited (DPL).<br />

Nearest Railway station: Durgapur.<br />

Site is about 3 Km from Railway station.<br />

The site is about 160 km from Kolkata.<br />

Nearest port is Kolkata.<br />

The nearest airport is Netaji Subhas International Airport, Kolkata.<br />

1.2 Owner of the project: Durgapur Projects Limited (DPL).<br />

1.3 APPROACH TO SITE<br />

Nearest railway station: Durgapur.<br />

Site is about 3 Km from railway station.<br />

The site is about 160 km from Kolkata.<br />

Nearest port is Kolkata.<br />

The nearest airport is Netaji Subhas International Airport, Kolkata.<br />

2.0 SITE VISIT<br />

The contractor should visit 1x250 MW DPL project site and acquire full knowledge<br />

and information about site conditions. The bidder must visit site, to acquaint himself<br />

with the conditions prevailing at site and in and around the plant premises, together<br />

with all the statutory, obligatory, mandatory requirements of various authorities<br />

before submission of the bid.<br />

3.0 SCOPE OF WORK<br />

3.1 The work to be done under this specification comprises of construction of 220 M<br />

high reinforced concrete single flue brick lined chimney complete with reinforced<br />

concrete raft foundation, RC shell, insulation and provision of other accessories<br />

including ash hoppers, external platforms, fabrication and fixing of flue duct inside<br />

the chimney, GI discrete strakes, complete interior and air aviation obstruction<br />

lighting system, lightning protection and grounding system, MS doors for access to<br />

the shell, external platforms and inspection of the liners, MS ladders,<br />

communication system components, embedments for installation of equipments<br />

and fixtures and painting both internal and external of the chimney shell as well as<br />

of all doors, ladders and other structural steel items in accordance with this<br />

specification and approved drawings.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 3 OF 35<br />

The chimney will be single flue reinforced concrete structure and flue will have first<br />

class acid/ heat proof firebrick lining. This brick lining work will be supported on<br />

internal RCC corbels at 10 mtr interval. Complete external surface of the chimney<br />

shall be painted in alternate band of signal red and white colour starting with signal<br />

red colour at the top and in line with aviation requirements. External painting shall<br />

have acid and heat resisting properties confirming to IS-158, total dry film thickness<br />

(DFT) shall be atleast 150 microns. Platforms on external surface of RCC<br />

windshield with provision of personnel access shall be provided at maximum<br />

twenty-five (25) metre interval. Suitable personnel access door and truck entry door<br />

shall be provided. The top of roof slab and top of acid resistant bricks over the roof<br />

shall be painted with two coats of ‘EXPILUX 5 coal tar epoxy paint’ over a thin coat<br />

of the same paint as manufactured by Berger Paints (India). The overall DFT shall<br />

be at least 230 microns. RCC hopper shall be provided at bottom level.<br />

Arrangement shall be provided for measuring concentration of particulate matters.<br />

NOX and SOX in the flue gas for monitoring and taking necessary measure for<br />

pollution control. It will also have necessary arrangement for earthing during<br />

construction. Access from ground to external platforms shall be provided with cage<br />

ladder.<br />

Receipt, unloading, erection, testing and commissioning of stack elevator and<br />

electrical equipments, allied items, cabling, earthing, etc including lightening<br />

protection system, communication system, aviation obstruction lighting system,<br />

temporary aviation obstruction lighting system during construction of chimney, acid<br />

and heat protection paints, are also under the scope of this of work. The complete<br />

works have to be carried out by providing all labour, supervision, materials,<br />

scaffolding, power, fuel, construction equipments, tools & plants, inspection,<br />

measuring, testing instruments, supplies, transportation, storage, and all incidental<br />

items not herein specifically mentioned but reasonably or found required for the<br />

successful completion of work including contractor’s and where necessary<br />

manufacturer’s expert supervision in strict compliance with the requirement of this<br />

specification and approved construction drawing.<br />

3.2 Any buried pipe/ cable/ trenches/ concrete structure coming in the working fronts<br />

are to be removed safely by the contractor at no extra cost to BHEL.<br />

3.3 The work to be performed under this specification consists of providing all labour,<br />

materials, consumables, equipment, temporary works, temporary storage sheds,<br />

material handling and storing of BHEL supplied items, temporary colony for labour<br />

and staff, temporary site offices, constructional plants, fuel supply, transportation<br />

and all incidental items not shown or specified but reasonably implied or necessary<br />

for the completion of subject scope, all in strict accordance with the specifications<br />

including revisions and amendments thereto as may be required during the<br />

execution of work.<br />

The scope shall also include setting up by the bidder a testing laboratory in the field<br />

to carry out all relevant tests.<br />

3.4 All quality standards, tolerances, welding standards and other technical<br />

requirements shall be strictly adhered to. The bidder shall fully apprise himself of<br />

the prevailing conditions at the proposed site, climatic conditions including<br />

monsoon pattern, soil conditions, local conditions and site specific parameters and<br />

shall include for all such conditions and contingent measures in the bid, including<br />

those which may not have been specifically brought out in the specifications<br />

4.0 DEVIATIONS<br />

The bidder is required to submit with his offer in the relevant schedule/ format<br />

without any ambiguity. Any assumptions, presumptions, deviations etc. indicated or<br />

implied anywhere by the bidder except those indicated in the deviation schedule/<br />

format will not be recognized and will not form a part of consideration / offer. In the<br />

absence of such filled-up schedule/ format it will be understood and agreed that the<br />

bidder’s offer is based on strict conformance to the specification and no negotiation


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 4 OF 35<br />

would be allowed in this regard. BHEL reserve the right not to recognize any / all<br />

deviations submitted after opening of the bid.<br />

5.0 DEWATERING<br />

The contractor shall ensure at all times that his work area & approach/ access<br />

roads are free from accumulation of water, so that the materials are safe and the<br />

erection/ progress schedule are not affected. No separate claim in this regard shall<br />

be admitted by BHEL. No separate payments for dewatering of subsoil, surface<br />

water or catchments water, if required, at any time during execution of the work<br />

including monsoon period shall be considered by BHEL.<br />

6.0 LAND<br />

6.1 Availability of land within plant boundary is very limited and the contractor has to<br />

plan and use the existing land considering the use of land by other<br />

mechanical/electrical contractors and the storage of plant machineries and<br />

materials. The existing land shall be shared by all erections agencies. The same<br />

will be reviewed by BHEL and allotted to the extent available/ considered<br />

necessary, depending upon the area availability. Contractor shall develop these<br />

areas (including work areas as provided by BHEL/ customer) including grass/tree<br />

cutting, leveling, grading etc. Material storage area, if more than the space allotted<br />

to the bidder, shall have to be arranged by the bidder locally as a temporary<br />

arrangement outside the project.<br />

6.2 No land will be provided for labour colony inside the project premises to the<br />

contractor to construct labour colony/ hutment. The contractor will have to make<br />

temporary arrangement (at his own cost) outside the project premises the same in<br />

consultation with customer/ BHEL.<br />

6.3 The contractor will be responsible for handing back all lands, as handed over to<br />

him.<br />

6.4 Area for fabrication, batching plant and storage area for BHEL’s material shall be<br />

provided as per availability free of cost as per enclosed Plot Plan.<br />

7.0 WATER<br />

7.1 BHEL will provide water connection at one point free of cost for construction as<br />

well as drinking water. For further distribution of pipeline net work up to chimney<br />

work spot are to be carried out by the bidder as per requirement at their own cost.<br />

Contractor will submit enabling work plan showing batching plant, civil laboratories,<br />

their own offices, temporary cement store (water tight) of 200 MT capacity, other<br />

strores etc.and construct at their own cost.<br />

7.2 Distribution network for construction and drinking water system within chimney area<br />

shall be done by the bidder at his own cost.<br />

7.3 The availability of water (construction as well as drinking) in customer project is<br />

limited. The contractor shall ensure that no water is wasted. In this regard the<br />

contractor shall take all necessary measure towards preservation of water.<br />

7.4 BHEL shall not be responsible for any inconvenience or delay caused due to any<br />

interruption of water supply and the contractor shall claim no compensation for<br />

delay in work for such interruption. Contractor may make standby arrangement for<br />

water for which no separate payment shall be made by BHEL.<br />

8.0 ELECTRICITY<br />

8.1 BHEL will provide construction power point on free of charge basis at LT voltage<br />

level (3-Ph., 415-V) at around 200M from chimney area. Further distribution<br />

(including laying of cables/ installation DBs and maintenance of the same) beyond<br />

this point to be arranged by the contractor at his own cost. If any other voltage level<br />

(other than normally available) is required, the same shall be arranged by the<br />

contractor from power supply as above. Contractor will have to provide at his own<br />

cost necessary calibrated energy meters (tamper proof, suitably housed in a<br />

weather proof box with lock & key arrangement) at point of power supply along with<br />

calibration certificate from authorized/ accredited agency for working out the power<br />

consumption. In case of recalibration required for any reason the necessary<br />

charges including replacement by calibrated meters is to be borne by contractor.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 5 OF 35<br />

Supply of electricity shall be governed by Indian Electricity Act and Installation<br />

Rules and other Rules and Regulation as applicable. The contractor shall ensure<br />

usage of electricity in an efficient manner and the same may be audited by BHEL<br />

time to time. In case of any major deviation from normally accepted norms is<br />

observed, BHEL will reserve the right to impose penalty as deemed fit for such<br />

cases. No bare conductor (for the purpose of drawing electricity for construction<br />

purposes) is allowed to be drawn within project premises.<br />

8.2 The bidder shall have to provide earth leakage circuit breaker at each point<br />

wherever human operated electrical drives/ T&Ps are deployed.<br />

8.3 The power supply will be from the available grid. BHEL shall not be responsible for<br />

any inconvenience or delay caused due to any interruption of power supply/<br />

variation in voltage level and no compensation for delay in work can be claimed by<br />

the contractor due to such non-supply on the grounds of idle labour, machinery or<br />

any other grounds.<br />

8.4 BHEL shall provide illumination on common erection approaches on a progressive<br />

basis; however the bidder will have to arrange sufficient illumination at their work<br />

areas.<br />

8.5 The contractor should ensure that the work in critical areas is not held up in the<br />

event of power breakdown. In the event of breakdown in the electric supply, if the<br />

progress of work is hampered, it will be the responsibility of the contractor to step<br />

up the progress of work after restoration of electric supply so that overall progress<br />

of work is not affected.<br />

8.6 The contractor shall have to make arrangement at their own cost for illumination<br />

that will be required in the working area for execution of the work & safety of<br />

workmen.<br />

8.7 Bidder also will install DG SET back up system for emergency night illumination<br />

and operation of passenger hoist during grid power failure or any emergency use of<br />

passenger hoist throughout the construction period.<br />

8.8 Bidder to provide temporary lightning arrestor along with ground earth-matting and<br />

electrode while doing the RCC shell concreting.<br />

9.0 GENERAL TECHNICAL REQUIREMENTS (CODES AND STANDARDS)<br />

9.1 Except where otherwise specified, the plant/ equipment shall comply with<br />

appropriate Indian Standard or an agreed internationally accepted Standard<br />

Specification as mentioned elsewhere in tender, each incorporating the latest<br />

revisions at the time of tendering. Where no internationally accepted standard is<br />

applicable, the bidder shall give all particulars and details as necessary; to enable<br />

BHEL to identify all of the plant/ equipment in the same detail as would be possible<br />

had there been a standard specification.<br />

9.2 Where the bidder proposes alternative codes or standards he shall include in his<br />

tender one copy (in English) of each standard specification to which materials<br />

offered shall comply. In such case, the adopted alternative standard shall be<br />

equivalent or superior to the standards mentioned in the specification.<br />

9.3 In the event of any conflict between the codes & standards referred above, and<br />

requirements of this specification, the requirements which are more stringent shall<br />

govern.<br />

9.4 Tools used during erection and commissioning shall not be accepted except with<br />

the specific approval of the engineer.<br />

9.5 Wherever specified or required the plant/ equipment shall conform to various<br />

statutory regulations such as Indian Boiler Regulation, Indian Electricity Rules,<br />

Indian Explosive Act, Factories Act etc, wherever required, obtaining approval for<br />

plant/ equipment supplied under the specification from statutory authorities shall be<br />

the responsibility of the contractor.<br />

10.0 SERVICES TO BE RENDERED BY THE BIDDER<br />

10.1 Services for construction, fabrication, equipment erection, testing as well as trial run<br />

& commissioning of various equipment and accessories under the contract shall<br />

include but not be limited to the following.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 6 OF 35<br />

10.2 Collecting materials from store/open yard from time to time for fabrication / erection<br />

as per the construction program and unloading of cement & steel as per flow of<br />

consignment. The contractor shall be the custodian of all the materials issued till<br />

the plant/equipment is officially taken over by the owner/ BHEL after complete<br />

erection and commissioning. The contractor shall maintain adequate security<br />

personnel and security measures for proper precaution and safety of material.<br />

10.3 Deployment of all skilled and unskilled manpower required for erection supervision,<br />

watch & ward, for commissioning and other services to be rendered under this<br />

specification.<br />

10.4 Deployment of all erection tools & tackle, construction machinery, transportation<br />

vehicles and all other implements in adequate number and size, appropriate for the<br />

erection work to be handled under scope of this specification except otherwise<br />

specified.<br />

10.5 Supply of all consumables, e.g. welding electrodes, etc as well as materials<br />

required for temporary supports, scaffolding etc as necessary for such construction<br />

work, unless specified other wise.<br />

10.6 Providing support services for the contractor's erection staff eg construction of site<br />

offices, temporary stores, residential accommodation and transport to work site for<br />

erection personnel, watch and ward for security and safety of the materials under<br />

the Contractor's custody etc. as required.<br />

10.7 Maintaining proper documentation of all site activities undertaken by the contractor<br />

as per the proforma mutually agreed with BHEL, submitting monthly progress<br />

reports as also any such document as and when desired by BHEL/ owner, taking<br />

approval of all statutory authorities e.g., Factory Inspector, Provident Fund authority<br />

etc. for respective portions of work under the jurisdiction of such statutes of laws.<br />

10.8 As part of overall project management activity, the contractor shall be responsible<br />

for proper co-ordination of erection activities during various phases of execution of<br />

the contract. The contractor shall identify a person designated as construction<br />

manager, with whom BHEL shall interact on matters related to execution of the<br />

contract. The construction manager shall be the single point contact person on<br />

behalf of the contractor. BHEL shall interact with the construction manager only on<br />

all matters on co-ordination between BHEL and the contractor. For timely<br />

completion of work the contractor may have to work in one or more shifts. He will<br />

not be eligible for any extra charge on this account.<br />

10.9 The contractor shall confine all his field operations to those works which can be<br />

reformed without subjecting the equipment and materials to adverse effects, during<br />

inclement weather conditions, like monsoon, storms etc and during other<br />

unfavourable construction conditions. No field activities shall be performed by the<br />

contractor under conditions which might adversely affect the quality and efficiency<br />

thereof, unless special precautions or measures are taken by the contractor in<br />

proper and satisfactory manner in the performance of such works and with the<br />

concurrence of the engineer. Such unfavourable construction conditions in no way<br />

relieve the contractor of his responsibility to perform the works as per the schedule.<br />

10.10 The contractor shall supply all the skilled workmen like mill-wright fitters, welders,<br />

gas cutters, electricians, riggers, sarangs, erectors, carpenters, pipe fitters,<br />

masons, laggers, tin-smiths, instrument machanics etc, in addition to other skilled,<br />

semi-skilled and unskilled workmen required for all works of handling and<br />

transportation from site store to erection site, erection, testing and commissioning<br />

contemplated under this specification. Only fully trained and competent men with<br />

previous experience on the job shall be employed. They shall hold valid certificates<br />

wherever necessary. BHEL reserve the right to decide on the suitability of the<br />

workers and the other personnel who will be employed by the contractor. BHEL<br />

reserves the right to insist on removal of any employee of the contractor at any<br />

time, if they find him unsuitable and the contractor shall forthwith remove him.<br />

10.11 The supervisory staff employed by the contractor shall be technically qualified and<br />

experienced in the area of work. They shall ensure proper out turn of work and<br />

discipline on the part of labour put on the job by the contractor and in general see


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 7 OF 35<br />

that the works are carried out in a safe and proper manner and in coordination with<br />

other labour and staff employed directly by BHEL or other contractors of BHEL and<br />

BHEL's client.<br />

10.12 The contractor shall also furnish daily labour report showing by classification the<br />

number of employees engaged in various categories of work a progress report of<br />

work as required by BHEL engineer.<br />

10.13 The work shall be executed under the usual conditions affecting major power plant<br />

construction and in conjunction with numerous other operations at site. The<br />

contractor and his personnel shall co-operate with other personnel, and other<br />

contractors, co-ordinating his work with others and proceed in a manner that shall<br />

not delay or hinder the progress of work as a whole.<br />

10.14 The contractor's supervisory staff shall execute the work in the most substantial<br />

and workman like manner in the stipulated time. Accuracy of work and aesthetic<br />

finish are essential part of this contract. The contractor shall be responsible to<br />

ensure that assembly and workmanship conform to the dimensions and tolerance<br />

given in the drawing / instruction given by BHEL Engineer from time to time.<br />

10.15 It is the responsibility of the contractor to engage his workman in shifts or on<br />

overtime basis for achieving the target set by BHEL during erection, commissioning<br />

and testing period. Contractor's quoted rate shall include all these contingencies.<br />

10.16 Any other service, although not specifically called for but required for a contract of<br />

the size and nature indicated in the specification.<br />

11.0 PROTECTION<br />

11.1 Equipment having anti-friction or sleeve bearings shall be protected by weather<br />

tight enclosures. Coated surfaces shall be protected against impact, abrasion,<br />

discoloration and other damages. Surfaces which are damaged shall be repainted.<br />

11.2 Electrical equipments, controls and insulations shall be protected against moisture<br />

and water damages. All external gasket surfaces and flange faces, couplings,<br />

rotating equipment shafts, bearings and like items shall be thoroughly cleaned and<br />

coated with rust preventive compound and protected with suitable wood, metal or<br />

other substantial type covering to ensure their full protection. All exposed threaded<br />

parts shall be greased and protected with metallic or other substantial type<br />

protectors<br />

11.3 All piping, tubing and conduit connections on equipment and equipment openings<br />

shall be closed with rough usage covers or plugs. Female threaded openings shall<br />

be closed with rough usage covers or plugs or forged steel plugs. The closures<br />

shall be taped to seal the interior of the equipment. Open ends of piping, tubing and<br />

conduit shall be sealed and taped.<br />

11.4 All other consumables including wire brush, emery papers, painting brush etc to be<br />

supplied by the contractor within the quoted rate.<br />

12.0 QUALITY CONTROL & QUALITY ASSURANCE<br />

Contractor’s Engineers and supervisors shall be adequately qualified and also<br />

inclined to do a quality job. The quality assurance engineer shall co-ordinate all<br />

aspects of quality control, inspection, implementation of quality assurance<br />

procedures laid down in Quality Plan and technical specification by BHEL. He shall<br />

fill up quality assurance log sheets/ formats and submit to BHEL for joint inspection<br />

and acceptance. The contractor shall fill up, maintain & preserve the quality<br />

records in computerized media. customer/ BHEL's authorized representative shall<br />

be given free access at all time to such quality related records etc for inspection,<br />

review etc.<br />

13.0 QUALITY ASSURANCE PROGRAMME<br />

13.1 The contractor shall arrange for suitable quality assurance program to control all<br />

activities pertaining to the scope of work, as necessary. Such programs shall be<br />

outlined by the contractor and shall be finally accepted by BHEL. A quality<br />

assurance program of the contractor shall generally cover the following.<br />

13.2 Organization structure and qualification data for key personnel of the contractor for<br />

the management & implementation of the proposed quality assurance program.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 8 OF 35<br />

13.3 The procedure for source inspection, incoming raw material inspection, verification<br />

of material purchased etc.<br />

13.4 Field quality plan will detail out the quality practices and procedures etc to be<br />

followed by the contractor’s site quality control organization, during various stages<br />

of site activities from receipt of material /equipment at site.<br />

13.5 Bidder to arrange temperature control at around 25˚ C during chimney raft, either<br />

by sprinkling water on course aggregate or by using Ice, including all related<br />

arrangements for providing, storing and mixing Ice with water, cooling of<br />

aggregates etc.<br />

14.0 HSE REQUIREMENTS (HEALTH, SAFETY AND ENVIRONMENT)<br />

14.1 The contractor shall ensure the safety of all workmen, materials and equipment<br />

either belonging to him or to others working at site. He shall observe safety rules<br />

and codes applied by the customer/ BHEL at site without exception.<br />

14.2 Passenger lift should have safety cage with multiple rope, i.e. with safety rope &<br />

limit switch.<br />

14.3 Safety nets with hand railings must be provided on all both inside & outside hanging<br />

platform of slip-form equipment & hanging platform from brickwork.<br />

14.4 Emergency vehicle must be provided & kept separately as stand-by.<br />

14.5 T&P used by contractor should be tested quality bearing ISI marks. Necessary test<br />

certificates to be produced by the contractor for all the T&P received by him at site<br />

for acceptance by BHEL Engineer. BHEL will reject any T&P without IS test<br />

certificate and the same cannot be utilized on job.<br />

14.6 Only trained and experienced personnel to be used on the job. Signalling for rigging<br />

operations must be given by workers who are possessing required skill and<br />

experience in handling materials.<br />

14.7 Non-conformity of safety rules and safety appliances will be viewed seriously and<br />

BHEL has right to impose fines on the contractor on each incident/each nonconformity<br />

as per details given below.<br />

Safety measure<br />

Fine (Rs)<br />

14.7.1 Not wearing safety helmet & safety shoe. Will not be permitted to<br />

enter the plant<br />

14.7.2 Not wearing safety belt. Will not be permitted to<br />

work at heights for erection<br />

job.<br />

14.7.3 Grinding without goggles. 25/workmen<br />

14.7.4 Not using 24V supply for internal work. 500/case<br />

14.7.5 Electrical plugs not used for hand machines. 100/case<br />

14.7.6 Welding cables, electrical wires not insulated with 50/joint<br />

proper/ standard.<br />

14.7.7 Not removing scrap from platform. Actual cost for removal plus<br />

30 %<br />

14.7.8 Gas cutting without taking proper precaution/not 100/case<br />

using sheet below per incidence.<br />

14.7.9 Electrical winches having no guards earthed properly 500/case<br />

etc.<br />

14.7.10 Improper earthing of electrical T&P. 200/ equipment<br />

14.7.11 Not protecting/locating the gas cylinder to avoid 100/cylinder<br />

catching of fire.<br />

14.7.12 Not providing earth leakage circuit breaker as per 1500/point<br />

direction of BHEL.<br />

14.7.13 Not slinging properly 200/case<br />

14.7.14 Using damaged sling 200/case<br />

14.7.15 Lifting cylinders without cage 500/case<br />

14.7.16 Backfire arrestor 500/case<br />

14.7.17 Life line 500/case<br />

14.7.18 Fall arrestor 500/case


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 9 OF 35<br />

14.8 Any other nonconformity noticed not listed above will also be fined. The decision of<br />

BHEL engineer is final on the above. The amount will be deducted from running<br />

bills of the contractor. The amount collected on the above will be utilised for giving<br />

award to the employee who could avoid accidents by following safety rules. Also,<br />

the amount will be spent for improving the safety at site.<br />

14.9 The contractor shall also be responsible for provision of all safety notices and<br />

safety equipment required both by the relevant legislation and BHEL/ customer, as<br />

he may deem necessary.<br />

14.10 The contractor will notify well in advance to BHEL/ customer his intention to bring to<br />

the site any container filled with liquid or gaseous fuel or explosive or petroleum<br />

substance or such chemicals, which may involve hazards. BHEL/ customer shall<br />

have the right to prescribe the conditions, under which such container is to be<br />

stored, handled and used during the performance of the works and the contractor<br />

shall strictly adhere to and comply with such instructions. BHEL/ customer shall<br />

have the right at his sole discretion to inspect any such container or such<br />

construction plant/equipment for which material in the container is required to be<br />

used and if in his opinion, its use is not safe, he may forbid its use. BHEL/ customer<br />

shall entertain no claim due to such prohibition and BHEL/ customer shall not<br />

entertain any claim of the contractor towards additional safety provisions/conditions<br />

to be provided for/constructed as per the BHEL/ customer’s instructions.<br />

14.11 Further, any such decision of the BHEL/ customer shall not, in any way, absolve the<br />

contractor of his responsibilities and in case, use of such a container or entry<br />

thereof into the site area is forbidden by the BHEL/ customer, the contractor shall<br />

use alternative methods with the approval of the BHEL/ customer without any cost<br />

implication to customer or extension of work schedule.<br />

14.12 Where it is necessary to provide and/or store petroleum products or petroleum<br />

mixtures and explosives, the Contractor shall be responsible for carrying-out such<br />

provision and/or storage in accordance with the rules and regulations laid down in<br />

Petroleum Act 1934, Explosives Act, 1948, and Petroleum and Carbide of Calcium<br />

Manual published by the Chief Inspector of Explosives of India. All such storage<br />

shall have prior approval of the BHEL/ customer. In case, any approvals are<br />

necessary from the Chief Inspector (Explosives) or any statutory authorities, the<br />

Contractor shall be responsible for obtaining the same.<br />

14.13 All equipment used in construction and erection by Contractor shall meet Indian/<br />

International Standards and where such standards do not exist, the Contractor shall<br />

ensure these to be absolutely safe. All equipments shall be strictly operated and<br />

maintained by the Contractor in accordance with manufacturer’s operation Manual<br />

and safety instructions and as per Guidelines/Rules of customer in this regard.<br />

14.14 Periodical examinations and all tests for all lifting/ hoisting equipment & tackles<br />

shall be carried-out in accordance with relevant provisions of Factories Act 1948,<br />

Indian Electricity Act 1910 and associated laws/ rules in force from time to time. A<br />

register of such examinations & tests shall be properly maintained by contractor<br />

and will be promptly produced as & when desired by BHEL/ customer or by the<br />

person authorized.<br />

14.15 The contactor shall be fully responsible for the safe storage of his and his subcontractor’s<br />

radioactive sources in accordance with BARC/ DAE (Bhabha Atomic<br />

Research Center/ Department of Atomic Energy, Govt of India) rules and other<br />

applicable provisions. All precautionary measures stipulated by BARC/ DAE in<br />

connection with use, contractor would take storage and handling of such material.<br />

14.16 The contractor shall provide suitable safety equipment of prescribed standard to all<br />

employees and workmen according to the need, as may be directed by BHEL/<br />

customer who will also have right to examine these safety equipments to determine<br />

their suitability, reliability, acceptability and adaptability.<br />

14.17 Where explosives are to be used, the same shall be used under the direct control<br />

and supervision of an expert, experienced, qualified and competent person strictly<br />

in accordance with the Code of Practices/ Rules framed under Indian Explosives<br />

Act pertaining to handling, storage and use of explosives.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 10 OF 35<br />

14.18 The contractor shall provide safe working conditions to all workmen and employees<br />

at the Site including safe means of access, railings, stairs, ladders, scaffoldings etc.<br />

The scaffoldings shall be erected under the control and supervision of an<br />

experienced and competent person. For erection, the contractor only shall use<br />

good and standard quality of material.<br />

14.19 The contractor shall not interfere or disturb electric fuses, wiring and other electrical<br />

equipment belonging to BHEL/ customer or other contractors under any circumstances,<br />

whatsoever, unless expressly permitted in writing by customer to handle<br />

such fuses, wiring or electrical equipment.<br />

14.20 Before the contractor connects any electrical appliances to any plug or socket<br />

belonging to the other contactor or BHEL/ customer, he shall fulfill following.<br />

14.20.1 Satisfy BHEL/ customer that the appliance is in good working condition.<br />

14.20.2 Inform BHEL/ customer of the maximum current rating, voltage and phases of the<br />

appliances.<br />

14.20.3 Obtain permission of BHEL/ customer detailing the sockets to which the appliances<br />

may be connected.<br />

14.21 The BHEL/ customer will not grant permission to connect until he is satisfied that:<br />

14.21.1 The appliance is in good condition and is fitted with suitable plug;<br />

14.21.2 The appliance is fitted with a suitable cable having two earth conductors, one of<br />

which shall be an earthed metal sheath surrounding the cores.<br />

14.22 No electric cable in use by contractor/ BHEL/ customer will be disturbed without<br />

prior permission. No weight of any description will be imposed on any cable and no<br />

ladder or similar equipment will rest against or attached to it.<br />

14.23 No repair work shall be carried out on any live equipment. BHEL/ customer must<br />

declare the equipment safe and a permit to work shall be issued by BHEL/<br />

customer before the contractor carries out any repair work. While working on<br />

electric lines/equipments whether live or dead, suitable type and sufficient quantity<br />

of tools will have to be provided by contractor to electricians/ workmen/ officers.<br />

14.24 The contractors shall employ necessary number of qualified, full time electricians/<br />

electrical supervisors to maintain his temporary electrical installations.<br />

14.25 The contractor shall employ trained safety officer to supervise day to day safety<br />

aspects of the equipments and workmen, who will co-ordinate with BHEL/ customer<br />

customer safety officer. In case of work being carried out through sub-contractors,<br />

sub-contractor’s workmen/ employees will also be considered as the contractor’s<br />

employees/ workmen for the above purpose.<br />

14.26 In case any accident occurs during the construction/ erection or other associated<br />

activities undertaken by the Contractor thereby causing any minor or major or fatal<br />

injury to his employees due to any reason, whatsoever, it shall be the responsibility<br />

of the contractor to promptly inform the same to BHEL/ customer in prescribed form<br />

and also to all the authorities envisaged under the applicable laws.<br />

14.27 BHEL/ customer shall have the right at his sole discretion to stop the work, if in his<br />

opinion the work is being carried out in such a way that it may cause accidents and<br />

endanger the safety of the persons and/or property, and/or equipments. In such<br />

cases, the contractor shall be informed in writing about the nature of hazards and<br />

possible injury/ accident and he shall comply to remove shortcomings promptly.<br />

14.28 The contractor shall not be entitled for any damages/ compensation for stoppage of<br />

work due to safety reasons above and the period of such stoppage of work will not<br />

be taken as an extension of time for completion of the facilities and will not be the<br />

ground for waiver of levy of penalty.<br />

14.29 The contractor shall follow and comply with all safety rules of BHEL/ customer,<br />

relevant provisions of applicable laws pertaining to the safety of workmen,<br />

employees plant and equipment as may be prescribed from time to time without<br />

any demur, protest or contest or reservation. In case of any inconformity between<br />

statutory requirement and customer’s Safety Rules of BHEL/ customer referred<br />

above, the later shall be binding on the contractor unless the statutory provisions<br />

are more stringent.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 11 OF 35<br />

14.30 If the Contractor fails in providing safe working environment as per BHEL's Safety<br />

Rules or continues the work even after being instructed in writhing to stop work by<br />

BHEL Manager, the Contractor shall promptly pay to BHEL, on demand by BHEL<br />

compensation at the rate of Rs. 5,000/- per day or part thereof till the instructions<br />

are complied with and so certified by BHEL. However, in case of accident taking<br />

place, causing injury, to any individual, the provisions contained in relevant<br />

paragraph above shall also apply in addition to compensation mentioned in this<br />

paragraph.<br />

14.31 If the Contractor does not take all safety precautions and/or fails to comply with the<br />

Safety Rules as prescribed by BHEL or under the applicable law for the safety of<br />

the equipment and plant and for the safety of personnel and the Contractor does<br />

not prevent hazardous conditions which cause injury to his own employees or<br />

employees of other Contractors, or BHEL's employees or any other person who are<br />

at Site or adjacent thereto, the Contractor shall be responsible for payment of<br />

compensation to Employer as per the following schedule.<br />

14.31.1 Fatal injury or accident causing death Rs.2,00,000.00/per person<br />

14.31.2 Major injuries or accident causing 25% or more Rs 50,000.00/per person<br />

permanent disablement to workmen or employees.<br />

14.32 Permanent disablement shall have same meaning as indicated in Workmen's<br />

Compensation Act. The compensation mentioned above shall be in addition to the<br />

compensation payable to the workmen/employees under the relevant provisions of<br />

the Workmen's Compensation Act and rules framed there under or any other<br />

applicable laws as applicable from time to time. In case BHEL is made to pay such<br />

Compensation then the Contractor is liable to reimburse BHEL such amount in<br />

addition to the compensation indicated above.<br />

14.33 In case BHEL/ customer is made to pay such compensation then the contractor is<br />

liable to reimburse BHEL/ customer such amount in addition to compensation<br />

indicated above.<br />

14.34 These insurance covers for his workmen as well as his T & P have to be taken by<br />

contractor prior to start of his work at the subject project and he shall make<br />

available the Policy to BHEL site-in-charge for necessary verification before<br />

commencement of work. However, irrespective of such verification/ acceptance, the<br />

sole responsibility to maintain adequate insurance cover for his workmen, T&P,<br />

assets etc. at all times during the period of contract shall lie with the contractor.<br />

Regarding the aforesaid insurance cover, the contractor shall directly deal with the<br />

Insurance Company for all matters regarding the insurance in his scope.<br />

14.35 You will follow HSE policy of BHEL/ PSER and work as per the safety guidelines<br />

which is in line with ISO:14001 and OHSAS:18001 standards. A list of the<br />

guidelines which should be strictly followed by you as follows. Your scope shall not<br />

be limited to the followings only but shall be guided by the HSE related policies/<br />

guidelines of BHEL as revised to suit the requirement of the standards and<br />

statutory requirements.<br />

14.36 Nominate a safety officer who will supervise all the HSE aspects.<br />

14.37 The safety officer will participate in all safety meeting conducted by BHEL.<br />

14.38 Submit site safety plan indicating safety measures to be taken, fire fighting<br />

equipments & PPE to be deployed.<br />

14.39 Report every near miss incident to BHEL.<br />

14.40 Report accident report immediately after the occurrence.<br />

14.41 Obtain operation control procedures (OCPs) from BHEL for the work to be<br />

executed<br />

14.42 Follow factory act.<br />

14.43 Every worker should use PPE as per his trade. All PPE should confirm to IS.<br />

14.44 Conduct tool box meeting with workers everyday before start of work instructing<br />

about the use of PPE. The outcome of the meeting to be recorded in a register.<br />

14.45 Check fitness of PPE and lifting tackles weekly and record in a register which will<br />

be verified by BHEL.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 12 OF 35<br />

14.46 No person below 18 years will be employed.<br />

14.47 Deploy fire-fighting equipments and refill before expiry.<br />

14.48 Keep fire extinguishers of adequate type near the hot job and near the electrical<br />

machines.<br />

14.49 Copy of valid test certificates of all T&Ps should be given to BHEL as soon as the<br />

item enters the project, without which the T&P can not be allowed to be used.<br />

14.50 No body will be allowed to work above 2 meters without safety belt/ harness with<br />

lifeline secured to a fixed member.<br />

14.51 Good housekeeping has to be maintained. All debris shall be removed from<br />

workplace within shortest possible time.<br />

14.52 Approach roads should not be blocked with cables, materials or debris.<br />

14.53 First aid boxes have to be kept and maintained with all requisite materials as per<br />

factory act.<br />

14.54 Trained person has to be kept for giving first aid.<br />

14.55 Adequate illumination shall be provided where working.<br />

14.56 All vehicles should have backlight, reverse horn and reversing light.<br />

14.57 Crane operator shall have proper license.<br />

14.58 Crane should have reverse horn.<br />

14.59 Only skilled person maintain and operate electrical items.<br />

14.60 ELCB has to be used. No temporary connection shall be allowed.<br />

14.61 All fuses shall have standard rating and capacity.<br />

14.62 All power supply cables should be laid above 3 meter level or underground.<br />

14.63 All hand lamps should be powered by 24 volts.<br />

14.64 Water-logging of working area shall be removed.<br />

14.65 For operating portable machines 3 pin plugs shall be used.<br />

14.66 Oxygen & DA cylinders shall be separated labeling full or empty. Full cylinders shall<br />

be kept upright.<br />

14.67 Cylinders are not transported by rolling.<br />

14.68 All oil drums shall be kept horizontal.<br />

14.69 Excavated area shall be barricaded off with red & white tape.<br />

14.70 Proper slope of excavation shall be maintained.<br />

14.71 Proper sign board and illumination shall be maintained at excavated area.<br />

14.72 Wherever possible safety net shall be provided.<br />

14.73 Proper platform and hand rail has to be provided at the work place.<br />

14.74 All electrical equipments shall be earthed at two points.<br />

14.75 Temporary platform should be strong enough, have proper approach and hand rails<br />

14.76 Above clauses are indicative only and not exhaustive. Other activities to maintain<br />

strong HSE conditions at site which may be beyond above list of guidelines shall<br />

have to be done by you.<br />

14.77 The Contractor shall provide necessary first-aid facilities for all his employees,<br />

representatives and workmen working at the Site. First-aid centre with Ambulance<br />

facility shall be established and maintained at site by the main Civil vendor. All<br />

other bidder of BHEL are expected to contribute towards establishing and<br />

maintaining the facility and the sum of contributions should be proportionate to their<br />

respective contract prices. This may be treated as mandatory stipulation and the<br />

bidder should carryout due liasioning work with the Civil vendor directly for smooth<br />

running of the first-aid centre. In the event of non-compliance of this, BHEL shall be<br />

constrained to pay the contribution and recover the cost with 30% overhead from<br />

the bill of the vendor.<br />

14.78 It is imperative on the part of the contractor to join and effectively contribute in joint<br />

measures such as tree plantation, environment protection, contributing towards<br />

social up-liftment, conversion of packing woods to school furniture, keeping good<br />

relation with local populace etc.<br />

14.79 Round the clock experienced paramedical personnel with first aid facility & one<br />

ambulance at site to be arranged by the bidder at his own cost. No medical facility<br />

within / near the site shall be provided by BHEL. However, BHEl/ customer shall


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 13 OF 35<br />

provide one room (without furniture) for use as first aid centre.<br />

14.80 No staff quarter shall be provided by BHEL.<br />

14.81 No borrow area for earth shall be arranged / provided by BHEL. The necessary<br />

approach road, as required for disposal of earth, is included in the scope of work of<br />

contractor.<br />

14.82 All temporary approaches required for movement of cranes, trailers, trucks, transit<br />

mixers, dumpers, etc shall be prepared / arranged by the contractor at his own cost.<br />

14.83 The contractor shall solely be responsible for the safety, quality, & quantity of<br />

material after it is handed over and issued to contractor by the BHEL.<br />

14.84 Centralized reinforcement cutting/ bending yard should be located within 1000m<br />

from the power house yard.<br />

15.0 SPEC<strong>IF</strong>IC REQUIREMENTS FOR ISO 9002<br />

15.1 Contractors shall ensure that all their staff/ employees are exposed to periodical<br />

training programmes conducted by qualified agencies/ personnel on ISO 9002<br />

Standards.<br />

15.2 Contractor shall ensure that the quality is maintained in all the works connected<br />

with this contract at all stages of the requirement of BHEL.<br />

15.3 Contractor shall ensure that all Inspection, Measuring and Testing equipment that<br />

are used, whether owned by the contractors or used on loan, are calibrated by the<br />

authorized agencies and the valid calibration certificate will be available with them<br />

for verification by BHEL. A list of such instruments possessed by the contractor at<br />

site with its calibration status is to be submitted to BHEL Engineer for control.<br />

15.4 Contractor shall ensure that fitness certificate of the tools & plants, that are in use,<br />

whether owned by contractor or issued on loan, are tested by authorised agency<br />

and the valid fitness certificate is available for verification by BHEL.<br />

15.5 Contractors shall arrange for the inspection of the works at various stages as<br />

required by BHEL. The contractors shall take immediate corrective action for the<br />

non-conformances if any, observed and pointed out by BHEL.<br />

16.0 GENERAL REQUIREMENTS<br />

16.1 The bidders are to consider this during quoting. BHEL is in the process of providing<br />

the first-aid centre within the project premises with ambulance facility on no profit<br />

no loss basis. The cost of running expenses will be shared between all the subcontractors<br />

engaged within project. The pro-rata charges shall be determined by<br />

the total contract price of the sub-contractor and no. of sub-contractors available<br />

within the project. The bidders are to consider this during quoting.<br />

16.2 Bidders to note that stipulations as per Govt. of West Bengal minimum wages Act<br />

including House Rent Act & Height allowance Act are applicable for this project.<br />

Any agency found to be violating these acts is liable for legal proceedings &<br />

compensation as per law and recovery from the RA bill as per actual cost (+) 30 %<br />

will be affected. Bidders to note that provisions & rules as per Factory Act (with<br />

amendments) is implemented and the same is applicable for this project.<br />

16.3 Since this is an extension unit, the construction area may be cordoned off by<br />

providing a temporary fencing arrangement. Bidders to take special care that none<br />

of his workmen ventures into the running plant area during any time of the day,<br />

except for interface area working, for which separate procedure will be issued at the<br />

time of execution.<br />

16.4 Before starting the work at site the bidder to apply for gate pass for his workmen.<br />

The application for gate pass shall be addressed to `The Chief Security Officer,<br />

DPL, DPL Power Station’. The application for gate pass should be first routed<br />

through authorized representative of BHEL and then by Project Department, DPL,<br />

before proceeding to IR section of DPL. The application must accompany the<br />

relevant & applicable documents like proof of residence, ESI no etc.<br />

16.5 The site is under Factory Act and all relevant statutory provision/ liabilities etc are to<br />

be taken care of by the bidder.<br />

16.6 Labour Requirements<br />

16.6.1 The contractor shall prepare and make available to the customer from time to time


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 14 OF 35<br />

details of the numbers and trades of workmen whom the contractor proposes to<br />

employ (whether directly or through sub-contractors) on the site throughout the<br />

periods shown in the Project Schedule. Such details shall be in the form of a<br />

periodic histogram, accumulative `S’ curve and summary line item tabulation or<br />

such other form as customer may reasonably request and the contractor normally<br />

utilizes.<br />

16.6.2 As far as practicable, the Contractor shall give preference in the employment of<br />

unskilled labourers at the Site to persons living locally in consultation with<br />

customer’s IR Department.<br />

16.7 Quality Assurance<br />

16.7.1 All materials, components and equipments covered under the specification shall be<br />

procured, manufactured, erected, commissioned and tested, as applicable, at all<br />

stages as per comprehensive quality assurance program. An indicative program for<br />

inspection/ test, to be carried out by the contractor, for some of the major items is<br />

given in the respective technical specification.<br />

16.7.2 Approved Field quality plan of BHEL/ customer will detail out the quality practices<br />

and procedures etc to be followed by the contractor’s site quality control<br />

organization, during various stages of site activities from receipt of material/<br />

equipment at site.<br />

16.7.3 Casting and forgings used for construction shall be of tested quality. Details of<br />

results of chemical analysis, mechanical properties test result, as necessary, shall<br />

be furnished.<br />

16.7.4 All welding shall be carried out as per procedure drawn and qualified in accordance<br />

with the requirements of ASME Section-1X/ BS4870 or other international<br />

equivalent standard acceptable to BHEL/ customer.<br />

16.7.5 All welders etc employed on any part of the contract at contractors’ work or at site<br />

shall be qualified as per ASME Section-IX or BS 4871 or equivalent international<br />

standard approved by BHEL/ customer. Such qualification test shall be conducted<br />

in presence of BHEL/ customer.<br />

16.7.6 All non-destructive examinations (NDT) shall be carried out in accordance with<br />

approved international standard. NDT operators shall be qualified as per SNT-TC-<br />

IA (of American society of non-destructive examination) Results of NDT shall be<br />

properly recorded and submitted for approval.<br />

16.7.7 All the purchase specifications for the major bought out items list of which shall be<br />

drawn up by the contractor and finalized with BHEL/ customer shall be furnished to<br />

BHEL for comments and approval before placement of orders.<br />

16.7.8 BHEL/ customer reserves the right to carry out quality audit and quality surveillance<br />

of the systems and procedures of contractor’s quality management. Contractor<br />

shall provide all necessary assistance to enable BHEL/ customer to carry out such<br />

audit.<br />

16.7.9 Quality audit/approval of the results of test and inspection will not prejudice the right<br />

of BHEL/ customer to reject an equipment service not giving the desired<br />

performance and shall not in no way limit the liabilities and responsibilities of the<br />

contractor in earning satisfactory performances of equipment/service as per<br />

specification.<br />

16.7.10 Repair/ rectification procedure to be adopted to make any job acceptable shall be<br />

subject to the approval of BHEL/ customer.<br />

16.7.11 All the latest relevant IS codes as per technical specification & requirement should<br />

be available with contractor at site within 45 days from the date of LOI.<br />

17.0 GENERAL GUIDELINES FOR FIELD ACTIVITIES<br />

17.1 The contractor shall execute the works in a professional manner so as to achieve<br />

the target schedule without any sacrifice on quality and maintaining highest<br />

standards of safety and cleanliness.<br />

17.2 The contractor shall co-operate with owner/ BHEL and other contractors working in<br />

site and arrange to perform his work in a manner so as to minimise interference<br />

with other contractor’s works. BHEL's engineer shall be notified promptly of any


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 15 OF 35<br />

defect in other contractors’ works that could affect the contractor’s work. If<br />

rescheduling of contractor’s work is requested by the owner's/ BHEL's engineer in<br />

the interest of overall site activities, the same shall be compiled with by the<br />

contractor. In all cases of controversy, the decision of BHEL shall be final and<br />

binding on the contractor without any commercial implication.<br />

17.3 The engineer shall hold weekly meeting of all the contractors working at site at a<br />

time and a place to be designated by the engineer. The contractor shall attend such<br />

meetings and take notes of discussions during the meeting and the decisions of the<br />

engineer and shall strictly adhere to those decisions in performing this work. In<br />

addition to the above weekly meeting, engineer may call for other meetings either<br />

with individual contractors or with selected number of contractors and in such a<br />

case the contractor, if called will also attend such meetings.<br />

17.4 Time is the essence of the contract and the contractor shall be responsible for<br />

performance of his work in accordance with the specified construction schedule. If<br />

at any time the contractor is falling behind the schedule, he shall take necessary<br />

action to make good of such delays by increasing his work to comply with the<br />

schedule and shall communicate such action in writing to the engineer, satisfying<br />

that his action will compensate for the delay. The contractor shall not be allowed<br />

any extra compensation for such action.<br />

17.5 The engineer shall however not be responsible for provision of additional labour<br />

and or materials or supply of any other services to the contractor except for the coordination<br />

work between various contractors as set out earlier.<br />

17.6 The works under execution shall be open to inspection & supervision by BHEL's /<br />

Owner's engineer at all times. The contractor shall give reasonable notice to BHEL<br />

before covering up or otherwise placing beyond the reach of inspection any work, in<br />

order that same may be verified, if so desired by owner/ BHEL.<br />

17.7 Every effort shall be made to maintain the highest quality of workmanship by<br />

stringent supervision and inspection at every stage of execution. Manufacturer's<br />

instruction manual and guidelines on sequence of erection and precautions shall be<br />

strictly followed. Should any error or ambiguity be discovered in such documents<br />

the same shall be brought to the notice of BHEL's engineer. Manufacturer's<br />

interpretation in such cases shall be binding on the contractor.<br />

17.8 The contractor shall comply with all the rules and regulations of the local<br />

authorities, all statutory laws including Minimum Wages, Workmen Compensation<br />

etc. All registration and statutory inspection fees, if any, in respect of the work<br />

executed by the contractor shall be to his account.<br />

17.9 All the works such as cleaning, checking, levelling, blue matching, aligning,<br />

assembling, temporary erection for alignment, opening, dismantling of certain<br />

equipment for checking and cleaning, surface preparation, edge preparation,<br />

fabrication of tubes and pipes as per general engineering practice at site, cutting,<br />

grinding, straightening, chamfering, filling, chipping, drilling, reaming, scrapping,<br />

shaping, fitting-up, bolting/ welding, etc as may be applicable in such erection and<br />

necessary to complete the work satisfactorily, are to be treated as incidental and<br />

the same shall be carried out by the contractor as part of the work.<br />

17.10 It is the responsibility of the contractor to do the alignment etc if necessary,<br />

repeatedly to satisfy engineer, with all the necessary tools & tackles, manpower etc.<br />

The alignment will be complete only when jointly certified so, by the contractor's<br />

engineer and BHEL. Also the contractor should ensure that the alignment is not<br />

disturbed afterwards.<br />

17.11 Equipment and material, in case wrongly installed, shall be removed and<br />

reinstalled to comply with the design requirement at the contractor expense, to the<br />

satisfaction of BHEL/ owner.<br />

17.12 After identification of erection materials by BHEL at BHEL's store/ storage yard, it<br />

shall be the responsibility of the contractor to take delivery of materials from BHEL's<br />

store/ storage yard by contractor's own manpower and re-stack the leftover<br />

materials as per erection sequence at BHEL store at their own cost. The entire<br />

activities are to be carried out under supervision of BHEL's engineer.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 16 OF 35<br />

18.0 PROJECT MANAGEMENT/ CONSTRUCTION MANAGEMENT<br />

To meet the need of construction management at site, contractor shall provide the<br />

following services within quoted/ accepted rates.<br />

18.1 PLANNING & MONITORING<br />

18.1.1 The bidder shall prepare detail construction schedule (L-3) as per completion dates<br />

given in this document. This schedule must include all milestone and key activities<br />

for each subsystems/ components in the areas of engineering (wherever<br />

applicable), procurement, manufacture (wherever applicable), despatch,<br />

excavation/ construction/ erection. This network must conform to the overall project<br />

schedule. The bidder should also ensure monitoring of these activities at least<br />

weekly basis to start with and on daily basis whenever required by BHEL.<br />

Sl<br />

Work to be completed Period from<br />

no<br />

start of work<br />

1 Completion of excavation, PCC Within 70 days<br />

2 Completion of chimney raft casting & order placing for stack Within 135<br />

elevator.<br />

days<br />

3 Completion of Inter form equipment erection (1st stage). Within 160<br />

days<br />

4 Completion of RCC shell concreting upto EL (+) 5 M. Within 190<br />

days<br />

5 Completion of electrical winch, passenger hoist external &<br />

internal platform etc fixing (2nd & final stage of Interform<br />

equipment erection), temporary lightening arrestor with<br />

electrode, temporary aviation obstruction lighting system,<br />

temporary communication system.<br />

6 Completion of slip form concreting, dismantling of slip form<br />

equipment (part), roof casting.<br />

7 Completion of mini shell concreting & slip form equipment<br />

dismantling (balance portion).<br />

8 Completion of all corbel, internal painting, brick flue lining,<br />

insulation, MS liner bands fixing, completion of permanent<br />

earthing system and hopper including AR bricks completion,<br />

and readiness for boiler light up.<br />

9 Completion of erection of external platform, ladder, all<br />

electrical installation. All MS doors & access doors and<br />

sampling pot erection completion, rain water pipe fixing and<br />

mini shell cap fixing, erection completion of stack elevator<br />

with commissioning.<br />

Within 220<br />

days<br />

Within 430<br />

days<br />

Within 480<br />

days<br />

Within 800<br />

days<br />

Within 930<br />

days<br />

10 Completion of external painting and all other finishing work Within 990<br />

and completion of all chimney works in all respects. days<br />

18.1.2 The bidder shall also prepare progress report indicating progress on key activities,<br />

management summary for critical activities, list of actions requiring attention of<br />

BHEL. This schedule is to be preferably made in MS PROJECTS, so that the same<br />

is compatible with BHEL’s project management software.<br />

18.1.3 The bidder will have to install one no PCs with the minimum specification of<br />

(multimedia PC work station Pentium-Duo, 1 GHZ or above, 120 GB HDD, 1GB<br />

RAM, 100 MBPS LAN card of HCL/ COMPAQ/ ZENITH or equivalent make with<br />

window XP (professional) O/S and required software like MS Office 2007<br />

Professional, AutoCAD 2007, PageMaker (7.0 etc), ADOBE PDF CREATOR with<br />

one no laser jet printer compatible for A3 size printing (cartridge to be supplied as 1<br />

cartridge per 4 months or depending on the requirement, whichever is less), one<br />

nos. laser jet printer compatible for A4 size printing ((cartridge to be supplied as 1<br />

cartridge per 4 months or depending on the requirement, whichever is less) with<br />

power backup at places, as per instruction of BHEL for exclusive use of BHEL.<br />

These computers, printers shall remain contractor’s property and they will be<br />

allowed to take out the same after completion of the site works. The contractor shall


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 17 OF 35<br />

provide data / information etc in prescribed formats for periodical updating of the<br />

progress reports, material management reports, updating of network pertaining to<br />

the contractor’s scope of work etc.<br />

The contractor shall also provide one no computer operator and two numbers<br />

service staff for miscellaneous service for BHEL’s exclusive use at site/ Kolkata for<br />

material and document reconciliation, progress MIR & day-to-day documentation<br />

etc. This facility to be provided from 2 nd month from LOI date till completion of site<br />

works or as decided by BHEL. If contractor fails to provide computer/ printer or<br />

personnel as per requirement, for a continuous period of thirty days or more, BHEL<br />

shall have the right to deduct the amount as per following rates on prorate basis,<br />

from contractor's RA bill or any other dues.<br />

18.1.3.1 @ Rs.10, 000/- (Ten thousand)/ month for each computer operator.<br />

18.1.3.2 @ Rs.9, 000/- (Nine thousand)/ month for each computer with printer.<br />

18.1.3.3 @ Rs.7,000/- (Seven thousand)/ month for each service staff.<br />

18.1.3.4 In the event of the contract period getting extended beyond the stipulated time for<br />

reasons not attributable to the bidder, the deployment of above personnel shall be<br />

reviewed by Construction Manager, BHEL for further continuation. If their services<br />

are still utilized, the bidder will be reimbursed the actual expenditure incurred by the<br />

bidder in providing the service limited to Rs 8000 per month for each computer<br />

operator, and Rs 6000 per month for each service staff.<br />

18.1.4 The contractor’s site office must have facilities of communications like Fax, E-mail,<br />

and telephone with STD facility within a month from LOI.<br />

18.2 PROGRESS REPORTING<br />

18.2.1 The bidder shall submit daily, weekly and monthly progress reports for work force,<br />

materials reports, consumables (gases/electrodes) report and other reports as per<br />

pro-forma considered necessary by the BHEL.<br />

18.2.2 The progress report shall indicate the progress achieved against planned with<br />

reasons indicating delays, if any, and shall give the remedial actions which the<br />

contractor intends to take to make good the slippage or lost time, so that further<br />

works again proceed as per the original program and the slippage's do not<br />

accumulate and effect the overall program.<br />

18.2.3 The daily work force reports shall clearly indicate the work force deployed,<br />

category-wise specifying also the activities in which they are engaged.<br />

18.2.4 Weekly progress review meetings will be held at site during which actual progress<br />

during the week vis-à-vis scheduled program shall be discussed or actions to be<br />

taken for achieving targets. For discussions, the contractor shall present program of<br />

subsequent week. The contractor shall constantly update/revise his work program<br />

to meet the overall requirement.<br />

18.2.5 Periodic progress reviews on the entire activities of execution in respect of supply<br />

and works in scope of bidder will be held once in a month at Kolkata/ site. These<br />

meetings will be attended by reasonably higher officials of the contractor and will be<br />

used as a forum for discussing all areas where progress needs to be speeded up.<br />

The contractor shall be further responsible for ensuring that suitable steps are<br />

taken to meet various targets decided upon such meetings.<br />

18.2.6 Two sets of color photographs in addition to colour photographs in the monthly<br />

progress report (Matt paper, post card size for each area per month of the contract<br />

execution period), depicting progress of the work, as directed by BHEL site<br />

engineer is to be arranged by the successful bidder at his own cost.<br />

18.2.7 Successful bidder has to provide for electronic/ computerized storing and reproduction/<br />

printing/ plotting of various data, log sheets, protocols, measurements<br />

etc. These may be stored in CD (as per requirement) and handed over to BHEL as<br />

per requirement.<br />

18.3 SITE ORGANIZATION<br />

18.3.1 The contractor shall maintain a site organization of adequate strength in respect of<br />

manpower, construction machinery and other implements at all time for smooth


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 18 OF 35<br />

execution of the contract headed by a competent construction manager for site<br />

operations with sufficient level of authority to take site decisions. The vendor will<br />

submit organization chart (showing the name of Site-in-charge) with individual biodata<br />

indicating various levels of experts to be posted for supervision in the fields of<br />

supervision and execution, quality, material management, planning, safety, etc. The<br />

organization shall be reinforced from time to time, as required to make up slippage<br />

(if any) from the schedule without any commercial implication to BHEL. The<br />

organization chart is to be submitted within 10 days from the date of LOI or as<br />

directed otherwise by Project Manager/ Construction Manager, BHEL.<br />

18.3.2 Following (minimum) engineering manpower with power plant construction<br />

background to be deployed at site by the successful vendor.<br />

18.3.2.1 Qualified safety officer (exclusive One no - from start of work.<br />

for safety supervision)<br />

18.3.2.2 Site supervising engineer Three nos - (1st civil engineer from the first<br />

month, 2nd civil eng from Third month<br />

onwards, 3rd engineer from 6th month after<br />

start of work.<br />

18.3.2.3 Engineer for quality inspection. One no. - from start of work.<br />

18.3.2.4 Supervisor As required for satisfactory execution of work.<br />

18.3.2.5 Material management, site enabling - one no.<br />

18.3.2.6 Engineer/ supervisor for other functions like store & purchase, material<br />

management, planning, fin, admn etc are to be provided as per site requirement<br />

and not considered above.<br />

18.3.2.7 In the event of non deputation of engineer/ supervisor/ BHEL shall reserve the right<br />

to deduct Rs 40000.00 per man-month for engineer and Rs 30000.00 per manmonth<br />

for the supervisor/ safety officer, from the date of deputation as indicated as<br />

above/as per job requirement from RA bills. Further induction of manpower<br />

regarding site supervisor & site engineer will be decided at site as per requirement.<br />

18.3.2.8 BHEL reserves the right to reject or approve the personnel proposed to be<br />

deployed by the contractor. The persons whose bio-data have been approved by<br />

BHEL will have to be posted at site and deviation in this regard will not be permitted<br />

unless specific & reasonable justification is made.<br />

18.3.2.9 In addition to above, a well experienced qualified engineer to be designated, as<br />

'Project Co-coordinator', shall be deployed by the contractor. Such engineer shall<br />

have adequate exposure on the job and shall remain fully involved in all planning<br />

activities, guidance etc to contractor's own team during the complete execution<br />

period of contract.<br />

18.3.2.10 The contractor should also submit to BHEL for approval a list of T&Ps along with<br />

their fitness certificates. The tools & tackles shall not be removed from site without<br />

written permission of BHEL.<br />

18.3.2.11 The contractor should also submit network programs for the erection of various<br />

items. These networks shall show the customer/ BHEL hold points (CHP), which<br />

have to be cleared by customer/ BHEL, or their authorized representatives before<br />

further erection can take place. These programs for the erection would clearly<br />

identify responsibilities of the contractor and customer/ BHEL. It is the responsibility<br />

of the contractor to get the Networks approved by BHEL within four weeks of the<br />

date of finalization of award of work/ placement of LOI.<br />

18.3.3 CONSTRUCTION MANAGEMENT<br />

18.3.3.1 Based on the approved program the contractor shall submit a program of<br />

construction/ erection/ commissioning for the implementation. These programs<br />

would be amplified showing start of erection and subsequent activities and shall<br />

form the basis for site execution and detail monitoring. The three monthly rolling<br />

program with the first month's program being tentative based on the site condition<br />

would be prepared based on these programs. The contractor shall also be involved<br />

along with customer/ BHEL to tie up detailed resources mobilization plan over the<br />

period of the contract matching with the performance targets.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 19 OF 35<br />

18.3.3.2 The program would be jointly finalized by the site in-charge of the contractor with<br />

BHEL/ customer's project coordinator as well as the site-planning representative.<br />

The erection program will also identify the sequential events matching financial<br />

turnover.<br />

18.3.3.3 The contractor is liable to furnish all documentary evidences towards payment of<br />

Works Contract Tax as when required by BHEL.<br />

19.0 RESPONSIBILITY OF CONTRACTOR<br />

19.1 ACCOMMODATION FOR THE LABOUR/ STAFF<br />

19.1.1 The contractor has to make his own arrangement for accommodation of his<br />

workmen and other employees. BHEL/ customer shall not provide any facility in this<br />

regard. As of now, no land will be provided by customer for construction of labour<br />

colony. However, if felt necessary, bidder may make appeal to customer for<br />

allotting some land for the same and subject to availability this may be allotted as<br />

per the terms and conditions of customer.<br />

In extreme exigency, subject to availability of residential accommodation from<br />

customer within project premises, BHEL may arrange the same for the contractor’s<br />

staff on chargeable basis. The charges to contractor by BHEL will be the same as<br />

the charges levied by customer on BHEL. Such availability of the residential quarter<br />

shall be subject to approval of customer.<br />

19.2 TOOLS AND TACKLES, MEASURING AND MONITORING DEVICES.<br />

19.2.1 The contractor shall provide all (excepting those in BHEL scope) required tools and<br />

plants, monitoring and measuring devices (MMD) and handling & transportation<br />

equipments for the scope of work covered under these specifications. Contractor<br />

has to provide suitable cranes for material handling at BHEL/ client’s stores/<br />

storage yard. BHEL’s crane will not be available for this purpose.<br />

19.2.2 Tentative list of T&P to be deployed for respective packages, by the contractor for<br />

successful completion of work is mentioned.<br />

19.2.3 It may be noted that the list is not exhaustive and is only for general guidance. The<br />

contractor is required to provide all necessary T&P (other than those specified to be<br />

provided by BHEL) measuring (calibrated) instruments and handing equipments for<br />

timely completion of the total works as per contract. In case of project requirement,<br />

some activities may have to pre-pone. In such cases the contractor may have to<br />

deploy additional T&P. The quoted rate shall be inclusive of such requirements.<br />

19.2.4 In the event of any failure of the part of the contractor, BHEL may at his discretion<br />

also terminate the contract on this ground and take out any or whole amount of the<br />

contract from the scope of the contractor. In the event of failure of contractor to<br />

deploy necessary and sufficient T&P/ IMTEs. BHEL will be at liberty to arrange the<br />

same at the risk and cost of contractor including transportation cost of same from<br />

any of BHEL site/ other agency and charges as applicable shall be deducted from<br />

contractor's R/A bill. Decision of BHEL in this regard will be final and binding on the<br />

contractor.<br />

19.2.5 All tools and tackles to be deployed by the contractor for the work shall have the<br />

prior approval of BHEL Engineer with regard to brand, quality and specification.<br />

19.2.6 Contractor’s responsibilities with regard to operator, fuel, lubricants and daily upkeep<br />

of T&P’s provided by BHEL is further detailed in relevant section.<br />

19.2.7 Timely deployment of adequate quantity of T&P is the responsibility of the<br />

contractor. The contractor shall be prepared to augment the T&P at short notice to<br />

match the planned programme and to achieve the milestones.<br />

19.2.8 Contractor shall maintain and operate his tools and plants in such a way that major<br />

breakdowns are avoided. In the event of major breakdown, contractor shall make<br />

alternative arrangements expeditiously so that the progress of work is not<br />

hampered.<br />

19.2.9 In the event of contractor failing to arrange the required tools, plants, machinery,<br />

equipment, material or non-availability of the same owing to breakdown, BHEL will<br />

make the alternative arrangement at the risk and cost of the contractor.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 20 OF 35<br />

19.2.10 The T&P to be arranged by the contractor shall be in proper working condition and<br />

their operation shall not lead to unsafe condition. The movements of cranes and<br />

other equipments should be such that no damage/ breakage occurs to foundations,<br />

other equipments, material, property and men. All arrangements for the movement<br />

of the T&P’s etc. shall be the contractor’s responsibility.<br />

19.2.11 Normally, for welding use of welding generators/ rectifiers only is permitted. The<br />

use of welding transformers will be subject to the approval of BHEL Engineer.<br />

19.2.12 The contractor at his cost shall carry out periodical testing of his construction<br />

equipments and calibration of measuring & monitoring devices (MMDs). Test /<br />

calibration certificates shall be furnished to BHEL. MMDs shall be calibrated only at<br />

accredited laboratory as per the list available with BHEL or any other laboratory<br />

approved by BHEL.<br />

19.2.13 T&P and IMTE/ MMD once deployed cannot be taken out without the written<br />

consideration of Construction Manager of BHEL.<br />

19.2.14 The requirement of the T&Ps deployed by the contractor for the work shall be<br />

reviewed by Construction Manager after sufficient work progress is made during<br />

execution of the contract including extensions, if any and BHEL may accord<br />

permission for release of the cranes based on requirement for the work.<br />

19.2.15 The contractor shall ensure deployment of reliable and calibrated instrument,<br />

measuring, and test equipment (IMTE). The IMTE shall have test calibration<br />

certificate from authorized/ Govt approved agencies. The contractor shall also keep<br />

provision of alternate engagement for such IMTE so that the work does not suffer<br />

when a particular IMTE is sent for calibration. Re-testing/ re-calibration shall also be<br />

arranged by the contractor at their own cost at regular interval during the period of<br />

use as advised by BHEL.<br />

19.3 CONSUMABLES<br />

19.3.1 Tentative list of major consumables to be provided by the contractor for respective<br />

packages of work under the scope is indicated in Annexure – VI.<br />

19.3.2 The contractor shall provide all consumables required for carrying out the work<br />

covered under these specifications excepting those, which are specifically indicated<br />

as BHEL scope.<br />

19.3.3 All consumables to be used for the work shall have prior approval of BHEL<br />

Engineer with regard to brand and quality specifications. Test reports / certificates<br />

in respect of these consumables, wherever applicable, shall be submitted to BHEL<br />

Engineer.<br />

19.4 PRIMERS & PAINTS<br />

19.5 WELDING ELECTRODES, FILLER WIRES FOR WELDING AND GASES<br />

19.5.1 All the required welding electrodes as approved by BHEL shall be arranged by<br />

contractor at his cost. It shall be the responsibility of the contractor to obtain prior<br />

approval of BHEL, before procurement, regarding manufacturer, type of electrodes<br />

etc. on receipt of the electrodes at site, it shall be subject to inspection and<br />

approval by BHEL regarding type of electrodes, batch number, date of expiry etc.<br />

Batch test certificates shall be made available for verification & record before the<br />

actual use of the welding consumables.<br />

19.5.2 BHEL reserves the right to reject the use of any electrodes, if found non-acceptable<br />

because of bad quality, deterioration in quality due to improper storage, shelf life<br />

expiry, unapproved type / band etc.<br />

19.5.3 Filler wires, for Tig welding of pressure parts & piping of Packge B, to the extent<br />

supplied by the manufacturing units of BHEL alongwith the components/<br />

equipments only shall be provided by BHEL free of cost. Contractor shall at his cost<br />

meet requirements of tig filler wires, if any, beyond these free issue of BHEL.<br />

19.5.4 All the required gases like argon, oxygen, acetylene etc. shall be arranged by the<br />

contractor at his cost. Nitrogen gas, if required, for chemical cleaning / preservation<br />

of boiler and piping system of Packge B will be provided by BHEL free of charge.<br />

19.6 FIELD/ SITE OFFICE<br />

19.6.1 The contractor shall make his own arrangements for field offices and stores for


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 21 OF 35<br />

accommodating necessary equipments, tools room for execution of the work. Only<br />

open space will be provided by BHEL/ customer, free of charges within the project<br />

premises as per the availability of space.<br />

In addition to his site office, the contractor shall arrange a temporary stores near<br />

the site of erection for temporary storage of small materials like fasteners, gaskets,<br />

valve and fittings and other instruments. The necessary structural steel, sheeting,<br />

racks etc. for this work shall be arranged by the contractor at his cost.<br />

19.6.2 On completion of work, all the temporary buildings, structures, pipelines, cables etc.<br />

shall be dismantled and leveled and debris shall be removed as per instruction of<br />

BHEL by the contractor at his cost. If contractor is failed to do so, BHEL will get the<br />

job done through other agency and the cost will be recovered from the contractor.<br />

The decision of BHEL Engineer in this regard shall be final. However, the scope of<br />

dismantling and leveling the area is limited only to the contractor’s site office, yard<br />

and other spaces occupied by the contractor.<br />

20.0 TOOLS & PLANTS (TO BE PROVIDED BY CONTRACTOR)<br />

20.1 Tentative list of T&P to be deployed by contractor for successful completion of work<br />

is detailed below. This supersedes corresponding Annexure of <strong>Volume</strong>-1E<br />

20.2 It may be noted that the list is not exhaustive and is only for general guidance. The<br />

contractor is required to provide all necessary T&P (other than those specified to be<br />

provided by BHEL) measuring (calibrated) instruments & handing equipments for<br />

timely completion of total work as per contract. In case of project requirement,<br />

some activities may have to pre-pone. In such cases the contractor may have to<br />

deploy additional T&P. Quoted rate shall be inclusive of such requirements.<br />

However, contractor shall submit deployment plan of all T&P along with tender bid.<br />

20.3 In the event of any failure of the part of the contractor and as a result progress of<br />

work suffered, BHEL may at his discretion also terminate the contract on this<br />

ground and take out any or whole amount of the contract from the scope of the<br />

contractor. In the event of failure of contractor to deploy necessary and sufficient<br />

T&P/ IMTEs. BHEL will be at liberty to arrange the same at the risk & cost of<br />

contractor including transportation cost of same from any of BHEL site/ other<br />

agency & charges as applicable shall be deducted from contractor’s RA bill.<br />

Decision of BHEL in this regard will be final & binding on contractor.<br />

20.4 Following Major T&Ps to be arranged by contractor within the time as indicated<br />

against each T&P.<br />

Major T&P items<br />

Mobilisation time (from<br />

the date of written<br />

intimation by BHEL)<br />

20.4.1 1 no hydra (10/ 12 T cap). within 30 days.<br />

20.4.2 Two numbers PLC based automatic batching plant with<br />

printing facility (15 cum/ hr) – to be commissioned at site.<br />

However, vendor may mobilize one batching plant<br />

provided he has tie-up arrangement with other vendor for<br />

supply of ready mixed concrete during chimney raft<br />

casting.<br />

Within 60 days.<br />

20.4.3 2 nos transit mixer (4.5/ 5/ 6 M3 capacity) Within 60 days.<br />

20.4.4 2 nos concrete pump (20 cum/ hr min capacity & lift Within 60 days.<br />

70M). Can be taken out after completion of raft casting.<br />

20.4.5 1 no air compressor. Within 45 days.<br />

20.4.6 2 nos self priming dewatering pump 5 HP (diesel/ Within 20 days.<br />

electric).<br />

20.4.7 2 nos self priming dewatering pump 2 HP (diesel/ Within 15 days.<br />

electric).<br />

20.4.8 2 no multi stage high lift water pump (for curing) (lifting<br />

height shall be 300 metre). One shall be working and<br />

other will be stand by.<br />

Within 150 days.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 22 OF 35<br />

20.4.9 1 no hydraulic excavator/ poclain. Within 20 days.<br />

20.4.10 1 no dozer. Within 20 days.<br />

20.4.11 1 no pneumatic hammer. As per site requirement<br />

20.4.12 4 nos dumper. Within 20 days.<br />

20.4.13 1 nos reinforcement bending machine. Within 20 days.<br />

20.4.14 1 nos reinforcement cutting machine. Within 20days.<br />

20.4.15 1 no compression testing machine (200 T cap). Within 75days.<br />

20.4.16 Other civil lab equipment with proper (15 M x 6 M) shed. Within 75days.<br />

20.4.17 1 no total station. Within 20 days.<br />

20.4.18 1 no theodolite 1 second accuracy. Within 20 days.<br />

20.4.19 2 nos auto level & staff. Within 20 days.<br />

20.4.20 1 nos DG set (180 KVA). Within 130 days.<br />

20.4.21 72 nos concrete cube moulds. Within 40days.<br />

20.4.22 Inter form equipment set including hydraulic spare pump, Within 130days<br />

10% spare jack, epoxy painted MS shutter plate,<br />

materials and passenger hoist with safety block (safety<br />

devices), hanging platform for inside and outside, safety<br />

ropes etc complete - 1 set.<br />

20.4.23 1 no drinking water tank – 3000 lit. Within 30 days.<br />

20.4.24 Radioset – 1 no (VHF/UHF.) Within 120 days.<br />

20.4.25 Portable fire extinguishers as below:<br />

Within 60 days<br />

Soda acid – 3 sets.<br />

Dry chemical powder – 2 sets<br />

CO2 – 2 sets.<br />

Water & sand bucket(4 buckets in one stand) – 2 sets.<br />

Fire hose with nozzle (50 M length) – 2 sets.<br />

20.5 T&P shown in the above mentioned list are minimum requirement. Mobilisation<br />

period shown above for major T&Ps have to be adhered and no change will be<br />

permitted without written approval of Construction Manage, BHEL. Further<br />

requirement will be reviewed time to time at site and vendors will provide additional<br />

T&P/ equipments to ensure completion of entire work within schedule time without<br />

any financial implication to BHEL. All other T&Ps shall be provided by the<br />

contractor without any extra cost to customer/ BHEL. Vendor will give advance<br />

intimation & certification regarding capacity etc prior to dispatch of heavy<br />

equipments.<br />

20.6 All T&P and all IMTEs, which are required for successful and timely execution of<br />

the work covered within the scope of this tender, shall be arranged and provided by<br />

the contractor at his own cost in working condition.<br />

21.0 INSURANCE<br />

20.1 BHEL shall arrange insurance coverage for the material and properties of BHEL/<br />

customer covering the risks during transit, storage, erection and commissioning.<br />

20.2 The contractor shall be responsible for timely submission of loss/damage/theft to<br />

the underwriter, assistance in lodging & settlement of claim for losses/ damages/<br />

theft/ lodging of FIR with police.<br />

20.3 It is the entire responsibility of the contractor to insure his workmen against<br />

accident and injury while at work as required by the relevant rules and to pay<br />

compensation, if any, to their workmen as per workmen's compensation act. The<br />

contractor has also to insure his staff against accident/injury. The contractor has to<br />

take insurance cover for his tools and plants, assets etc.<br />

20.4 These insurance covers have to be taken prior to start of work at the subject project<br />

and he shall make available the policy to BHEL site-in-charge for necessary<br />

verification before commencement of work. However, irrespective of such<br />

verification/ acceptance, the sole responsibility to maintain adequate insurance<br />

cover for his workmen, T&P, assets etc at all times during the period of contract<br />

shall lie with the contractor. Regarding the aforesaid insurance cover, the contractor<br />

shall directly deal with the Insurance Company for all matters regarding the


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 23 OF 35<br />

insurance in his scope.<br />

22.0 MATERIAL HANDLING OF CEMENT & STEEL<br />

22.1 Cement, steel (reinforcement TMT bar, MS round for under ground earthing and<br />

structural rolled steel sections like plate, beams, channels, angles) will be issued<br />

free of cost by BHEL for use in the work covered in this contract.<br />

22.2 Consignment of steel/ cement will be directly issued to the contractor as received<br />

by BHEL, on weighment basis from its supplier, as per delivery challan of the<br />

supplier.<br />

22.3 It would be the responsibility of the contractor to keep in constant contact with<br />

BHEL/ site to find out the delivery status, arrival of the consignments and arrange<br />

for escort to accompany the truck/ trailor for transportation of above materials by<br />

BHEL’S supplier, if necessary. The lorry, truck way bill for the consignment as shall<br />

be received by BHEL would be handed over to the contractor immediately for<br />

unloading of materials including all arrangement for necessary gate passes etc.<br />

Unloading of cement and steel from trailer/truck/wagon is in the scope of the<br />

contractor and contractor’s quoted rate shall be inclusive of the same<br />

The arrangement for unloading of cement and steel with necessary cranes and<br />

workmen is the responsibility of the contractor.<br />

22.4 Payment of all demurrages that may result due to contractor’s fault/ delay would be<br />

the responsibility of the contractor. If BHEL have to make payment of demurrage<br />

together with freight, the amount so paid as demurrages for the reasons stated<br />

above, shall be recovered from the bills of the contractor. The decision of BHEL’s<br />

engineer in this regard will be final and binding on the contractor. However the<br />

contractor has to clear all such charges, if any in this regard and complete the job<br />

without waiting for BHEL’s decision.<br />

22.5 It would be the responsibility of the contractor to sign on the delivery book<br />

acknowledgement slip of supplier/ transport authorities etc.<br />

22.6 Consignments coming on Sundays and holidays are also required to be handled<br />

/unloaded by the contractor. Since the offices and stores will probably remain<br />

closed on such days, it will be the responsibility of the contractor to contact BHEL<br />

Engineers at their residence and obtain instructions.<br />

22.7 Since the consignments are expected to arrive during any time of the day or night,<br />

the contractor shall have his workmen round the clock at site as well as other<br />

places as required to unload the materials immediately on arrival.<br />

22.8 Unloading of materials at the storage yard or at places designated by BHEL,<br />

stacking & restacking, shifting & re-shifting, using contractor’s own cranes, trailers<br />

and other equipments with the valid road permit for their operation, unloading and<br />

stacking etc shall be responsibility of the contractor under this contract. All<br />

materials/equipments shall be stacked, stored above ground level by use of<br />

concrete or wooden sleepers. No materials shall remain on ground at any time. All<br />

concrete or wooden sleepers required for stacking the materials shall be arranged<br />

by the contractor at his own cost. All other material handling equipments like<br />

winches, d-shackles, slings of various sizes, max puller, pulley blocks, jacks, trucks,<br />

tailors etc. required for such material handling of steel, cements etc. shall be<br />

arranged by the contractor within quoted/accepted rates.<br />

22.9 It will be the responsibility of the contractor to submit computerized account of all<br />

such consignments of materials received by them, daily to BHEL.<br />

22.10 BHEL reserve the right to recover from the contractor any loss arising out of<br />

damage/ theft or any other causes of the materials issued to him at any point.<br />

22.11 Open land (very limited space) for storage shall be provided by BHEL on free of<br />

cost basis. Temporary barbed wire fencing of the open storage yard is to be done<br />

by the contractor and is included under the scope of his work. The contractor shall<br />

also remove grass, bushes, trees etc wherever required off the land provided to<br />

him and shall make proper continuous up-keepment of the open yard /land by


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 24 OF 35<br />

removing grass, bushes trees etc. and same is included under the scope of his<br />

work & no extra payment shall be made to the contractor in this regard. The bidder<br />

shall make complete arrangement of necessary security personnel, to safeguard all<br />

such materials in his custody. Materials issued will be used only for construction of<br />

permanent work. The contractor shall take care of material issued by BHEL and<br />

shall protect the same from theft, damage and weathering.<br />

22.12 The contractor shall construct waterproof cement stores (Capacity minimum 200<br />

MT) for storing and stacking of cement at his own cost.<br />

22.13 The contractor shall in no case be entitled for any compensation or damages on<br />

account of any delay in supply or non-supply thereof for all or any such material.<br />

22.14 Clotting of cement and excessive rusting of steel must be avoided. In case, due to<br />

any cause attributable to the contractor, such clotting of cement and/or rusting of<br />

steel occur rendering the same unusable, then such quantity of cement /steel shall<br />

be recovered from the interim payment at the penal rate specified in the tender.<br />

22.15 No material shall be issued to the contractor except as those indicated above i.e.<br />

cement and steel unless otherwise expressly provided for in the contract.<br />

Contractor will have to make his own arrangement at his own cost for procurement<br />

of any other material as required for the works and of such quality as acceptable to<br />

BHEL.<br />

22.16 The contractor shall maintain proper computerized store account for all the BHEL<br />

issued materials and shall give three copies of monthly computerised reconciliation<br />

statement of such account to the BHEL.<br />

22.17 The contractor shall carry out in complete association with BHEL, the material<br />

management functions and execution like day to day update of materials, issued to<br />

the contractor, accounting for surplus/ scrap material returned etc. These functions<br />

shall also be carried out through computerised system utilizing suitable software.<br />

The contractor shall provide experienced software personnel to associate on<br />

dedicated basis for efficient discharge of the same.<br />

22.18 The contractor shall solely be responsible for the safety & quality of material after it<br />

is handed over and issued to contractor by BHEL.<br />

22.19 BHEL issued materials shall not under any circumstances taken out of the project<br />

site unless otherwise permitted by BHEL.<br />

22.20 All the necessary lifting tackles, cranes, hydra, tools & plants including tractors,<br />

trailers, trucks, pulley blocks, jacks, winches, wire ropes etc, of suitable capacities<br />

and other equipments incidental to carry out this work shall have to be arranged by<br />

the contractor at his cost. BHEL Engineer reserves the right to inspect lifting tackles<br />

and equipment before allowing their use. Such approval however shall not relieve<br />

the responsibility of the contractor to ensure safe handling of equipment taking the<br />

precautions to avoid any accident and damage to other equipment and personnel.<br />

22.21 No separate rate will be applicable for the above jobs. The contractor shall organise<br />

necessary escort, as required, time to time during the transport of steel material<br />

from stock-yard of supplier to site with in quoted rate.<br />

23.0 ISSUE OF MATERIALS<br />

23.1 ISSUE OF CEMENT<br />

23.1.1 Cement as received from the manufacturer/ stockiest will be issued free of cost to<br />

the contractor. The theoretical weight or each bag of cement for issued purposes<br />

will be considered as 50 kg, the contractor shall be accountable for the cement<br />

issued to him on this notional weight only. No claim whatsoever will be entertained<br />

because of difference between theoretical and actual weight of the bags of cement.<br />

23.1.2 The empty cement bags duly accounted for against issue shall be the property of<br />

the bidder and the same shall be disposed by the bidder as per statutory regulation<br />

prevailing in the project.<br />

23.2 ISSUE OF STEEL<br />

23.2.1 The steel shall be issued to the contractor free of cost on the following basis.<br />

23.2.1.1 Rolled steel section ISMB, angles, plates, channels - Weighment basis (unit - MT).<br />

23.2.1.2 Reinforcement steel (TMT bars) and MS round for under ground earthmat -


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 25 OF 35<br />

Weighment basis (unit - MT).<br />

23.2.2 All the steel (reinforcement TMT bar, MS round for under ground earthmat and<br />

structural rolled steel sections like plate, beams, channels, angles and SS liner<br />

plate) issued by the BHEL shall be properly accounted for. The total quantity of<br />

steel required for the work will be calculated from the approved Bar Bending<br />

schedule, fabrication drawings, approved laps, chairs and lugs. The measurement<br />

for payment as well as for accounting shall be based on the sectional weights as<br />

indicated in the following IS specifications.<br />

IS: 808-1964 Beams, Channels and Angles<br />

IS: 1730-1961 Plates, Sheets and Strips<br />

Reinforcements Fe-500 confirming to IS: 1786. or grade-1 of IS:432 (part-I)<br />

23.2.3 In case any such sectional weights are not available in the above documents, the<br />

manufacturer recommendation shall be binding.<br />

23.2.4 The steel issued to the contractor shall be mainly in standard length and sections<br />

as received from the supplier. However, the contractor shall be bound to accept the<br />

steel in length as available in the project stores no claims for extra payment<br />

because of issue of non-standard length will be entertained.<br />

23.2.5 In case MS flats as required in the fabrication of structures are not available, the<br />

contractor shall cut such width out of the available MS plates to make flats at no<br />

extra cost till such material is available and procured by BHEL.<br />

23.2.6 The contractor shall satisfy himself of the quality and quantity of the materials at the<br />

time of taking delivery from BHEL/ customer stores. No claims whatsoever will be<br />

entertained by BHEL because of quality or quantity after the materials are taken by<br />

the contractor from BHEL/ customer stores.<br />

23.2.7 The contractor shall submit to the engineer, a statement indicating estimated<br />

quantity of cement and steel required at least two months in advance. In addition,<br />

the contractor shall also furnish the estimated requirement of cement and steel<br />

during a month by the third week of the previous month indicating his requirement.<br />

23.2.8 Bidders to ensure that no lamination material are taken over by them from BHEL.<br />

Fabrication wastage, if any due to above, shall not be compensated by BHEL<br />

23.2.9 Bidder to note that all fasteners like MS/ HT/ HSFG bolts/ nuts, lock nuts, washers<br />

etc shall be supplied by the bidder as per applicable item of BOQ-cum price<br />

schedule.<br />

23.2.10 Bidder to note that cement and steel required for his enabling job like store/ site<br />

office etc shall be arranged at his own cost. All TG staging material shall be<br />

arranged by contractor at his own cost. Bidder shall do the design for its structure<br />

just immediately after receipt of TG deck drawing and obtain approval from BHEL.<br />

24.0 RETURN OF MATERIALS<br />

24.1 RETURN OF CEMENT<br />

Sealed cement bags remaining unused and in perfectly good condition at the time<br />

of completion or termination of the contract shall be returned promptly, (within 15<br />

days from assessment) if BHEL/ Engineer is satisfied of the physical condition of<br />

the cement. Return of such cement to the project stores/ place as identified within<br />

the project area by Engineer/ BHEL will not be entitled to handling and incidental<br />

charges. Surplus sealed and good conditioned cement bags will be taken back on<br />

weighment basis.<br />

24.2 RETURN OF STEEL INCLUDING SCRAP<br />

24.2.1 All surplus steel and all wastage materials will be taken back on weighment basis.<br />

24.2.2 Surplus, unused and un-tampered steel shall be sorted dia-wise and returned<br />

separately for a place directed by BHEL/ engineer within the project area; Return of<br />

such materials will not be entitled to any handling and incidental charges.<br />

24.2.3 All wastage/ scrap (including wastage, unusable scrap) shall be returned to the<br />

stores on weighment basis and a receipt obtained for material accounting<br />

purposes. Return of such material will not be entitled to any additional cost due<br />

handling and transportation and incidental charge.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 26 OF 35<br />

24.2.4 Scrap for reinforcement steel and structural steel shall be returned separately<br />

25.0 CEMENT AND STEEL CONSUMPTION AND WASTAGE<br />

25.1 CEMENT CONSUMPTION<br />

25.1.1 The theoretical consumption of cement shall be based on the following.<br />

25.1.2 For design mix concrete as per approved design mix.<br />

25.1.3 For nominal mix concrete work, as per minimum cement as specified or as<br />

approved by Engineer-in-charge.<br />

25.1.4 For item of works, where volume mix is permitted in writing by the BHEL, for<br />

masonry works, plaster other miscellaneous items, the cement consumption shall<br />

be governed by the “Statement of Cement Consumption” attached to Delhi<br />

schedule of Rates of CPWD-DSR-2007 unless otherwise specified in the<br />

specifications or the drawing of contract of contract or mutually agreed by Engineerin-charge<br />

and contractor.<br />

25.1.5 Actual consumption= Issue – Surplus/unused quantity of cement returned in good<br />

condition by contractor to store. (No sweep cement will be taken back by BHEL).<br />

25.2 CEMENT WASTAGE<br />

25.2.1 Allowable wastage – One and half percent (+1.5%) of theoretical consumption of<br />

cement unless specified otherwise in the technical specification.<br />

25.2.2 For any material issued by BHEL to the contractor free of cost, and which is not<br />

accounted for by the contractor to BHEL, then recovery for such material shall be<br />

effected at penal rates.<br />

25.2.3 Sl Cement consumption<br />

Basis of issue<br />

no<br />

& penal<br />

recovery<br />

C-1 Theoretical consumption (without considering any wastage Free<br />

or loss).<br />

C-2 Actual consumption being Limited to plus one and half Free<br />

percent (+1.5%) of aforesaid theoretical consumption<br />

towards allowable wastage.<br />

C-3 Actual consumption beyond one and half percent (+1.5%) of Penal rate<br />

above (C-1).<br />

25.3 REINFORCEMENT STEEL & EARTHING MS ROUND CONSUMPTION<br />

25.3.1 The theoretical consumption of various diameter of reinforcement and earthing MS<br />

round shall be based on approved construction drawing and bar bending schedule.<br />

Weight shall be calculated considering the sectional weights as per Indian<br />

standards. No extra cost shall be payable to the contractor for any deviation in<br />

weights for the different procedures adopted for issue and calculation of the<br />

theoretical consumption including rolling tolerances.<br />

25.3.2 Actual consumption = Issue – Surplus.<br />

25.3.3 Surplus = Un-tampered and unused quantity of steel returned by the contractor to<br />

BHEL store along-with relevant documents.<br />

25.3.4 Wastage = Actual consumption – Theoretical consumption.<br />

25.4 REINFORCEMENT STEEL & EARTHING MS ROUND WASTAGE<br />

25.4.1 Allowable wastage – (+4%) of the theoretical consumption shall be considered as<br />

allowable wastage. Wastage is further classified as cut pieces and scrap measured<br />

as per actual weighment basis including rolling tolerance. Invisible wastage (loss of<br />

materials due to gas cutting, straightening of edges etc) shall be limited to 0.5 %<br />

(zero point five percent) of theoretical consumption and shall be considered for<br />

reconciliation purposes only. But this invisible wastage shall be considered to be<br />

included in allowable wastage (i.e. five percent)<br />

25.4.2 Wastage and scrap shall be as per actual weighment basis.<br />

25.4.3 Sl Reinforcement steel & earthing rod M S round<br />

Basis of issue<br />

no<br />

& penal<br />

R-1 Theoretical consumption (without considering wastage and<br />

scrap or loss)<br />

recovery<br />

Free


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 27 OF 35<br />

R-2 Wastage limited to plus four percent (+4%) of aforesaid Free<br />

theoretical consumption (R-1) towards allowable wastage.<br />

R-3 Wastage beyond four percent (+4%) of the theoretical Penal rate<br />

consumption above (R-1).<br />

25.5 STRUCTURAL STEEL MATERIALS CONSUMPTION<br />

25.5.1 The theoretical consumption of various sections shall be based on approved<br />

drawings. Weights shall be calculated considering the sectional weights as per<br />

Indian standard as mentioned in relevant clause. No extra shall be payable to the<br />

contractor for any deviation in weights for the two different procedures adopted for<br />

issue and calculation of the theoretical consumption including rolling tolerances.<br />

25.5.2 Actual consumption = Issue – Surplus.<br />

25.5.3 Surplus = Untempered, unused, uncut quantity of steel returned by the contractor to<br />

BHEL store.<br />

25.5.4 Wastage = Actual consumption – Theoretical consumption.<br />

25.6 STRUCTURAL STEEL WASTAGE<br />

25.6.1 Allowable wastage – 4 % (four percent) of the theoretical consumption shall be<br />

considered. Wastage is further classified as cut pieces and scrap measured as per<br />

actual weightment basis including rolling tolerance. Invisible wastage (loss of<br />

materials due to gas cutting, straightening of edges etc) shall be limited to 0.5 %<br />

(zero point five percent) of theoretical consumption and shall be considered for<br />

reconciliation purposes only. But this invisible wastage shall be considered to be<br />

included in allowable wastage (i.e. five percent).<br />

25.6.2 Sl Structural steel materials<br />

Basis of issue<br />

no<br />

& penal<br />

recovery<br />

S-1 Theoretical consumption (without considering any wastage, Free<br />

scrap or loss) as per specification & drg.<br />

S-2 Wastage limited to plus four percent (+4%) of the aforesaid Free<br />

theoretical consumption (S-1) towards allowable wastage.<br />

S-3 Wastage beyond four percent (4%) of the aforesaid Penal rate<br />

theoretical consumption (S-1).<br />

25.7 All wastage reinforcement, MS round (for earthing), structural steel shall be<br />

returned to BHEL.<br />

26.0 RECONCILIATION OF BHEL ISSUED MATERIALS<br />

26.1 The contractor shall submit a reconciliation statement of cement and steel issued to<br />

him with each RA bill.<br />

26.2 At the time of submission of bills, the contractor shall properly account for the<br />

material issued to him as specified herein to the satisfaction of BHEL certifying that<br />

the balance material are available with contractor’s custody at site.<br />

26.3 At the time of submission of bills by the contractor, if it is noticed by BHEL that the<br />

wastage is high and calls recovery at the penal rate, then BHEL will proceed for<br />

recovery for the excess wastage as per penal recovery rates as specified.<br />

26.4 The approved drawings/ bar bending schedules are to be considered for the<br />

purpose of reconciliation of materials.<br />

27.0 RECOVERY OF MATERIAL<br />

27.1 If wastage exceeds the specified limit, the recovery of excess wastage shall be<br />

made from monthly RA bill at the penal rate stipulated below.<br />

27.2 PENAL RATE OF MATERIALS<br />

Item<br />

Penal rate (Rs)<br />

27.2.1 Cement (OPC/ PPC/ PSC). 6,500/- per MT.<br />

27.2.2 Reinforcement steel and earthing rod etc. 58,000/- per MT.<br />

27.2.3 Structural steel. 65,000/- per MT.<br />

28.0 CONSTRUCTION OF TEMPORARY OFFICE, STORES ETC<br />

28.1 The contractor shall arrange at his own cost cleaning and grass removing of area<br />

allotted, construction of his temporary office/ stores, cement godown, fabrication<br />

yards etc. and also the watch and ward of all the above. Materials required for the


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 28 OF 35<br />

same shall be provided by contractor at his own cost.<br />

28.2 Customer/ BHEL will provide space for fabrication yard within plant premises.<br />

However; during execution, based on actual site conditions, requirement and layout<br />

and approaches, the above may change suitably.<br />

29.0 CIVIL LABORATORY AT SITE<br />

29.1 Contractor shall establish and maintain civil laboratory at site with equipments as<br />

listed in Annexure `A`<br />

29.1.1 Setting time of cement, compressive strength of cement, concrete cubes, bricks<br />

etc.<br />

29.1.2 Water absorption test of bricks.<br />

29.1.3 Earth compaction test (proctor density/ dry density and optimum moisture content,<br />

etc).<br />

29.1.4 Conducting of test for setting time and compressive strength of cement.<br />

29.1.5 Sieve analysis of fine aggregates and coarse aggregates.<br />

29.1.6 Bulking test of fine aggregates.<br />

29.1.7 Sieve analysis, moisture content, specific gravity and crushing strength of course<br />

aggregates<br />

29.1.8 Rapid moisture meter<br />

29.2 Other than above mentioned test, any testing required to be carried out at site as<br />

per Quality Plan and technical specification have to be arranged by contractor for<br />

all the works at his own cost.<br />

30.0 CONSTRUCTION SCHEDULE<br />

30.1 Entire work shall be carried out in accordance with the construction schedule within<br />

the stipulated completion period. Within 30 days of LOI, the contractor shall discuss<br />

with BHEL site engineer & furnish the (L-3) construction schedule based on<br />

milestones as per clause 14.1.1 for approval.<br />

30.2 Contractor will establish mix design within 40 days from the date of LOI.<br />

31.0 COMPLETION PERIOD<br />

The entire work under this scope shall be successfully completed in all respect<br />

within 33 months from the date of start of work as certified by BHEL engineer at<br />

site.<br />

The contractor shall mobilize at site and start the work within 30 days from date of<br />

written clearance by Construction Manager, BHEL, customer site.<br />

32.0 LIQUIDATED DAMAGE<br />

As per the provision of GCC.<br />

33.0 CERT<strong>IF</strong>ICATE TOWARDS COMPLETION<br />

The work under the scope of the contractor shall be deemed to have been<br />

completed in all respects only when so certified by BHEL. The decision of BHEL in<br />

this regard shall be final and binding on the contractor.<br />

34.0 GUARANTEE<br />

34.1 Even though the work will be carried out under supervision of BHEL, the contractor<br />

will be responsible for the quality of workmanship, quality of materials/ items and<br />

design for which the contractor is responsible.<br />

34.2 The contractor shall guarantee the work executed under the scope of the contract<br />

for a period of 12 (twelve) months from the date of start of guarantee period as<br />

certified by the Engineer (ie on completion of total work under scope and/ or taking<br />

over by BHEL) and shall rectify free of cost all defects due to faulty supply or work<br />

done. In case the contractor fails to repair/ replace the defective works within the<br />

time specified by the Engineer, BHEL may proceed to undertake the repairs/<br />

replace such defective works at contractor’s risk and cost without prejudice to any<br />

other rights and recover the same from security deposit/ other dues.<br />

35.0 INTEREST BEARING RECOVERABLE ADVANCE<br />

Not applicable for this tender.<br />

36.0 OVER RUN CHARGES<br />

No over run charges shall be paid to the contractor in the event the completion


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 29 OF 35<br />

period is extended for any reason whatsoever.<br />

37.0 REVISION ON ACCEPTED CONTRACT RATE<br />

No revision of rates shall be applicable in the event the completion period is<br />

extended for any reason whatsoever.<br />

38.0 PRICE VARIATION CLAUSE<br />

38.1 FOR CIVIL CONSTRUCTION PART (PART-IA OF PRIICE SCHEDULE)<br />

As per provision of GCC vide clause no 2.17.3 under column `A’ for civil packages.<br />

38.2 FOR ERECTION, COMMISSIONING PART (PART-IB OF PRICE SCHEDULE)<br />

As per provision of GCC vide clause no 2.17.3 for mechanical packages.<br />

39.0 SECURITY DEPOSIT & PERFORMANCE BOND<br />

39.1 Security deposit shall be applicable for Part-IA & Part-IB together as per relevant<br />

clause of GCC (<strong>Volume</strong>-IB).<br />

39.2 Performance bond is applicable for Part-IB of price schedule value as per following<br />

terms.<br />

39.2.1 In addition to the security deposit the contractor shall provide to BHEL bank<br />

guarantee of an approved nationalized bank for an amount equal to 5 % of the<br />

stated price as performance bond (under the terms of a bond) within 30 days from<br />

the date of LOI and the terms of the said bond shall be such as shall be approved<br />

by BHEL. The bond shall remain valid until 6 month after the expiry of warranty/<br />

guarantee period. The obtaining of such guarantee and the cost of bond to be so<br />

entered into shall be at the expense in all respects to the contractor.<br />

39.2.2 BHEL reserve the right of forfeiture of the above bond in addition to other claims<br />

and penalties in the event of the contractor’s failure to fulfil any of the contractual<br />

obligations or in the event of termination of contract as per terms and conditions of<br />

contract. BHEL reserve the right to set off this bond against any claim of any other<br />

contract with BHEL.<br />

40.0 CONTRACT PRICE<br />

40.1 The bidder shall quote their rates strictly in accordance with prescribed rate<br />

schedule of <strong>Volume</strong>-III/IIIA.<br />

40.2 The quantities of the various items mentioned in the BOQ cum rate schedules of<br />

items of <strong>Volume</strong>-IIIA are approximate, based on very preliminary information and<br />

may vary to any extent or to be deleted altogether. The quoted rates of each item<br />

will remain firm throughout the period of execution including extension, for reasons<br />

whatsoever, as long as variation in the total value of the work executed under any<br />

part of the this contract including extra items, if any, but excluding any price<br />

variation, remains within +/- 30 % (plus/minus thirty percent) of the awarded price<br />

as per LOI/ WO.<br />

41.0 TAXES, DUTIES ETC<br />

41.1 TDS under Income Tax, VAT etc, if any, shall be deducted at prevailing rates on<br />

Gross Invoice Value from the running bills unless Exemption Certificate from the<br />

appropriate authority/ authorities is furnished.<br />

41.2 All taxes (except Service Tax including Educational Cess and other Cess, if any),<br />

Works Contract Tax under VAT ACT, charges royalties, duties, Octroi, any State<br />

or Central Levy and other taxes for materials obtained for the work and for the<br />

Execution of the contract shall be borne by the contractor and shall not be payable<br />

extra. Any increase of the same at any stage during execution of the contract shall<br />

have to be borne by the contractor. Quoted rates/ price of the bidder shall be<br />

inclusive of all such requirements after taking the Input Credit, if any, as per<br />

provisions of the state VAT Act. The contractor is responsible to furnish all<br />

documentary evidences towards payment of Works Contract Tax as and when<br />

required by BHEL. Submission of Tax Invoice is a must after grossing up the bills<br />

as the price is inclusive of VAT.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 30 OF 35<br />

41.3 The contractor has to make his own arrangement at his cost for completing the<br />

formalities, if required, with state VAT Act authorities, for bringing their materials,<br />

plants and machinery at site for the execution of the works under this contract,<br />

Road Permit/ Way Bill, if required, shall be arranged by the contractor and BHEL-<br />

PSER will not supply any Road Permit/ Way Bill for this purpose. The contractor<br />

must be a Registered Dealer with the state VAT Act, if not registered yet and a<br />

copy of the said Registration Certificate along with TIN Number must be provided to<br />

site RAO.<br />

41.4 Service Tax: Finance Act, 2007 introduced a new sub-clause (zzzza) to Section 65<br />

(105) which provided for levying Service Tax on execution of Works Contract with<br />

effect from 01-06-07.<br />

Notification No 32/2007-Service Tax provides an option (of composition) to the<br />

person liable to pay Service Tax in relation to works contract service to pay an<br />

amount equal to 4.12 % of the gross amount charged for the Works Contract<br />

instead of normal rate provided in the Sec 66 of the Act. However, this option of<br />

paying service tax @4.12 % (at present) on gross value can be exercised prior to<br />

payment of Service Tax in respect of said Works Contract and the option so<br />

exercised shall be applicable for the entire works contract and shall not be<br />

withdrawn until the completion of said works contract.<br />

The contractor shall furnish proof of Service Tax registration with Central Excise<br />

Division covering the services as well as exercising the aforesaid option ie the<br />

Composition Scheme under Notification 32/2007 under this contract.<br />

Contractor is allowed to include the value of free issue of materials mainly steel,<br />

cement & other materials, supplied under supply contract based on monthly<br />

consumption basis to enable them to comply with Notification 23/2009–ST for<br />

arriving at Gross Amount charged .<br />

Alternatively:<br />

Vendor can avail Notification 29/2007–ST, dated 22-05-2007 where the “Taxable<br />

Service is value of works contract service determined shall be equivalent to the<br />

gross amount charged for the works contract less the value of transfer of property<br />

in goods involved in the execution of the said works contract.<br />

As such, Service Tax as legally leviable & payable by the contractor under the<br />

above provisions of applicable law/ act, shall be paid by BHEL-PSER on<br />

contractor’s gross bill.<br />

Registration should also bear endorsement for the premises from where the billing<br />

shall be done by the Contractor on BHEL-PSER for this project.<br />

BHEL-PSER will not be held to be responsible for non-compliance of various<br />

Service Tax rules, being framed from time to time.<br />

41.5 New tax & duties, if imposed subsequent to latest due date of offer submission (as<br />

per NIT and subsequent TCN, if any), by statutory authority during contract period<br />

(including extension, if the same is not attributable to the contractor), shall be<br />

reimbursed by BHEL on production of relevant supporting document to the<br />

satisfaction of BHEL. However, the vendor shall obtain prior approval from BHEL<br />

before depositing new taxes and duties.<br />

42.0 INTERIM PAYMENTS<br />

42.1 For all items of work as per <strong>Volume</strong>-III, Price Schedule, interim payment shall be<br />

limited to 95 % of the gross value of interim bill on item rate basis which will be<br />

prepared and submitted by the contractor on the basis of measurement sheet duly<br />

checked and signed by BHEL and/ or customer engineers. All admissible


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 31 OF 35<br />

recoveries/ adjustments etc shall be made from the interim payable amount. The<br />

balance 5 % shall be payable along with final bill.<br />

42.2 Out of above mentioned 95 % of gross bill value, 0.5 % shall be paid after<br />

ratification by BHEL engineer on compliance of house keeping, work area<br />

illumination by bidder. Also 0.2 % of above mentioned 95 % gross bill value shall be<br />

paid after certification by BHEL engineer on compliance of HSE activities at site.<br />

42.3 Contractor’s RA bill, complete & correct in all respects, certified by BHEL/ customer<br />

engineer, shall be paid within 30 days of date receipt of bill.<br />

42.4 Customer/ BHEL site at its discretion may further split up the above percentages of<br />

break up and effect payment to suit the site condition, cash flow requirement,<br />

according to the progress of work. BHEL reserve the right to release payment<br />

through electronic mode, for which bidder shall comply with requisite formalities<br />

42.5 Such payment as above shall be effected only on certification by BHEL against<br />

completion of each stage.<br />

43.0 METHOD OF MEASUREMENT<br />

IS 1200 in conjunction of IS code 3385 shall be adopted. In case the item of<br />

measurement is not available in the IS 1200, the standard procedure adopted in<br />

CPWD shall be adopted. In case the same is also not available in CPWD, the<br />

measurement of the work done will be based on the mutual agreement between<br />

BHEL and contractor. In all the above cases, the interpretation of BHEL will be final<br />

and binding to the contractor.<br />

44.0 EXTRA/ ADDITIONAL ITEMS OF WORK<br />

If any extra or additional items, which are not incorporated in the BOQ schedule,<br />

have to be executed by the contractor, the rate of such extra or additional work<br />

shall be as per the following:<br />

a) If rates for such items cannot be derived from the rate schedule of this contract<br />

as mentioned above, but are covered under CPWD, DSR-2007 schedules of<br />

rates. Contractor shall be quote against the relevant item as indicated in BOQ.<br />

b) If the items are not covered under above schedule, the rate of such items shall<br />

be derived, by a duly approved committee, if possible, from the available rates,<br />

agreed upon in the rate schedule of this contract.<br />

c) If the items are not covered under above schedule, the rate of such items shall<br />

be derived, by a duly approved committee, based on the rates to be agreed<br />

upon mainly on the basis of prevailing market rates for which all documentary<br />

evidences, as required by BHEL shall have to be produced by the contractor.<br />

Decision of BHEL in such cases shall be final and binding on the contractor.<br />

45.0 DESIGN OFFICE AND FABRICATION DRAWING<br />

45.1 Since time is the essence of the contract, the contractor must indicate the location<br />

of their design office where from such detailed activities will be made operative. It<br />

is preferred that the contractor have establishment / liason office at Delhi /Noida<br />

with a co-ordinator for better co-ordination with BHEL-PEM.<br />

45.2 Contractor shall submit progress report pertaining to fabrication drawing, by 7th of<br />

each month, drawing-wise, section-wise cumulative bill of materials for which<br />

engineering drawing has been issued to them and status of fabrication drawing.<br />

46.0 FABRICATION / GALVANISING<br />

46.1 All the fabrication of structural steel items (except nuts/ bolts) shall be done in<br />

fabrication yard inside project premises. Bidders to note that all fasteners like<br />

MS/HT/HSFG bolts, nuts, lock nuts, washers etc. shall be supplied by bidder as per<br />

technical specification/ drawings and BOQ items.<br />

46.2 Bidder, at his own cost, shall supply electrodes required for fabrication, erection of<br />

structural steel as per specification and approval of BHEL.<br />

46.3 However, in case of exigency as considered fit by BHEL, BHEL may permit the<br />

contractor to get some specific portion of fabrication/ galvanizing work done at


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 32 OF 35<br />

qualified shop (s) outside the project premises. For steel to be issued to the<br />

contractor for such purpose, 50% of the value of such steel as worked out as per<br />

BHEL’s procurement rates shall be furnished by the contractor in the form of BG.<br />

Such BG shall be returned depending on the receipt of fabricated/ galvanized steel<br />

back to site<br />

47.0 DIVISIBLE CONTRACT<br />

Notwithstanding anything stated elsewhere in this tender, the contract to be<br />

awarded shall be on the basis of supply & erection contract (divisible contract) on<br />

single source responsibility. In the mode of contracting on the basis of supply &<br />

erection, the civil & erection portion of the contract will relate to the BOQ cum price<br />

schedule of (1) Part-1 and supply portion of the contract will relate to the BOQ cum<br />

price schedules of (1) Part-2.<br />

But the two contract shall not in any way dilute the responsibility of the bidder for<br />

the successful completion of the job as per tender specification and both the<br />

contracts shall contain a cross-fall breach clause, namely that a breach in one<br />

contract shall automatically be classified as a breach on the other contract which<br />

will confer a right on BHEL to terminate the other contract at the risk and cost of the<br />

bidder.<br />

The title of the ownership of goods to be supplied shall pass on to the owner on<br />

dispatch ex-works/ FOR destination. However till the scope is completed in all<br />

respect and the plant/ equipment is taken over by the owner the goods shall remain<br />

with the custody of the bidder.<br />

48.0 OTHER TERMS<br />

48.1 While bidder's scope include deployment of all resources, like T&P, materials,<br />

consumables, manpower including supervision etc for proper completion of the<br />

subject job and no sub-contracting for execution of the job is allowed by BHEL,<br />

depending on project's requirement and on prior acceptance of BHEL, bidder may<br />

associate agencies for deployment of skilled/ un-skilled manpower only for site<br />

execution. Bidder should arrange all resources, like T&P, materials, consumables,<br />

supervision etc directly for the subject job.<br />

48.2 All other term & conditions of this specification, not mentioned above shall be<br />

governed by the pertinent provisions of GCC.


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 33 OF 35<br />

ANNEXURE - A<br />

LIST OF EQUIPMENTS FOR CIVIL SITE LABORATORY<br />

SL NAME OF TEST NAME OF EQUIPMENT SIZE OF IS REF<br />

NO<br />

EQIPMENT<br />

CONCRETE TESTING EQUIPMENT<br />

1 Initial & final setting time, Vicat Apparatus with Standard<br />

IS<br />

Consistency of cement desk pot<br />

5513<br />

2 Shrinkage of cement, Auto Le Chatelier's appratus Standard<br />

IS<br />

Clave Test<br />

Auto Clave Equipment<br />

5514<br />

3 Abrasion value test Los Angles Abrasion Standard<br />

IS<br />

testing machine<br />

2386<br />

4 Aggregate Impact value test Aggregate Impact value Standard<br />

IS<br />

testing machine with<br />

9377<br />

blow counter<br />

5 Aggregate crushing value Crushing value Standard<br />

IS<br />

test<br />

apparatus<br />

2386<br />

6 Flakiness index Thickness gauge for Standard<br />

IS<br />

measuring flakiness<br />

2386<br />

index<br />

7 Elongation Index Elongation guage Standard IS<br />

2386<br />

8 Bulk density, voids and Measuring cylinders 3, 5,10 & 15 liters<br />

bulking appratus<br />

cylinders<br />

9 Concrete Compressive test Digital Compressive 2000KN capacity IS<br />

Testing Machine with<br />

2505<br />

2000 KN capacity.<br />

10 Cement motor cube casting Mortor Cube mould 70.6 x 70.6 x 70.6<br />

mm, minimum 06<br />

sets desired.<br />

11 Concrete Cube casting Concrete Cube Mould 150x150x150mm,<br />

minimum 20 sets<br />

desired<br />

considering TG<br />

Raft major<br />

concereting<br />

activity.<br />

12 Workability of concrete Slump cone Standard, atleast<br />

04 nos<br />

13 Specific gravity of aggregates Pycnometer Standard, atleast<br />

02 nos<br />

14 Cement mortor cube Motorised vibration Standard<br />

vibrating<br />

machine for cement<br />

testing<br />

15 Course agregate Sieve<br />

analysis (Concrete & Road<br />

Works)<br />

Sieve set 450mm dia GI<br />

Frames Size: 125<br />

mm, 90 mm, 75<br />

mm, 63 mm, 53<br />

mm, 40 mm, 20<br />

mm, 16 mm, 12.5<br />

mm, 10 mm, 4.75<br />

mm, Pan and<br />

cover<br />

IS<br />

10086<br />

IS<br />

10086<br />

IS 456<br />

IS 383<br />

IS<br />

4031<br />

IS 383


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 34 OF 35<br />

16 Fine agregate sieve analysis Sieve set 200 mm dia Brass IS 383<br />

sieves; Size 4.75<br />

mm, 2.36 mm,<br />

1.18 mm 600<br />

micron, 300<br />

micron, 150<br />

micron, 75 micron,<br />

75 micron, Pan<br />

and cover<br />

17 Seive Shaker Motorised Sieve shaker Mfg. Catalogue<br />

18 Silt content check Sand silt content beaker Standard<br />

19 Ultrasonic pulse velocity test UPV appratus for Standard<br />

concrete<br />

SOIL TESTING EQUIPMENT (LEVELLING & GRADING)<br />

1 Liquid limit test Liquid limit apparatus Standard IS<br />

2 Core Cutter test core cutter appratus Rammer, 6 nos of<br />

std core cutter<br />

mould, dolly<br />

3 Proctor density test Std proctor Compaction Standard<br />

apparatus<br />

4 Moisture Content Rapid moisture meter Standard, atleast<br />

PROCESS CONTROL ACCESSORIES<br />

1 Hot air oven Temperature range 50°<br />

C to 300° C<br />

04 nos<br />

600x600x600mm<br />

(min.size)<br />

2 Electronic balance 3 nos 600gx0.01g, 10g<br />

and 50 kg<br />

3 Physical balance 5 kg capacity Weights upto 5 kg<br />

4 Thermometer Temperature range 0° C Digital<br />

to 150° C<br />

5 Poker Thermometer Temperature range 0° C 02 nos each<br />

(Concrete Road)<br />

to 50° C & 150° C required<br />

6 Measuring jars 2 nos set of each size 100ml, 200ml,<br />

500ml & 1000 ml<br />

7 Gauging trowlers 4 nos 100mm & 200 mm<br />

with wooden<br />

handle<br />

8 Sptula 2 nos each size 100mm & 200 mm<br />

with long blade<br />

wooden handle<br />

9 Stainless steel scoop 2 nos each 2 kg and 5 kg<br />

10 Vernier calipers 2 nos each 12" and 6" Sizes<br />

11 Digital pH meter 01 nos .01 mm least<br />

count<br />

12 Digital micrometer 01 nos 0.01 mm least<br />

count<br />

13 Digital paint thickness meter 02 nos 500 micron Range<br />

for steel<br />

14 GI tray 02 nos each 600x450x50mm,<br />

450x300x40mm,<br />

300x250x40mm<br />

15 Electric morter mixer 01 nos 0.25 CUM<br />

capacity<br />

16 Rebound hammer test 01 nos Digital Rebound<br />

hammer<br />

2720<br />

IS<br />

2720<br />

IS<br />

2720<br />

IS<br />

2720<br />

IS<br />

13311


VOLUME-<strong>IF</strong><br />

(SER)<br />

TENDER NO – PSER:SCT:DPL-C1154:10<br />

TECHNICAL CONDITIONS OF CONTRACT, SCOPE ETC<br />

(SERVICE)<br />

PAGE 35 OF 35<br />

17 Screw Gauge 02 nos 0.1 mm-10mm,<br />

Least count 0.05<br />

18 Digital paint thickness meter 02 nos 150 micron range<br />

for masanory/concrete<br />

painting measurement


THE DURGAPUR PROJECTS LIMITED<br />

DURGAPUR PROJECTS POWER STATION<br />

1 X 250 MW EXTENSION UNIT-8<br />

VOLUME--II B<br />

RCC SINGLE FLUE CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

BHARAT HEAVY ELECTRICALS LIMITED NEW DELHI


SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION -<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

PROJECT TITLE :<br />

1 X 250 MW (TPS)<br />

EXTENSION UNIT-8<br />

NO. OF UNITS<br />

: ONE UNIT<br />

RATING<br />

: 250 MW<br />

LOCATION :<br />

DURGAPUR,<br />

WEST BENGAL


SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION -<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

PREAMBLE<br />

This Tender document contains three (3) volumes. The bidder shall meet<br />

the requirement of all three volumes.<br />

VOLUME – II<br />

This volume is subdivided into following sections:<br />

Section-A: This section outlines the scope of enquiry.<br />

Section-B: This section provides “Project Information”.<br />

Section-C: This section indicates the technical requirements specific to<br />

the contract not covered in the section-D.<br />

Section-D: This section comprises of technical specification.


SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION -<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

INDEX<br />

VOLUME -II B<br />

SECTION DESCRIPTION SHEET NO.<br />

Section-A SCOPE OF ENQUIRY 3<br />

Section-B PROJECT INFORMATION 3<br />

Section-C SPEC<strong>IF</strong>IC TECHNICAL 12<br />

REQUIREMENTS<br />

i) CIVIL<br />

ii) ELECTRICAL<br />

iii) Chimney Elevator<br />

Section-D 1) SPEC<strong>IF</strong>ICATION FOR CIVIL, STRUCTURAL 22<br />

AND ARCHITECTURAL WORKS<br />

2) SPEC<strong>IF</strong>ICATION FOR ELECTRICAL WORKS


TITLE:<br />

SCOPE OF WORK<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - A<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

VOLUME – II B<br />

SECTION-A<br />

SCOPE OF WORK<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001


1.0.0 SCOPE<br />

TITLE:<br />

SCOPE OF WORK<br />

Scope of Work<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - A<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

1.1.0 The chim ney will be si ngle f lue r einforced concrete st ructure of 220 metres<br />

height. Flue w ill ha ve f irst c lass a cid/heat proof firebrick lining. This brick<br />

lining w ork w ill be s upported on i nternal R CC c orbels a t 10 Metres i nterval.<br />

Apart from aviation warning light, complete external surface of the windshield<br />

shall be pa inted i n a lternate ba nd of s ignal r ed a nd white c olour starting with<br />

signal red c olour a t t he t op a nd i n l ine w ith a viation r equirements. E xternal<br />

painting shall have acid and heat resisting properties confirming to IS-158, total<br />

dry thickness(DFT) shall be atleast 150 microns. Platforms on external surface<br />

of R CC w indshield w ith pr ovision of pe rsonnel a ccess s hall be pr ovided at<br />

maximum t wenty-five (2 5) metre i nterval. Suitable pe rsonnel access door and<br />

truck entry door shall be provided. The top of roof slab and top of acid resistant<br />

bricks ove r t he r oof s hall be pa inted w ith t wo c oats of ‘ EXPILUX 5 C OAL<br />

TAR EPOXY PAINT’ over a t hin coat of t he same paint a s manufactured by<br />

M/s. Berger Paints (India). The overall DFT shall be at least 230 microns. RCC<br />

hopper shall be provided at bot tom l evel. A rrangement s hall be pr ovided f or<br />

measuring concentration of particulate matters. NO X AND SO X in the flue gas<br />

for monitoring and taking necessary measure for pollution control. It will also<br />

have necessary arrangement for e arthing dur ing c onstruction. A ccess f rom<br />

ground to external platforms shall be provided with cage ladder.<br />

1.1.1 The w ork t o be done unde r t his specification comprises of c onstruction of<br />

220M high Reinforced Concrete single flue brick lined Chimney complete with<br />

reinforced concrete raft foundation, R.C shell, insulation and provision of other<br />

accessories including ash hoppers, external platforms, fabrication and fixing of<br />

flue duc t i nside t he c himney, G .I. di screte s trakes, complete interior and Air<br />

Aviation O bstruction l ighting s ystem, l ightning pr otection a nd grounding<br />

system, M.S. doors for access to the shell, external platforms and inspection of<br />

the liners, M .S. l adders, c ommunication s ystem c omponents, e mbedments f or<br />

installation of equipments and fixtures and painting both internal and external of<br />

the chimney shell as well as of all doors, ladders and other structural steel items<br />

in accordance with this specification and approved drawings.<br />

1.1.2 The supply, erection, testing and commissioning of chimney Elevator are in the<br />

scope of t his w ork. T he t enderer s hall m ake pr ovision to accommodate<br />

chimney e levator w ithin t he a nnular s pace of R .C.C. Shell a nd a ll C ivil a nd<br />

structural s teel w orks r equired f or e rection, t esting a nd c ommissioning of t he<br />

elevator s hall be i n t he s cope of t his w ork. T he t enderer s hall provide all<br />

necessary ope nings of r equired s izes i n R .C.C. s hell (along with bird<br />

screen/louvres w herever appl icable) and platforms and shall al so consider all<br />

loads exterted by t hese s ystems on R .C.C. s hell or on i ts c omponents i n hi s<br />

design without any extra cost to the purchaser.


TITLE:<br />

SCOPE OF WORK<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - A<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

1.1.3 The scope unde r t his spe cification covers t he c onstruction of Single flue<br />

Reinforced Concrete Chimney including providing all labour,<br />

supervision, materials, scaffolding, power, fuel, construction equipments, tools<br />

and plants, supplies, transportation, storage, insurance and all incidental items<br />

not he rein s pecifically m entioned but r easonably i mplied or w hich m ay be<br />

found necessary for successful completion of the work including c ontractor's,<br />

and where necessary manufacturer's expert supervision in strict compliance with<br />

the requirements of this specification and approved construction drawings. The<br />

tendered amount shall be for the chimney to be completed in all respect as per<br />

this specification for the purpose required.<br />

1.1.4 The suc cessful t enderer sha ll ha ve t o prepare ba r be nding schedule & s chedule of<br />

embedments and get the same approved by t he Engineer. T he detailed fabrication<br />

drawings for doors, flue ducts, ladders, M.S. staircases, hand rails and other fixtures<br />

shall also be prepared by the successful tenderer and got approved from the Engineer<br />

before undertaking the actual fabrication or erection of construction.<br />

1.1.5 The contractor shall prepare, at his own cost, the detailed working drawings showing<br />

all details of the formwork staging (adequacy to be supported by design calculations)<br />

and other arrangements for the concreting work and submit six copies of the same for<br />

the a pproval of t he E ngineer-in-Charge / consultants a nd onl y on t he receipt of the<br />

approval of the consultants the work shall be taken up.<br />

1.1.6 The contractor shall prepare, at his own cost, the detailed working drawings showing<br />

all Electrical details and Elevator details.<br />

2.0.0 TENDER DRAWINGS<br />

2.1.1 The f ollowing dr awing w hich f orms pa rt of T ender D ocuments are indicative and<br />

give ove rall di mensions, a nd s ome ot her typical de tails of t he w ork r equired t o be<br />

done under this contract. The accessories shown in the drawings are also indicative :<br />

S. NO. DRG. NO. TITLE<br />

1. PE-DG-360-620-C001 GENERAL ARRANGE MENT OF<br />

CHIMNEY.<br />

2.1.2 The drawings and specifications furnished are to be considered as explanatory of each<br />

other. S hould anything a ppear in one drawing that is not described in the other, no<br />

advantage s hall be t aken of s uch om ission. S hould a ny di screpancies, how ever,<br />

appear, or should any misunderstanding of drawings or as to the dimensions or quality<br />

of the materials or the due a nd i mproper e xecution of t he w orks or a s t o t he<br />

measurements or quality or valuation of the works executed under this contract or as


TITLE:<br />

SCOPE OF WORK<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - A<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

extra t hereupon, the sam e sha ll be cl arified by t he E ngineer-in-charge or hi s<br />

authorised r epresentative a nd hi s e xplanation s hall be binding upon the contractor.<br />

Directions as given by the Engineer-in-charge or his author ised representatives being<br />

considered ne cessary f or t he pr oper c ompletion of t he work as i mplied by t he<br />

specifications a nd dr awings, e ven t hough s uch w orks a nd things are not specially<br />

shown and described in the said drawings and specifications shall be binding on the<br />

contractor. Supplementary dimensions or dr awings m ay be gi ven by t he<br />

Engineer/Engineer-in-charge in addition to those already given and changes may also<br />

be effected in them and the contractor shall have to execute the works on the basis of<br />

the s upplementary dr awings or c hanged dr awings and specifications without any<br />

additional claim whatsoever.<br />

3.0.0 DOCUMENTS MUTUALLY EXPLANATORY AND SECTION C.<br />

3.1.0 Contractor shall read the parts of t he specification relevant to the contract and<br />

shall ignore the other parts of t he sp ecification. In cas e of amb iguity between<br />

BOQ, part C and part D of specification, the following priority for acceptance of<br />

items may be followed :-<br />

a) BOQ b) Part C c) Part D<br />

3.2.0 GENERAL<br />

3.2.1 The ove rall c oordination f or a ll w orks s pecified i n t he s cope of work will be the<br />

responsibility of t he c ontractor. T he c ontractor shall also provide adequate<br />

supervisory personnel for works executed under his Scope of Work.<br />

3.2.2 Any clarification from customer/customer's representative shall have to be furnished<br />

by the contractor.


TITLE:<br />

PROJECT INFORMATION<br />

SPEC<strong>IF</strong>ICATION NO.PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - B<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

VOLUME – II B<br />

SECTION-B<br />

PROJECT INFORMATION


TITLE:<br />

PROJECT INFORMATION<br />

SPEC<strong>IF</strong>ICATION NO.PE-TS-360-620-C001<br />

VOLUME - II<br />

SECTION - B<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

DURGAPUR PROJECTS POWER S TATION: 1 X 250 MW E XTENSION UNI T-8 is<br />

being set up by THE DURGAPUR PROJECT LIMITED.<br />

The B idder s hall acquaint himself by a visit to the s ite, if f elt ne cessary, with the<br />

conditions prevailing at site before submission of the bid. The information given here in<br />

under is for general guidance and shall not be contractually binding on BHEL/Owner. All<br />

relevant site data /information as may be necessary shall have to be obtained /collected by<br />

the Bidder.<br />

APPROACH TO SITE<br />

Durgapur city is disposed at 28º48’ N latitude and 85 º 33’45” E longitudes located at the<br />

left bank of river Damodar, in the district of Burdwan at a distance of about 160 KM from<br />

Kolkata. T he pl ant s ite i s 3 K M a way f rom Durgapur Barrage located on the river<br />

Damodar. The site is well connected by roads with important industrial centres in the area.<br />

Broad Gauge Railway line of the Eastern Railway and all-weather roads connect Durgapur<br />

with Kolkata and nearby collieries.<br />

The equipment will be normally transported by road only and under exceptional cases by<br />

rail. The m aterial c onsignments s hall be a s pe r the re strictions of ra il a nd road<br />

transportation prevailing in the country.<br />

Nearest ports of entry are Kolkata and Haldia.


TITLE:<br />

PROJECT INFORMATION<br />

SPEC<strong>IF</strong>ICATION NO.PE-TS-360-620-C001<br />

VOLUME - II<br />

SECTION - B<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

1. Owner DURGAPUR PROJECTS LIMITED (DPL)<br />

2. Owner Consultant DEVELOPMENT CONSULTANTS PRIVATE LIMITED<br />

3. Project Title 1 X 250 MW Extension Unit-8 at Durgapur Projects Power<br />

Station<br />

4. Location 3 Km from Durgapur Barrage<br />

5. Nearest Railway Stn. Durgapur<br />

6. Ambient Air Temperature<br />

a. Maximum refer ANNEXURE I<br />

b. Minimum refer ANNEXURE I<br />

7. Relative Humidity<br />

a. Maximum refer ANNEXURE I<br />

b. Minimum refer ANNEXURE I<br />

8. Rainfall<br />

a. Maximum Rainfall refer ANNEXURE I<br />

9. Wind Data<br />

a. Basic wind speed at 10m height<br />

47 m/sec<br />

b. Wind pressure As per IS: 875 Part III-1984<br />

10. Seismic Zone Zone III as per IS: 1893-2002


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

VOLUME – II B<br />

SECTION-C<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENTS<br />

FOR CIVIL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

1.0 BRIEF DESCRIPTION<br />

.<br />

The chimney will be single flue reinforced concrete structure of 220 m etres height.<br />

Flue will have first class acid/heat proof firebrick lining. This brick lining work will<br />

be supported on internal RCC corbels at 10 M etres i nterval. A part f rom a viation<br />

warning l ight, c omplete e xternal s urface of t he w indshield s hall be pa inted i n<br />

alternate band of signal red and white colour starting with signal red colour at the top<br />

and i n l ine w ith a viation r equirements. E xternal pa inting s hall ha ve acid and heat<br />

resisting properties c onfirming to IS-158, t otal dr y t hickness(DFT) sha ll be atleast<br />

150 microns. Platforms on e xternal s urface of R CC w indshield w ith pr ovision of<br />

personnel access sha ll be provi ded at maximum twenty-five (25) m etre int erval.<br />

Suitable personnel access door and truck entry door shall be provided. The top of roof<br />

slab and top of acid resistant bricks over the roof shall be painted with two coats of<br />

‘EXPILUX 5 COAL T AR E POXY P AINT’ ove r a t hin coat of t he same paint as<br />

manufactured by M/s. Berger P aints ( India). The ove rall D FT sha ll be at l east 230<br />

microns. RCC hoppe r s hall be pr ovided a t bot tom l evel. A rrangement shall be<br />

provided for measuring concentration of particulate matters. NO X AND SO X in the<br />

flue gas for monitoring and taking necessary measure for pollution control. It will also<br />

have necessary arrangement for earthing during construction. Access from ground to<br />

external platforms shall be provided with cage ladder.<br />

The grade level slab shall be of r einforced c oncrete w ith a n i ronite f inish. T he<br />

chimney shall have a suitable foundation system depending upon soil characteristics.<br />

Apart from aviation warning light, the complete external surface of the wind shield<br />

shall be painted in alternate band of red and white colour and in line with aviation<br />

requirements, out of which the top 50 metre of paint shall have acid and heat resistant<br />

properties and rest of the surface shall be painted with water proof cement paint or<br />

synthetic enamel paint.<br />

The c himney r oof s lab if re quired shall be of r einforced concrete t reated for w ater<br />

proofing and protected by a layer of acid resistant tiles laid in acid resistant mortar.<br />

Suitable personnel access door and truck entry door shall be provided. A personnel<br />

access hatch in the of slab, liner access hatches, rain water drainage system, flue acid<br />

drainage, bird screens or louvers on the ventilation openings shall also be provided.<br />

Arrangement shall be provided for m easuring c oncentration of pa rticulate m atters,<br />

Nox & Sox in the flue gas for monitoring and taking necessary measure for pollution<br />

control. It w ill a lso have necessary arrangement f or el ectrical pow er suppl y ,<br />

distribution boards, socket outlets, power and control cabling raceways system, stair<br />

and platform lighting, lightening protection and earthing system.<br />

Stack elevator will be provided to run along outside surface of wind shield.


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

Galvanised mild steel discrete strakes shall be provided over the required length of<br />

the chimney at the t op, i f f ound ne cessary f rom w ind t unnel s tudies f or c himney<br />

model.<br />

2 0 APPROACH TO WORK SITE<br />

The contractor sha ll make his ow n arrangements at his ow n cost f or t he ne cessary<br />

approach r oads f or t ransport of m aterials t o s ite of w ork. N o extra charge will be<br />

paid.<br />

3.0 DAMAGES TO THE OTHER STRUCTURE AND PLANT<br />

The contractor shall be totally held responsible for any loss or damages caused by an<br />

any act of t he c ontractors, l abour or hi s s ub-contractor's l abour i ncluding but not<br />

limited t o c overed/open bl asting t o t he e xisting s tructures and plant or any other<br />

structures or plant that may be under construction/erection by any other agency at this<br />

site during the entire period covered by this contract along with time extension if any.<br />

Any permission given by the Engineer to the contractor to carry out such work, such<br />

as blasting etc. shall not be construed to be waiver of the Contractor's responsibility.<br />

In such cases the amount in respect of loss of damage. shall be considered as final and<br />

binding on the contractor & shall stand recoverable.<br />

4.0 DE-WATERING<br />

No separate pa yments f or de watering of sub -soil or surf ace water if re quired or<br />

removal of slush at any time dur ing c onstruction w ork i ncluding m onsoon pe riods<br />

would be made and the rates quoted by the Tenderers for various items under in Vol.<br />

III are deemed to be inclusive of cost of such dewatering & removal of slush where<br />

necessary.<br />

5.0<br />

FORM WORK<br />

The c himney s hell s hall be c onstructed by us ing s lip f orm technique only. The<br />

contractor s hall be a llowed t o us e f orm w ork a s pe r hi s own design subject to<br />

however that the design shall conform to the most acceptable practice for such type of<br />

work a nd t he r elevant I S s pecification. T he de sign shall also be approved by the<br />

Engineer-in-charge. T he re sponsibility of f orm s triking period shall re st with<br />

contractor subject to however t hat t he sam e sha ll not be l ess t han the minimum<br />

recommended under the relevant IS specification.<br />

6.0 EMBEDDING FIXTURES IN CONCRETE<br />

6.1 Proper steel templates shall be used for fixing anchor bolts, pipe sleeves etc. to ensure<br />

that they are fixed precisely as per dimensions shown on dr awings. S uch templates<br />

are subject to the Engineer’s approval.


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

6.2 The contractor shall exercise great care to ensure that these inserts are accurately held<br />

in position and maintained undisturbed during placing and vibrating of concrete and<br />

that pipe sleeves do not get filled in with concrete. I f found desirable the Engineer<br />

may direct the contractor to tie or weld the inserts to the reinforcement to ensure that<br />

are maintained undisturbed. All such works shall be done by the contractor at no extra<br />

cost.<br />

6.3 The contractor shall ensure that the anchor bolts, inserts etc. are properly protected as<br />

under-<br />

a) From w eather by a pproved m eans s uch a s w hite l ead putty and wrapping them<br />

with gunny ba g or c anvas or by ot her m eans a s directed by the engineer.<br />

However before actual fixing in position the anchors shall be cleaned of all oil and<br />

grease and the protruding positions sha ll aga in be cl eaned and grease af ter<br />

concreting is over.<br />

b) From damage due to movement of contractor's labour staff, materials and<br />

equipment a nd pr oviding s uitable gua rds a round t hem a s di rected by the<br />

Engineer-in- charge.<br />

6.4 In the event of pockets, bolts, pipe sleeves, channels and other inserts not being found<br />

in correct position whole work shall be liable to be rejected.<br />

6.5 Removal of bolt hole pockets shall only be done by w elding. In no c ase burning of<br />

bolt hol e f orms s hall be pe rmitted on r emoval of f orms, the pockets shall be<br />

temporarily pl ugged by t he hessian c ement ba gs or ot her m ethod t o prevent them<br />

from getting filled in with dust debris, concrete etc.<br />

7.0 QUALITY ASSURANCE PLAN<br />

The contractor shall submit Quality Assurance Plan for complete works after awards<br />

of contract and shall get for the same approved by employer/owner.<br />

8.6 SUPERVISION BY CUSTOMER OR THEIR CONSULTANT<br />

The owner or his r epresentative m ay depute t heir r epresentatives f or che cking and<br />

supervision of important stages of work. The contractor shall be required to provide<br />

all f acilities f or ins pection of w orks by the customer/consultants or the ir<br />

representatives w ithout a ny c ost i mplication t o t he e mployer or E ngineer. Any<br />

defects in quality of w ork, or de viations f rom dr awings s pecifications, poi nted out<br />

during s uch i nspection s hall be m ade good by the contractor in the same way as<br />

pointed out the Engineer without any cost implications.


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

9.0 SURVEY EQUIPMENT<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

9.1 The contractor shall have on s ite a good num ber of accurate survey instruments such as<br />

levels, theodolite, staffs, measuring devices, survey umbrellas, etc. to ensure s mooth.<br />

progress of work.<br />

10.0 SPEC<strong>IF</strong>ICATIONS AND CODES<br />

10.1 All works shall be carried out strictly in accordance with the technical specifications<br />

unless ot herwise a pproved by t he E ngineer i n w riting. W here not s pecified i n t he<br />

technical specifications the relevant latest Indian Standards Codes shall be followed.<br />

10.2 Field quality s hall be a dhered t o s trictly i n a ccordance w ith t he s tandards a nd<br />

applicable codes various checks during the process of work at different stages shall be<br />

performed according to the checklist. Tests wherever required for these checks shall<br />

be c onducted by t he c ontractor a t his own cost i n pr esence of t he E ngineer. T he<br />

record of all such checks shall be jointly signed by the Engineer and the contractor<br />

and maintained with the Engineer.<br />

10.3 Any deviations in execution of t he w orks a s a r esult of c hances i n s pecifications.<br />

contract dr awings, i naccurate w orkmanship, t ype, s ize or gr ade of m aterials to be<br />

used etc sha ll be f irst discus sed by the cont ractor w ith the Engineer at site and<br />

feasibility of s uch non -conformances possible ascertained. The cont ractor sha ll<br />

initiate the matter by submitting a Non Conformance Request (NCR). The contractor<br />

shall not proceed with construction or pr eparation of dr awings or pur chase of<br />

materials or r emedial measures for de fective work not c onforming t o s pecifications<br />

without the approval in writing by Engineer on the NCR submitted by the contractor.<br />

10.4 Proprietary Items: All proprietor, items of m aterials s pecified/required as pe r ite m<br />

description s hall be pr ocured f rom t he m anufacturers/reputed s uppliers only after<br />

obtaining the approval of Engineer. Unpriced copies of such order shall be submitted<br />

to the Engineer for any follow up action as deemed fit by the Engineer.<br />

11.0 TECHNICAL INSTRUCTIONS<br />

i) The successful tenderer on receipt of letter of intent shall prepare a de tailed<br />

work pr ogramme i ncluding i tems of w ork w ithin t he ove r a ll time period<br />

allowed and shall submit the same to the Engineer for approval. The drawings<br />

as listed in section 'A' are enclosed with the tender documents.<br />

ii)<br />

iii)<br />

The work ha s t o be t aken up i mmediately on i ssue of w ork or der/letter of<br />

intent/telex and completed within the scheduled time of completion.<br />

The work has to be carried out according to priority that may be fixed by the<br />

site Engineer at site.


iv)<br />

TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

The m aterials a nd w orkmanship m ust be of good qua lity a nd a ccepted<br />

standards and specifications.<br />

v) All materials for construction are to be procured by the contractor and should<br />

conform to relevant I.S. specification.<br />

vi)<br />

vii)<br />

viii)<br />

The site Engineer reserves the right to reject a ny material not upt o the<br />

specifications.<br />

Unless specified other otherwise rates quoted under the contractor shall apply<br />

for works irrespective of lifts and leads. R ates shall also. include providing<br />

scaffolding and its subsequent removal.<br />

After completion of the work the buildings and areas around them should be<br />

cleared all rubbish debris etc. and handed over in fit condition for occupation.<br />

12.0 INSULATION<br />

12.1 The heat insulation to be fixed on t he inner surface of shell shall be semi-rigid resin<br />

bonded f ibrous m aterial c onforming t o I S: 819, or e quivalent with a maximum<br />

coefficient of thermal conductivity of 0.52 MW/CM/Deg. C at a mean temperature of<br />

100 deg. C . The Insulation material shall have a delivered density of 100 K g/Cu.M<br />

for resin-bonded rock wool or 64 Kg/Cu.M for resin-bonded glass wool. Thickness of<br />

the insulation as specified in BOQ 's is the minimum as installed.<br />

12.2 No negative tolerance shall be pe rmitted i n t he bul k de nsity of i nsulation. T he<br />

insulation s hall be i n t he f orm of s labs w rapped on t he i nner s urface of shell with<br />

galvanized wire mesh as specified. The insulation should not be affected by acid and<br />

should be free from any impurities which may cause corrosion.<br />

12.3 The i nsulation should be a ble t o s ustain s tructural vi brations a nd s hould not s ettle<br />

under these conditions during erection, construction and operation in any case. The<br />

insulation shall also be suitable tied to prevent dislocation under adverse conditions.<br />

Care sh ould be t aken i n t he s election of t he i nsulation m aterial t o e nsure t hat t he<br />

material can safely withstand the l ong term expos ure to the maximum flue gas<br />

temperature without deterioration or break-down. Slag Wool insulation shall not be<br />

acceptable.<br />

12.4 Unbounded wool shall be of Type–I loose, glass wool in conformance with IS: 3690<br />

or T ype-I l oose r ock W ool i n c onformance W ith I S: 3677. The insulation shall be<br />

packed to achieve a density of 64 Kg/Cu.M in case of glass wool and 100 kg/Cu.M in<br />

case of rock Wool. Bonded and unbonded insulation shall be of the same material.<br />

12.5 The insulation material shall be tested for its stipulated characteristics and properties<br />

listed i n t his s pecification a nd I S : 8183 a nd t he dr awing a ccordance w ith the IS:


TITLE:<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

REINFORCED CONCRETE<br />

CHIMNEY<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUBSECTION : I<br />

REV.NO. 0 DATE 18.09.2010<br />

SHEET<br />

OF<br />

3144 and IS: 3346 a nd/or a s directed by t he Engineer at the Contractor's own cost.<br />

The tests shall be conducted in the presence of the Engineer and the reports of such<br />

testing shall be submitted to the Engineer before application of the material.<br />

12.6 The insulated material shall be protected against weather at all times from delivery up<br />

to completion of work. Insulation material shall not be stacked directly on the<br />

ground. The contractor shall provide covered storage for insulation material<br />

accessories to the satisfaction of the Engineer.<br />

13.0 CONSTRUCTION<br />

13.1 INSULATION<br />

13.1.1 The fixing details shall be as per specification, approved drawings and the directions<br />

of the Engineer.<br />

13.1.2 T he i nsulation s hall be pr ovided i n m ore t han one l ayer and the joints staggered.<br />

Each layer shall be minimum 25 mm thick.<br />

13.1.3 P articular care shall be taken to ensure that all semi rigid resin bonded fibrous slabs<br />

are tightly butted. The insulation shall be tightly secured to the exterior of the liner or<br />

the inner surface or the shell or on and other surface leaving no air gap at the interface<br />

13.1.4 P ins and studs shall be anchored/fixed to the surface receiving insulation at 500 mm<br />

centers maximum horizontally and vertically. Pins and studs shall be minimum 10<br />

gauge and plated. These shall be 25 m m longer than the thickness of insulation.An<br />

alternative arrangement with anchor f asteners i nstead of pins can also be m ade as<br />

approved by the engineer incharge.<br />

13.1.5 The insulation shall be impaled on the studs and secured in place with 63 mm round<br />

or square metal plated speed washers.<br />

13.1.6 20 gauge galvanized wire netting shall be wrapped continuously over external surface<br />

of the insulation. The wire mesh shall be 25 mm hexagonal conforming to IS: 3150.<br />

All joints in the mesh shall be lapped in minimum of 150 mm and tied with 16-gauge<br />

soft annealed wire at 300 mm centers. Lacing will not be permitted.<br />

13.1.7 The insulation shall be fixed after painting the inner surface of the shell with acid and<br />

heat resistant paint.<br />

14.0 COATING S YSTEM O N S TRUCTURAL F RAMING: Acid and heat r esistant<br />

paint as per IS: 158 for surfaces which are not insulated nor protected by galvanising,<br />

high temperature f ormulation for pot entially hot s urfaces m ainly platform framing<br />

system. Two coats of finish paint on two coats of primer is to be applied on complete<br />

framing system other than flues.


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

ELECTRICAL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUB SECTION: II<br />

REV.NO. 0 DATE: 18.09.2010<br />

SHEET 1 OF 6<br />

VOLUME – II B<br />

SECTION-C<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENTS<br />

FOR ELECTRICAL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

ELECTRICAL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUB SECTION: II<br />

REV.NO. 0 DATE: 18.09.2010<br />

SHEET 2 OF 6<br />

1.00 ELECTRICAL SYSTEM<br />

1.01 415V, normal and emergency AC power supply for chimney shall be derived<br />

from main plant power supply system. Emergency supply shall feed 20% of<br />

platform lighting, 50% of staircase lighting, aviation obstruction lighting and<br />

elevator load. All other loads shall be connected on normal power supply.<br />

1.02 Ambient temperature for design of all equipment shall be considered as 55<br />

deg. C which is likely to be encountered inside the chimney.<br />

1.03 The distribution boards of chimney shall comprise switch-fuse units of<br />

appropriate ratings. Emergency board shall have two incomers, one from<br />

emergency supply and other from normal AC distribution board itself. Autochangeover<br />

scheme shall be provided in emergency board to enable<br />

changeover to healthy source on failure of any source.<br />

1.04 Dry type isolating transformer of Dyn connection shall be provided in<br />

emergency board to obtain neutral lead, in case 3 phase 3 wire emergency<br />

supply is derived from main plant.<br />

1.05 Various platforms shall be illuminated by 70/150W HPSV well glass lighting<br />

fixtures. Staircase lighting shall be with 70W HPSV well glass fixtures.<br />

Average illuminations level of 150 lux shall be maintained on equipment and<br />

50 lux on platforms/staircases. Lighting system shall be controlled through<br />

MCB provided in lighting panel.<br />

1.06 A lighting panel each shall be located at grade level and at other in between<br />

levels as required. All distribution boards, aviation lighting controls, etc. shall<br />

be located at grade level only. At each platform, 1 No. 63A, 415V welding<br />

receptacle and 1 No. 15A, 240V receptacle shall be provided. Wiring<br />

installation for lighting fixture shall be of PVC insulated copper/aluminum<br />

wires through galvanized steel conduits.<br />

1.07 Aviations obstruction lighting system shall conform to the requirements of the<br />

latest rules and regulations of the International Civil Aviation Organization<br />

(ICAO), National Airports Authority (NAA) and Directorate of Air Routes<br />

and Aerodromes (DARA). The type of aviation obstruction lighting system<br />

shall be of high intensity aviation obstruction lights having an intensity of<br />

4000 to 200000 cd depending upon background illuminance. The aviation<br />

obstruction lighting system shall be of type FTB205 and FTC 110N of Flash<br />

Technology Corporation of USA or equivalent. A minimum of three levels<br />

will be provided with aviation obstruction lights and there will be four lights<br />

per level The obstacle lights shall flash simultaneously at a rate between 40<br />

and 60 per minute. Aviation obstruction lighting shall be provided as per the<br />

approved drawings. Aviation obstruction lighting shall be complete with<br />

lights, photo cell, controller, special cables, etc.


TITLE:<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

SECTION - C SUB SECTION: II<br />

REV.NO. 0 DATE: 18.09.2010<br />

ELECTRICAL WORKS<br />

SHEET 3 OF 6<br />

1.08 A temporary aviation obstruction lighting system shall be provided during<br />

construction of the chimney.<br />

1.09 Cables from distribution board to lighting panels/receptacles shall be 1100V<br />

grade, PVC/XLPE insulated armoured aluminum conductor with a minimum<br />

size of 4 mm 2 Cables shall be laid on galvanized sheet steel cable trays. Cables<br />

shall be terminated using double compression type cable glands and cable<br />

lugs.<br />

1.10 Lightning protection system shall comprise minimum 3 vertical air<br />

terminations for each flue liner, horizontal air termination and minimum 4<br />

Nos. of down conductors spaced 90 degrees apart routed all along chimney<br />

height and connected to the earthing system. Above ground level, earthing and<br />

lightning protection system shall comprise galvanized steel strips. These<br />

materials provided at top 12 meters shall have additional coating of 2 mm<br />

thick seamless lead cover or it shall be of stainless steel to take care of<br />

corrosion. Chimney earthing system shall be inter connected to main plant<br />

earthing system.<br />

1.11 Communication system comprising of telephone socket at every internal<br />

platform level and at grade level, necessary wiring installation, junction boxes<br />

etc. shall also be provided. Requirement of telecommunication system as per<br />

pt. no. 18 of spec no. –DCPL-K9A01, doc. no.- V.II-D2/S-XXIV:22 (pg.330)<br />

are to be complied with.<br />

1.12 For various equipment, the technical requirements and practices shall conform<br />

to the relevant clauses of the main plant electrical specification and customer<br />

specification no. –DCPL-K9A01, doc. no.- V.II-D2/S-XXIV:30-33 (pg.338 to<br />

341).<br />

2.00 ELECTRICAL EQUIPMENT SCOPE<br />

The Bidder’s scope of supply, installation, testing and commissioning shall<br />

include but not be limited to the following:<br />

2.01 Lighting of chimney as per specification no. PE-DG-XXX-558-0004<br />

including aviation obstruction lighting system and 15A industrial switch<br />

socket & 63A welding socket.<br />

2.02 Lightning protection & earthing of chimney as per specification no. PES-509-<br />

02A Rev. 0 and PE-DG-XXX-509-0004. Also refer enclosed typical drawing<br />

of Lightning Protection and Earthing system drg. No. PE-DG-179-620-7272<br />

REV.1<br />

2.03 Power Distribution Boards<br />

:<br />

2.03.1 415 V, 3∅, 4 wire AC distribution board (ACDB) as per specification no.<br />

PES-506-05. 415 V, 3∅, 3 wire AC Emergency Lighting distribution board<br />

(ELDB) & Lighting panels (LP) as per Specification no. PES-558-01A .<br />

2.04 Power & control cables HRPVC, armoured, FRLS type 1100 V grade as per<br />

specification no. Section E18 <strong>Volume</strong> II Part B.


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

ELECTRICAL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C<br />

SUB SECTION: II<br />

REV.NO. 0 DATE: 18.09.2010<br />

SHEET 4 OF 6<br />

2.05 PVC insulated 1100V grade stranded copper conductor lighting wires.<br />

2.06 Aviation obstruction lighting system :<br />

2.06.1 Supply and installation of single obstruction lights with fixtures ( LED<br />

BASED with 20 years maintainance free life) equivalent to Type ‘B’ Low<br />

intensity aviation obstruction lights as per ICAO, at location as per approved<br />

drawings, complete with all accessories and suitable supporting arrangement<br />

to withstand high wind pressure.<br />

2.06.2 Supply and installation of red flashing aviation obstruction lights at different<br />

floor levels as per aviation obstruction lighting system conforming to the<br />

requirements of the latest Indian Standard IS-4998 & International civil<br />

aviation organisation (ICAO) and approved drawings.<br />

2.06.3 Supply and installation of medium intensity flashing light with fixtures (<br />

LED BASED with 20 years maintainance free life) equivalent to Type ‘B’<br />

Medium intensity aviation obstruction lights as per ICAO, at location as per<br />

approved drawings, complete with all accessories and suitable supporting<br />

arrangement to withstand high wind pressure.. The flash frequency shall be<br />

40-60/min.<br />

2.07 The lighting system also includes supply and installation of GS Cable Trays,<br />

GI conduits, conduits fitting, weatherproof junction boxes, lead coated<br />

flexible conduits (PLICA make), all accessories viz. supports, clamps,<br />

mounting structure/brackets etc. to make the installation complete.<br />

Supporting structure for the above shall be hot dip galvanised.<br />

2.08 Temporary obstruction lighting system :<br />

2.08.1 Temporary obstruction lighting shall be provided by the bidder during<br />

construction as per specification requirements. The fixture shall be<br />

equivalent to Type B, Low intensity Light , minimum 4 nos. on the upper<br />

most part of the chimney.<br />

2.08.2 Power for these lights shall be obtained from the construction power system<br />

including cable, cabling & maintenance by bidder.<br />

2.09 Painting and lead coating shall be carried out as per specification<br />

requirements.<br />

2.10 Communication System<br />

Telephone sockets at 0.0 M and at every platform for connection of telephone<br />

handset shall be provided. Purchaser will provide necessary connection to the<br />

JB at 0.0 M from telephone exchange. Bidder shall provide telephone cable<br />

(as per ITD specification) installed in independent G.I. conduit and wired<br />

upto junction boxes with telephone socket.<br />

2.11 Photo Electric light detector along with timer & contactor etc. shall be<br />

supplied and installed to monitor the aviation obstruction lighting system.<br />

2.12 Any item or work either supply of equipment or erection material which have<br />

not been specifically mentioned but are necessary to complete the work for<br />

trouble free and efficient operation of the plant shall be deemed to be<br />

included within the scope of this specification and shall be provided by the<br />

tenderer without any extra charge.<br />

2.13 All equipment offered shall have suitable provision for termination and<br />

connection of power, control and special cables and shall also be complete


TITLE:<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

SECTION - C SUB SECTION: II<br />

ELECTRICAL WORKS<br />

SHEET 5 OF 6<br />

with cable boxes, double compression nickel-chromium plated brass cable<br />

glands (heavy duty type), solderless tinned copper crimping cable lugs etc.<br />

2.14 The size of two nos. down conductors for earthing are 50 x 6 mm GS flat<br />

extending at different platforms for electrical equipment earthing. These<br />

down conductor are in addition to lightning down conductor.Total four nos.<br />

down conductor shall be provided<br />

2.15 Various drawings, data, calculations, test reports, test certificates, operation<br />

and maintenance manuals etc. as specified shall be furnished after award of<br />

contract for approval of purchaser/customer/consultant.<br />

2.16 Make of equipment/components shall be subject to<br />

purchaser/customer/consultant approval after award of contract without any<br />

commercial or delivery implications to the purchaser.<br />

2.17 Bidder shall quote for mandatory spares for electrical equipment as per<br />

attached list. Bidder may further note that purchaser reserves the right to<br />

delete any item/ all items from the list after award of contract.<br />

2.18 Bidder shall furnish list of recommended spares for 3 years for all electrical<br />

equipments with unit prices.<br />

2.19 Start-up & commissioning spares for electrical equipment shall be supplied<br />

on as required basis and cost for the same shall be included in the main<br />

equipment cost.<br />

2.20 Bidder shall furnish List of Erection & maintenance tools & tackles with the<br />

offer.<br />

2.21 Bidder shall furnish unpriced “Price Schedule” for electrical equipments with<br />

the offer.<br />

2.22 All equipment shall be suitable for the power supply fault levels and other<br />

climatic conditions mentioned in the enclosed project electrical information.<br />

2.23 Bidder shall furnish electrical load requirements for normal 415V AC &<br />

Emergency 415V AC after award of contract.<br />

2.24 The final technical particulars of various electrical equipment/ components/<br />

items shall be subject to purchaser/consultant/customer approval after award<br />

of contract.<br />

2.25 The detailed Schedule of Equipment is enclosed in the form of Electrical<br />

Equipments BOQ.<br />

2.26 Various drawings/ documents for electrical equipments for chimney shall be<br />

prepared by bidder after award of contract for approval of<br />

purchaser/customer/consultant.<br />

REV.NO. 0 DATE: 18.09.2010<br />

3.00 EQUIPMENT & SERVICES TO BE PROVIDED BY PURCHASER FOR<br />

ELECTRICAL & TERMINAL POINTS<br />

3.01 Power cables for incomer to 415 V AC Distribution Board (ACDB) and AC<br />

Emergency Lighting distribution board (ELDB). However, termination of<br />

incomer power cables in ACDB & ELDB shall be carried out by bidder.<br />

ACDB & ELDB shall be located inside the chimney. Bidder to note that the<br />

second incomer to ELDB shall be derived from ACDB by the bidder. Cable<br />

glands and lugs shall be supplied by the bidder.<br />

3.02 Cable trench, cable trays/GI pipes up to the boundary limit of the chimney<br />

i.e. 3M away from outer shell. Bidder shall coordinate with the purchaser for


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENTS FOR<br />

ELECTRICAL WORKS<br />

layout and matching.<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - C SUB SECTION: II<br />

REV.NO. 0 DATE: 18.09.2010<br />

SHEET 6 OF 6<br />

4.00 OTHER REQUIREMENTS<br />

4.01 In case of any deviation the bidder shall indicate the same clause by clause in<br />

enclosed deviation schedule. In the absence of duly filled in schedules, it will<br />

be construed that the offer confirms strictly to the specification.<br />

4.02 Bidder shall furnish duly filled in data sheets (enclosed with specification) for<br />

electrical equipments after the award of contract for approval. Technical data<br />

sheet of any other electrical equipment if required by the purchaser shall be<br />

furnished to the contractor after award of contract to enable them to furnish<br />

the same.<br />

4.03 The bidder shall furnish signed and stamped copy of the specification as a<br />

token of acceptance and submit the same along with the technical offer.<br />

Further, Quality plan shall be subject to BHEL/customer/consultant approval<br />

after award of contract without any commercial or delivery implication.<br />

Inspection shall be carried out as per approved Quality Plan approved during<br />

detailed engineering.<br />

4.04 Bidder shall furnish details of aviation obstruction lights with catalogues.<br />

4.05 Bidder shall furnish all drawings/data/catalogues as indicated in different<br />

electrical equipment specifications along with the offer in sufficient nos. as<br />

indicated in the civil part of the specification.<br />

4.06 The minimum illumination level shall be provided as indicated below :<br />

- Ground Floor, platforms, stairs & landings 50 LUX<br />

- Area of different distribution boards 150 LUX<br />

4.07 In case of any conflict between various sections of the specification, decision<br />

of the Purchaser shall be final and binding on the bidder.


SPEC<strong>IF</strong>IC TECHNICAL<br />

REQUIREMENT<br />

SPEC<strong>IF</strong>ICATION NO.PE-TS-360-620-C001<br />

VOLUME II B<br />

SECTION C SUB-SECTION III<br />

REV. 0 DATE:<br />

SHEET<br />

SUB SECTION – III<br />

STACK ELEVATOR


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

SYSTEM DESCRIPTION AND VOLUME II B<br />

SCOPE OF WORK FOR SECTION C SUB SECTION : III<br />

STACK ELEVATOR REV 0 DATE<br />

SHEET<br />

OF<br />

1.00 SYSTEM DESCRIPTION<br />

One (1) no. Rack and pinion type stack elevator is required for installation inside multi-flue or<br />

outside single flue chimney. The stack Elevator is normally used for the movement of the<br />

maintenance personnel and for materials such as refractory bricks, etc. for maintenance of<br />

chimney.<br />

2.0 SCOPE OF SUPPLY AND SERVICES<br />

The scope of supply and services covered under the specification are broadly described below:<br />

- One No. Rack and Pinion type stack elevator complete with all other accessories and<br />

associated steel work.<br />

- Drive motor and control panel for Stack elevator<br />

- Control Panel<br />

- Equipment earthing<br />

- All power and control cables, trailing cables<br />

- Limit switches<br />

- Over speed governor<br />

- Alarm push button in the cage connected to battery operated alarm at elevator base.<br />

- Reverse phase relay connected to prevent operation of the cab with improper phase<br />

rotation or failure in any phase of power supply.<br />

- Continuous duty electrical torque motor recoil cable reels or cable trolley or any<br />

equivalent arrangement to maintain electrical power service to all electrical components of<br />

the elevator for complete travel of stack elevator.<br />

- One auxiliary panel shall be provided and mounted on the graded level enclosure<br />

equipped with a main ON-OFF selector switch, main contactor, breaker, relays, control<br />

transformer and fuses, tone frequency transmitter or equivalent arrangement, , terminal<br />

blocks and all other accessories required for normal operation of the elevator.<br />

- One main control panel shall be furnished and mounted on top of the cab. Panel shall be<br />

in enclosure equipped with necessary equipment like rectifier, battery charger charger,<br />

tone frequency receiver, contactors, breakers, control transformer and fuses, thermal<br />

overload relays, and all other equipment and accessories required for normal operation of<br />

the elevator.<br />

- Cab shall be controlled by semi automatic floor selection control system. Cab shall be<br />

furnished with 240 V grounding receptacle, emergency alarm push button with normally<br />

open contact, indicating light, limit switches, and all other necessary control devices<br />

required to ensure safe and continuous cab operation. One trailing cable shall connect<br />

the main control panel to aux. Panel at ground level. Cable shall supply the cab necessary<br />

power supply requirements. Cable guides shall be installed at every 6 m intervals to avoid<br />

entanglement of this cable. Control signal between the aux. Panel at ground level, the


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

SYSTEM DESCRIPTION AND VOLUME II B<br />

SCOPE OF WORK FOR SECTION C SUB SECTION : III<br />

STACK ELEVATOR REV 0 DATE<br />

SHEET<br />

OF<br />

main control panel on the cab and the landings shall be provided with tone frequency<br />

receiver or any other equivalent arrangement by trailing control cable.<br />

- Each landing assembly shall include a limit switch and push button control station installed<br />

and wired to a landing junction box.<br />

- All power cable and race way shall be provided and installed by the bidder for<br />

interconnection of the main control panel, auxiliary panel and landing junction boxes.<br />

Trailing cables shall be as per relevant IS/IEC standard.<br />

- Bidder shall provide, install and connect a system equipment ground to owner’s chimney<br />

grounding system. Equipment grounding system shall electrically connect panels and<br />

junction boxes which contain electrical devices, motors and elevator platform and<br />

structures. Raceway system shall not be considered as an equipment ground.<br />

- All enclosures containing electrical devices shall be provided with 240 V, single phase<br />

heaters with adjustable thermostat control.<br />

- Cab shall be equipped with a 240 V AC interior light and duplex outlet.<br />

- Cable accessories as required to install the cables in bidder’s scope shall be provided by<br />

the bidders.<br />

- Complete erection, testing and commissioning including all erection materials,<br />

consumables and other tools and tackles required for erection along with commissioning<br />

spares.<br />

- All inserts, anchor bolts, sleeves, anchoring steel and any other items required to<br />

complete the job satisfactorily shall be in bidder’s scope.<br />

- First fill of lubricant and consumables shall be in bidder’s scope.<br />

- Satisfactory running and maintenance of elevator for a continuous period of 30 days<br />

including training of owner’s operators.<br />

- Supply of One complete set of special maintenance tools and tackles shall be in bidder’s<br />

scope.<br />

- Any other equipment or accessories not specified, but required for the satisfactory<br />

operation of chimney elevator shall be in bidder’s scope.<br />

- Recommended spares including instrumentation for 3 years of normal operation of stack<br />

elevator. ( List to be furnished by the bidder and for which order shall be placed separately<br />

by owner as per their requirements)<br />

3.0 SPEC<strong>IF</strong>IC REQUIREMENTS<br />

- The equipment supplied, erected and commissioned shall meet the technical requirements<br />

of respective Section –D and Data Sheet-A.<br />

- Bidder shall note that all QP and Field quality plans shall be subject to purchaser’s<br />

approval.<br />

- All equipment offered shall have suitable provision of termination and connection of power<br />

and control cables inclusive of cable boxes, lugs and glands, etc.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

SYSTEM DESCRIPTION AND VOLUME II B<br />

SCOPE OF WORK FOR SECTION C SUB SECTION : III<br />

STACK ELEVATOR REV 0 DATE<br />

SHEET<br />

OF<br />

- All the equipment shall be suitable for the power supply fault level and other climatic<br />

conditions as indicated in project information.<br />

- The bidder shall guarantee the rating and performance parameters of the system/equipment<br />

offered in accordance with specification requirements.<br />

- It is the responsibility of bidder to arrange license for operation of chimney elevator from<br />

statutory body of that area before handing over.<br />

- Bidder shall furnish deviation (clause wise) in the deviation schedule. In absence of dully filled<br />

deviation list, it will be presumed that offer is exactly in line with the technical specification.<br />

- Bidder shall furnish duly filled data sheet –B alongwith the offer. In absence of same, offer shall<br />

be treated as incomplete.<br />

- Bidder shall offer the stack elevator considering prevailing statutory and regulatory requirements<br />

of project location.<br />

- Bidder shall indicate degree of protection of various electrical equipment in the offer.<br />

- Makes of all bought out items shall subject to purchaser’s approval after award of contract.<br />

- All drawings/documents shall subject to purchaser’s approval after award of contract.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

1.00.00 DESIGN AND CONSTRUCTION<br />

1.01.00 Stack Elevator - General<br />

1.01.01 The stack elevator including mechanical and electrical components shall be installed<br />

outside/inside Single flue/ multi flue chimney. Since chimney is a free standing structure,<br />

deflection of chimney top is expected during the normal operation, so the design of the elevator<br />

shall be in such a way that the elevator operation will be safe even with the expected maximum<br />

deflection of the chimney structure. The stack elevator shall lift a pay load as indicated against<br />

rated load as mentioned in Data sheet-A or its nearest as per manufacturer’s present standard<br />

in addition to the weight of the car and its accessories and shall travel at a rated speed as<br />

indicated in the data sheet-A. Travel of the elevator car, number of landings and levels shall be<br />

as per Data sheet-A attached to this section.<br />

1.01.02 Stack elevator mechanical and electrical operating devices and trailing cable shall be designed<br />

for operation indoors/out door with dusty and high humidity conditions and shall operate equally<br />

well in any ambient temperature encountered in the site conditions. Additionally, all mechanical<br />

and electrical components of the elevator shall be designed to withstand without damage a<br />

temperature of 100 o C when the elevator is not operating.<br />

1.01.03 Cage earthing shall be done through trailing cable.<br />

1.01.04 Stack elevator shall be attached to the chimney shell using expansion type anchor bolts drilled<br />

in to chimney shell. Elevator shall be capable of operating from the ground floor to the top<br />

platform with intermediate stops at all platforms. Landing for elevator parking shall be one (1)<br />

metre above the stack ground floor. Suitable concrete/brick steps leading to the landing for<br />

entry to cabin shall also be provided,<br />

1.01.05 The stack elevator shall be designed in line with recommendations contained in the latest<br />

editions of the applicable codes and standards.<br />

1.02.00 Equipment Specification<br />

1.02.01 Enclosures<br />

1.02.02 Mast<br />

1.02.03 Cab<br />

A three-sided enclosure with one access door shall be provided at graded level. At each<br />

platform landing above graded level, a one sided enclosure with access door shall be provided.<br />

Enclosures shall be fabricated from tubular steel and expanded metal or wire mesh, 2.1 m high<br />

and one coat of epoxy primer coated. Enclosure access doors shall be electrically and<br />

mechanically interlocked so that they remain closed and locked except when the Cab is at the<br />

landing. Doors shall be bi-parting and swinging type.<br />

Base of three-sided enclosure shall be securely anchored to the grade level floor slab using<br />

expansion type anchors.<br />

Mast shall be provided in sections approximately 1.52 m in lengths considering of tubular<br />

sections and/or structural shapes welded together to form a frame work to which the rack is<br />

bolted. Mast shall be securely anchored to the concrete chimney walls.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Cab frame shall be fabricated from tubular steel and enclosed with expanded metal or wire<br />

mesh.<br />

Cab floor shall be of skid resistant glass fibre reinforced plywood or approved equal. Cab shall<br />

be attached to a framed structure and form integral part with the drive mechanism located atop<br />

the cab.<br />

Framed structure shall include guide rollers and safety hooks to ensure positive engagement of<br />

the rack and pinion to prevent cab disengagement in case of roller failure.<br />

1.02.04 Buffers<br />

Sufficient numbers of buffers of spring loaded/hydraulic type shall be fitted below the cab. The<br />

buffers shall be capable of stopping the cab without permanent damage or deformation to<br />

themselves or any other part of the equipment. The number of buffers shall be so fixed as to<br />

ensure proper sharing of impact loads by all of them.<br />

1.02.05 Drive unit and safety Device<br />

Drive unit located on the top of the cab shall be complete with Ac squirrel cage induction motor,<br />

reduction gear, drive pinion and an over speed governor. Drive unit shall incorporate an electric<br />

disc brake and an external manual brake release. The brake on the electric motor will be of the<br />

electromagnetic single disc self-adjusting type with the mechanical compression spring being<br />

held off by the electromagnet.<br />

The hoist shall be provided with a centrifugal brake to prevent accidental tripping of safety<br />

device when the cage shall be taken to the ground by gravity in case of power failure.<br />

1.02.05 Power and Control<br />

All electrical components furnished with the elevator shall be completely wired, energised and<br />

checked. Necessary power distribution arrangement shall be provided by the contractor to feed<br />

the electrical power to the elevator.<br />

All electrical control devices shall be in enclosures. Equipment furnished shall also include the<br />

following:<br />

a) Momentary contact push button for raise lower control.<br />

b) Reversing combination motor starter with a moulded case circuit breaker for the motor.<br />

Starter shall be equipped with three thermal overload relays for motor protection. Operating<br />

handle for the combination starter circuit breaker shall be accessible from inside the cab and<br />

shall also serve as an emergency stop switch.<br />

c) Electrical and mechanical interlocks on cab access door and landing level enclosure doors.<br />

d) Over travel protection, emergency stop push button, over speed governors.<br />

e) All electrical and mechanical interlocks on cab access door and landing level enclosure doors,<br />

phase reversal protection shall be provided.<br />

f) An alarm push button shall be provided in the cage connected to a battery-operated alarm at the<br />

elevator base. Simultaneous alarm shall also sound at the plant control room in the event of any<br />

fault in the stack elevator for which one potential free contact shall be provided in each elevator<br />

for audiovisual alarm in PCR for “Stack Elevator fault” indication.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

g) Reverse phase relay connected to prevent operation of the cab with improper phase rotation or<br />

failure in any phase in the power supply.<br />

h) Continuous duty electric torque motor recoil cable reels as required to maintain electrical power<br />

service to all elevator electrical components throughout the limits of travel.<br />

i) One auxiliary panel shall be furnished and mounted on the grade level enclosure. Panel shall<br />

be equipped with a main ‘ON-OFF’ isolating switch, main contactor, relays, control transformer<br />

and fuses, tone frequency transfer, terminal blocks and all other accessories required for normal<br />

operation of the elevator.<br />

j) One main control panel shall be furnished and mounted on the top of the cab. Panel shall be<br />

equipped with necessary, equipped like rectifier, battery, charger, tone frequency receiver,<br />

contactors, MCBs, control transformer and fuses, thermal overload relays, and all other<br />

equipment and accessories required for normal operation of the elevator.<br />

k) Control cabinets shall be sheet steel enclosed and shall be dust, weather and vermin proof.<br />

Sheet steel used shall be cold rolled and at least 2.0 mm thick and properly braced to prevent<br />

wobbling. Degree of protection of the control cabinets shall be IP-52 as per IS:2147. Control<br />

cabinets shall be provided with hinged door(s) with padlocking arrangement. All doors,<br />

removable covers and plates shall be gasketed all around with neoprene gaskets, louvers,<br />

when provided, shall have screeners and filters. The screens shall be of fine wire mesh made<br />

of brass or GI wire. Suitable cable gland plate shall be supplied fitted on to this gland plate. All<br />

cable glands shall be screwed on type and made of brass.<br />

l) Each motor to be controlled from the control cabinet shall be provided with 3 pole isolating<br />

switch. HRC fuses, contactors of AC4 duty class with thermal overload relays with single<br />

phasing preventer and other equipment required for satisfactory control motor. The isolating<br />

switch and contractor shall be rated at least 20% more than the connected motor full load<br />

current. Motors of 0.2 KW and above shall be rated for 415 V 3 Phase and below 0.2 KW will<br />

be 240 V single phase supply.<br />

m) The controllers and resistors for motors shall conform to IS-8544 (latest edition) and IS-2959<br />

(latest edition) and shall be continuously rated for 150% full load current of the motor. Switches<br />

shall be hand operated, air breaker heavy duty, quick make, quick break type conforming to IS-<br />

4064. The rating of switch shall be so chosen as to get complete protection by associated O/L<br />

relay or fuse under all normal / abnormal conditions such as full load, overload, locked rotor,<br />

short circuit. The incoming power supply isolating switch shall be inter-locked with the control<br />

cabinet door so as to prevent opening of the door when the switch is closed. Device for<br />

bypassing the door interlock shall also be provided. Switch handle shall have provision for<br />

locking in both fully open and fully closed positions.<br />

n) All fuses shall be of the HRC cartridge type mounted on plug in type of fuse base having a<br />

prospective current rating of not less than 80 KA. Fuses shall be provided with visible operation<br />

indicators to show that they have operated. All accessible live connections shall be adequately<br />

shrouded and it shall be possible to change fuses with the circuit alive without danger of contact<br />

with live metal.<br />

o) Contractor shall provide dry type transformers with class B insulation for control power supply,<br />

lighting and space heating. Control supply will be 240 V AC. Transformer for control supply<br />

shall be provided with a control tap at 110 V, which will be earthed. Power and control supply to<br />

individual drives and users shall be distributed with separate isolating switches and primary and<br />

secondary fuses.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

p) All push buttons shall be of push to actuate type having 2 “NO” and 2 “NC” self reset contacts.<br />

They shall be provided with integral escutcheon on plate engraved with their functions. Push<br />

button contacts shall be rated for 5 Amp at 415 V AC and 1 Amp. Inductive breaking at 250 V,<br />

DC. Mushroom type emergency push button to open the main contactor shall be provided in<br />

the operator’s cabin and two on the bridge platform within easy reach indicating lamps shall be<br />

of the filament type and low watt consumption lamps shall be provided with series resistors.<br />

q) Strip type space heaters of adequate capacity shall be provided inside in each cabinet.<br />

r) Control cabinets shall be supplied completely wired. All wiring shall be carried out with 650 V<br />

grade PVC insulated, stranded conductors. Power circuits shall be wired with stranded<br />

aluminum conductors of adequate sizes to suit the rated circuit shall be wired with stranded<br />

copper conductors of sizes not small than 1.5 Sq.mm. Control circuits shall be isolated from<br />

power circuits.<br />

s) Cab shall be controlled by a semi-automatic floor selection control system. Cab shall be<br />

furnished with 240 Volt grounding type receptacle, emergency alarm push button with a<br />

normally open contact rated 0.5 ampere at 220 VDC volts, indicating light, limit switches, and all<br />

other necessary control devices required to ensure safe and continuous cab operation. One<br />

trailing cable shall connect the cab main control panel to the auxiliary panel at ground level.<br />

Cable shall supply the cab with all power requirements. Cable guides shall be installed at every<br />

6 metres to avoid entanglement of this cable. Control signals between the auxiliary panel at<br />

ground level and the main control panel on the cab. Will be provided with the tone frequency<br />

receiver. However control and interlocks from the landings shall be connected to the auxiliary<br />

panels located at ground level through fixed armoured cables. The power and control cables<br />

and training power cables shall be FRLS type.<br />

s) Each landing assembly shall include a limit switch for door interlock and push button control<br />

station installed and wired to a landing junction box.<br />

t) Cable trolley with cable guides for recoil of cable on to cable reel to maintain electrical power<br />

service to all elevator components through out the limits of travel.<br />

u) Contractor shall furnish, install, and connect a system equipment ground to the Owner’s existing<br />

chimney ground system. System equipment ground shall electrically connect panels and<br />

junction boxes, which contain electrical devices, motors, and elevator platforms and support<br />

structure. Raceway system shall not be considered as an equipment ground.<br />

v) All enclosures containing electrical devices shall be provided with 240 Volt, single-phase space<br />

heaters with adjustable thermostat control.<br />

w) All power cables and race way shall be furnished and installed by the Contractor for<br />

interconnection of the main control panel, auxiliary panel and landing junction boxes etc.<br />

Conductors included in the cable shall be as required to energise all electrical equipment<br />

furnished with the elevator. Transmission of alarm signals is done by means of tone frequency<br />

equipment. Hence communication conductors are not required.<br />

6.03.07 Electric Motor<br />

Elevator drive motor shall be squirrel-cage induction type designed and fabricated to conform to<br />

the requirements indicated below.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Motor shall be designed for operation at the required speed: 415 Volts, 3 phase, 50 hertz. And<br />

shall be suitable for full voltage starting, S4 duty class as per IS-4722 with CDF of 25% and<br />

maximum number of 120 starts per hour in 55 Deg. C ambient temperature. Motor shall be<br />

tested at the factory to determine that it is free from electrical or mechanical defects.<br />

6.03.08 Raceway<br />

a) General<br />

Complete raceway system for the elevator shall be furnished and installed in accordance with<br />

this section and the Contractor’s shop drawings as reviewed and accepted by the Engineer-in-<br />

Charge. The Contractor shall provide drawings for acceptance showing the routing of conduit<br />

and wiring for the control circuits associated with the elevator.<br />

Raceway system is defined to include conduit and all related materials and devices required to<br />

support, secure and provide a complete system for support and protection of electrical cable<br />

and wiring.<br />

b)Materials<br />

Raceway shall be rigid galvanized steel conduit, provided in accordance with IS-1653 (latest<br />

edition).<br />

Steel conduit, couplings, and elbows shall be hot-dip galvanized rigid mild steel. Each length of<br />

threaded conduit shall be complete with a coupling on one end and a thread protector on the<br />

other. Thread protector shall have sufficient mechanical strength to protect the threads during<br />

normal handling and storage. Flexible conduits shall be plastic jacketed, liquid tight galvanized<br />

steel.<br />

Galvanised iron or galvanized cast steel fittings shall be used with galvanized steel conduit.<br />

Fittings installed outdoors or in damp locations shall be sealed and gasketted. Outdoor fittings<br />

shall be of heavy cast construction.<br />

6.03.09 PVC Insulated FRLS Cable<br />

a) Materials<br />

Electrical part of this specification shall be referred for FRLS cable. Unless specified otherwise,<br />

Contractor shall submit to the Engineer-in-Charge four copies of the manufacturer’s test report<br />

on each cable furnished. Conductor accessories including terminal materials like glands, lugs<br />

etc. makers, tying materials and cable support shall be furnished and installed. Wire<br />

termination materials for conductors 10 Sq. mm and larger shall be pressure or bolted type.<br />

Terminals for conductors smaller than 10 Sq. mm shall be an insulated pressure connection in<br />

the shape of a ring.<br />

b) Installation<br />

6.03.10 Earthing<br />

Power and control cable shall be routed as required by the drawings. Cables pulled into the<br />

wrong conduit or cut too short shall be replaced. Cables removed from one conduit shall not be<br />

installed in another conduit.<br />

a) General


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION III<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Earthing system furnished and installed and include a complete earthing system for the<br />

elevator. Earthing equipment and materials shall be furnished and installed in accordance with<br />

the reference codes and standards these specification and the contractor’s shop drawings as<br />

reviewed and accepted by the Engineer-in-Charge.<br />

b) Materials<br />

The earthing of all electrical items being supplied by the Bidder shall be in his scope. For<br />

earthing the various equipment, conductor sizes shall be as listed below:<br />

i) MCCs Motor above 90 KW : 50 x 6 Sq.mm G.I. flat<br />

ii) Motors above 30 KW, upto<br />

75 KW and lighting panel/<br />

control panels/auxiliary panels : 25 x 6 Sq. mm G.I. flat<br />

iii) Motor above 5 KW upto 30 KW : 25 x 3 mm G.I. flat<br />

iv) Motors upto 5 KW and misc. : 8 SWG GI wire<br />

Small item like conduits,<br />

Junction boxes etc.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

1.00.00 DESIGN AND CONSTRUCTION<br />

1.01.00 Stack Elevator - General<br />

1.01.01 The stack elevator including mechanical and electrical components shall be installed inside Single flue/<br />

multi flue chimney. Since chimney is a free standing structure, deflection of chimney top is expected<br />

during the normal operation, so the design of the elevator shall be in such a way that the elevator<br />

operation will be safe even with the expected maximum deflection of the chimney structure. The stack<br />

elevator shall lift a pay load as indicated against rated load as mentioned in Data sheet-A or its nearest<br />

as per manufacturer’s present standard in addition to the weight of the car and its accessories and shall<br />

travel at a rated speed as indicated in the data sheet-A. Travel of the elevator car, number of landings<br />

and levels shall be as per Data sheet-A attached to this section.<br />

1.01.02 Stack elevator mechanical and electrical operating devices and trailing cable shall be designed for<br />

operation indoors/out door with dusty and high humidity conditions and shall operate equally well in any<br />

ambient temperature encountered in the site conditions. Additionally, all mechanical and electrical<br />

components of the elevator shall be designed to withstand without damage a temperature of 100 o C when<br />

the elevator is not operating.<br />

1.01.03 Cage earthing shall be done through trailing cable.<br />

1.01.04 Stack elevator shall be attached to the chimney shell using expansion type anchor bolts drilled in to<br />

chimney shell. Elevator shall be capable of operating from the ground floor to the top platform with<br />

intermediate stops at all platforms. Landing for elevator parking shall be one (1) metre above the stack<br />

ground floor. Suitable concrete/brick steps leading to the landing for entry to cabin shall also be provided,<br />

1.01.05 The stack elevator shall be designed in line with recommendations contained in the latest editions of the<br />

applicable codes and standards.<br />

1.02.00 Equipment Specification<br />

1.02.01 Enclosures<br />

1.02.02 Mast<br />

1.02.03 Cab<br />

A three sided enclosure with one access door shall be provided at graded level. At each platform landing<br />

above graded level, a one sided enclosure with access door shall be provided. Enclosures shall be<br />

fabricated from tubular steel and expanded metal or wire mesh, 2.1 m high and one coat of epoxy primer<br />

coated. Enclosure access doors shall be electrically and mechanically interlocked so that they remain<br />

closed and locked except when the Cab is at the landing. Doors shall be bi-parting and swinging type.<br />

Base of three sided enclosure shall be securely anchored to the grade level floor slab using expansion<br />

type anchors.<br />

Mast shall be provided in sections approximately 1.52 m in lengths considering of tubular sections and/or<br />

structural shapes welded together to form a frame work to which the rack is bolted. Mast shall be securely<br />

anchored to the concrete chimney walls.<br />

Cab frame shall be fabricated from tubular steel and enclosed with expanded metal or wire mesh.<br />

Cab floor shall be of skid resistant glass fibre reinforced ply wood or approved equal. Cab shall be<br />

attached to a framed structure and form integral part with the drive mechanism located atop the cab.<br />

Framed structure shall include guide rollers and safety hooks to ensure positive engagement of the rack<br />

and pinion to prevent cab disengagement in case of roller failure.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

1.02.04 Buffers<br />

One cabin fan, two recessed fluorescent lamp fittings and one number receptacle with duplex outlet (5A,<br />

240V each) to be provided alongwith one number emergency light with battery and charger.<br />

Cab roof shall be provided with an escape hatch electrically interlocked with the hoist control system.<br />

Tubular steel hand rail shall enclose the cab roof for maintenance operations.<br />

Cab door and landing level enclosure doors shall be electrically and mechanically interlocked to prevent<br />

the cab from being operated unless the cab door and landing level enclosure doors are fully closed and<br />

to prevent doors from being opened while the cab is in motion.<br />

Other accessories such as cab control station, load plate, etc. to be provided in the cab.<br />

Sufficient numbers of buffers of spring loaded/hydraulic type shall be fitted below the cab. The buffers<br />

shall be capable of stopping the cab without permanent damage or deformation to themselves or any<br />

other part of the equipment. The number of buffers shall be so fixed as to ensure proper sharing of impact<br />

loads by all of them.<br />

1.02.05 Drive unit and safety Device<br />

drive unit located on the top of the cab shall be complete with Ac squirrel cage induction motor, reduction<br />

gear, drive pinion and an over speed governor. Drive unit shall incorporate an electric disc brake and an<br />

external manual brake release. The brake on the electric motor will be of the electromagnetic single disc<br />

self adjusting type with the mechanical compression spring being held off by the electromagnet. In the<br />

event of power failure, the brake will be automatically applied and will stop the cab. A hand lever, which<br />

can be operated from the cage, is to be provided to enable the occupants to ease the brake and lower the<br />

cage to the bottom level. Motor shall be connected to a reduction worm gear, which drives the pinion.<br />

An over speed governor in constant mesh with the rack by means of frame hardened steel pinion is<br />

incorporated to protect the cab against over speed during the cab downward motion. At the predetermined<br />

speed higher than normal, the centrifugal action of the governor pawl will actuate the<br />

incorporated brake mechanism and stop the downward motion of the cab gradually. The brake should<br />

remain locked on following this action and has to be manually reset before normal elevator operation can<br />

be resumed.<br />

A remote control shall be provided for testing the safety device to ensure that no individual is in the cab<br />

during the test.<br />

The drive system shall be designed so that it will be capable to operate smoothly without any tendency to<br />

rock or judder with all vertical, horizontal forces as well as the moments through the rack.<br />

The hoist shall be provided with a centrifugal brake to prevent accidental tripping of safety device when<br />

the cage shall be taken to the ground by gravity in case of power failure.<br />

1.02.05 Power and Control<br />

All electrical components furnished with the elevator shall be completely wired, energised and checked.<br />

Necessary power distribution arrangement shall be provided by the contractor to feed the electrical;<br />

power to the elevator.<br />

All electrical control devices shall be in enclosures. Equipment furnished shall also include the following:<br />

a) Momentary contact push button for raise lower control.<br />

b) Reversing combination motor starter with a moulded case circuit breaker for the motor. Starter shall be<br />

equipped with three thermal overload relays for motor protection. Operating handle for the combination<br />

starter circuit breaker shall be accessible from inside the cab and shall also serve as an emergency stop<br />

switch.<br />

c) Electrical and mechanical interlocks on cab access door and landing level enclosure doors.<br />

d) Over travel protection, emergency stop push button, over speed governors.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

e) All electrical and mechanical interlocks on cab access door and landing level enclosure doors, phase<br />

reversal protection shall be provided.<br />

f) An alarm push button shall be provided in the cage connected to a battery operated alarm at the elevator<br />

base. Simultaneous alarm shall also sound at the plant control room in the event of any fault in the stack<br />

elevator for which one potential free contact shall be provided in each elevator for audio visual alarm in<br />

PCR for “Stack Elevator fault” indication.<br />

g) Reverse phase relay connected to prevent operation of the cab with improper phase rotation or failure in<br />

any phase in the power supply.<br />

h) Continuous duty electric torque motor recoil cable reels as required to maintain electrical power service to<br />

all elevator electrical components throughout the limits of travel.<br />

i) One auxiliary panel shall be furnished and mounted on the grade level enclosure. Panel shall be<br />

equipped with a main ‘ON-OFF’ isolating switch, main contactor, relays, control transformer and fuses,<br />

tone frequency transfer, terminal blocks and all other accessories required for normal operation of the<br />

elevator.<br />

j) One main control panel shall be furnished and mounted on the top of the cab. Panel shall be equipped<br />

with necessary, equipped like rectifier, battery, charger, tone frequency receiver, contactors, MCBs,<br />

control transformer and fuses, thermal overload relays, and all other equipment and accessories required<br />

for normal operation of the elevator.<br />

k) Control cabinets shall be sheet steel enclosed and shall be dust, weather and vermin proof. Sheet steel<br />

used shall be cold rolled and at least 2.0 mm thick and properly braced to prevent wobbling. Degree of<br />

protection of the control cabinets shall be IP-52 as per IS:2147. Control cabinets shall be provided with<br />

hinged door(s) with padlocking arrangement. All doors, removable covers and plates shall be gasketed<br />

all around with neoprene gaskets, louvers, when provided, shall have screeners and filters. The screens<br />

shall be of fine wire mesh made of brass or GI wire. Suitable cable gland plate shall be supplied fitted on<br />

to this gland plate. All cable glands shall be screwed on type and made of brass.<br />

l) Each motor to be controlled from the control cabinet shall be provided with 3 pole isolating switch. HRC<br />

fuses, contactors of AC4 duty class with thermal overload relays with single phasing preventer and other<br />

equipment required for satisfactory control motor. The isolating switch and contractor shall be rated<br />

atleast 20% more than the connected motor full load current. Motors of 0.2 KW and above shall be rated<br />

for 415 V 3 Phase and below 0.2 KW will be 240 V single phase supply.<br />

The controllers and resistors for motors shall conform to IS-8544 (latest edition) and IS-2959 (latest<br />

edition) and shall be continuously raed for 150% full load current of the motor. Switches shall be hand<br />

operated, air breaker heavy duty, quick make, quick break type conforming to IS-4064. The rating of<br />

switch shall be so chosen as to get complete protection by associated O/L relay or fuse under all normal /<br />

abnormal conditions such as full load, overload, locked rotor, short circuit. The incoming power supply<br />

isolating switch shall be inter-locked with the control cabinet door so as to prevent opening of the door<br />

when the switch is closed. Device for bypassing the door interlock shall also be provided. Switch handle<br />

shall have provision for locking in both fully open and fully closed positions.<br />

m) All fuses shall be of the HRC cartridge type mounted on plug in type of fuse base having a prospective<br />

current rating of not less than 80 KA. Fuses shall be provided with visible operation indicators to show<br />

that they have operated. All accessible live connections shall be adequately shrouded and it shall be<br />

possible to change fuses with the circuit alive without danger of contact with live metal.<br />

n) Contractor shall provide dry type transformers with class B insulation for control power supply, lighting<br />

and space heating. Control supply will be 240 V AC. Transformer for control supply shall be provided<br />

with a control tap at 110 V which will be earthed. Power and control supply to individual drives and users<br />

shall be distributed with separate isolating switches and primary and secondary fuses.<br />

o) All push buttons shall be of push to actuate type having 2 “NO” and 2 “NC” self reset contacts. They shall<br />

be provided with integral escutche on plate engraved with their functions. Push button contacts shall be<br />

rated for 5 Amp at 415 V AC and 1 Amp. Inductive breaking at 250 V, DC. Mushroom type emergency<br />

push button to open the main contactor shall be provided in the operator’s cabin and two on the bridge<br />

platform within easy reach indicating lamps shall be of the filament type and low watt consumption lamps<br />

shall be provided with series resistors.<br />

p) Strip type space heaters of adequqte capacity shall be provided inside in each cabinet.<br />

q) Control cabinets shall be supplied completely wired. All wiring shall be carried out with 650 V grade PV<br />

Cinsulated, stranded conductors. Power circuits shall be wired with stranded aluminium conductors of<br />

adequate sizes to suit the rated circuit shall be wired with stranded copper conductors of sizes not small<br />

than 1.5 Sq.mm. Control circuits shall be isolated from power circuits.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

r) Cab shall be controlled by a semi-automatic floor selection control system. Cab shall be furnished with<br />

240 Volt grounding type receptacle, emergency alarm push button with a normally open contact rated 0.5<br />

ampere at 220 VDC volts, indicating light, limit switches, and all other necessary control devices required<br />

to ensure safe and continuous cab operation. One trailing cable shall connect the cab main control panel<br />

to the auxiliary panel at ground level. Cable shall supply the cab with all power requirements. Cable<br />

guides shall be installed at every 6 metres to avoid entanglement of this cable. Control signals between<br />

the auxiliary panel at ground level and the main control panel on the cab. Will be provided with the tone<br />

frequency receiver. However control and interlocks from the landings shall be connected to the auxiliary<br />

panels located at ground level through fixed armoured cables. The power and control cables and training<br />

power cables shall be FRLS type.<br />

s) Each landing assembly shall include a limit switch for door interlock and push buttom control station<br />

installed and wired to a landing junction box.<br />

t) Cable trolley with cable guides for recoil of cable on to cable reel to maintain electrical power service to<br />

all elevator component through out the limits of travel.<br />

u) Contractor shall furnish, install, and connect a system equipment ground to the Owner’s existing chimney<br />

ground system. System equipment ground shall electrically connect panels and junction boxes which<br />

contain electrical devices, motors, and elevator platforms and support structure. Raceway system shall<br />

not be considered as an equipment ground.<br />

v) All enclosures containing electrical devices shall be provided with 240 Volt, single-phase space heaters<br />

with adjustable thermostat control.<br />

w) All power cables and race way shall be furnished and installed by the Contractor for interconnection of<br />

the main control panel, auxiliary panel and landing junction boxes etc. Conductors included in the cable<br />

shall be as required to energise all electrical equipment furnished with the elevator. Transmission of<br />

alarm signals is done by means of tone frequency equipment. Hence communication conductors are not<br />

required.<br />

6.03.07 Electric Motor<br />

Elevator drive motor shall be squirrel-cage induction type designed and fabricated to conform to the<br />

requirements indicated on the drawings.<br />

Motor shall be designed for operation at the required speed: 415 Volts, 3 phase, 50 hertz. And shall be<br />

suitable for full voltage starting, S4 duty class as per IS-4722 with CDF of 25% and maximum number<br />

of 120 starts per hour in 55 Deg. C ambient temperature. Motor shall be tested at the factory to<br />

determine that it is free from electrical or mechanical defects.<br />

Motor nameplate KW rating shall not be exceeded when the equipment is operating within the limits of<br />

the maximum load requirements.<br />

Motor shall have sealed Class B nonhygroscopic insulation IIS-325) or equivalent international<br />

standard included two additional dips and bakes of epoxy varnish or vacuum impregnation. Insulation<br />

system shall be the motor manufacturer’s standard premium insulation offering.<br />

Motor shall be totally enclosed and furnished with cast iron frame, brackets, gasketed conduct box and<br />

fan cover. Motor shall be furnished with grease prelubricated, double-shielded, anti-friction bearings<br />

having life rating of not less than 42,500 hours under coupled service retirements. All exposed metal<br />

surfaces shall be protected with a polyester paint or coating which is moisture and corrosion resisdtant.<br />

Motor shall be provided with internal 240 Volt AC single-phase space heaters or an alternate heating<br />

system to prevent condensation within the motor during extended periods of idleness. Motorheating<br />

system shall be acceptable to the Engineer-in-Charge.<br />

Motor and driven equipment shall be direct coupled or belted as required, and mounted on a common<br />

baseplate with coupling or belt guard. Motor shall be completely assembled, lubricated, and ready for<br />

operation.<br />

Intent of these specifications is that the motor supplied be designed and constructed for the intended<br />

service. Motor construction and duty cycle shall conform with all requirements of applicable safety<br />

codes and standards for the service. For additional requirements <strong>Volume</strong>-I<strong>IF</strong> shall be referred to.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

6.08.08 Raceway<br />

a) General<br />

Complete raceway system for the elevator shall be furnished and installed in accordance with<br />

this section and the Contractor’s shop drawings as reviewed and accepted by the Engineer-in-<br />

Charge. The Contractor shall provide drawings for acceptance showing the routing of conduit<br />

and wiring for the control circuits associated with the elevator.<br />

Raceway system is defined to include conduit and all related materials and devices required to<br />

support, secure and provide a complete system for support and protection of electrical cable<br />

and wiring.<br />

Raceway shall be furnished and installed as required to extend raceway which has been<br />

installed under separate specifications for entry for circuits to the chimney facilities from<br />

external plant area. Raceway shall be provided for all cable and wiring installed under these<br />

specifications.<br />

b) Materials<br />

Raceway shall be rigid galvanized steel conduit, provided in accordance with IS-1653 (latest<br />

edition).<br />

Steel conduit, couplings, and elbows shall be hot-dip galvanized rigid mild steel. Each length<br />

of threaded conduit shall be complete with a coupling on one end and a thread protector on the<br />

other. Thread protector shall have sufficient mechanical strength to protect the threads during<br />

normal handling and storage. Flexible conduits shall be plastic jacketed, liquid tight galvanized<br />

steel.<br />

Galvanised iron or galvanized cast steel fittings shall be used with galvanized steel conduit.<br />

Fittings installed outdoors or in damp locations shall be sealed and gasketed. Outdoor fittings<br />

shall be of heavy cast construction.<br />

Bushings shall be provided at the termination of all conduit not terminated in hubs and<br />

couplings, insulated bushings with insulating inserts metal housings shall be provided on<br />

conduit 32 mm diameter and larger. Insulated bushings shall be grounding type standard<br />

bushings shall be galvanized.<br />

One interior and one exterior locknut shall be provided for all conduit terminations not provided<br />

with threaded hubs and couplings. Lockouts shall be designed to securely bond the conduit to<br />

the box when tightened. Locknuts shall be constructed that they will not be loosened by<br />

vibration.<br />

Raceway supports shall be galvanized steel materials. Hanger rods shall be 13 mm diameter<br />

threaded steel rods. Supports for conduits in single runs or groups of two shall be one-hole<br />

cast metal straps and clamps-backs unless other types are acceptable to the Engineer-in-<br />

Charge. Supports for banks of three or more conduits shall be constructed of support<br />

channels with associated conduits clips. Supports channels for galvanized steel conduit shall<br />

be hot-dip galvanized after fabrication.<br />

Junction box enclosure, type, and material shall be as indicated on the drawings or as stated in<br />

these specifications. Junction boxes, pull boxes, and cabinets shall not have knockouts.<br />

Junction boxes for indoor service shall be of sheet steel hot-dip galvanized after fabrication<br />

and shall be dust resisting enclosure. Except as indicated otherwisde in these specifications,<br />

all junction boxes for use in outdoor or damp locations shall be galvanized malleable iron or<br />

equivalent cast ferrous metal. Junction boxes and outlet boxes installed on the exterior shall<br />

be galvanized steel.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Outlet boxes, switch boxes, and associated fittings shall be galvanized iron or equivalent cast<br />

ferrous metal.<br />

c) Installation<br />

Contractor shall field route conduit according to the general routing indicated on the drawings<br />

reviewed and accepted by the Engineer-in-Charge and shall coordinate conduit locations with<br />

other equipment and structures. Wherever practical, conduit shall be routed so that, except<br />

where it is changing elevation or being lowered to enter equipment, the lowest part of the<br />

conduit, including its associated supports and appurtenances, is at least 2.05 metres above<br />

the closest walking surface beneath it. Conduit, including its associated supports and<br />

appurtenances, routed above work areas, walkways and platforms, shall be at least 2.05<br />

metres above the closest walking surface beneath it may be routed a reasonable disdtance<br />

away from the supporting wall of ceiling, so long as the specified support is provided,<br />

interference with other equipment and structures is avoided, and the routing is acceptable to<br />

the Engineer-in-Charge. Conduit including its associated supports and appurtenances, which<br />

must be routed closer than 2.05 metres above the closest walking surface beneath it shall be<br />

routed as closer than 2.05 metres above the closest walking surface beneath it shall be routed<br />

on the inside wall of the concrete chimney. Conduit which is stubbed up shall remain plugged<br />

until the conduit is extended. Conduit field routing shall be acceptable to ther Engineer-in-<br />

Charge. Routing not acceptable shall be rerouted and replaced without expenses to the<br />

Owner.<br />

Moisture pockets shall be eliminated from conduits. If water cannot drain to the natural<br />

opening in the conduit system, a hole shall be drilled in the bottom of a pull box or a “C-type”<br />

conduit fitting provided in the lower part of the conduit run.<br />

Metal conduit shall be joined by threaded conduit couplings with the conduit ends butted. Use<br />

of running threads will not be permitted. Where metal conduit cannot be joined by standard<br />

threaded couplings, conduit unions or split couplings may be used if both material and location<br />

are acceptable to the Engineer-in-Charge. Only ground seat type watertight unions shall be<br />

used where the union may be submerged.<br />

Run of conduit shall not contain more than the equivalent of four quarter bends, including<br />

those immediately at outlets or fittings. Bends in conduit shall be made without reducing the<br />

internal diameter of the conduit. Use of a pipe tee or vise for bending conduit will not be<br />

permitted. Inside radius of conduit bends shall be not less than six times the inside diameter of<br />

the conduit. Conduits deformed or crushed in any way shall be removed from the job site.<br />

Plane of all conduit ends shall be square with the center line. Where threads are required,<br />

they shall be cut and cleaned prior to conduit reaming. Ends of all conduits shall be reamed to<br />

remove all rough edges and burrs. Cutting oil shall be used in threading operations, the dies<br />

shall be kept sharp, and provisions shall be made for chip clearance. All steel conduit, after<br />

threading, shall be regalvanised by an acceptable galvanizing process. Contractor shall<br />

supply this protective material and shall apply it in the field.<br />

Conduit shall be securely fastened to all boxes and cabinets. Threads on metallic conduit<br />

shall project through the wall of the box to allow the bushing to butt against the end of the<br />

conduit. Lockouts both inside and outside shall then be tightened sufficiently to bond the<br />

conduit securely to the box.<br />

Precautions shall be taken to prevent the accumulation of water, dirt, or concrete in the<br />

conduit. Conduit in which water or other foreign materials have been permitted to accumulate<br />

shall be thoroughly cleaned or, where such accumulations cannot be removed by methods<br />

acceptable to the Engineer-in-Charge, the conduit shall be replaced.<br />

Equipment and devices which move in relation to the supply conduit due to vibration, normal<br />

operation of the mechanism, or thermal expansion shall be connected to the supply conduit<br />

using not more than 760 mm of flexible conduit adjacent to the equipment or device.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Expansion fittings shall be installed between rigidly mounted fittings in vertical raceway.<br />

Distance between expansion fittings in any individual raceway shall not exceed 15 metres.<br />

All conduit runs shall be rigidly supported. Each conduit shall be supported within 300 mm of<br />

junction boxes and fittings. Support spacing along conduit runs shall be as follows:<br />

Conduit Size<br />

Maximum Distance<br />

Between Supports<br />

Small than 40 mm dia. : 1.5 metres<br />

40 mm dia. And larger : 3 metres<br />

Cabinets and boxes shall be rigidly mounted. Mounted on concrete shall be with bolts and<br />

expansion anchors. Mounting on steel shall be by drilled and tapped screw holes, or by<br />

special support channels welded to the steel, or by both. Cabinets shall be leveled and<br />

fastened to the mounting surface with not less than 7 mm air space between the enclosure and<br />

mounting surface. All mounting holes in the enclosure shall be used. Except as prevented by<br />

the location of other work, all junction boxes and outlet boxes shall be centered on structures.<br />

Conduit openings in steel boxes shall be made with a hole saw or shall be punched. Cable<br />

support boxes shall be installed to be accessible from platforms and to limit the distance<br />

between vertical cable supports to the lengths specified as described in Clause 6.03.09.<br />

Where supports for raceway, boxes, and cabinets are mounted on concrete surfaces, they<br />

shall be fastened with expansion shell anchors with externally split expansion shells, single<br />

cone expander and anchor break off grooved checking cones.<br />

Contractor shall be responsible for all openings for passage of electrical raceways. Required<br />

openings not provided during chimney construction shall be provided by the Contractor using a<br />

hacksaw, a hole saw, or a core drill subject to the acceptance by the Engineer-in-Charge.<br />

Opening in concrete for single conduits shall be cut by the Contractor with core drills and the<br />

conduits shall be grouted in place after being installed.<br />

Field cutting of grating will be allowed only where specially acceptable to the Engineer-in-<br />

Charge. Alternate routing of raceways should be used to avoid conflict with grating. If held<br />

cutting is absolutely necessary, the openings shall be made at divisions or ends of grating<br />

sections. Openings shall be square and shall be neatly finished. Rough spots shall be ground<br />

until smooth and regalvanised as required. Openings in grating shall be sawed, not burned.<br />

Openings that have been cut through masonry or concrete for the passage of raceways shall<br />

be finished by grouting around the conduis.<br />

Welding shall completely fuse the welded member to the supporting steel and shall be neat in<br />

appearance. Clamps shall be used for making attachments to structural steel for installation<br />

purposes wherever possible. Welded lugs will be permitted only when specifically accepted by<br />

the Engineer-in-Charge. All temporary supports which have been welded to the structural<br />

steel shall be removed as promptly as possible. After removal, the roughened surface of the<br />

steel shall be ground smooth and a protective primer paint applied equal to that which was<br />

initially applied in the shop.<br />

Unfinished runs of raceways shall not be used. Supports and connections for each raceway<br />

run shall be completed prior to the pull-in of any pulling line or conductor.<br />

6.03.08 PVC Insulated FRLS Cable<br />

a) Materials


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

<strong>Volume</strong> : II –F of this specification shall be referred for FRLS cable. Unless specified<br />

otherwise, Contractor shall submit to the Engineer-in-Charge four copies of the<br />

manufacturer’s test report on each cable furnished. Conductor accessories including terminal<br />

materials like glands, lugs etc. makers, tying materials and cable support shall be furnished<br />

and installed. Wire termination materials for conductors 10 Sq. mm and larger shall be<br />

pressure or bolted type. Terminals for conductors smaller than 10 Sq. mm shall be an<br />

insulated pressure connection in the shape of a ring.<br />

b) Installation<br />

Power and control cable shall be routed as required by the drawings. Cables pulled into the<br />

wrong conduit or cut too short shall be replaced. Cables removed from one conduit shall not<br />

be installed in another conduit.<br />

Only lubricants recommended by the cable manufacturer and acceptable to the Engineer-in-<br />

Charge shall be used.<br />

Outside of each cable reel shall be carefully inspected and protruding nails, fastenings, or<br />

other objects which might damage the cable shall be removed. Thorough visual inspection<br />

for flaws, breaks, or abrasions in the cable sheath shall be made as the cable leaves the reel,<br />

and the pulling speed shall be slow enough to permit this inspection. Damage to the sheath<br />

or finish of the cable shall be sufficient cause for rejecting the cable. Cable damaged in any<br />

way during installation shall be replaced by and at the expense of the Contractor.<br />

Pulling tension of any cable shall not exceed the maximum tension recommended by the<br />

cable manufacturer. Pulling mechanisms of both the manual and power types used by the<br />

Contractor shall have the rated capacity clearly marked on the mechanism. Whenever the<br />

capacity of the pulling mechanism exceeds the recommended pulling tension of the cable as<br />

given by the cable manufacturer, a dynamometer shall be used to indicate the tension on the<br />

cable and the indicator shall be constantly watched. If any excessive strain develops, the<br />

pulling operation shall be stopped at once and the difficulty determined and corrected.<br />

Extreme care shall be exercised during the installation of all cable to prevent tension and<br />

bending conditions in excess of the manufacturer’s recommendations. Permanent radius of<br />

bend after cable installation shall b e in accordance with the cable manufacturer’s<br />

recommendations.<br />

Cable supports and securing devices shall have bearing surfaces located parallel to the<br />

surfaces of the cable sheath and shall be installed to provide adequate support without<br />

deformation of the cable jacket or insulation. Adequate cable end lengths shall be provided<br />

and properly installed in junction boxes to avoid longitudinal strains and distorting pressures<br />

on the cable at conduit bushings.<br />

Final inspection shall be made after all cables are in place, and where supports and bushings<br />

deform the cable jacket, additional supports shall be provided as directed by the Engineer-in-<br />

Charge. Additional cable protection such as a wrapping of light rubber belting, friction tape, or<br />

similar material, may be required. Cables in vertical runs shall be supported as indicated on<br />

the drawings.<br />

Not less than 8 mm shall be allowed in each 15 metres vertically supported length of<br />

conductor for expansion and contraction.<br />

Contractor shall identify the ends of all power and control circuits. He shall also identify all<br />

circuits in pull boxes. Each maker shall bear the number of the corresponding circuit<br />

according to the drawings.<br />

Splices shall not be made in conductors.<br />

Terminations shall be in accordance with the following requirements:


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

i) Train cable in place and cut squarely to required length, Avoid sharp bends.<br />

ii)<br />

iii)<br />

iv)<br />

Remove necessary amount of cable jacket and insulation without damage to the<br />

conductor.<br />

Install terminals or connectors as required, ensuring a firm metal-to-metal contact.<br />

If the connection requires insulation, (i.e. cable connects to insulated conductors),<br />

apply three half-lapped layers of insulating tape over the joint, extending to two cable<br />

diameters over the cable jacket and a similar distance over any other insulation or<br />

connection requiring insulation.<br />

6.03.09 Earthing<br />

Insulated conductors shall be tested after installation with a 1000 volt megger or an eqivalent<br />

testing device and shall indicate approximately infinite resistance between conductors of the<br />

same circuit and between conductors and ground. Equipment and labour required for testing<br />

shall be provided by the Contractor. Any circuit failing to test satisfactorily shall be replaced<br />

or repaired and retested as directly by the Engineer-in-Charge.<br />

a) General<br />

Earthing system furnished and installed and include a complete earthing system for the<br />

elevator. Earthing equipment and materials shall be furnished and installed in accordance with the<br />

reference codes and standards these specification and the contractor’s shop drawings as reviewed and<br />

accepted by the Engineer-in-Charge.<br />

b) Materials<br />

The earthing of all electrical items being supplied by the Bidder shall be in his scope. For earthing the<br />

various equipment, conductor sizes shall be as listed below:<br />

i) MCCs Motor above 90 KW : 50 x 6 Sq.mm G.I. flat<br />

ii)<br />

Motors above 30 KW, upto<br />

75 KW and lighting panel/<br />

control panels/auxiliary panels : 25 x 6 Sq. mm G.I. flat<br />

iii) Motor above 5 KW upto 30 KW : 25 x 3 mm G.I. flat<br />

iii)<br />

Motors upto 5 KW and misc.<br />

Small item like conduits,<br />

Junction boxes etc.<br />

The earthing strip/wire shall be connected to the earthing mat by the Bidder provided in the<br />

chimney area. Clamps and other hardware of iron or steel used with the grounding system<br />

shall be hot-dip galvanized. Bolts, washers and nuts shall be hot-dip galvanized steel.<br />

Installation<br />

Exposed conductors shall be installed inconspicuously in vertical or horizontal positions on<br />

supporting structures. When located on irregular supporting surfaces or equipment, the<br />

conductors shall run parallel or normal to dominant surfaces.<br />

Conductors routed over concrete steel or equipment surfaces shall be kept in close contact<br />

with those surfaces by using fasteners located at intervals not to exceed one (1) metre.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR<br />

VOLUME: IIB<br />

STACK ELEVATOR<br />

SECTION C<br />

REV 0 DATE<br />

SHEET<br />

OF<br />

Damaged earth system conductors or cables shall be repaired or replaced by the Contractor as<br />

directly by the Engineer-in-Charge.<br />

Earth connections except equipment earthing connections shall be made by electric arc<br />

welding. Bolted connections shall be used for earthing equipment.<br />

Earthing bushings within all enclosures, including equipment enclosure, shall be wired together<br />

and connected internally to the enclosure earthing lug at earthing bus with bare conductor.<br />

Electrical equipment shall be earthed. Large equipment will be furnished with a earthing bus.<br />

Most other equipment will be furnished with earthing pads and/or earthing lugs. Earthing<br />

connection surfaces shall be cleaned immediately prior to connection. Contractor shall provide<br />

all earthing material required but not furnished with the equipment. Where the earth conductor<br />

is included with the power conductors in the motor circuit raceway a compression type earth<br />

conductor termination shall be used and connected to the motor frame inside the motor<br />

terminal housing. Where the earth conductor is not included with the power conductors in the<br />

motor circuit raceway, the motor frame shall be earthed to the earth grid.<br />

Suitable earthing facilities acceptable to the Engineer-in-Charge shall be furnished on motors<br />

not so equipped. Earthing facilities shall consist of compression type earth conductor<br />

termination bolted to the motor frame and providing a minimum of joint resistance. Conduit<br />

system is not considered to be a earthing conductor. No earthing conductor shall be smaller in<br />

size than 4 Sq. mm unless it is a part of an acceptance cable assembly.<br />

7.00.0 INSPECTION AND TESTING<br />

7.01.0 The following specific test as applicable shall be carried out by the Contractor as minimum<br />

requirement for the elevators.<br />

7.01.01 All materials used in manufacture of various components shall be of tested quality<br />

and shall conform to relevant standards / specifications.<br />

7.01.02 All welding shall be carried out as per welding procedures qualified as per ASME<br />

Section-IX. Welding procedures shall be forwarded for approval. Only welders<br />

qualified as per ASWME Section-IX shall be employed for welding.<br />

7.01.03 All NOT operators should be qualified as per SNT-TC-IA.<br />

7.01.04 All forgings shall be subjected to ultrasonic test to ensure free from internal defects.<br />

7.01.05 All welds shall be subjected to dye-penetration test and visual examination.<br />

7.01.06 All forged components shall be subjected to DP/MPI after machining.


PEM-6666-0<br />

TITLE SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

TECHNICAL SPEC<strong>IF</strong>ICATION FOR VOLUME II B<br />

STACK ELEVATOR SECTION C SUB SECTION : III<br />

REV 0 DATE<br />

SHEET 1 OF 1<br />

Data Sheet–A<br />

1 Designation : Rack and Pinion type Stack Elevator<br />

2 Type of loading : Passenger-cum-goods<br />

3 Quantity : One (1) No.<br />

4 Carrying Capacity : 400 Kg<br />

5 Operating Speed : 40 m/min (Approx)<br />

6 Dimension of lift and lift well/cut out : As per requirement (Bidder to furnish)<br />

7 No. of landings : 07 Nos. including Ground<br />

8 Total vertical travel : 215 m, to suit the chimney height<br />

9 Electrical power supply system : 415 V, 3 ph, 4 wire, 50 Hz<br />

10 Other accessories : As required


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

1.01.00 ELEVATOR PARTICULARS<br />

i) Load Carrying Capacity in Kg<br />

ii) Type of loading for which the<br />

stack elevator is designed<br />

iii) Type of stack elevator<br />

iv) Rated Load in Kg<br />

v) Speed in metre/minute<br />

vi) Chimney height in metre<br />

vii) Total travel height in metre<br />

viii) No. of floors to be served<br />

ix) Elevations of the floors to be served<br />

x) Method of control<br />

xi) Details of indicators and control<br />

xii) Weight of cab complete without load in Kg<br />

xiii) Weight of hoist cab in Kg<br />

xiv) Efficiency of Elevator<br />

1.02.00 GROUND ENCLOSURE<br />

i) Size of the enclosure<br />

(Length x breadth x height)<br />

ii) Material of construction<br />

iii) Size of landing entrance<br />

iv) Method of door operation<br />

v) Electrical & mechanical interlocking<br />

Of the door provided.<br />

vi) Method of fixing enclosure to chimney<br />

vii) Any other details not covered above<br />

1.03.00 LANDING ENCLOSURES<br />

viii) Size of the enclosure<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

(Length x breadth x height)<br />

ix) Material of construction<br />

x) Size of landing entrance<br />

xi) Method of door operation<br />

xii) Electrical & mechanical interlocking<br />

Of the door provided.<br />

xiii) Method of fixing enclosure<br />

xiv) Any other details not covered above<br />

1.04.00 MAST<br />

i) Material of mast<br />

ii) Section of mast<br />

iii) Size of each piece of mast<br />

iv) Method of fixing of mast<br />

v) Type of mast<br />

1.05.0 CAB<br />

i) Internal size<br />

(Length x breadth x height)<br />

ii) Material of construction<br />

iii) Type of floor<br />

iv) Size of the cab door<br />

v) Method of operation of cab door<br />

vi) Electrical & mechanical interlocking provided<br />

vii) Escape hatch, electrically interlocked<br />

viii) Guide roller and safety hooks provided<br />

ix) Arrangement of light/fan inside the cab.<br />

x) Indicators & controls inside the cab.<br />

1.06.00 ELEVATOR DRIVE UNIT<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

i) Location of drive unit<br />

ii)<br />

Name of components of drive unit<br />

1.07.00 DETAILS OF ELECTRIC MOTOR<br />

i) Manufacturer<br />

ii) Equipment driven by motor<br />

iii) Type<br />

iv) Frame size, type & designation<br />

v) Maximum load considered for<br />

Sizing of motor<br />

vi) Margin considered for sizing motor<br />

vii) Rated power in KW<br />

viii) Service factor<br />

ix) Speed in rpm<br />

x) Rated voltage in V<br />

xi) Current at rated voltage<br />

- Full load<br />

- Locked rotor<br />

xii) Insulation class<br />

xiii) Type of bearing and type of lubricant<br />

xiv) Space heater rating<br />

xv) Duration considered for specified<br />

Ambient temperature<br />

xvi) Applicable standard to which motor conforms<br />

xvii) Degree of protection<br />

xviii) Efficiency at rated output<br />

xix) Power factor<br />

xx) Type of mounting<br />

1.08.00 DETAILS OF REDUCTION GEAR<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

i) Make<br />

ii) Material of the gears and hardness in BHN<br />

iii) Type of gear<br />

iv) Gear ratio<br />

v) Gear power transmitted<br />

vi) Input and output speed<br />

1.09.0 DETAILS OF DRIVE AND PINION<br />

i) Material<br />

ii) Hardness<br />

iii) Fixing arrangement<br />

1.10.0 DETAILS OF RACK<br />

i) Material<br />

ii) Hardness<br />

iii) Fixing arrangement<br />

1.11.00 SAFETY DEVICE<br />

i) Make<br />

ii) Type of safety device<br />

iii) Speed at which the safety device<br />

Come into action<br />

iv) Method operation<br />

v) Other details<br />

vi) Remote control for testing<br />

The safety device<br />

1.12.00 BRAKES<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

i) Manufacturer<br />

ii) Types of brakes provided<br />

iii) Method of operation<br />

iv) Interlocking if any<br />

v) Electromagnetic brake and external<br />

Manual brake release<br />

vi) Degree of protection<br />

1.13.00 CENTR<strong>IF</strong>UGAL BRAKE<br />

i) Make<br />

ii) Details<br />

iii) Remote control for testing<br />

The safety device provided.<br />

iv) Any other details of drive unit<br />

Not covered above.<br />

1.14.00 BUFFERS<br />

i) No. and location of the buffers provided<br />

ii) Type of buffers<br />

iii) If the buffers are spring type<br />

Furnish the following:<br />

- Diameter of the spring in mm<br />

- Max. Compression under extreme cond.<br />

- No. of spring coil<br />

- Sectional dimension<br />

- Material of spring<br />

- Compression /unit load<br />

1.15.00 POWER CABLES Fixed Trailing<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

i) Manufacturer<br />

ii) Type and material<br />

iii) Rated voltage<br />

iv) Rated current<br />

v) Type of insulation<br />

vi) No. of strands<br />

vii) No. of cores<br />

viii) Short circuit current rating<br />

ix) Resistance per 1000 metres<br />

x) Applicable standards<br />

1.16.00 CONTROL CABLES<br />

xi) Manufacturer<br />

xii) Type and material<br />

xiii) Rated voltage<br />

xiv) Rated current<br />

xv) Type of insulation<br />

xvi) No. of strands<br />

xvii) No. of cores<br />

xviii) Short circuit current rating<br />

xix) Resistance per 1000 metres<br />

xx) Applicable standards<br />

1.17.00 CONDUITS/ACCESSORIES AND FITTINGS<br />

i) Material<br />

ii) Manufacturer<br />

iii) Applicable standard<br />

1.18.00 CONTACTORS<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

i) Make<br />

ii) Type<br />

iii) Applicable standards<br />

iv) No. of poles<br />

v) Rated voltage<br />

vi) Rated frequency<br />

vii) Rated current<br />

viii) Closing coil<br />

- Rated voltage<br />

- Current consumption<br />

- Power consumption in KW<br />

- Insulation class for electromagnet<br />

ix)<br />

Rated duty<br />

ix)<br />

- Rated insulation category<br />

- No. of operations per hour<br />

- Rated breaking capacity<br />

- Rated making capacity<br />

- Short time rating in sec<br />

Limits of operation<br />

- Supply voltage variations (%)<br />

- Supply frequency variations (%)<br />

- Drop out voltage (%)<br />

- Min. pick up voltage (%)<br />

x) Thermal overload relay setting range available<br />

xi)<br />

Auxiliary contacts<br />

- Numbers<br />

- Current rating (Make and break)<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

xi) Rated utilization category as per IS 2459<br />

xii)<br />

Max. recommended back up HRC fuse size<br />

1.19.00 FUSES<br />

i) Make<br />

ii) Type<br />

iii) Continuous current<br />

iv) Rated voltage<br />

v) Rated frequency<br />

vi) Rupturing capacity<br />

vii) Mounting details<br />

viii) Fixing and removing arrangement<br />

ix) Visual indication for fuses<br />

x) Applicable standards<br />

1.20.00 INDICATING LAMPS<br />

i) Make<br />

ii) Type<br />

iii) Rated voltage<br />

iv) Rated power consumption in Watt<br />

v) Permissible voltage variation<br />

vi) Series resistance provided<br />

1.21.00 PUSH BUTTONS<br />

i) Make<br />

ii) Type<br />

iii) Rating<br />

- Voltage<br />

- Continuous current<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

iv) No. of aux. Contacts<br />

- Normally open<br />

- Normally closed<br />

v) Contact rating<br />

vi) Colours<br />

vii) Mounting arrangement<br />

1.22.00 OVER TRAVEL LIMIT SWITCH<br />

i) Make<br />

ii) Type<br />

iii) Material of contacts<br />

iv) Contact rating<br />

v) Numbers furnished<br />

1.23.00 CONTROL TRANSFORMER<br />

i) Make<br />

ii) Type<br />

iii) Output rating (VA)<br />

iv) Ratio<br />

v) Class of insulation<br />

vi) Max. temp rise of winding over<br />

Specified ambient temperature.<br />

vii) One minute power frequency test voltage<br />

viii) Applicable standards<br />

1.24.00 CIRCUIT BREAKER AND ISOLATOR<br />

i) Make<br />

ii) Type<br />

iii) Current rating in amps<br />

iv) Interruption duty<br />

v) Max. breaking capacity<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

vi)<br />

vii)<br />

Operating voltage of tripping and closing coils<br />

Max. permissible variation of operating voltage<br />

1.25.00 RACEWAY<br />

i) Raceway as per specification<br />

ii) Material of<br />

- Indoor fittings<br />

- Outdoor fittings<br />

- Raceway support<br />

- Junction boxes<br />

1.26.0 EARTHING<br />

i) Earthing conductor<br />

- Size<br />

- Material<br />

ii)<br />

iii)<br />

Material of earthing cable<br />

Clamps. Bolts, washers, nuts and another<br />

Hardware of iron steel are galvanized.<br />

1.27.00 MOTOR STARTER<br />

i) Make & Size<br />

ii) Rating]<br />

iii) Mechanically latched type<br />

iv) Single phase prevention feature provided<br />

v) Degree of protection<br />

1.28.00 DETAILS OF CONTROL PANELS<br />

i) No. of panels<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


Title<br />

Spec. No.: PE-TS-360-620-C001<br />

STACK ELEVATOR <strong>Volume</strong> II B SUB SECTION III<br />

DATA SHEET ‘B’ Sheet of<br />

ii) Type of enclosures (Degree of protection)<br />

iii) Thickness of sheet metal<br />

iv) Painting<br />

- Colour<br />

- Finish<br />

v) Cable entry<br />

vi) Manufacturer<br />

Name of Bidder / Vendor<br />

Project<br />

Revision No. 0 1 2 3 4 5<br />

Signature of Bidder / Vendor /<br />

Authorised Representative<br />

Date


TITLE: 1X250 MW EXTENSION UNIT-8 AT<br />

DURGAPUR PROJECTS POWER STATION<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - D SUB SECTION :I<br />

REV.NO. 0<br />

SHEET<br />

OF<br />

THE DURGAPUR PROJECTS<br />

LIMITED<br />

DURGAPUR PROJECTS POWER STATION<br />

1 x 250 MW EXTENSION UNIT- 8<br />

VOLUME – II B<br />

SECTION – D<br />

SUB SECTION I<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

CIVIL , STRUCTURAL & ARCHITECTURAL WORKS<br />

Bharat Heavy Electricals Limited<br />

Project Engineering Management<br />

PPEI Building, Power Sector,<br />

Plot No. 25, Sector 16A,<br />

Noida (U.P.)-201301


DCPL-K4A02<br />

THE DURGAPUR PROJECTS LIMITED<br />

NEW ADMINISTRATIVE BUILDING<br />

DURGAPUR – 713 201<br />

WEST BENGAL<br />

INDIA<br />

MAIN PLANT PACKAGE<br />

SPEC<strong>IF</strong>ICATION NO.: MP-1<br />

O V E R A L L C O N T E N T S<br />

VOLUME-I : CONDITIONS OF CONTRACT<br />

VOLUME-II : TECHNICAL SPEC<strong>IF</strong>ICATIONS<br />

VOLUME-III : BID PROPOSAL SHEETS (TECHNICAL PART)<br />

VOLUME-IV : BID PROPOSAL SHEETS (PRICE PART)<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

VOLUME : II<br />

TECHNICAL SPEC<strong>IF</strong>ICATIONS<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

CONTENTS<br />

VOLUME : II<br />

TECHNICAL SPEC<strong>IF</strong>ICATIONS<br />

VOLUME II-A : GENERAL AND MECHANICAL<br />

VOLUME II-B/1 & : SPEC<strong>IF</strong>ICATIONS FOR ELECTRICAL EQUIPMENT<br />

VOLUME II-B/2<br />

& ACCESSORIES (IN TWO VOLUMES)<br />

VOLUME II-C : SPEC<strong>IF</strong>ICATIONS FOR CONTROLS & INSTRUMENTATION<br />

VOLUME II-D/1 & : SPEC<strong>IF</strong>ICATIONS FOR CIVIL, STRUCTURAL<br />

VOLUME-II-D/2<br />

AND ARCHITECTURAL WORKS (IN TWO VOLUMES)<br />

VOLUME II-E : TENDER DRAWINGS<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

TECHNICAL SPEC<strong>IF</strong>ICATIONS<br />

FOR<br />

CIVIL, STRUCTURAL AND ARCHITECTURAL WORKS<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

CONTENTS<br />

VOLUME : II-D/2<br />

SECTIONS<br />

SPEC<strong>IF</strong>ICATIONS FOR CIVIL, STRUCTURAL AND<br />

ARCHITECTURAL WORKS<br />

DESCRIPTION<br />

SECTION-I : AREA GRADING<br />

SECTION-II : EARTHWORK IN EXCAVATION AND BACKFILLING<br />

SECTION-III : CEMENT CONCRETE (PLAIN & REINFORCED)<br />

SECTION-IV : FABRICATION OF STRUCTURAL STEELWORK<br />

SECTION-V : ERECTION OF STRUCTURAL STEELWORK<br />

SECTION-VI : R. C. MULT<strong>IF</strong>LUE STACK ( REFER ANNEXURE A)<br />

SECTION-VII : ROADS AND DRAINS<br />

SECTION-VIII : MASONRY AND ALLIED WORKS<br />

SECTION-IX : FINISH TO MASONRY AND CONCRETE<br />

SECTION-X : FLOOR FINISH AND ALLIED WORKS<br />

SECTION-XI : FALSE FLOORING<br />

SECTION-XII : CARPENTERY AND JOINERY<br />

SECTION-XIII : SUSPENDED CEILING<br />

SECTION-XIV : METAL DOORS, WINDOWS, VENTILATORS, LOUVRES<br />

ETC.<br />

SECTION-XV : GLASS AND GLAZING<br />

SECTION-XVI : ROLLING STEEL SHUTTERS AND GRILLS<br />

SECTION-XVII : MISCELLANEOUS METAL<br />

SECTION-XVIII : PAINTING, WHITEWASHING, POLISHING ETC.<br />

SECTION-XIX : ROOF WATERPROOFING,INSULATION AND ALLIED WORKS<br />

SECTION-XX : SHEETWORK IN ROOF AND SIDING<br />

SECTION-XXI : WATER SUPPLY<br />

SECTION-XXII : DRAINAGE AND SANITATION<br />

SECTION-XXIII : ANTI-TERMITE TREATMENT<br />

SECTION-XXIV : SANDWICH METAL CLADDING (REFER ANNEXURE B)<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-I<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

AREA GRADING<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D/2/S-I : 1<br />

2.0.0 GENERAL V.II-D/2/S-I : 1<br />

3.0.0 EXECUTION V.II-D/2/S-I : 4<br />

4.0.0 TESTING AND ACCEPTANCE V.II-D/2/S-I : 18<br />

CRITERIA<br />

5.0.0 INFORMATION TO BE SUBMITTED V.II-D/2/S-I : 19<br />

(PCA.774.S034sca)


DCPL-K4A02<br />

VOLUME: II-D/2<br />

SECTION-I<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

AREA GRADING<br />

1.0.0 SCOPE<br />

This specification shall govern all clearing, grubbing, excavating, area filling,<br />

grading and compacting soils for areas designated on the drawings. The<br />

work shall include clearing and grubbing, stripping and storage of top soil,<br />

excavation, blasting (if required), hauling, dumping and spreading of soil,<br />

undercutting to remove unstable soil areas, compacting existing soil<br />

surfaces and bottom of excavated areas to receive fills, compacting<br />

excavated areas for subgrade, placing and compacting soils in fills,<br />

dealing with surface water, pumping to keep excavated areas and areas<br />

to be filled dry, final grading of designated areas, disposing of unsuitable<br />

and excess excavated materials and incidentals thereof.<br />

2.0.0 GENERAL<br />

2.1.0 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless specified otherwise,<br />

shall include but not be limited to the following :<br />

a) Furnish all labour, supervision, services, earth-moving<br />

machineries and equipment, compaction plant and equipment,<br />

tools and plants, survey instruments, transportation etc. required<br />

for the work.<br />

b) Prepare and submit working drawings showing the approaches,<br />

slopes, berms, sumps for dewatering, space for temporary<br />

stacking of spoils, disposal area, borrow pits, fencing etc. and all<br />

other details as may be required by the Engineer.<br />

c) To carry out and submit to the Engineer, results of soil<br />

compaction tests whenever required by the Engineer to assess the<br />

degree of compaction.<br />

d) If blasting is resorted to, necessary licenses to be procured from the<br />

proper authorities.<br />

2.2.0 Work to be provided for by others<br />

No work under this specification will be provided by any agency other than<br />

the Contractor unless specifically mentioned elsewhere in the Contract.<br />

2.3.0 Codes and Standards<br />

(PCA.774.S034sca) V.II-D2/S-I : 1


DCPL-K4A02<br />

All work under this specification, unless specified otherwise, shall<br />

conform to the latest revision and/or replacements of the following or any<br />

other relevant Indian Standard Specifications and Codes of Practice. In<br />

case any particular aspect of work is not covered specifically by Indian<br />

Standard Specification any other standard practice as may be specified by<br />

the Engineer shall be followed :<br />

IS : 1200 : Method of Measurement of Building and Civil<br />

Engineering work, Part-I Earthwork<br />

IS : 2720 : Determination of Moisture Content<br />

(Part-II)<br />

IS : 2720 : Grain Size Analysis<br />

(Part-IV)<br />

IS : 2720 : Determination of Moisture Content/Dry<br />

(Part-VII)<br />

IS : 2720 : Determination of Moisture Content/Dry<br />

(Part-VIII)<br />

IS : 2720 : Determination of Density Index (Relative<br />

(Part-XIV)<br />

IS : 2720 : Determination of Dry Density, in place,<br />

(Part-XXIV)<br />

IS : 2720 : Determination of Dry Density of Soils,<br />

(Part-XXVIII)<br />

IS : 3764 : Safety Code for Excavation Work<br />

IS : 4081 : Blasting and related drilling operations<br />

IRC : SP-11 : Hand book of quality control for construction of roads<br />

and runways<br />

IRC : 36 : Construction of Earth Embankments for Road Work<br />

2.4.0 Conformity with Designs<br />

The Contractor shall carry out the work as per the drawings issued to him<br />

and/or Contractor's drawings which are approved by the Engineer and/or<br />

the Engineer's instructions.<br />

2.5.0 Materials to be used<br />

(PCA.774.S034sca) V.II-D2/S-I : 2


DCPL-K4A02<br />

2.5.1 General<br />

All materials required for the work shall be of best commercial variety and<br />

as approved by the Engineer.<br />

2.5.2 Borrow Material<br />

Borrow material required for area filling shall be excavated from approved<br />

locations and levels, and shall consist of selected material, approved by<br />

the Engineer, free from roots, vegetations, decayed organic matter, harmful<br />

salts and chemicals, free from lumps and clods. Clean graded sand,<br />

free from harmful and deleterious materials from approved quarries, shall be<br />

used as fill material at places approved during detail engineering stage.<br />

Necessary arrangement shall be done by the Contractor at his own cost for<br />

locating and using the borrow areas as the source of supply of filling<br />

material.<br />

The depth of borrow pits should be so regulated that the borrow pits do<br />

not cut an imaginary line having a slope of 1 vertical in 4 horizontal projected<br />

from the edge of final section of the adjacent embankment of stack of<br />

excavated soil.<br />

2.6.0 Quality Control<br />

The Contractor shall establish and maintain quality control for the various<br />

aspects of the work, method, materials and equipment used. The quality<br />

control operation shall include but not be limited to the following items of<br />

work :<br />

a) Lines, Levels and Grades : i) Periodic Surveys<br />

ii)<br />

Establishment of markers,<br />

Boards etc.<br />

iii) Checking levels and slopes<br />

of the graded surface.<br />

b) Area filling : i) Checking the quality of fill<br />

material<br />

ii) Checking moisture content<br />

of the fill.<br />

iii) Checking the degree of<br />

compaction.<br />

2.6.1 Any work which fails to conform to the specifications will be subject to the<br />

issue of a Non-conformance Report in line with the Quality Control<br />

Procedure to be implemented at site. Corrective or remedial action, design<br />

modifications or product rejection will be reviewed in accordance with the site<br />

(PCA.774.S034sca) V.II-D2/S-I : 3


DCPL-K4A02<br />

Quality Plan.<br />

2.7.0 Information regarding Site Conditions<br />

Boring and sub-surface data regarding the nature of soil, rock, sub-soil<br />

water etc. shown on drawings or otherwise furnished to the Contractor<br />

shall be taken as a guidance only and variation therefrom shall not affect<br />

the terms of the Contract. The Contractor must satisfy himself regarding<br />

the character and volume of all work under this contract and expected<br />

surface, sub-surface and/or sub-soil water to be encountered. He must<br />

also satisfy himself about the general conditions of site and ascertain the<br />

existing and future construction likely to come up during the execution of<br />

the Contract so that he may evolve a realistic programme of execution.<br />

3.0.0 EXECUTION<br />

3.1.0 General<br />

The work shall be undertaken in accordance with the lines,<br />

levels,grades and details shown on the drawings, specification and the<br />

approved method of work.<br />

The works shall be carried out in a workman like manner without<br />

endengering the safety of nearby structures, roads, railway tracks,<br />

cable, pipelines, etc. and without causing hindrance to construction<br />

activities.<br />

Suitable approaches, fencing, area lighting and temporary works required<br />

for the works shall be provided by the contractor. Sturdy and elegent<br />

fencing is to be provided around the top edge of the exavation as well as<br />

the bottom of the fill at the surplus disposal area where damping from a<br />

high bench is in progress, if directed by the Engineer. Adequate area<br />

lighting shall be provided by the contractor, if night work is undertaken.<br />

The Contractor shall submit a proposal covering the proposed<br />

excavation and placement of fill material for approval of the Engineer.<br />

The proposal shall include but not be limited to the following.<br />

a) Mobilisation and demobilisation of plant<br />

b) Proposed plant and equipment, labour resources & supervision.<br />

c) Details of proposed method of clearing and grubbing for each area of<br />

cut and fill.<br />

d) Drawings showing the areas for placement of material.<br />

e) Management of excavation and filling works i.e., control of setting out,<br />

testing procedures, handling, temporary stockpiles, etc.<br />

f) Temporary works proposals<br />

(PCA.774.S034sca) V.II-D2/S-I : 4


DCPL-K4A02<br />

g) Excavation, filling and compaction by mechanical plant<br />

h) Dealing with surface water<br />

i) Dewatering<br />

3.2.0 Setting Out<br />

3.3.0 Initial Levels<br />

j) Disposal of materials<br />

k) Safety precautions, fencing and lighting<br />

l) Calculations as appropriate to support work proposal<br />

The Contractor will prepare and submit to the Engineer, detailed drawings<br />

of the excavation and filling work necessary, as proposed to be executed<br />

by him, showing the dimensions as per drawings and specification, adding<br />

his proposals for slopes, approaches, dewatering sumps, berms etc. On<br />

receiving the approval from the Engineer with modifications and corrections if<br />

necessary, the Contractor will set out the work from the control points<br />

furnished by the Engineer and fix permanent points and markers for future<br />

checking. These permanent points and markers will be checked by the<br />

Engineer and certified by him after which the Contractor will proceed with<br />

the work. Engineer shall be provided with necessary men, material and<br />

instruments for such checking. It should be noted that this checking by<br />

the Engineer prior to start of the work will in no way absolve the Contractor of<br />

his responsibility of carrying out the work to true lines, levels and grades as<br />

per drawing and subsequent corrections, if any. In case any errors are<br />

noticed in the Contractor's work at any stage, the same shall be remedied by<br />

the Contractor.<br />

Initial levels either in a definite grid pattern or as directed by the Engineer<br />

will be taken by the Contractor jointly with the Engineer over the original<br />

ground prior to starting actual excavation work and after setting out.<br />

These initial levels will be used for preparing cross-sections for volume<br />

measurement or for cross-checking the depths obtained from tape<br />

measurements. These initial levels and cross-sections shall be jointly<br />

signed by the Contractor and the Engineer before commencement of work.<br />

(PCA.774.S034sca) V.II-D2/S-I : 5


DCPL-K4A02<br />

3.4.0 Clearing and Grubbing etc.<br />

3.5.0 Classification<br />

The area to be excavated or filled shall be cleared out of fences, trees,<br />

logs, stumps, bush, vegetation, rubbish, slush, etc. and levelled up. Trees<br />

upto 300 mm girth shall be uprooted. Trees above 300mm girth which<br />

are required to be cut, shall be got identified by the Engineer and then<br />

marked.<br />

Felling of trees shall include taking out roots upto 600 mm below ground<br />

level. After the tree is cut and roots taken out, the pot- holes formed shall be<br />

filled with good earth in 250 mm layers and compacted to acceptable<br />

degree unless directed by the Engineer otherwise. The trees shall be cut in<br />

suitable pieces as instructed by the Engineer and then shall be transported<br />

to the Owner's store or any other space as directed by the Engineer.<br />

Before earthwork is started, all the spoils and unserviceable materials<br />

and rubbish shall be burnt or removed from the site to approved disposal<br />

areas as may be specified. Ash shall be spread or removed as directed by<br />

the Engineer. Useful materials, saleable timber, firewood, etc. shall be the<br />

property of the Owner and shall be stacked properly at the worksite in a<br />

manner as directed by the Engineer.<br />

Materials involved in earthwork shall be classified under the following<br />

categories. No distinction will be made whether the material is dry or wet.<br />

The Engineer's decision in regard to such classification shall be final and<br />

binding on the Contractor :<br />

a) Ordinary and hard soil<br />

This shall include clay, silt, sand, moorum, shingle, kankar, gravel,<br />

loam, peat, ash and other similar materials in soft, hard or dense<br />

state which can generally be excavated with ordinary spade, pick<br />

axe, shovel etc. and does not require the use of wedges,<br />

pneumatic breaking equipment and/or blasting for removal. It<br />

shall also include loose rock boulders present in the soil, with<br />

dimensions not exceeding 500 mm in any direction. Breaking of<br />

consolidated brick ballast and mud concrete shall be considered<br />

equivalent to excavation work under this type of soil.<br />

b) Soft and Decomposed Rock<br />

This shall include rocks like chalk, slate, mica schist, laterite and<br />

other similar materials which in the opinion of the Engineer is<br />

rock, but does not require blasting for removal and could be<br />

removed with picks, hammers, crow bars, wedges, pneumatic<br />

breaking equipment etc. It shall also include boulders with<br />

dimensions greater than 500 mm but not exceeding 1000 mm in any<br />

direction. The mere fact that the Contractor resorts to blasting for<br />

his own convenience shall not mean that the rock will be classified<br />

as hard rock.<br />

(PCA.774.S034sca) V.II-D2/S-I : 6


DCPL-K4A02<br />

c) Hard Rock<br />

3.6.0 Earthwork in Excavation<br />

3.6.1 General<br />

This shall include rocks occuring in large masses which cannot<br />

be removed except by blasting. Harder varieties of rock such as<br />

trap, with or without veins and secondary mineral which in the<br />

opinion of the Engineer require blasting for removal shall also be<br />

considered as hard rock. It shall also include boulders bigger than<br />

1000 mm in any direction. Construction in concrete, both reinforced<br />

and unreinforced, which is required to be dismantled during<br />

earthwork.<br />

Before commencement of excavation the existing ground surface shall be<br />

cleared in accordance with Clause no. 3.4.0.<br />

All excavation shall be done to the minimum dimensions as required for<br />

safety and working facility. Prior approval of the Engineer shall be obtained<br />

by the Contractor, in each individual case, for the method he proposes to<br />

adopt for the excavation including dimension, side slopes, dewatering,<br />

disposal, etc.<br />

This approval, however, shall not in any way make the Engineer<br />

responsible for any consequent loss or damage. The excavation must be<br />

carried out in the most expeditious and efficient manner.<br />

Prior to starting the excavation, the ground level at the location shall be<br />

checked jointly with the Engineer.<br />

The rough excavation may be carried upto a maximum depth of 150 mm<br />

above the final level. The balance shall be excavated with special care.<br />

If directed by the Engineer, soft and undesirable spots shall be removed<br />

even below the final level.<br />

3.6.2 Excavation in Ordinary Soil, Hard Soil<br />

and Soft and Decomposed Rock<br />

The excavation in ordinary soil, hard soil and soft and decomposed rock<br />

shall be carried out as per the approved proposal, modified and corrected<br />

where necessary by the Engineer. The work shall be carried out in a<br />

workmanlike manner without endangering the safety of nearby structures or<br />

roads, railway tracks, cables, pipelines etc. if any, and without causing<br />

hindrance to other activities in the area. As the excavation reaches the<br />

required dimensions, lines, levels and grades, the work will be checked by<br />

the Engineer thoroughly and the balance work will be carried out carefully<br />

to avoid any over-excavation.<br />

(PCA.774.S034sca) V.II-D2/S-I : 7


DCPL-K4A02<br />

On completion, the work will be finally checked and approved by the<br />

Engineer. In case where excavation in soil, soft and decomposed rock<br />

and/or hard rock are involved, the soil or soft and decomposed rock layers,<br />

shall be removed by turn and levels of the underlying rock surfaces observed<br />

to enable measurements. Further work shall be resumed after getting<br />

clearance from the Engineer.<br />

3.6.3 Excavation in Hard Rock<br />

3.6.4 Blasting<br />

3.6.4.1 General<br />

Overburden, if any, consisting of top soil, ordinary and hard soil, soft<br />

and decomposed rock as per classification of soil, which do not require<br />

blasting shall be completely stripped off and the levels of the hard rock<br />

surface shall be taken to enable measurement. Further work in hard rock<br />

shall be resumed after clearance from the Engineer.<br />

Personnel deployed for rock excavations shall be protected from all<br />

hazards such as loose rock/boulder rolling down and from general slips of<br />

excavated surfaces. Where the excavated surface is such that it is not<br />

stable against sliding, necessary supports, props, bracings or bulkheads<br />

shall be provided and maintained during the period of construction. Where<br />

danger exists of loose rock/boulder falling from the excavated surfaces<br />

deeper than 2 metres, steel mesh anchored to the lower edge of<br />

excavation and extending over and above the rock face, adequate to<br />

retain the dislodged material shall be provided and maintained.<br />

In case where blasting, though otherwise required, is prohibited for any<br />

reasons, the excavation shall be carried out by chiselling, wedging or<br />

any other approved method. All loose or loosened rock in the sides shall be<br />

removed by barring, wedging, etc.<br />

Excavation shall be continued in hard rock to such widths, lengths,<br />

depths and profiles as are shown on the drawings or such other lines and<br />

grades as may be specified by the Engineer. As far as possible all blasting<br />

shall be completed prior to commencement of construction. At all stages of<br />

excavation, precautions shall be taken to preserve the rock below and<br />

beyond the lines for the excavation, in the soundest possible condition.<br />

The quantity and strength of explosive used, shall be such as will neither<br />

damage nor crack the rock outside the limits of excavation. All<br />

precautions, as directed by Engineer, shall be taken during the blasting<br />

operations and care shall be taken that no damage is caused to adjoining<br />

buildings or structure as a result of blasting operations. In case of damage<br />

to permanent or temporary structures, Contractor shall repair the same<br />

to the satisfaction of Engineer. As excavation approaches its final lines and<br />

levels, the depth of the charge holes and amount of explosives used shall be<br />

progressively and suitably reduced.<br />

Unless otherwise stated herein, I.S. Specification IS:4081 "Safety Code for<br />

Blasting & Related Drilling Operation" shall be followed.<br />

(PCA.774.S034sca) V.II-D2/S-I : 8


DCPL-K4A02<br />

Specific permission of Engineer will have to be taken by Contractor<br />

for blasting rock and he shall also obtain a valid Blasting licence from the<br />

authorities concerned.<br />

Contractor shall obtain necessary licence for storage of explosives,<br />

fuses and detonators issued to him from owner's stores or from supplier<br />

arranged by him, from the authorities dealing with explosives.<br />

The fees, if any, required for obtaining such licence, shall be borne by<br />

Contractor. Contractor shall have to make necessary storage facilities for<br />

the explosives etc. as per rules of local, State and Central Govt.<br />

authorities and statutory bodies/regulations.<br />

In no case shall blasting be allowed closer than 30 metres to any structure<br />

or to locations where concrete has just been placed. In the latter case the<br />

concrete must be at least 7 days old.<br />

Contractor shall employ a competent experienced supervisor and licensed<br />

blaster in-charge of each set of operation, who shall be held personally<br />

responsible to ensure that all safety regulations are carried out.<br />

Before any blasting is carried out, Contractor shall intimate Engineer and<br />

obtain his approval in writing for resorting to such operations. He shall<br />

intimate the hours of firing charges, the nature of explosive to be used<br />

and the precautions taken for ensuring safety.<br />

The blasting of rock near any existing buildings, equipments or any other<br />

property shall be done under cover and Contractor has to make all such<br />

necessary muffling arrangements. Covering may preferably be done by<br />

M.S. plates with adequate dead weight over them. Blasting shall be done<br />

with small charges and where directed by Engineer, a trench shall have to<br />

be cut by chiselling prior to the blasting operation seperating the area under<br />

blasting from the existing structures.<br />

When excavation has almost reached the desired level, hand trimming<br />

shall have to be done for dressing the surface to the desired level. Any<br />

rock excavation beyond an overbreak limit of 75 mm shall be filled up as<br />

instructed by Engineer, with concrete of strength not less than M 10.<br />

Stepping in rock excavation shall be done by hand trimming.<br />

Contractor shall be responsible for any accident to workmen, public or<br />

Owner's property due to blasting operations. Contractor shall also be<br />

responsible for strict observance of rules, laid by Inspector of Explosives,<br />

or any other authority duly constituted under the State and/or Union<br />

Government.<br />

Storage, handling and use of explosives shall be governed by the current<br />

explosive rules laid down by the Central and the State Governments. The<br />

Contractor shall ensure that these rules are strictly adhered to. The<br />

following instruction, wherever found in variance with the above rules, shall<br />

(PCA.774.S034sca) V.II-D2/S-I : 9


DCPL-K4A02<br />

3.6.4.2 Material<br />

be considered as superceeded by the above rules.<br />

No child under the age of 16 and no person who is in a State of<br />

intoxication shall be allowed to enter the premises where explosives<br />

are stored nor they shall be allowed to handle the explosives.<br />

All materials such as explosives, detonators, fuses tamping materials<br />

etc. are proposed to be used in the blasting operations shall have the prior<br />

approval of the Engineer.<br />

Only explosives of approved make and strength are to be used. The fuses<br />

known as instantaneous fuse must not be used.<br />

The issue of fuse with only one protective coat is prohibited. The fuse shall<br />

be sufficiently water resistant as to be unaffected when immersed in water<br />

for thirty minutes. The rate of burning of the fuse shall be uniform and not<br />

less than 4 seconds or inch of length with 10% tolerance on either side.<br />

Before use, the fuse shall be inspected and moist damaged or broken<br />

ones discarded. The rate of burning of fuses or when they have been in<br />

stock for long shall be tested before use.<br />

The detonators used shall be capable of giving an effective blasting of<br />

the explosives, moist; and damaged detonators shall be discarded.<br />

3.6.4.3 Storage of Explosive<br />

Storage of explosives shall be governed by the current Explosive Rules.<br />

Explosives shall be stored in a clean, dry, well ventilated magazine to be<br />

specially built for the purpose. Under no circumstances should a<br />

magazine be erected within 400 m of the actual work site or any source of<br />

fire. A space surrounding the magazine shall be fenced in. The ground<br />

inside the fence shall be kept clear and free from trees, bushes etc. The<br />

admission to this fenced space shall be by one gate only and no person<br />

shall be allowed inside this fence without permission of the Officer-incharge.<br />

The clear space between the fence and the magazine shall not be<br />

less than 90m. The megazine shall be perfectly well drained.<br />

Two lightning conductors shall be provided to the magazine, one at each<br />

end. The lightning conductors shall be tested once in every year.<br />

Fuses and detonators shall be stored in separate magazines. However,<br />

detonators can be kept in an annexe adjoining the magazine provided<br />

that their number does not exceed 25,000 and that the annexe is so<br />

constructed that not less than 60 cm masonry and 100 cm of air space shall<br />

intervene between any detonators in such annexe and the interior of the<br />

main magazine. Cases containing explosives are not to be opened in<br />

(PCA.774.S034sca) V.II-D2/S-I : 10


DCPL-K4A02<br />

a magazine.<br />

Explosive in open cases are not to be received into a magazine.<br />

Explosives which appear to be in a damaged or dangerous condition are<br />

not to be kept in any magazine, but must be removed without delay to a<br />

safe distance and destroyed.<br />

Persons entering the magazine, must put on the magazine shoes which<br />

shall be provided at the magazine for this purpose and should be careful :<br />

Not to put their feet on the clean floor unless they have the magazine<br />

shoes on.<br />

Not to allow the magazine shoes to touch the ground outside the clean<br />

floor.<br />

Not to allow any dirty or grit to fall on the clean floor.<br />

Persons with bare feet, shall before entering the magazine dip their feet<br />

in water and then step direct from the tub over the barrier (if there be one)<br />

on to the clean floor.<br />

A brush broom shall be kept in the lobby of the magazine for cleaning<br />

out the magazine, on each occasion if it is opened for the receipt, delivery<br />

or inspection of explosives.<br />

No matches or inflammable materials shall be allowed inside the<br />

magazine. Illumination shall be obtained from an electric storage battery<br />

lantern. No smoking shall be allowed within 100 m of a magazine.<br />

No person having article of steel or iron on him shall be allowed to enter the<br />

magazine.<br />

Oily cotton, rag waste and articles liable to spontaneous ignition shall not be<br />

allowed inside the magazine.<br />

Workmen shall be examined before they enter the magazine to see that<br />

they have none of the prohibited articles on their person.<br />

The mallets, levers, wedges etc. for opening barrels or cases are to be of<br />

wood. Inside a magazine the cases of explosives are to be carried by hand<br />

and shall not be rolled or dragged. Explosives which have been issued<br />

and returned to the magazine are to be issued first; otherwise those which<br />

have been longest in store are to be issued first.<br />

Cases of explosives must be kept clear of the walls and floors for free<br />

circulation of air on all sides, special care is to be taken to keep the floor<br />

free from grains of powder or portions of explosive matter fallen on the<br />

floors due to leakage of cases etc.<br />

The magazine shall not be opened during any duststorm or<br />

thunderstorm nor any person shall be allowed in the vicinity of the<br />

magazine.<br />

(PCA.774.S034sca) V.II-D2/S-I : 11


DCPL-K4A02<br />

All magazines shall be officially inspected at definite intervals and a record<br />

kept of the results of such inspections.<br />

3.6.4.4 Carriage of Explosives<br />

Detonators and explosives shall be transported separately to the blast site.<br />

Explosives shall be kept dry and away from the direct rays of the sun, naked<br />

lights, steam pipes or heated metal and other sources of heat. Before<br />

explosives are removed, each cage or package is to be carefully examined<br />

to ascertain that it is properly closed and shows no sign of leakage.<br />

No person except the driver shall be allowed to travel on a vehicle<br />

conveying explosives. No carriage or vessel shall be used for transporting<br />

explosives unless all iron or steel therein with which a package containing<br />

any explosive is likely to come in contact is effectually covered with lead,<br />

leather, wood, cloth or other suitable material. No lights shall be carried<br />

on the vehicle carrying explosives.<br />

No operation connected with the loading, unloading and handling of<br />

explosives shall be conducted after sunset.<br />

3.6.4.5 Use of Explosives<br />

The Contractor shall appoint an agent who shall personally superintend<br />

the firing and all operations connected therewith.<br />

The contractor shall satisfy himself that the person so appointed is fully<br />

acquainted with the responsibilities imposed on him.<br />

Holes for charging explosives shall be drilled with Pneumatic drills, the<br />

drilling pattern being so planned that the rock pieces after blasting will be<br />

suitable for handling.<br />

The hole diameter shall be of such a size that cartridges can easily pass<br />

down them and undue force is not required during charging. Charging<br />

operations shall be carried out by or under the personal supervision of the<br />

shotfirer. Wrappings shall never be removed from explosive cartridges.<br />

Only wooden rods shall be used for loading and stemming shotholes. Only<br />

one cartridge at a time shall be inserted and gently passed home with the<br />

wooden tamping rod.<br />

(PCA.774.S034sca) V.II-D2/S-I : 12


DCPL-K4A02<br />

Only such quantities of explosives as are required for the particular<br />

amount of work to be done shall be brought to the works. Should any<br />

surplus remain when all the holes have been charged, it shall be carefully<br />

removed to a point at least 300 m from the firing point.<br />

The explosives shall be fired by means of an electric detonator placed<br />

inside the cartridge. For simultaneous firing of a number of charges the<br />

electric detonators shall be connected with the exploder through the<br />

shotfiring cable in a simple series circuit.<br />

Due precautions shall be taken to keep the firing circuit insulated from<br />

the ground, bare wires, rails, pipes or any other path of stray current and to<br />

keep the lead wires short circuited until ready to fire. Any Kinks in detonator<br />

leading wire shall be avoided.<br />

For simultaneous firing of a large number of shotholes, use of cordtex<br />

may be done. Cordtex shall be initiated by an electric detonator attached to<br />

its side with adhesive tape, connecting wire or string.<br />

All connections shall be made by the authorised shotfirer himself. The<br />

shotfiring cable shall not be dragged along the ground to avoid possible<br />

damage to the insulation. The shotfiring cable shall be tested for<br />

continuity and possible short circuiting before it is used each time.<br />

The shotfirer shall always carry the exploder handle on his person until he is<br />

ready to fire shots. The number of shots fired at a time shall not exceed the<br />

permissible limits.<br />

Before any blasting is carried out, it shall be ensured that all workmen,<br />

vehicles and equipment on the site are cleared from an area of minimum<br />

300 metres radius from the firing point, or as required by statutory<br />

regulations, at least ten minutes before the time of firing by sounding a<br />

warning siren. The area shall be encircled by red flags.<br />

At least five minutes after the blast has been fired in case of electric firing<br />

or as stipulated in the regulations the authorised shotfirer shall return to the<br />

blast area and inspect carefully and shall compare the number of blasts<br />

planted/fired to the actual number of shorts heard and satisfy himself that<br />

all blast have exploded. Withdrawl unexploded charges shall not be<br />

permitted.<br />

The unexploded charges shall be flooded with water and the hole shall be<br />

marked distinguishable manner. Another hole shall be made by drilling a<br />

parallel fresh hole not less than 450 mm from misfired hole and fired in<br />

the usual way. The process shall be continued till the original blast is<br />

exploded. The engineer shall also be informed by the Contractor of all<br />

the cases of misfired/unexploded charges, their causes and steps taken.<br />

The authorised shotfirer shall be present during removal of the debris liable<br />

to contain unexploded explosives near the misfired hole. The workmen<br />

shall not return to the site of firing until at least half an hour after firing.<br />

Adequate safety precautions as per building bye-laws, safety code, statutory<br />

regulations etc. shall be taken during blasting operations.<br />

(PCA.774.S034sca) V.II-D2/S-I : 13


DCPL-K4A02<br />

3.6.5 Disposal<br />

The excavated spoils will be disposed off within the specified lead in any<br />

or a combination of some of the following manners, as directed by the<br />

Engineer :<br />

a) By stacking separately the materials suitable for area filling and<br />

materials not suitable.<br />

b) By stacking it temporarily for use in backfilling at a later date.<br />

c) i) By either spreading, or<br />

ii)<br />

Spreading and compacting at designated filling areas and/or<br />

disposal areas.<br />

3.6.6 Dewatering<br />

All areas shall be kept free of water. Grading in the vicinity of excavations<br />

shall be controlled to prevent surface water running into excavated areas.<br />

The Contractor shall remove by pumping or other means approved by the<br />

Engineer, any water inclusive of rain water and subsoil water accumulated in<br />

the area. Method of dewatering shall be got approved by the Engineer.<br />

3.6.7 Dealing with Surface Water<br />

All working areas shall be kept free of surface water as far as reasonably<br />

practicable. Works in the vicinity of cut areas shall be controlled to<br />

prevvent the ingress of surface water.<br />

Working surfaces shall be formed to such falls to shed water and prevent<br />

ponding.<br />

No works shall commence until surface water streams have been<br />

properly intercepted, redirected or otherwise dealt with.<br />

Where works are undertaken in the monsoon period, the Contractor may<br />

need to construct temporary drainage systems to drain surface water from<br />

working areas.<br />

3.7.0 Treatment of Slips<br />

The Contractor will take all precautions to avoid high surcharges and<br />

provide proper surface drainage to prevent flow of water over the sides.<br />

These precautions along with proper slopes, berms, and control of ground<br />

water should cause no slips to occur. If however slips do occur due to<br />

causes beyond control of the Contractor, the same shall be removed by<br />

him.<br />

(PCA.774.S034sca) V.II-D2/S-I : 14


DCPL-K4A02<br />

3.8.0 Earthwork in Filling<br />

3.8.1 Area Filling for Grading<br />

The material to be used for area filling shall be selected material<br />

capable of being compacted to the requirements stated herein below and<br />

approved by the Engineer, obtained directly from excavation for area<br />

grading, from nearby areas where excavation work by the same agency is<br />

in progress, from temporary stacks of excavated spoils or from borrow<br />

pits in selected areas designated/approved by the Engineer. The quality<br />

of the material shall conform to that mentioned in clause 2.5.2 of this<br />

specification.<br />

Where excavated material is mostly rock, the boulders shall be broken<br />

into pieces not longer than 150 mm size, mixed with properly graded<br />

fine material consisting of murum or earth to fill up the voids and the<br />

mixtures used for filling.<br />

If any material is rejected by the Engineer, Contractor shall remove the<br />

same forthwith from the site at no extra cost of the owner. Surplus fill<br />

material shall be deposited/disposed of as directed by the Engineer after the<br />

fill work is completed.<br />

No earthfill shall commence until surface water discharges and streams<br />

have been properly intercepted or otherwise dealt with as directed by the<br />

Engineer.<br />

Before commencement of area filling the existing top soil shall be removed<br />

upto a minimum depth of 150 mm, or more, as directed by the Engineer<br />

in order to clear the surface of undesirable materials. After this the<br />

filling operation shall be performed with earth in layers not exceeding 250<br />

mm, loose thickness. Successive layers shall not be placed until the<br />

layer under construction has been thoroughly compacted to the<br />

specified requirements as given below and got approved by the Engineer.<br />

a) Each layer of earth of cohesive in nature shall be compacted to 90%<br />

of proctors dry density unless otherwise permitted/directed by<br />

the Engineer.<br />

b) Each layer of earth of non-cohesive in nature shall be compacted<br />

to minimum 75% relative density unless otherwise permitted/directed<br />

by the Engineer. Each shall be compacted with approved machine<br />

(mechanical plant) and usually manual compaction shall not be<br />

allowed unless specifically permitted by the Engineer. The<br />

original ground formation and each fill layer shall be compacted by<br />

rollers as described below with a maximum of six posses of 8/10<br />

tonne roller.<br />

i) When the optimum moisture content of soil is relatively high, a<br />

pneumatic tyred roller (type pressure 3.0 - 3.5 kg/sq.cm) shall<br />

be considered to give better performance for mechanical<br />

compaction.<br />

(PCA.774.S034sca) V.II-D2/S-I : 15


DCPL-K4A02<br />

ii)<br />

When the optimum moisture content of soil is relatively low, a<br />

vibrating roller shall be considered to give better<br />

performance for mechanical compaction.<br />

Since the degree of compaction depends on the moisture content of the soil,<br />

a close watch shall be kept on this aspect and corrections done to<br />

optimise the moisture content. The adequacy of the compaction and<br />

moisture content of the soil shall be determined by performing field density<br />

tests and other tests as and when directed by the Engineer and shall<br />

conform to the stipulations laid down in IS:4701.<br />

The cohesionless soil to be used for area filling, should be placed in fully<br />

saturated condition to obtain the maximum possible density. The saturation<br />

moisture content shall be determined by laboratory tests prior to<br />

commencement of work.<br />

Field compaction test shall be carried out at different stages of filling and<br />

also after the fill to the entire height has been completed.<br />

When density measuements reveal soft areas in the construction, further<br />

compaction shall be undertaken at the contractor's cost as directed by the<br />

Engineer. If the required compaction is then not achieved the material in<br />

the soft area shall be removed and replaced by approved material and<br />

compacted in accordance with this specification all to the contractor's<br />

account.<br />

The fill shall be carried out to such dimensions and levels as indicated on<br />

the drawings after the stipulated compaction. The fill will be considered as<br />

incomplete if the desired compaction has not been obtained.<br />

If so specified, the rock as obtained from excavation may be used for filling<br />

and levelling to indicated grades without further breaking. In such an<br />

event, filling shall be done in layers not exceeding 50 cms. approximately.<br />

After rock filling to the approximate level, indicated above has been<br />

carried out, the void in the rocks shall be filled with finer materials such as<br />

earth, broken stone, etc. and the area flooded so that the finer<br />

materials fill up the voids. Care shall be taken to ensure that the finer fill<br />

material does not get washed out. Over the layer so filled, a 100 mm thick<br />

mixed layer of broken material and earth shall be laid and consolidation<br />

carried out by a 12 tonne roller. No less than 12 passes of the roller shall<br />

be accepted before subsequent similar operations are taken up.<br />

3.8.2 Filling in Disposal Areas<br />

Excavated materials if not used in area filling, will be disposed of in<br />

designated disposal areas as directed or as indicated in the drawings. The<br />

earth shall not be dumped haphazardly but shall be spread in horizontal<br />

layers not exceeding 500 mm in thickness and nominal compaction done to<br />

the satisfaction of the Engineer.<br />

All clods shall be broken before placing the fill. Earthmoving machinery<br />

(PCA.774.S034sca) V.II-D2/S-I : 16


DCPL-K4A02<br />

including dumpers, dozers and trucks shall be allowed to ply over the fill to<br />

permit compaction to take place.<br />

In wide areas rollers may be employed and nominal compaction done to the<br />

satisfaction of the Engineer.<br />

3.9.0 Compaction Control<br />

The density of each layer of compacted soil shall be ascertained by testing<br />

a number of samples. For this purpose the necessary arrangements for<br />

soil testing at the site shall be made by the Contractor in accordance<br />

with these specifications and as directed by the Engineer.<br />

The Contractor shall arrange the provision of the field laboratory including<br />

the testing equipment and a suitable motor vehicle. He shall also supply<br />

all consumable materials such as kerosene, spirit, gas and sample bags as<br />

required.<br />

All soil testing is to be carried out by a competent and suitable qualified<br />

engineering testing firm. The Contractor is to obtain the Engineer's<br />

approval for the firm to be used. The Contractor may undertake this work<br />

with the Engineer's approval.<br />

All density testing shall be carried out on a lot by lot basis. A lot shall be<br />

considered to be a portion of work which is essentially homogeneous<br />

with respect to material type general appearance response during<br />

compaction, moisture condition during compaction, compaction process and<br />

state of underlying material.<br />

All fill testing shall be carried out in accordance with the recent editions<br />

of relevant Indian Standards. The chainage and the off-set from the centre<br />

line of the fill of each test sample shall be recorded and presented along with<br />

the test results.<br />

Each test lot shall be classified as cohesionless or cohesive. The<br />

classification shall be determined by the Engineer based upon particle<br />

size distribution. Cohesionless fill shall have 10% or less by mass of<br />

particles finer than 0.075 mm. Otherwise fill shall be treated cohesive.<br />

For cohesionless fill material, a representative laboratory sample obtained<br />

from three field samples from each test lot shall be tested to determine<br />

its maximum and minimum dry density. These reference values of dry<br />

density shall be used to compute the density index (relative density) of<br />

each of the field density test samples taken from the test lot.<br />

For cohesive fill material, a representative laboratory sample obtained<br />

from three field samples from each test lot shall be tested to determine its<br />

(PCA.774.S034sca) V.II-D2/S-I : 17


DCPL-K4A02<br />

maximum dry density and optimum moisture content (OMC). These<br />

reference values of dry density and moisture content shall be used to<br />

compute the dry density ratio of each of the field density test samples taken<br />

from that test lot.<br />

The degree of compaction shall be determined by considering the mean<br />

density of the samples in each test lot. The mean dry density shall be equal<br />

to or exceed the minimum specified density. In no individual case shall<br />

density be less than the minimum value specified by more than 2 percent,<br />

otherwise further rolling shall be done at the appropriate locations.<br />

The contractor shall lay a further layer or fill only after compaction or a<br />

particular layer has been found and approved by the Engineer.<br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA<br />

4.1.0 Soil Testing<br />

The following tests shall be undertaken by the Contractor and results and<br />

reports shall be submitted to the Engineer for approval. Test failures<br />

are to be immediately notified to the Engineer, otherwise results to be<br />

submitted within 24 hours of testing. Each layer of material shall be tested<br />

for compaction.<br />

Each layer is to be tested in a manner that is representative of its full<br />

depth. The Engineer may at his discretion instruct the Contractor to<br />

increase or decrease the frequency of testing.<br />

a) Minimum one test per 500 cu.m. of soil coming out of the borrow<br />

pits for determination of natural moisture contents in order to<br />

evaluate how far the natural moisture content tallies with the<br />

optimum value and whether further addition or reduction of water<br />

content would be necessary. Test to be done in accordance with IS<br />

: 2720 (Part-II).<br />

b) Minimum two sets of laboratory tests per 8000 cu.m. of soil coming<br />

out of the borrow pits for determination of dry density at optimum<br />

moisture content. Test to be done in accordance with IS : 2720<br />

(Part-VII, XIV, XXVIII, XXIV) as applicable.<br />

c) Minimum two sets of test per 500 cu.m. of loose fill for<br />

determination of moisture content just prior to compaction of area<br />

filling. Test to be done in accordance with IS: 2720 (Part-II).<br />

d) For each compacted layer, minimum one test per 2000 sq.m. of<br />

compacted area for determination of moisture content and dry<br />

density.<br />

(PCA.774.S034sca) V.II-D2/S-I : 18


DCPL-K4A02<br />

e) Minimum two tests per 8000 cu.m. of soil for determination of soil<br />

classification. Test to be done in accordance with IS: 2720 (Part-IV).<br />

f) Minimum 10 (ten) density measurements shall be plotted to<br />

establish moisture content-dry density relationship.<br />

4.2.0 Acceptance Criteria<br />

4.2.1 Excavation<br />

4.2.2 Area-filling<br />

On completion of excavation, the dimensions of the area will be checked<br />

as per the drawings after the area is completely dewatered. The work will be<br />

accepted after all undercuts have been set right and all over excavations<br />

filled back to required lines, levels and grades by compacted earth. Over<br />

excavation of the sides will be made good free of cost by the Contractor.<br />

The excavation work will be accepted after the above requirements are<br />

fulfilled & all temporary approaches encroaching inside the required<br />

dimension of the excavation have been removed.<br />

The degree of compaction required will be as per the stipulations laid down<br />

in appropriate sections of this specification. The actual method for<br />

measuring the compaction achieved will be as decided by the Engineer.<br />

The work of area filling will be accepted after the Engineer is satisfied<br />

with the degree of compaction achieved.<br />

5.0.0 INFORMATION TO BE SUBMITTED<br />

5.1.0 With Tender<br />

Following details of Machineries, transport vehicles, equipment proposed<br />

to be used for excavation, area-filling and compaction have to be submitted<br />

along with the tender :<br />

i) Equipment, machinery & earthmoving vehicles, available with the<br />

Contractor and proposed to be used for excavation and haulage<br />

giving details regarding make, model, capacity, year of manufacture,<br />

numbers available for this contract and general condition.<br />

ii)<br />

iii)<br />

Equipment proposed to be used for area filling and compaction giving<br />

similar details as in item 5.1.0 (i) above.<br />

Method of transportation.<br />

5.2.0 After Award<br />

After award of contract the successful tenderer shall submit the following for<br />

approval and adoption:<br />

a) Within 15 days of Award of the contract, the Contractor shall submit a<br />

(PCA.774.S034sca) V.II-D2/S-I : 19


DCPL-K4A02<br />

detailed programme of work as proposed to be executed giving<br />

completion dates of excavation of the various areas and the time<br />

required for area-filling and compaction. The programme should also<br />

show how the excavation and area- filling quantities will be<br />

balanced, minimising temporary stacking of spoils. It is to be noted<br />

that the Engineer even after initial approval of the programme, may<br />

instruct to enhance or retard the progress of work during the actual<br />

execution, in order to match with overall construction schedule<br />

without attracting any claims from the Contractor. The initial<br />

programme being submitted by the Contractor should have<br />

sufficient flexibility to take care of such reasonable variations.<br />

b) Within 15 days of award, the Contractor shall submit drawings<br />

showing details of slopes, approaches, sump pits, dewatering lines,<br />

borrow pits, if any, fencing etc. for approval of the Engineer for<br />

adoption.<br />

(PCA.774.S034sca) V.II-D2/S-I : 20


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-II<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

EARTHWORK IN EXCAVATION AND BACKFILLING<br />

(PCA.774.S034sca1)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-II : 1<br />

2.0.0 GENERAL V.II-D2/S-II : 1<br />

3.0.0 EXECUTION V.II-D2/S-II : 3<br />

4.0.0 TESTING AND ACCEPTANCE V.II-D2/S-II : 16<br />

CRITERIA<br />

5.0.0 INFORMATION TO BE V.II-D2/S-II : 17<br />

SUBMITTED<br />

(PCA.774.S034sca1)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-II<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

EARTHWORK IN EXCAVATION AND BACKFILLING<br />

1.0.0 SCOPE<br />

2.0.0 GENERAL<br />

This specification covers excavation in all types of soil, soft and<br />

decomposed rock not requiring blasting and rocks requiring blasting,<br />

shoring, dewatering, filling around foundations and to grade, compaction of<br />

fills and approaches, protective fencing, lighting, etc. relevant to structures<br />

and locations covered under the scope of this contract.<br />

2.1.0 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless specified<br />

otherwise, shall include but not be limited to the following :<br />

a) Furnish all labour, supervision, services including facilities as<br />

required under statutory labour regulations, materials, scaffolds,<br />

equipment, tools and plants, transportation, etc. required for the<br />

work.<br />

b) Prepare and submit working drawings showing the approaches,<br />

slopes, berms, shoring, sumps for dewatering, including drains and<br />

outfall for drainage, space for temporary stacking of spoils, disposal<br />

area, fencing, etc. and all other details as may be required by the<br />

Engineer.<br />

c) To carry out sampling and testing and submit to the Engineer,<br />

results of soil compaction tests whenever required by the Engineer<br />

to assess the degree of compaction.<br />

d) Construction, maintenance and removal after completion of magazine<br />

of proper capacity as well as design for storing of explosives<br />

required for blasting work to be carried out under the scope of this<br />

tender including procurement of necessary licenses from proper<br />

authorities.<br />

2.2.0 Work to be provided for by others<br />

No work under this specification will be provided by any agency other<br />

than the Contractor unless specifically mentioned elsewhere in the<br />

Contract.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 1


DCPL-K4A02<br />

2.3.0 Codes and Standards<br />

All works under this specification, unless specified otherwise, shall conform<br />

to the latest revision and/or replacement of the following or any other Indian<br />

Standard Specifications and Codes of Practice. In case any particular aspect<br />

of work is not covered specifically by Indian Standard Specification any other<br />

standard practice as may be specified by the Engineer shall be followed :-<br />

IS:1200<br />

(Part-I)<br />

IS:2720<br />

(Part-II)<br />

IS:2720<br />

(Part-VII)<br />

IS:2720<br />

(Part-xiv)<br />

IS:2720<br />

(Part-xxix)<br />

IS:2720<br />

(Part- xxviii)<br />

IS:3764<br />

IS:4081<br />

IS:4701<br />

Method of Measurement of Building and Civil<br />

Engineering work; Part - I Earthwork.<br />

Determination of Moisture Content<br />

Determination of Moisture content / Dry Relation<br />

using Light Compaction.<br />

Determination of Density Index (Relative Density)<br />

of cohesionless soils.<br />

Determination of Dry Density , in place, by core<br />

cutter method.<br />

Determination of Dry Density of soils, in place,<br />

by sand replacement methods.<br />

Safety code for Excavation work.<br />

Blasting and Related Drilling Operations<br />

Earthwork on canals<br />

2.4.0 Conformity with Designs<br />

The Contractor is to carry out the work as per the drawings issued to him<br />

and/or Contractor's drawings which are approved by the Engineer and/or the<br />

Engineer's instructions.<br />

2.5.0 Materials to be used<br />

2.5.1 General<br />

All materials required for the work shall be of best commercial variety<br />

and approved by the Engineer.<br />

2.5.2 Borrow Material<br />

(PCA.774.S034sca1) V.II-D2/S-II : 2


DCPL-K4A02<br />

Borrow material required for back-filling shall be excavated from approved<br />

locations and levels, and shall consist of material, approved by the<br />

Engineer, free from roots, vegetations, decayed organic matter, harmful salts<br />

and chemicals, free from lumps and clods. If specified, clean graded sand<br />

free from harmful and deleterious material from approved quarries, shall be<br />

used as fill material.<br />

2.6.0 Quality Control<br />

The Contractor shall establish and maintain quality control for the various<br />

aspects of the work, method, materials and equipment used. The quality<br />

control operation shall include but not be limited to the following items of<br />

work :<br />

a) Lines, Levels and Grades : i) Periodic surveys<br />

ii) Establishment of markers, boards etc.<br />

b) Back-filling : i) Checking the quality of fill material<br />

backfill<br />

ii) Checking moisture content of the<br />

2.7.0 Information regarding site conditions<br />

iii) Checking the degree of compaction<br />

Surface and Sub-surface data regarding the nature of soil, rock, sub-soil<br />

water etc. shown on drawing or otherwise furnished to the Contractor<br />

shall be taken as a guidance only and variation therefrom shall not affect<br />

the terms of the contract. The Contractor must satisfy himself regarding<br />

the character and volume of all work under this contract and expected<br />

surface, sub-surface and / or sub-soil water to be encountered. He must also<br />

satisfy himself about the general conditions of site and ascertain the existing<br />

and future construction likely to come up during the execution of the<br />

contract so that he may evolve a realistic programme of execution.<br />

3.0.0 EXECUTION<br />

3.1.0 Setting Out<br />

The Contractor will prepare and submit to the Engineer, detailed drawings<br />

of the excavation work as proposed to be executed by him showing the<br />

dimensions as per drawings and specification adding his Proposals of slopes,<br />

shorings, approaches, dewatering sumps, berms, etc. On receiving the<br />

approval from the Engineer with modifications and corrections, if necessary,<br />

the Contractor will set out the work from the control points furnished by the<br />

Engineer and fix permanent points and markers for ease of future checking.<br />

These permanent points and markers will be fixed at intervals prescribed by<br />

the Engineer and checked by the Engineer and certified by him after which<br />

the Contractor will proceed with the work. Engineer shall be provided with<br />

(PCA.774.S034sca1) V.II-D2/S-II : 3


3.2.0 Initial Levels<br />

DCPL-K4A02<br />

necessary men, material and instructions for such checking. It should be<br />

noted that this checking by the Engineer prior to start of the work will in no<br />

way absolve the Contractor of his responsibility of carrying out the work to<br />

true lines and levels and grades as per drawing and subsequent<br />

corrections, if necessary, in case any errors are noticed in the Contractor's<br />

work at any stage.<br />

Initial levels of the ground either in a definite grid pattern or as directed<br />

by the Engineer will be taken by the Contractor jointly with the Engineer over<br />

the original ground prior to starting actual excavation work and after setting<br />

out. These initial levels will be used for preparing cross-sections for volume<br />

measurement or for cross-checking the depths obtained from tape<br />

measurements.<br />

All records of levels, measurements etc. and also any drawing, cross<br />

section etc. made therefrom, shall be jointly signed by the authorised<br />

representative of the contractor and the Engineer before the<br />

commencement of work and they shall form the basis of all payments in<br />

future.<br />

3.3.0 Clearing and Grubbing, etc.<br />

The area to be excavated or filled shall be cleared out of fences, trees,<br />

logs, stumps, bush, vegetation, rubbish, slush, etc. and levelled up. Trees<br />

upto 300mm girth shall be uprooted. Trees above 300 mm girth to be cut,<br />

shall be approved by the Engineer and then marked. Felling of trees shall<br />

include taking out roots upto 600 mm below ground level or 150 mm below<br />

formation level whichever is lower. After the tree is cut and roots taken out<br />

the pot-holes formed shall be filled with good earth in 250 mm layers and<br />

consolidated unless directed by the Engineer otherwise. The trees shall be<br />

cut in suitable pieces as instructed by the Engineer.<br />

Before earthwork is started, all the spoils and unserviceable materials and<br />

rubbish shall be burnt or removed from the site to approved disposal areas<br />

as may be specified. Ash shall be spread or removed. Useful materials,<br />

saleable timber, firewood, etc. shall be the property of the Owner and shall<br />

be stacked properly at the worksite in a manner as directed by the<br />

Engineer.<br />

3.4.0 Classification<br />

All earthwork shall be classified under the following categories :<br />

No distinction will be made whether the material is dry or wet.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 4


DCPL-K4A02<br />

a) Ordinary Soil<br />

This shall comprise vegetable or organic soil, turf, sand, silt, loam,<br />

clay, mud, peat, black cotton soil, soft shale or loose moorum, a<br />

mixture of these and similar material which yields to the ordinary<br />

application of pick and shovel, rake or other ordinary digging<br />

implement. Removal of gravel or any other nodular material having<br />

diameter in any one direction not exceeding 75 mm occurring in such<br />

strata shall be deemed to be covered under this category.<br />

b) Hard Soil<br />

This shall include :<br />

i) stiff heavy clay, hard shale, or compact moorum requiring<br />

grafting tool or pick or both and shovel, closely applied ;<br />

ii)<br />

gravel and cobble stone having maximum diameter in any one<br />

direction between 75 and 300 mm ;<br />

iii) soling of roads, paths, etc., and hard core ;<br />

iv)<br />

macadam surfaces such as water bound, and bitumen/tar<br />

bound;<br />

v) lime concrete, stone masonry in lime mortar and brick work in<br />

lime/cement mortar, below ground level ;<br />

vi)<br />

vii)<br />

soft conglomerate, where the stones may be detached from the<br />

matrix with picks ; and<br />

generally any material which requires the close application of<br />

picks, or scarifiers to loosen and not affording resistance to<br />

digging greater than the hardest of any soil mentioned in (i)<br />

and (vi) above.<br />

c) Soft and Decomposed Rock<br />

This shall include :<br />

i) limestone, sandstone, laterite, hard conglomerate or other soft<br />

or disintegrated rock which may be quarried or split with<br />

crowbars ;<br />

ii)<br />

unreinforced cement concrete which may be broken up with<br />

crowbars or picks and stone masonry in cement mortar below<br />

ground level ;<br />

iii)<br />

boulders which do not require blasting having maximum<br />

diameter in any direction of more than 300 mm, found lying<br />

loose on the surface or embedded in river bed, soil, talus, slope<br />

wash and terrace material of dissimilar origin ; and<br />

(PCA.774.S034sca1) V.II-D2/S-II : 5


DCPL-K4A02<br />

iv)<br />

any rock which in dry state may be hard, requiring blasting, but<br />

which when wet becomes soft and manageable by means<br />

other than blasting.<br />

d) Hard Rock (requiring blasting)<br />

This shall include :<br />

i) any rock or cement concrete for the excavation of which the<br />

use of mechanical plant or blasting is required ;<br />

ii)<br />

iii)<br />

reinforced cement concrete (reinforcement cut through but not<br />

separated from the concrete) below ground level; and<br />

boulders requiring blasting.<br />

e) Hard Rock (blasting prohibited)<br />

Hard rock requiring blasting as described under (d) but where blasting<br />

is prohibited for any reason and excavation has to be carried out by<br />

chiselling, wedging or any other agreed method.<br />

In case of any dispute regarding classification, the decision of the<br />

Engineer shall be final.<br />

3.5.0 Excavation for Foundations and Trenches<br />

3.5.1 General<br />

All excavations shall be done to the minimum dimensions as required for<br />

safety and working facility. Prior approval of the Engineer shall be obtained<br />

by the Contractor, in each individual case, for the method he proposes to<br />

adopt for the excavations including dimension, side slopes, shoring,<br />

dewatering, disposal, etc. This approval, however, shall not in any way<br />

make the Engineer responsible for any consequent loss or damage. The<br />

excavation must be carried out in the most expeditious and efficient<br />

manner.<br />

All excavation in open cuts shall be made true to line, slopes and grades<br />

shown on the drawing or directed by the Engineer. No material shall project<br />

within the dimension of minimum excavation lines marked. Boulders<br />

projecting out of the excavated surfaces shall be removed, if in the opinion of<br />

the Engineer they are likely to be a hindrance to the workers.<br />

Method of excavation shall be in every case subject to the approval of the<br />

Engineer and the Contractor shall ensure the stability and safety of the<br />

excavation, adjacent structures, services and works.<br />

The Contractor shall have full responsibility of the stability of the<br />

excavation and safety of the workmen. If any slip occurs, the Contractor<br />

shall remove all slipped material from the excavated pit.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 6


DCPL-K4A02<br />

All loose boulders, semi-detached rocks, not directly in excavation but so<br />

close to the area to be excavated as to be liable, in the opinion of the<br />

Engineer, to fall or otherwise endanger the workmen, equipment of the<br />

work, etc., shall be stripped off and removed away from the areas of<br />

excavation. The method used shall be such as not to shatter or render<br />

unstable or unsafe the portion which was originally sound and safe. Any<br />

materials not requiring removal as contemplated in the work, but which, in<br />

the opinion of the Engineer, is later to become loose or unstable shall also<br />

be promptly and satisfactorily removed as directed by the Engineer.<br />

Prior to starting the excavation, the ground level at the location shall be<br />

checked jointly with the Engineer.<br />

The rough excavation may be carried upto a maximum depth of 150 mm<br />

above the final level. The balance shall be excavated with special care. If<br />

directed by the Engineer, soft and undesirable spots shall be removed even<br />

below the final level. The extra excavation shall be filled up as instructed<br />

by the Engineer.<br />

If the excavation is done to a depth greater than that shown on the<br />

drawing, or directed by the Engineer, due to the Contractor's fault, the<br />

excess depth shall be filled up to the required level (with cement concrete<br />

not leaner than 1:4:8 ordinary concrete or richer) as directed by the<br />

Engineer in each individual case.<br />

In formation of rock requiring blasting, those overcuts which are unavoidable<br />

will be made up by ordinary cement concrete 1:2:4. All excavated materials<br />

such as hard rock, boulders, bricks, dismantled concrete blocks, etc. shall be<br />

stacked separately as directed by the Engineer and shall be the property of<br />

the Owner.<br />

3.5.2 Excavation in Ordinary Soil, Hard Soil<br />

and Soft and Decomposed Rock<br />

The excavation in ordinary soil, hard soil, soft and decomposed rock<br />

will be carried out as per the approved proposal, modified and corrected<br />

where necessary by the Engineer. The work will be carried out in a<br />

workmanlike manner without endangering the safety of nearby<br />

structures/services or works and without causing hindrance to other activities<br />

in the area. As the excavation reaches the required dimensions, lines,<br />

levels and grades, the work will be checked by the Engineer thoroughly and<br />

the balance work will be carried out carefully to avoid any over-excavation.<br />

On completion, the work will be finally checked and approved by the<br />

Engineer. In certain cases, where deterioration of the ground, upheaval,<br />

slips, etc. are expected, the Engineer may order to suspend the work at any<br />

stage and instruct the Contractor to carry out the balance work just before<br />

the foundation work of the structure can be started.<br />

3.5.3 Excavation in Hard Rock<br />

In case where excavation, both in ordinary soil and hard rock, are<br />

involved, the ordinary soil comprising of soft, hard and dense soils (including<br />

laterite formations) and rock including weathered rocks, lateritic rocks, etc.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 7


3.5.4 Blasting<br />

3.5.4.1 General<br />

DCPL-K4A02<br />

which can be excavated without blasting, shall be completely stripped off.<br />

Further work in hard rock shall be resumed after clearance from the<br />

Engineer.<br />

Personnel deployed for rock excavations shall be protected from all<br />

hazards such as loose rock/boulder rolling down and from general slips of<br />

excavated surfaces. Where the excavated surface is such that it is not<br />

stable against sliding, necessary supports, props, bracings or bulkheads<br />

shall be provided and maintained during the period of construction.<br />

Where danger exists of loose rock/boulder falling from the excavated<br />

surfaces deeper than 2 metres, steel mesh anchored to the lower edge<br />

of excavation and extending over and above the rock face, adequate to<br />

retain the dislodged material shall be provided and maintained.<br />

In case where blasting, though otherwise required, is prohibited for any<br />

reasons, the excavation shall be carried out by chiselling, wedging or any<br />

other approved method.<br />

Storage, handling and use of explosives shall be governed by the current<br />

explosive rules laid down by the Central and the State Governments. The<br />

Contractor shall ensure that these rules are strictly adhered to. The following<br />

instruction, wherever found in variance with the above rules, shall be<br />

considered as superseded by the above rules.<br />

No child under the age of 16 and no person who is in a State of intoxication<br />

shall be allowed to enter the premises where explosives are stored nor they<br />

shall be allowed to handle the explosives.<br />

3.5.4.2 Storage of Explosive<br />

Storage of explosives shall be governed by the current Explosive Rules,<br />

Explosives shall be stored in a clean, dry, well ventilated magazine to be<br />

specially built for the purpose. Under no circumstances should a magazine<br />

be erected within 400 m of the actual work site or any source of fire. A<br />

space surrounding the magazine shall be fenced in. The ground inside the<br />

fence shall be kept clear and free from trees, bushes etc. The admission to<br />

this fenced space shall be by one gate only and no person shall be allowed<br />

inside this fence without permission of the Officer-in-charge. The clear space<br />

between the fence and the magazine shall not be less than 90m. The<br />

mezzanine shall be perfectly well drained.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 8


DCPL-K4A02<br />

Two lightning conductors shall be provided to the magazine, one at each<br />

end. The lightning conductors shall be tested once in every year.<br />

Fuses and detonators shall be stored in separate magazines. However,<br />

detonators can be kept in an annexe adjoining the magazine provided that<br />

their number does not exceed 25,000 and that the annexe is so<br />

constructed that not less than 60 cm masonry and 100 cm of air space shall<br />

intervene between any detonators in such annexe and the interior of the<br />

main magazine. Cases containing explosives are not to be opened in a<br />

magazine. Explosive in open cases are not to be received into a magazine.<br />

Explosives which appear to be in a damaged or dangerous condition are not<br />

to be kept in any magazine, but must be removed without delay to a safe<br />

distance and destroyed.<br />

Artificial light is not to be allowed in any magazine. No smoking shall be<br />

allowed within 100 m of a magazine.<br />

Magazine shoes without nails shall be used while entering the magazine.<br />

The mallets, levers, wedges etc. for opening barrels or cases are to be of<br />

wood. Inside a magazine the cases of explosives are to be carried by hand<br />

and shall not be rolled or dragged. Explosives which have been issued<br />

and returned to the magazine are to be issued first; otherwise those which<br />

have been longest in store are to be issued first.<br />

Cases of explosives must be kept clear of the walls and floors for free<br />

circulation of air on all sides, special care is to be taken to keep the floor<br />

free from grains of powder or portions of explosive matter fallen on the<br />

floors due to leakage of cases etc.<br />

The magazine shall not be opened during any duststorm or thunderstorm<br />

nor any person shall be allowed in the vicinity of the magazine.<br />

All magazines shall be officially inspected at definite intervals and a record<br />

kept of the results of such inspections.<br />

3.5.4.3 Carriage of Explosives<br />

Detonators and explosives shall be transported separately to the blast site.<br />

Explosives shall be kept dry and away from the direct rays of the sun,<br />

naked lights, steam pipes or heated metal and other sources of heat. Before<br />

explosives are removed, each cage or package is to be carefully examined to<br />

ascertain that it is properly closed and shows no sign of leakage.<br />

No person except the driver shall be allowed to travel on a vehicle conveying<br />

explosives. No carriage or vessel shall be used for transporting explosives<br />

unless all iron or steel therein with which a package containing any<br />

explosive is likely to come in contact is effectually covered with lead,<br />

leather, wood, cloth or other suitable material. No lights shall be carried on<br />

the vehicle carrying explosives.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 9


DCPL-K4A02<br />

No operation connected with the loading, unloading and handling of<br />

explosives shall be conducted after sunset.<br />

3.5.4.4 Use of Explosives<br />

The Contractor shall appoint an agent who shall personally superintend<br />

the firing and all operations connected therewith. The contractor shall satisfy<br />

himself that the person so appointed is fully acquainted with the<br />

responsibilities imposed on him.<br />

Holes for charging explosives shall be drilled with Pneumatic drills, the<br />

drilling pattern being so planned that the rock pieces after blasting will be<br />

suitable for handling.<br />

The hole diameter shall be of such a size that cartridges can easily pass<br />

down them and undue force is not required during charging. Charging<br />

operations shall be carried out by or under the personal supervision of the<br />

shotfirer. Wrappings shall never be removed from explosive cartridges. Only<br />

wooden rods shall be used for loading and stemming shotholes. Only one<br />

cartridge at a time shall be inserted and gently passed home with the<br />

wooden tamping rod.<br />

Only such quantities of explosives as are required for the particular<br />

amount of work to be done shall be brought to the works. Should any<br />

surplus remain when all the holes have been charged, it shall be carefully<br />

removed to a point at least 300 m from the firing point.<br />

The explosives shall be fired by means of an electric detonator placed<br />

inside the cartridge. For simultaneous firing of a number of charges the<br />

electric detonators shall be connected with the exploder through the<br />

shotfiring cable in a simple series circuit. Due precautions shall be taken<br />

to keep the firing circuit insulated from the ground, bare wires, rails, pipes<br />

or any other path of stray current and to keep the lead wires short circuited<br />

until ready to fire. Any kinks in detonator leading wire shall be avoided.<br />

For simultaneous firing of a large number of shotholes, use of cordtex may<br />

be done. Cordtex shall be initiated by an electric detonator attached to its<br />

side with adhesive tape, connecting wire or string.<br />

All connections shall be made by the authorised shotfirer himself. The<br />

shotfiring cable shall not be dragged along the ground to avoid possible<br />

damage to the insulation. The shotfiring cable shall be tested for continuity<br />

and possible short circuiting before it is used each time.<br />

The shotfirer shall always carry the exploder handle on his person until he is<br />

ready to fire shots. The number of shots fired at a time shall not exceed the<br />

permissible limits.<br />

Blasting shall only be carried out at certain specified times to be agreed<br />

jointly by the contractor and the Engineer.<br />

Before any blasting is carried out, it shall be ensured that all workmen,<br />

vehicles and equipment on the site are cleared from an area of minimum<br />

(PCA.774.S034sca1) V.II-D2/S-II : 10


3.5.5 Disposal<br />

DCPL-K4A02<br />

300 metres radius from the firing point, or as required by statutory<br />

regulations, at least ten minutes before the time of firing by sounding a<br />

warning siren. The area shall be encirled by red flags.<br />

At least five minutes after the blast has been fired in case of electric firing or<br />

as stipulated in the regulations the authorised shotfirer shall return to the<br />

blast area and inspect carefully the work and satisfy himself that all<br />

charged holes have exploded. Cases of misfired unexploded charges shall<br />

be exploded by drilling a parallel fresh hole not less than 600 mm from the<br />

misfired hole and by exploding a new charge. The authorised shotfirer shall<br />

be present during removal of the debris liable to contain unexploded<br />

explosives near the misfired hole. The workmen shall not return to the site<br />

of firing until at least half an hour after firing.<br />

When blasting is conducted in the neighbourhood of roads, structures,<br />

buildings etc. controlled blasting has to be carried out by drilling shallow<br />

shotholes and filling the same with light charge of explosives.<br />

Adequate safety precautions as per building bye-laws, safety code, statutory<br />

regulations etc. shall be taken during blasting operations.<br />

The excavated spoils will be disposed of in any or all the following<br />

manners :<br />

a) By using it for backfilling straightway.<br />

b) By stacking it temporarily for use in backfilling at a later date during<br />

execution of the Contract.<br />

c) i) By either spreading, Or<br />

ii) spreading and compacting at designated<br />

disposal areas.<br />

filling areas and / or<br />

d) By selecting the useful material and stacking it neatly in areas<br />

designated by the Engineer for use in backfilling by some other<br />

agency.<br />

3.5.6 Disposal of Surplus<br />

3.5.7 Protection<br />

All surplus material from excavation shall be carried away from the<br />

excavation site to designated disposal area selected by the Engineer.<br />

All good and sound rock excavated from the pits and all assorted materials<br />

of dismantled structures shall be the property of the Owner.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 11


DCPL-K4A02<br />

The Engineer shall be notified by the Contractor as soon as the excavation<br />

is expected to be completed within a day so that it may be inspected by him<br />

at the earliest. Immediately after approval of the Engineer, the excavation<br />

must be covered up in the shortest possible time. But, in no case the<br />

excavation shall be covered up or worked on before approval and<br />

measurement by the Engineer. Excavated material shall be placed beyond<br />

1.5 metres from the edge of the pit or trench or half the depth of the pit or<br />

trench whichever is more or further away if directed by the Engineer.<br />

Excavation shall not be carried out below the foundation level of structure<br />

close by until required precautions have been taken.<br />

Adequate fencing is to be made enclosing the excavation.<br />

The Contractor shall protect all under-ground services exposed by<br />

excavation. The Contractor shall also divert all surface drains, etc. affected<br />

by the excavation to maintain the working area neat and clean.<br />

3.5.8 Dealing with Surface Water<br />

All working areas shall be kept free of surface water as far as reasonably<br />

praticable. Works in the vicinity of cut areas shall be controlled to prevent the<br />

ingress of surface water.<br />

No works shall commence until surface water streams have been properly<br />

intercepted , redirected or otherwise dealt with.<br />

Where works are undertaken in the monsoon period, the Contractor<br />

may need to construct temporary drainage systems to drain surface water<br />

from working areas.<br />

3.5.9 Dewatering<br />

All excavations shall be kept free of water and slush. Grading in the<br />

vicinity of excavations shall be controlled to prevent surface water running<br />

into excavated areas. The Contractor shall remove by pumping or other<br />

means approved by the Engineer any water inclusive of rain water and<br />

subsoil water accumulated in excavation and keep the trench dewatered until<br />

the construction of foundation structure and backfilling are complete in all<br />

respects. (except where such dewatering would need installation of well<br />

points or deep wells for which separate payment will be made) Sumps made<br />

for dewatering must be kept clear of the foundations. Method of pumping<br />

shall be approved by the Engineer but in any case, the pumping<br />

arrangement shall be such that there shall be no movement of subsoil or<br />

blowing in due to differential head of water during pumping.<br />

3.5.10 Timber Shoring<br />

Timber Shoring made out of approved quality of timber shall be 'close' or<br />

'open' type, depending on the nature of soil and the depth of pit or trench<br />

and the type of timbering shall be determined by the Engineer. It shall be<br />

(PCA.774.S034sca1) V.II-D2/S-II : 12


DCPL-K4A02<br />

the responsibility of the Contractor to take all necessary steps to prevent<br />

the sides of trenches and pits from collapsing.<br />

3.5.10.1 Close Timbering<br />

Close timbering shall be done by completely covering the sides of the<br />

trenches and pits generally with short, upright members called 'polling<br />

boards'. These shall be of minimum 250 x 40 mm sections as directed by<br />

the Engineer. The boards shall generally be placed in position vertically in<br />

pairs, one board on each side of cutting, and shall be kept apart by<br />

horizontal walers of strong wood at maximum 1.2 metres spacings,<br />

cross strutted with ballies or as directed by the Engineer. The length of the<br />

bally struts shall depend on the width of the trench or pit.<br />

In case where the soil is very soft and loose, the boards shall be placed<br />

horizontally against the sides of the excavation and supported by vertical<br />

walers, which shall be strutted to similar timber pieces on the opposite face<br />

of the trench or pit. The lowest board supporting the sides shall be taken<br />

into the ground. No portion of the vertical side of the trench or pit shall<br />

remain exposed, so that the earth is not liable to slip out.<br />

The withdrawal of the timber shall be done very carefully to prevent the<br />

collapse of the pit or trench. It shall be started at one end and proceeded<br />

systematically to the other end. Concrete or masonry shall not be damaged<br />

during the removal of the timber. No claim shall be entertained for any<br />

timber which cannot be withdrawn and is lost or buried.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 13


DCPL-K4A02<br />

3.5.10.2 Open Timbering<br />

In the case of open timbering, the entire surface of the side of trench pit is<br />

not required to be covered. The vertical board of minimum 250 mm width and<br />

minimum 40 mm depth shall be spaced sufficiently apart to leave<br />

unsupported strips of maximum 500 mm average width. The detailed<br />

arrangement, sizes of the timber and the distances apart shall be subject to<br />

the approval of the Engineer. In all other respects, specification for close<br />

timbering shall apply to open timbering.<br />

3.6.0 Treatment of Slips<br />

3.7.0 Back-filling<br />

3.7.1 General<br />

The Contractor will take all precaution to avoid high surcharges and<br />

provide proper surface drainage to prevent flow of water over the sides.<br />

These precautions along with proper slopes, berms, shoring and control of<br />

ground water should cause no slips to occur. If however slips do occur<br />

due to causes beyond the control of the Contractor, the same shall be<br />

removed by him. Slips caused due to negligence of the Contractor will be<br />

cleared and back-filled later by him.<br />

The material used for backfilling shall consist of material, approved by the<br />

Engineer obtained directly from nearby areas where excavation work by the<br />

same agency is in progress, from temporary stacks of excavated spoils or<br />

from borrow pits from selected areas designated by the Engineer. The<br />

material shall be free from lumps and clods, roots and vegetations, harmful<br />

salts and chemicals, organic materials, etc.<br />

In certain locations, the Engineer may direct sand fillings. The sand should<br />

be clean, well graded and be of quality normally acceptable for use in<br />

concrete.<br />

3.7.2 Filling and Compaction in Pits and Trenches around Structures<br />

As soon as the work in foundations has been accepted and measured,<br />

the spaces around the foundation structures in pits and trenches shall be<br />

cleared of all debris, brick bats, mortar droppings, etc., and filled with<br />

earth in layers not exceeding 250 mm in loose thickness each layer being<br />

watered, rammed and properly compacted to achieve a dry density of not<br />

less that 90% of proctor's dry density at optimum moisture content as per<br />

IS-2720 ( Part-VII) where backfilling with cohesive soil and sandy silt<br />

containing high percentage of silt. For back filling with sand having little or<br />

no silt, each layer shall be compacted to a relative density of 75% as per<br />

IS-2720 part XIV. Earth shall be rammed with approved mechanised<br />

compaction machine. Usually, no manual compaction shall be allowed unless<br />

specifically permitted by the Engineer. The final surface shall be trimmed<br />

and levelled to proper profile as shown in the drawing and as desired by the<br />

Engineer.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 14


DCPL-K4A02<br />

3.7.3 Plinth Filling<br />

Since the degree of compaction depends on the moisture content of the<br />

soil, a close watch should be kept on it and corrections done to optimise the<br />

moisture content.<br />

The plinth shall be filled with earth in layers not exceeding 250 mm in loose<br />

thickness, watered and compacted as stated under clause no. 3.7.2 with<br />

approved compaction machine or manually, if specifically permitted by the<br />

Engineer. When the filling reaches the finished level, the surface shall be<br />

flooded with water for at least 24 hours, allowed to dry and then rammed<br />

and compacted, in order to avoid any settlement at a later stage. The<br />

finished level of the filling shall be trimmed to the slope intended to be given<br />

to the floor.<br />

3.7.4 Filling in Trenches for Water Pipes and Drains<br />

Earth used for filling shall be free from salts, organic or other foreign matter.<br />

All clods of earth shall be broken or removed. Where excavated material<br />

is mostly rock, the boulders shall be broken into pieces not bigger than 150<br />

mm size in any direction, mixed with fine material consisting of disintegrated<br />

rock, moorum or earth as available, so as to fill up the voids as far as<br />

possible and then the mixture used for filling. The types of bedding &<br />

pipe surround material shall be as specified in the drawings .<br />

Filling in trenches for pipes and drains shall be commenced as soon as the<br />

joints of pipes and drains have been tested and passed.<br />

Where the trenches are excavated in soil, the filling shall be done with<br />

earth on the sides and top of pipes in layers not exceeding 150 mm,<br />

watered, rammed and compacted taking care that no damage is caused to<br />

the pipe below. Filling of trenches shall be carried out simultaneously on<br />

both sides of the pipe in such a manner that unequal pressures do not<br />

occur.<br />

In case of excavation of trenches in rock, the filling upto a depth of 300 mm<br />

or the diamter of the pipe whichever is more, above the crown of pipe or<br />

barrel shall be done with fine material such as earth, moorum, disintegrated<br />

rock or ash according to the availability at site. The remaining filling<br />

shall be done with rock filling of boulders of size not exceeding 150 mm<br />

mixed with fine material as available to fill up the voids, watered, rammed<br />

and compacted.<br />

3.7.5 Filling in Disposal Area<br />

(PCA.774.S034sca1) V.II-D2/S-II : 15


DCPL-K4A02<br />

Surplus material from excavation which is not required for backfilling will be<br />

disposed of in designated disposal areas. The spoils shall not be dumped<br />

haphazardly but should be spread in layers approximately 250 mm thick<br />

when loose and compacted with the help of compacting equipment. In<br />

wide areas rollers will be employed and compaction done to the<br />

satisfaction of the Engineer at the optimum moisture content which shall be<br />

checked and controlled by the Contractor.<br />

In certain cases the Engineer may direct disposal without compaction<br />

which can be done by tipping the spoils from a high bench neatly<br />

maintaining always a proper level and grade of the bench.<br />

3.8.0 Approaches and Fencing<br />

3.9.0 Lighting<br />

The Contractor should provide and maintain proper approaches for<br />

workmen and for inspection. The roads and approaches around the<br />

excavated pits should be kept clear at all times so that there is no hindrance<br />

to the movement of men, material and equipment of various agencies<br />

connected with the Project. Sturdy and elegant fencing is to be provided<br />

around the top edge of the excavation as well as the bottom of the fill at<br />

the surplus disposal area where dumping from a high bench is in progress.<br />

Full scale area lighting is to be provided if night work is permitted or<br />

directed by the Engineer. If no night work is in progress, red warning lights<br />

should be provided at the corners of the excavated pit and the edges of the<br />

fill.<br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA<br />

4.1.0 Excavation<br />

On completion of excavation, the dimensions of the pits will be checked as<br />

per the drawings after the pits are completely dewatered the work will be<br />

accepted after all undercuts have been set right and all over excavations<br />

filled back to required lines, levels and grades by placing ordinary<br />

concrete of 1:4:8 proportion and/or richer and/or by compacted earth, as<br />

directed by the Engineer. The choice of grade of concrete will be a matter<br />

of unfettered discretion of the Engineer. Over excavation of the sides will<br />

be made good by the Contractor while carrying out the back-filling. The<br />

excavation work will be accepted after the above requirements are fulfilled<br />

and all temporary approaches encroaching inside the required dimension of<br />

the excavation have been removed.<br />

4.2.0 Back-filling<br />

(PCA.774.S034sca1) V.II-D2/S-II : 16


DCPL-K4A02<br />

The degree of compaction shall be sufficient to achieve a dry density of not<br />

less than 90% of proctor's dry density at optimum moisture content as<br />

per IS-2720 (Part - VII) or a relative density of 75% as per IS-2720<br />

(Part-XIV) as applicable depending on the nature of back filling material as<br />

stated in clause no. 3.7.2 of this specification. The work of back-filling will<br />

be accepted after the Engineer is satisfied with the degree of compaction<br />

achieved.<br />

5.0.0 INFORMATION TO BE SUBMITTED<br />

5.1.0 With Tender<br />

5.2.0 After Award<br />

Details of Equipment proposed to be used for excavation, back-filling and<br />

compaction have to be submitted along with the tender.<br />

After award of the Contract the successful tenderer shall submit the<br />

following for approval and adoption :<br />

a) The Contractor shall submit a detailed programme of the work<br />

as proposed to be executed giving completion dates of<br />

excavation of the various foundations and the time required for<br />

back-filling and compaction after completing the foundation for<br />

structures.<br />

The programme should show how the excavation and back-filling<br />

quantities will be balanced, minimising temporary stacking of spoils.<br />

It is to be noted that the Engineer even after initial approval of the<br />

programme, may instruct to enhance or retard the progress of<br />

work during the actual execution, in order to match with the<br />

progress of foundations without attracting any claims from the<br />

Contractor. The initial programme being submitted by the<br />

Contractor should have sufficient flexibility to take care of such<br />

reasonable variations.<br />

b) The Contractor shall submit drawings showing details of slopes,<br />

shorings, approaches, sump pits, dewatering lines, fencing etc. for<br />

approval of the Engineer for adoption.<br />

(PCA.774.S034sca1) V.II-D2/S-II : 17


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-III<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

CEMENT CONCRETE (PLAIN & REINFORCED)<br />

(PCA.774.S034sca2)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0 SCOPE V.II-D2/S-III : 1<br />

2.0 GENERAL V.II-D2/S-III : 1<br />

3.0 INSTALLATION V.II-D2/S-III : 11<br />

4.0 SAMPLING AND TESTING V.II-D2/S-III : 45<br />

5.0 ACCEPTANCE CRITERIA V.II-D2/S-III : 47<br />

6.0 LIST OF I.S. CODES AND STANDARDS V.II-D2/S-III : 48<br />

FOR REFERENCE<br />

(PCA.774.S034sca2)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-III<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

CEMENT CONCRETE (PLAIN & REINFORCED)<br />

1.0 SCOPE<br />

1.1 General<br />

This specification covers all the requirements, described hereinafter for<br />

general use of Plain and Reinforced Cement Concrete work in Structures<br />

and locations, cast-in-situ or precast, and shall include all incidental items of<br />

work not shown or specified but reasonably implied or necessary for the<br />

completion of the work.<br />

1.2 This specification shall also apply to the extent it has been referred to or<br />

applicable with the special requirements of structures covered in SCOPE of<br />

IS:456.<br />

1.3 IS:456 shall form a part of this specification and shall be complied with<br />

unless permitted otherwise. For any particular aspect not covered by this<br />

Code, appropriate IS Code, specifications and/or replacement by any<br />

International Code of practice as may be specified by the Engineer shall<br />

be followed. All codes and Standards shall conform to its latest revisions. A<br />

list of IS codes and Standards is enclosed hereinafter for reference.<br />

2.0 GENERAL<br />

2.1 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless<br />

specified shall include but not be limited to the following :-<br />

otherwise<br />

a) Furnish all labour, supervision, services including facilities as may<br />

be required under statutory labour regulations, materials, forms,<br />

templates, supports, scaffolds, approaches, aids, construction<br />

equipment, tools and plants, transportations, etc. required for the<br />

work.<br />

b) Except where it is excluded from the Scope of Contract, Contractor<br />

shall prepare progressively and submit for approval detailed<br />

drawings and Bar Bending Schedules for reinforcement bars showing<br />

the positions and details of spacers, supports, chairs, hangers etc.<br />

c) Design and prepare working drawings of formworks, scaffolds,<br />

supports, etc. and submit for approval.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 1


DCPL-K4A02<br />

d) Submit for approval shop drawings for various inserts, anchors,<br />

anchor bolts, pipe sleeves, embedments, hangers, openings,<br />

frames etc.<br />

e) Submit for approval detailed drawings of supports, templates,<br />

hangers, etc. required for installation of various embedments<br />

like inserts, anchor bolts, pipe sleeves, frames, joint seals, frames,<br />

openings etc.<br />

f) Submit for approval detailed schemes of all operations required for<br />

executing the work, e.g. Material handling, Concrete mixing,<br />

Placement of concrete, Compaction, curing, services, Approaches,<br />

etc.<br />

g) Design and submit for approval concrete mix designs required to<br />

be adopted on the job.<br />

h) Furnish samples and submit for approval results of tests of various<br />

properties of the following :<br />

i) The various ingredients of concrete<br />

ii)<br />

iii)<br />

iv)<br />

Concrete<br />

Embedments<br />

Joint seals<br />

i) Provide all incidental items not shown or specified in particular but<br />

reasonably implied or necessary for successful completion of the<br />

work in accordance with the drawings and specifications.<br />

j) For supply of certain materials normally manufactured by specialist<br />

firms, the Contractor may have to produce, if directed by the<br />

Engineer, a guarantee in approved proforma for satisfactory<br />

performance for a reasonable period as may be specified,<br />

binding both the manufacturers and the Contractor, jointly and<br />

severally.<br />

2.2 Work by Others<br />

No work under this specification will be provided by any agency other<br />

than the Contractor unless specifically mentioned elsewhere in the<br />

contract.<br />

2.3 Information to be submitted by the Tenderer<br />

(PCA.774.S034sca2) V.II-D2/S-III : 2


DCPL-K4A02<br />

2.3.1 With Tender<br />

2.3.2 After Award<br />

The following technical information are required with the tender :<br />

a) Source and arrangement of processing of aggregates proposed to be<br />

adopted.<br />

b) Type of plant and equipment proposed to be used.<br />

c) Names of firms, if any, with which association is sought for to<br />

execute the special items of work in the contract.<br />

d) Types of formwork proposed to be used.<br />

The following information and data including samples where necessary,<br />

shall be submitted by the Contractor progressively during the execution of the<br />

contract.<br />

a) Programme of Execution and Requirement of Materials<br />

The Contractor will submit a Master Programme for completion of<br />

the work giving monthwise requirements of materials for the<br />

procurement.<br />

This Master Programme may have to be reviewed and updated<br />

by the Contractor, quarterly or at more frequent intervals as may be<br />

directed by the Engineer depending on the exigencies of the work.<br />

Detailed day to day programme of every month is to be submitted<br />

by the Contractor before the end of the previous month.<br />

b) Samples<br />

Samples of the following materials and any other materials<br />

proposed to be used, shall be submitted as directed by the<br />

Engineer, in sufficient quantities for approval. Approved samples<br />

will be preserved by the Engineer for future reference. The<br />

approval of the Engineer shall not, in any way, relieve the<br />

Contractor of his responsibility of supplying materials of specified<br />

qualities :<br />

i) Coarse and fine aggregates.<br />

ii)<br />

iii)<br />

Admixtures.<br />

Plywood for Formwork.<br />

iv) Embedded and anchorage materials as may be desired by<br />

the Engineer.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 3


DCPL-K4A02<br />

v) Joint sealing strips and other waterproofing materials.<br />

vi)<br />

vii)<br />

Joint filling compounds.<br />

Foundation quality Rubber Pads.<br />

c) Design Mix<br />

Design mix as per Clauses 2.1 (g) & 3.4 of this specification<br />

giving proportions of the ingredients, sources of aggregates<br />

and cement, along with accompanying test results of trial mixes<br />

as per relevant I.S., is to be submitted to the Engineer for his<br />

approval before it can be used on the works.<br />

d) Detail Drawings and Bar Bending Schedules<br />

Detailed working drawings and Bar Bending Schedules in<br />

accordance with Clause 2.1(b) and 3.16.1 of this specification.<br />

e) Detailed Drawings and Designs of Formworks to be used<br />

Detailed design data and drawings of standard formworks<br />

used as per clause 2.1 (c).<br />

to be<br />

f) Detailed Drawings for Templates & Temporary Supports for<br />

Embedments<br />

As per Clause 2.1 (e).<br />

g) Mill Test Reports for Cement & Reinforcing Steel<br />

h) Inspection Reports<br />

Inspection Reports in respect of Formwork and<br />

Reinforcement and any other item of work as may be desired<br />

by the Engineer in accordance with Clause 2.4 of this specification.<br />

i) Test Reports<br />

Reports of tests of various materials and concrete as required<br />

under Clause 4.0 : SAMPLING & TESTING of this specification.<br />

j) Any other data which may be required as per this<br />

specification.<br />

2.4 Conformity with Design<br />

The Contractor will prepare check lists in approved proforma which will<br />

be called 'Pour Cards'. These Pour Cards will list out all items of work<br />

involved. The Contractor will inform the Engineer, sufficiently in<br />

(PCA.774.S034sca2) V.II-D2/S-III : 4


DCPL-K4A02<br />

advance, whenever any particular pour is ready for concreting. He shall<br />

accord all necessary help and assistance to the Engineer for all<br />

checking required in the pour. On satisfying himself that all details are<br />

in accordance to the drawings and specifications, the Engineer will<br />

give written permission on the same 'Pour Card' allowing the Contractor<br />

to commence placement of concrete. Details of all instructions issued by<br />

the Engineer and the records of compliance by the Contractor,<br />

deviations allowed by the Engineer and any other relevant information will<br />

be written on accompanying sheets attached to the Pour Cards. These<br />

sheets, termed as 'Progress Cards', will be prepared by the Contractor<br />

on approved proforma. The Pour Cards along with accompaniments will<br />

be handed over to the Engineer before starting placement of concrete.<br />

One of the mix designs developed by the Contractor as per the I.S.<br />

Specifications and established to the satisfaction of the Engineer by trial<br />

mixes shall be permitted to be used by the Engineer, the choice<br />

being dictated by the requirements of designs and workability. The methods<br />

of mixing, conveyance, placement, vibration, finishing, curing, protection<br />

and testing of concrete will be as approved or directed by the Engineer.<br />

2.5 Materials to be used<br />

2.5.1 General Requirement<br />

2.5.2 Cement<br />

All materials whether to be incorporated in the work or used temporarily for<br />

the construction shall conform to the relevant IS Specifications unless<br />

stated otherwise and be of best approved quality.<br />

Generally cement shall be 33 grade ordinary Portland Cement conforming<br />

to IS-269 . In special cases any of the following type of cement may be<br />

permitted or directed to be used with prior approval by the Engineer :<br />

a) 43 Grade ordinary Portland Cement conforming to IS-8112<br />

b) 53 Grade ordinary Portland Cement conforming to IS-12269<br />

c) Rapid hardening Portland Cement conforming to IS-8041<br />

d) Portland slag cement conforming to IS-455<br />

e) Portland Pozzolona Cement (flyash based) Conforming to IS- 1489<br />

(Part -1)<br />

f) Portland pozzolona Cement (calcined clay based) conforming to IS-<br />

1489 (Part-2)<br />

g) Hydrophobic Cement conforming to IS-8043<br />

h) Low heat Portland Cement conforming to IS : 12600<br />

(PCA.774.S034sca2) V.II-D2/S-III : 5


2.5.3 Aggregates<br />

i) Sulphate Resisting Portland Cement conforming to IS-12330<br />

DCPL-K4A02<br />

Aggregates shall be natural or crushed gravel or crushed rock and free from<br />

deleterious material. It shall comply with the requirements of IS-383. All fine<br />

and coarse aggregate shall be tested for susceptibility to Alkali Silicate<br />

reaction in a laboratory approved by the Engineer.<br />

a) Coarse Aggregate<br />

Aggregate of sizes ranging between 4.75 mm and 150 mm will be<br />

termed as Coarse Aggregate. Only Coarse Aggregate from<br />

approved quarries and conforming to IS:383 will be allowed to be<br />

used on the works. Aggregates shall be washed to make it free from<br />

deleterious materials, if necessary.<br />

The grading of coarse aggregates by seive analysis shall be as per<br />

IS:383. If by the analysis the deficiency of a particular grain size is<br />

found, which could affect the density of the concrete, the Engineer<br />

may ask the contractor to avoid such quantities of aggregate of<br />

the particular size or and such quantity of aggregate of any<br />

particular size to achieve the required grading as per IS:383.<br />

b) Fine Aggregate<br />

Aggregate smaller than 4.75 mm and within the grading limits and<br />

other requirements set in IS:383 is termed as Fine Aggregate or<br />

Sand. Only Fine Aggregate from approved sources and conforming<br />

to the above IS Specification will be allowed to be used on works.<br />

In certain cases there may be two types of sand , one very fine<br />

and the other very coarse. In such cases , the two types shall be<br />

combined to meet the requirements of a particular zone of IS:383.<br />

In all cases , the preferred zone is Zone - II.<br />

In certain cases crushed stone sand may be added to natural<br />

sand in order to achieve the required grading. Crushed stone sand<br />

alone may be used only with the approval of the Engineer.<br />

2.5.4 Water<br />

Water for use in Concrete shall be clear and free from injurious oils,<br />

acids, alkalis, organic matter, salt, silts or other impurities. Normally<br />

potable water is found to be suitable. Generally, IS:3550 will be followed<br />

for routine tests. Acceptance test for water shall be as per IS:3025, and<br />

Table-1 of IS:456.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 6


2.5.5 Admixture<br />

DCPL-K4A02<br />

In case of doubt regarding development of strength , the suitability of<br />

water for making concrete shall be ascertained by compressive strength and<br />

initial setting time tests as per method of tests in accordance with the<br />

requirements of IS-516 & IS- 4031 respectively. The PH value of water<br />

shall generally be not less than 6.<br />

Only admixture of approved quality will be used when directed or permitted<br />

by the Engineer . The different types of admixtures which may be<br />

necessary to satisfy the concrete mix and the design requirement shall be as<br />

per the following I.S. Standards :<br />

IS : 2645 - Integral cement water proofing compound<br />

IS : 9103 - Indian standard specification for Admixtures for<br />

Concrete or equivalent American Codes (ASTM C494<br />

and ASTM C260 ) or British Codes ( BS 5075 , Part<br />

1 to 3 ) and may be one of the following :<br />

a) Accelerating admixtures :<br />

- Set accelerating admixtures like "Sigunit Powder" or<br />

"Sigunit LN10" .<br />

b) Retarding admixtures :<br />

- Modified ligno sulphonate based set retarding concrete<br />

admixture like , "Plastiment R".<br />

c) Water reducing admixtures :<br />

- Modified sulphonated melamine formaldehyde based water<br />

reducing concrete admixture like, "Sikament" .<br />

d) Air entraining admixtures :<br />

- Modified ligno sulphonate based air entraining concrete<br />

admixture like "FLOMO AEP " or surface - active agents<br />

like "Sika AER".<br />

(PCA.774.S034sca2) V.II-D2/S-III : 7


DCPL-K4A02<br />

e) Water proofing admixtures<br />

- Modified ligno-sulphonate based waterproofing admixture<br />

like "Plastocrete Super".<br />

However, the Contractor shall furnish following technical<br />

information about the admixtures (alongwith the manufacturer's<br />

Catalogue) which he is planning to use in different areas within the<br />

scope of work for the approval of the Engineer :<br />

i) Type of admixture<br />

ii)<br />

Mix proportion & mode of application in concrete/mortar<br />

2.5.6 Reinforcement<br />

iii) Manufacturer's specification & necessary quality assurance<br />

certificates ( mainly on chloride & suphate content , PH value<br />

infra red analysis & solid content. )<br />

Reinforcement shall be as per relevant IS Specification as mentioned in<br />

the Contract/Drawing/Instructions. All bars shall be of tested quality.<br />

2.6.0 Storage of Materials<br />

2.6.1 General<br />

2.6.2 Cement<br />

All materials shall be so stored as to prevent deterioration or intrusion of<br />

foreign matter and to ensure the preservation of their quality and fitness for<br />

the work. Any material, which has deteriorated or has been damaged or is<br />

otherwise considered defective by the Engineer, shall not be used for<br />

concrete and shall be removed from site immediately, failing which, the<br />

Engineer shall be at liberty to get the materials removed and Storage of<br />

materials shall conform to IS:4082.<br />

Sufficient space for storage, with open passages between stacks,<br />

shall be arranged by the Contractor to the satisfaction of the Engineer.<br />

Cement shall be stored off the ground in dry, leak proof, well-ventillated<br />

ware-houses at the works in such a manner as to prevent deterioration due<br />

to moisture or intrusion of foreign matter.<br />

Cement shall be stored in easily countable stacks with consignment<br />

identification marks. Consignments shall be used in the order of their<br />

receipts at site. Sub-standard or partly set cement shall not be used and<br />

shall be removed from the site, with the knowledge of the Engineer, as soon<br />

as it is detected.<br />

Different types of cement shall be clearly marked with the Type and<br />

different types of cement shall not be intermixed.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 8


DCPL-K4A02<br />

2.6.3 Aggregates<br />

Aggregates shall be stored on planks or steel plates or on concrete or<br />

masonry surface. Each size shall be kept separated with wooden or<br />

steel or concrete or masonry bulk-heads or in separate stacks and<br />

sufficient care shall be taken to prevent the material at the edges of the<br />

stock piles from getting intermixed. Stacks of fine and coarse<br />

aggregates shall be kept sufficiently apart with proper arrangement of<br />

drainage. The aggregates shall be stored in easily measurable stacks of<br />

suitable depths as may be directed by the Engineer.<br />

2.6.4 Reinforcement<br />

Reinforcing steel shall be stored consignment-wise and sizewise off the<br />

ground and under cover, if desired by the Engineer. It shall be protected<br />

from rusting, oil, grease and distortions. If necessary, the reinforcing steel<br />

may be coated with cement wash before stacking to prevent scale and<br />

rust. The stacks shall be easily measurable. Steel needed for immediate<br />

use shall only be removed from storage.<br />

2.7 Quality Control<br />

Contractor shall establish and maintain quality control for different items of<br />

work and materials as may be directed by the Engineer to assure<br />

compliance with contract requirements and maintain and submit to the<br />

Engineer records of the same.<br />

The quality control operation shall include but not be limited to the<br />

following items of work :<br />

a) Admixture : Type, quantity, physical and chemical<br />

properties that affect strength, workability<br />

and durability of concrete.<br />

For air entraining admixtures, dosage to be<br />

adjusted to maintain air contents within<br />

desirable limits<br />

b) Aggregate : Physical, chemical and mineralogical<br />

qualities. Grading, moisture content and<br />

impurities.<br />

c) Water : Impurities tests.<br />

d) Cement : Tests to satisfy relevant IS Specifications<br />

(only association with Owner's tests, if the<br />

supply is made by Owner).<br />

(PCA.774.S034sca2) V.II-D2/S-III : 9


DCPL-K4A02<br />

e) Formwork : Material, shapes, dimensions, lines,<br />

elevations, surface finish, adequacy of form,<br />

ties, bracing and shoring and coating.<br />

f) Reinforcement : Shapes, dimensions, length of plices,<br />

clearances, ties and supports. Quality and<br />

requirement of welded splices.<br />

Material tests or certificates to satisfy<br />

relevant IS Specification (If Contractor's<br />

supply).<br />

g) Grades of<br />

concrete : Usage and mix design, testing of all<br />

properties.<br />

h) Batching &<br />

Mixing : Types and capacity of plant, concrete<br />

mixers and transportation equipment.<br />

i) Joints : Locations of joints, water stops and filler<br />

materials. Dimension of joints, quality and<br />

shape of joint material and splices.<br />

j) Embedded<br />

and Anchorage<br />

Items : Material, shape, location, setting.<br />

k) Placing : Preparation, rate of pouring, weather<br />

limitations, time intervals between mixing and<br />

placing and between two successive lifts,<br />

covering over dry or wet surfaces, cleaning<br />

and preparation of surfaces on which<br />

concrete is to be placed, application of<br />

mortar/slurry for proper bond, prevention of<br />

cold joint, types of chutes or conveyors.<br />

l) Compaction : Number of vibrators, their prime mover,<br />

frequency and amplitude of vibration,<br />

diameter and weight of vibrators, duration of<br />

vibration, hand-spreading, rodding and<br />

tamping.<br />

m) Setting of<br />

base &<br />

Beaming<br />

plates : Lines, elevations and bedding mortar.<br />

n) Concrete<br />

(PCA.774.S034sca2) V.II-D2/S-III : 10


DCPL-K4A02<br />

Finishes : Repairs of surface defects, screening,<br />

floating, steel trowelling and brooming, special<br />

finishes.<br />

o) Curing : Methods and length of time.<br />

Copies of records and tests for the items noted above, as well as,<br />

records of corrective action taken shall be submitted to the Engineer for<br />

approval as may be desired.<br />

3.0 INSTALLATION<br />

All installation requirements shall be in accordance with IS:456 and as<br />

supplemented or modified herein or by other best possible standards<br />

where the specific requirements mentioned in this section of the<br />

specification do not cover all the aspects to the full satisfaction of the<br />

Engineer.<br />

3.1 Washing and Screening of Aggregates<br />

3.2 Admixture<br />

Washing and Screening of coarse aggregate shall be carried out to remove<br />

fines , dirts or other deleterious materials.<br />

Washing of fine aggregate shall not be allowed, Fine aggregates shall<br />

be screened only to remove dirt or other deleterious materials.<br />

However , all washing & screening of aggregates shall be carried out by<br />

approved means to ensure compliance with the aggregate specification.<br />

All concrete shall be designed for normal rate of setting and hardening at<br />

normal temperature. Variations in temperature and humidity under different<br />

climatic conditions will affect the rate of setting and hardening, which will,<br />

in turn, affect the workability and quality of the concrete.<br />

Admixtures may be permitted to be used in accordance with IS:456 to<br />

modify the rate of hardening, to improve workability or as an aid to<br />

control concrete quality. The Engineer reserves the right to require<br />

laboratory test or use test data, or other satisfactory reference before<br />

granting approval. The admixture shall be used strictly in accordance<br />

with the manufacturer's directions and/or as directed by the Engineer.<br />

3.3 Grades of Concrete<br />

(PCA.774.S034sca2) V.II-D2/S-III : 11


DCPL-K4A02<br />

Structural concrete shall be of M20/M25/M30 grade and for other part of the<br />

work shall be as shown on the drawing as per grade classification of IS-456.<br />

In case of liquid retaining structures, IS:3370 will be followed.<br />

3.4 Proportioning and Works Control<br />

3.4.1 General<br />

Proportioning of ingredients of concrete shall be made by any of the two<br />

following methods as directed by the Engineer.<br />

a) With preliminary tests by designing the concrete mix. Such concrete<br />

shall be called 'Design Mix Concrete'.<br />

b) without preliminary tests adopting nominal concrete mix. Such<br />

concrete shall be called 'Nominal Mix Concrete'.<br />

As far as possible, design mix concrete shall be used on all concrete works.<br />

Nominal mix concrete, in grades permitted in accordance with IS:456, may<br />

be used if shown on drawings or approved by the Engineer. In all cases the<br />

proportioning of ingredients and works control shall be in accordance with<br />

IS:456 and shall be adopted for use after the Engineer is satisfied<br />

regarding its adequacy and after obtaining his approval in writing.<br />

3.4.2 Mix Design Criteria<br />

Concrete mixes will be designed by the Contractor to achieve the strength,<br />

durability and workability necessary for the job, by the most economical<br />

use of the various ingredients. In general, the design will keep in view<br />

the following considerations :<br />

a) Consistent with the various other requirements of the mix, the<br />

quantity of water should be kept at the lowest possible level.<br />

b) The nominal maximum size of coarse aggregate shall be as large as<br />

possible within the limits specified.<br />

c) The various fractions of coarse and fine aggregates should be<br />

mixed in such a proportion as to produce the best possible combined<br />

internal grading giving the densest and most workable mix.<br />

d) Chemical admixtures may be used to modify the rate of hardening, to<br />

improve workability (maintaining low water - cement ratio) or as<br />

an aid to control concrete quality.<br />

e) The finished concrete should have adequate durability in all<br />

conditions, to withstand satisfactorily the weather and other<br />

destructive agencies which it is expected to be subjected to in actual<br />

service.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 12


DCPL-K4A02<br />

The requirement of adequate structural strength is catered for by<br />

the choice of proper grade of concrete by the Engineer. The<br />

Contractor will strictly abide by the same in his design of concrete mix<br />

installation. Notwithstanding anything mentioned in various tables<br />

given in IS:456 giving specific values and degrees of workability for<br />

different condition of concrete placing, minimum cement content and<br />

maximum water-cement ratio for concrete exposed to sulphate<br />

attack and for concrete to ensure durability under different condition<br />

of exposure, strength requirement for different grades of concrete,<br />

proportion for nominal mix concrete, values given in the tables in<br />

IS:456, shall be followed.<br />

Various trials shall be given by the contractor with specific<br />

cement content on each trial . In some cases, plasticizers and<br />

other admixtures may be necessary to achieve the desired results.<br />

TABLE - I<br />

STRENGTH REQUIREMENT OF CONCRETE<br />

Specified Characteristic Compressive<br />

Grade of concrete<br />

strength of 15 cm Cubes at 28<br />

days conducted in accordance<br />

with IS:516 (All values in<br />

N/Sq.mm)<br />

Note -1:<br />

M - 10 10<br />

M - 15 15<br />

M - 20 20<br />

M - 25 25<br />

M - 30 30<br />

M - 35 35<br />

M - 40 40<br />

Nominal mix concrete of proportions 1:4:8 or 1:3:6 may be used as lean<br />

concrete for simple foundations for masonry walls , below the reinforced<br />

concrete foundations and mass filling . These mixes need not be designed.<br />

TABLE - II<br />

MIX PROPORTIONS (BY WEIGHT) EXPECTED TO GIVE<br />

D<strong>IF</strong>FERENT DEGREES OF WORKABILITY WITH D<strong>IF</strong>FERENT<br />

(PCA.774.S034sca2) V.II-D2/S-III : 13


DCPL-K4A02<br />

WORKABILITY<br />

WATER/CEME<br />

NT/RATIO<br />

VALUES OF WATER - CEMENT RATIO<br />

(FOR GUIDANCE)<br />

CEMENT/TOTAL AGGREGATE RATIOS<br />

RATIO BY WEIGHT OF<br />

CEMENT OF GRAVEL<br />

AGGREGATE<br />

RATIO BY WEIGHT OF<br />

CEMENT OF CRUSHED<br />

STONE AGGREGATE<br />

20 mm 38 mm 20 mm 38 mm<br />

size size size size<br />

Very low 0.4 01:04.8 01:05.3 01:04.5 01:05.0<br />

Slump 0.5 01:07.2 01:07.7 01:06.5 01:07.4<br />

0-25 mm 0.6 01:09.4 1:10 01:07.8 01:09.6<br />

0.7 1:10 1:12 01:08.7 01:10.6<br />

Low 0.4 01:03.9 01:04.5 01:03.5 01:04.0<br />

Slump 0.5 01:05.5 01:06.7 01:05.0 01:05.5<br />

25-50 mm 0.6 01:06.8 01:07.4 01:06.3 01:07.0<br />

0.7 01:08.0 01:08.5 01:07.4 01:08.0<br />

Medium 0.4 01:03.5 01:03.8 01:03.1 01:03.6<br />

Slump 0.5 01:04.8 01:05.7 01:04.2 01:05.0<br />

50-100 mm 0.6 01:06.0 01:07.3 01:05.2 01:06.2<br />

High 0.4 01:03.2 01:03.5 01:02.9 01:03.3<br />

Slump 0.5 01:04.4 01:05.2 01:03.9 01:04.6<br />

100-175 mm 0.6 01:05.4 01:06.7 01:04.7 01:05.7<br />

0.7 01:06.2 01:07.4 01:05.5 01:06.5<br />

NOTE : 1 - Notwithstanding anything mentioned above, the cement/Total<br />

aggregate ratio is not to be increased beyond 1:9.0 without specific<br />

permission of the Engineer.<br />

NOTE : 2 -<br />

NOTE : 3 -<br />

It should be noted that such high aggregate cement ratios will be required<br />

for concretes of very low slump and high water- cement ratios which may<br />

be required to be used in mass concrete work only.<br />

The above figures are for guidance only, the actual cement/aggregate<br />

ratios are to be worked out from the specific gravities of coarse<br />

aggregates and sand being used and from trial mixes.<br />

3.5 Strength Requirements<br />

The strength requirements of both design mix and nominal mix concrete<br />

where ordinary Portland Cement or Portland slag cement is used, shall be<br />

(PCA.774.S034sca2) V.II-D2/S-III : 14


DCPL-K4A02<br />

as per Table-2 of IS:456. All other relevant clauses of IS:456 shall also<br />

apply.<br />

3.6 Minimum Cement Content<br />

The minimum cement content for each grade of concrete shall be as per<br />

Table-5 of IS : 456.<br />

3.7 Water-Cement Ratio<br />

The choice of water-cement ratio in designing a concrete mix will depend on -<br />

a) The requirement of strength.<br />

b) The requirement of durability.<br />

3.7.1 Strength Requirement<br />

In case of 'Design Mix Concrete', the water-cement ratio of such value as to<br />

give acceptable test results as per IS:456, will be selected by trial and error.<br />

The values of water-cement ratios for different grade and mix designs will<br />

have to be established after conducting sufficiently large number of<br />

preliminary tests in the laboratory to the satisfaction of the Engineer.<br />

Frequent checks on test will have to be carried out and the water-cement<br />

ratios will be revised if the tests produce unsatisfactory results.<br />

Notwithstanding anything stated above the Contractor's responsibility to<br />

produce satisfactory test results and to bear all the consequences in<br />

case of default remains unaltered.<br />

In case of nominal mix concrete, proportions for different grades of<br />

concrete is specified in Table-9 of IS:456 and no tests are necessary. The<br />

acceptance test criteria for nominal mix concrete shall be as per IS:456.<br />

3.7.2 Durability Requirement<br />

Table-5 of IS:456 gives the maximum water-cement ratio permissible<br />

from the point of view of durability of concrete subjected to adverse exposure<br />

to weather, sulphate attacks, and contact with harmful chemicals.<br />

Impermeability may also be an important consideration.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 15


3.8 Workability<br />

DCPL-K4A02<br />

Whenever the water-cement ratio dictated by durability consideration is<br />

lower than that required from strength criterion, the former shall be<br />

adopted.<br />

In general the water cement ratio between 0.4 and 0.45 will be desirable to<br />

satisfy the durability requirement and from the consideration of<br />

impermeability of conrete. The contractor may propose lower water<br />

cement ratio as mentioned above by addition of a suitable plasticizer /<br />

super-plasticizer. However the contractor has to propose specifically<br />

along with field trials in the event of lower cement content if found suitable<br />

along with a plasticizer. It will be preferable to use Melamine based<br />

plasticizer.<br />

The degree of workability necessary to allow the concrete to be well<br />

consolidated and to be worked into the corners of formwork and around<br />

the reinforcement and embedments and to give the required surface finish<br />

shall depend on the type and nature of structure and shall be based on<br />

experience and tests. The usual limits of consistency for various types of<br />

structures are given below :<br />

TABLE - III<br />

LIMITS OF CONSISTENCY<br />

Degree of<br />

workability<br />

Slump in mm with<br />

Standard Cone as<br />

per IS:1199<br />

Min. Max.<br />

Use for which concrete<br />

is suitable.<br />

Very low 0 25 Large Mass concrete<br />

structure with heavy<br />

compaction equipment,<br />

roads and like.<br />

Low 25 50 Uncongested wide and<br />

shallow R.C.C. structures.<br />

Medium 50 100 Deep but wide R.C.C.<br />

structures with congestion<br />

or reinforcement and<br />

inserts.<br />

High 100 150 Very narrow and deep<br />

R.C.C. structures with<br />

congestion due to<br />

reinforcement and inserts.<br />

(NOTE : Notwithstanding anything mentioned above, the slump to<br />

be obtained for work in progress shall be as per direction of<br />

the Engineer)<br />

(PCA.774.S034sca2) V.II-D2/S-III : 16


DCPL-K4A02<br />

With the permission of the Engineer, for any grade of concrete, if the<br />

water has to be increased in special cases, cement shall also be<br />

increased proportionately to keep the ratio of water to cement same as<br />

adopted in trial mix design for each grade of concrete. The workability of<br />

concrete shall be checked at frequent intervals by slump tests.<br />

Alternatively where facilities exist or if required by the Engineer, the<br />

compacting factor test in accordance with IS:1199.<br />

3.9 Size of Coarse Aggregates<br />

The maximum size of coarse aggregates for different locations shall be as<br />

follows unless otherwise directed by the Engineer :-<br />

Very narrow space<br />

Reinforced concrete except foundation<br />

Ordinary Plain concrete and Reinforced concrete foundations<br />

Mass concrete<br />

Mass concrete in very large structure<br />

- 12 mm<br />

- 20 mm<br />

- 40 mm<br />

- 80 mm<br />

- 150 mm<br />

Grading of coarse aggregates for a particular size shall conform to relevant<br />

I.S. Codes and shall also be such as to produce a dense concrete of<br />

the specified proportions, strength and consistency that will work readily<br />

into position without segregation.<br />

Coarse aggregate will normally be separated into the following sizes and<br />

stacked separately in properly designed stockpiles :<br />

150 mm to 80 mm, 80 mm to 40 mm, 40 mm to 20 mm and 20 mm to 5<br />

mm. In certain cases it may be necessary to further split the 20 mm to 5<br />

mm fraction into 20 mm to 10 mm and 10 mm to 5 mm fractions.<br />

This separation of aggregates in different size fractions is necessary<br />

so that they may be remixed in the desired proportion to arrive at a correct<br />

internal grading to produce the best mix.<br />

3.10 Mixing of Concrete<br />

Concrete shall always be mixed in mechanical mixer unless specifically<br />

approved by the Engineer for concrete to be used in unimportant out<br />

of the way locations in small quantities. Water shall not normally be<br />

charged into the drum of the mixer until all the cement and aggregates<br />

constituting the batch are already in the drum and mixed for at least one<br />

minute. Mixing of each batch shall be continued until there is a uniform<br />

distribution of the materials and the mass is uniform in colour and<br />

consistency, but in no case shall mixing be done for less than 2 (two)<br />

minutes and at least 40 (forty) revolutions after all the materials and water<br />

(PCA.774.S034sca2) V.II-D2/S-III : 17


DCPL-K4A02<br />

are in the drum. When absorbent aggregates are used or when the mix is<br />

very dry, the mixing time shall be extended as may be directed by the<br />

Engineer. Mixers shall not be loaded above their rated capacity as this<br />

prevents thorough mixing.<br />

The entire contents of the drum shall be discharged before the<br />

ingredients for the next batch are fed into the drum. No partly set or<br />

remixed or excessively wet concrete shall be used. Such concrete shall<br />

be immediately removed from site. Each time the work stops, the mixer<br />

shall be thoroughly cleaned & when the next mixing commences, the first<br />

batch shall have 10% additional cement to allow for loss in the drum.<br />

Regular checks on mixer efficiency shall be carried out as directed by the<br />

Engineer as per IS:4634 on all mixers employed at site. Only those mixers<br />

whose efficiencies are within the tolerances specified in IS:1791 will be<br />

allowed to be employed.<br />

Ingradients for design mix concrete shall be measured by wieght. For small<br />

jobs portable swing weigh Bachers conforming to IS:2722 may be used.<br />

Batching plant conforming to IS:4925 shall be used for large jobs. The<br />

accuracy of the measuring equipment shall be within + 2% of the quantity<br />

of Cement , water or total aggregates being measured and within + 5% of<br />

the quantity of any admixture being used . The batching equipment shall be<br />

fitted with an accurate mechanism for weighing separately the cement,<br />

fine aggregate and coarse aggregate. Water may be measured by volume<br />

or by weight. All measuring equipment should be maintained in a clean<br />

serviceable condition, and their accuracy shall be checked periodically.<br />

Mechanical / electrical control shall be provided on the mixing equipment<br />

to ensure the batch cannot be discharged until approved mixing time has<br />

elapsed and the entire batch shall be discharged before the mixer is<br />

recharged.<br />

Where admixtures are employed, separate containers & measuring<br />

devices shall be used.<br />

For minor concreting works, batching by volume according to specific<br />

weight may be permitted by the Engineer. In that case the whole bags of<br />

cement shall be used and gauge boxes used for measuring aggregates.<br />

When hand mixing is permitted by the Engineer, it shall be carried out on a<br />

water-tight platform and care shall be taken to ensure that mixing is<br />

continued until the mass is uniform in colour and consistency. In case of<br />

hand-mixing, 10% extra cement shall be added to each batch.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 18


DCPL-K4A02<br />

3.11 Conveying Concrete<br />

Concrete shall be handled and conveyed from the place of mixing to the<br />

place of laying as rapidly as practicable by approved means and placed and<br />

compacted in the final position before the initial setting of the cement<br />

starts. Concrete should be conveyed in such a way as will prevent<br />

segregation or loss of any of the ingre- dients. For long distance haulage,<br />

agitator cars of approved design will be used. If, inspite of all<br />

precautions, segregation does occur during transport, the concrete shall<br />

be properly re-mixed before placement. During very hot or cold weather,<br />

if directed by the Engineer, concrete shall be transported in deep<br />

containers which will reduce the rate of loss of water by evaporation or<br />

loss of heat. If necessary, the container may have to be covered and<br />

insulated. Conveying equipments for concrete shall be well<br />

maintained and thoroughly cleaned before commencement of concrete<br />

mixing. Such equipments shall be kept free from set concrete.<br />

3.12 Placing and Compacting Concrete<br />

Where specifically covered, the relevant I.S. Code will be followed for the<br />

procedure of surface preparation, placement, consolidation, curing,<br />

finishes, repairs and maintenance of concrete. If, however, there is no<br />

specific provision in the relevant I.S. Code for any particular aspect of<br />

work, any other standard Code of practice, as may be specified by the<br />

Engineer, will be adopted. Concrete may have to be placed against the<br />

following types of surfaces :<br />

a) Earth foundation<br />

b) Rock foundation<br />

c) Formwork<br />

d) Construction joint in concrete or masonry<br />

The surface on or against which concrete is to be placed has to be cleaned<br />

thoroughly. Rock or old construction joint has to be roughened by wire<br />

brushing, chipping, sand blasting or any other approved means for proper<br />

bond. All cuttings, dirt, oil, foreign and deleterious material, laitance, etc.<br />

are to be removed by air water jetting or water at high pressure. All<br />

excavated areas for foundations, ring beams, plinths, pile caps etc. shall<br />

be rammed & consolidated properly before blinding with nominal mix<br />

plain concrete, as per drawing and / or direction of the Engineer and<br />

shall be allowed to cure prior to setting out steel fixing, shuttering and<br />

concrete pouring for the main structural element.<br />

Formwork, reinforcement, preparation of surface, embedments, joint<br />

seals etc., shall be approved in writing by the Engineer before concrete is<br />

placed. As far as possible, concrete shall be placed in the formwork<br />

by means approved by the Engineer and shall not be dropped from a height<br />

(PCA.774.S034sca2) V.II-D2/S-III : 19


DCPL-K4A02<br />

or handled in a manner which may cause segregation. Any drop over 1500<br />

mm shall have to be approved by the Engineer.<br />

Rock foundation or construction joint will be kept moist for at least 72 hours<br />

prior to placement. Concrete will be placed always against moist surface<br />

but never on pools of water. In case the foundation cannot be<br />

dewatered completely, special procedure and precaution, as directed by the<br />

Engineer will have to be adopted.<br />

Formwork will be cleaned thoroughly and smeared lightly with form oil or<br />

grease of approved quality just prior to placement.<br />

A layer of mortar of thickness 12 mm of the same or less w/c ratio and the<br />

same proportion as that of the concrete being placed and cement slurry<br />

will be spread thoroughly on the rock foundation or construction joint just<br />

prior to placement of concrete. The cost of application of such cement<br />

slurry and mortar will be deemed to be included.<br />

After concrete has been placed, it shall be spread, if necessary and<br />

thoroughly compacted by approved mechanical vibration to maximum<br />

subsidence without segregation and thoroughly worked around<br />

shape. Vibrators shall not be used for pushing concrete into adjoining<br />

areas. Vibrators must be operated by experienced workmen and the<br />

work carried out as per relevant IS Code of Practice. In thin members<br />

with heavy congestion of reinforcement or other embedments, where<br />

effective use of internal vibrator is, in the opinion of the Engineer,<br />

doubtful, in addition to immersion vibrators the contractor may have to<br />

employ form vibrators conforming to IS:4656. For slabs and other<br />

similar structures, the contractor will additionally employ screed<br />

vibrator as per IS:2506. Hand tamping may be allowed in rare cases,<br />

subject to the approval of the Engineer. Care must be taken to ensure<br />

that the inserts, fixtures, reinforcement and formwork are not displaced or<br />

distorted during placing and consolidation of concrete.<br />

The rate of placement of concrete shall be such that no cold joint is formed<br />

and fresh concrete is placed always against green concrete which is still<br />

plastic and workable. No concrete shall be placed in open, during rains.<br />

During rainy season, no placement in the open is to be attempted unless<br />

sufficient tarpaulins or other similar protective arrangement for completely<br />

covering the still green concrete from rain is kept at the site of placement.<br />

If there has been any sign of washing of cement and sand, the entire<br />

affected concrete shall be removed immediately. Suitable precautions<br />

shall be taken in advance to guard against rains before leaving the fresh<br />

concrete unattended. No accumulation of water shall be permitted on or<br />

around freshly laid concrete.<br />

The size of the concrete pours must be carefully considered prior to<br />

commencement to ensure the structural elements are poured in on<br />

contineous shift to avoid cold joints.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 20


DCPL-K4A02<br />

Slabs, beams and similar members shall be poured in one operation, unless<br />

otherwise instructed by the Engineer. Moulding, throating, drip course, etc.,<br />

shall be poured as shown on the drawings or as directed by the Engineer.<br />

Holes shall be provided and bolts, sleeves, anchors, fastenings or other<br />

fixtures shall be embedded in concrete as shown on the drawings or as<br />

directed by the Engineer. Any deviation therefrom shall be set right by the<br />

Contractor as instructed by the Engineer.<br />

In case the forms or supports get displaced during or immediately after<br />

the placement and bring the concrete surface out of alignment beyond<br />

tolerance limits, the Engineer may direct to remove the portion and<br />

reconstruct or repair the same.<br />

The Engineer shall decide upon the time interval between two placements of<br />

concrete of different ages coming in contact with each other, taking in<br />

consideration the degree of maturity of the older concrete, shrinkage,<br />

heat dissipation and the ability of the older concrete to withstand the load<br />

imposed upon it by the fresh placement.<br />

Once the concrete is deposited, consolidated and finished in its final<br />

position, it shall not be distributed.<br />

3.13 Construction Joints and Cold Joints<br />

3.13.1 Construction Joints<br />

It is always desirable to complete any concrete structure by continuous<br />

pouring in one operation. However, due to practical limitation of methods<br />

and equipment and certain design considerations, construction joints<br />

are formed by discontinuing concrete at certain predetermined stages. These<br />

joints will be formed in a manner specified in the drawings/ Instruction.<br />

Vertical construction joints will be made with rigid stop-board forms having<br />

slots for allowing passage of reinforcement rods and any other<br />

embedments and fixtures that may be shown. Next stage concrete shall be<br />

placed against construction joint as per clause 3.12. For water retaining<br />

structures and leak-proof buildings suitable approved water bars will be<br />

installed at the construction joints.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 21


DCPL-K4A02<br />

3.13.2 Cold Joint<br />

Where the location of the joints are not specified, it will be in accordance<br />

with the following :<br />

a) In a column, the joint shall be formed 75 mm below the lowest soffit<br />

of the beam framing into it.<br />

b) Concrete in a beam shall preferably be placed without a joint, but<br />

if provision of a joint is unavoidable, the joint shall be vertical and<br />

within the middle third of the span.<br />

c) A joint in a suspended floor slab shall be vertical and within the<br />

middle third of the span and at right angles to the principal<br />

reinforcement.<br />

d) Feather-edges in concrete shall be avoided while forming a joint.<br />

e) A construction joint should preferably be placed in a low-stress zone<br />

and at right angles to the direction of the principal stress.<br />

f) In case the Contractor proposes to have a construction joint<br />

anywhere to facilitate his work, the proposal should be sub-mitted<br />

well in advance to the Engineer for study and approval without<br />

which no construction joint will be allowed.<br />

An advancing face of a concrete pour, which could not be covered by fresh<br />

concrete before expiry of initial setting time (due to an unscheduled stoppage<br />

or delay on account of breakdown in plant, inclement weather, low rate of<br />

placement or any other reason), is called a cold joint. The Contractor should<br />

always remain vigilant to avoid cold joints.<br />

If, however, a cold joint is formed due to unavoidable reasons, the<br />

following procedure shall be adopted for treating it :<br />

a) If the concrete is so green that it can be removed manually and if<br />

vibrators can penetrate the surface without much effort, fresh<br />

concrete can be placed directly against the old surface. The old<br />

concrete should be covered by fresh concrete as quickly as<br />

possible and the joint thoroughly and systemetically vibrated.<br />

b) In case concrete has hardened a bit more than (a) but can still be<br />

easily removed by a light hand pick, the surface will be raked<br />

thoroughly and the loose concrete removed completely without<br />

disturbing the rest of the concrete in depth. A rich mortar layer<br />

12 mm in thickness, will be placed on the cold joint fresh concrete<br />

shall be placed on the mortar layer and the joint will be thoroughly<br />

and systematically vibrated penetrating the vibrator deep into the old<br />

layer of concrete.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 22


DCPL-K4A02<br />

c) In case the concrete at the joint has become so stiff that it cannot<br />

be remoulded and mortar or slurry does not rise inspite of<br />

extensive vibration, the joint will be left to harden for at least 12 - 24<br />

hrs. It will then be treated as a regular construction joint, after<br />

cutting the concrete to required shape and preparing the<br />

surface as described under clause 3.12.<br />

3.14 Repairs, Finishes and Treatment of Concrete surfaces<br />

3.14.1 Adequate and sound concrete surfaces, whether formed or unformed, can<br />

be obtained by employing a concrete mix of proper design, competent<br />

formwork, appropriate methods of handling, placing and consolidation by<br />

experienced workmen.<br />

Unsound concrete resulting from improper mix design, incompetent<br />

methods, equipment and formwork, poor workmanship and protection will<br />

not be accepted and will have to be dismantled, removed and replaced by<br />

sound concrete. The Engineer may, at his sole discretion, allow to retain<br />

concrete with minor defects provided the Contractor is able to repair it by<br />

approved methods. All concrete work shall be inspected by the<br />

Contractor immediately after the forms are removed and he will promptly<br />

report occurence of any defects to the Engineer. All repair works will be<br />

carried out as per the instructions and in the presence of the Engineer or<br />

his representative. Generally, repair work will consist of any or all of the<br />

following operations :<br />

a) Sack rubbing with mortar and stoning with carborundum stone.<br />

b) Cutting away the defective concrete to the required depth and shape.<br />

c) Cleaning of reinforcement and embedments. It may be necessary to<br />

provide an anti-corrosive coating on the inforcement.<br />

d) Roughening by sand blasting or chipping.<br />

e) Installing additional reinforcement/welded mesh fabric.<br />

f) Dry packing with stiff mortar.<br />

g) Plastering, guniting, shotcreting etc.<br />

h) Placing and compacting concrete in the void left bycutting out<br />

defective concrete.<br />

i) Groting with a cement sand slurry of 1:1 mix.<br />

j) Repairing with a suitable mortar either cement or resin modified<br />

mortar.<br />

k) Polyer modified patching and adhesive repair mortar for beams &<br />

columns.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 23


DCPL-K4A02<br />

3.14.2 Finishing Unformed Surface<br />

A few typical and common cases of treatment of concrete surface are cited<br />

below :<br />

a) Floor<br />

Whenever a non-integral floor finish is indicated, the surface of<br />

reinforcement concrete slab shall be struck off at the specified levels<br />

and slopes and shall be finished with a wooden float fairly smooth<br />

removing all laitance. No overtrowelling, to obtain a very smooth<br />

surface, shall be done as it will prevent adequate bond with the<br />

subsequent finish. If desired by the Engineer, the surface shall be<br />

scored and marked to provide better bond.<br />

Where monolithic finish is specified or required, concrete shall be<br />

compacted and struck off at the specified levels and slopes with<br />

a screed, preferably a vibrating type and then floated with a wooden<br />

float. Steel trowelling by hand or by rotary power float is then<br />

started after the moisture film and shine have disappeared from the<br />

surface and after the concrete has hardened enough to prevent<br />

excess of fines and water to rise to the surface but not hard enough<br />

to prevent proper finishing of aberrations. Steel trowelling properly<br />

done will flatten and smoothen sandy surface left by wooden floats<br />

and produce a dense surface free from blemishes, ripples and trowel<br />

marks. A fine textured surface that is not slick and can be used where<br />

there is likelihood of spillage of oil or water can be obtained by<br />

trowelling the surface lightly with a circular motion after initial<br />

trowelling keeping the steel trowel flat on the surface.<br />

To provide a better grip the Engineer may instruct marking the floor<br />

in a regular geometric pattern after initial trowelling.<br />

b) Beams, Columns & Walls<br />

If on such or any other concrete structure it is intended to apply<br />

plaster or such concrete surfaces against which brickwork or other<br />

allied works are to be built, the Contractor shall hack the surface<br />

adequately as soon as the form is stripped off so that proper bond<br />

can develop. Pattern, adequacy and details of such hacking shall<br />

meet with the approval of the Engineer, who shall be informed to<br />

inspect such surfaces before they are covered up.<br />

3.15 Protection and Curing of concrete<br />

(PCA.774.S034sca2) V.II-D2/S-III : 24


DCPL-K4A02<br />

Newly placed concrete shall be protected by approved means from rain,<br />

sun and wind. Concrete placed below the ground level shall be protected<br />

against contamination from falling earth during and after placing.<br />

Concrete placed in ground containing deleterious substances, shall be<br />

protected from contact with such ground, or with water draining from<br />

such ground, during placing of concrete and for a period of at least three<br />

days or as otherwise instructed by the Engineer. The ground water around<br />

newly poured concrete shall be kept to an approved level by pumping out or<br />

other adequate means of drainage to prevent floatation or flooding. Steps, as<br />

approved by the Engineer, shall be taken to protect immature concrete from<br />

damage by debris, excessive loadings, vibration, abrasion, mixing with earth<br />

or other deleterious materials, etc. that may impair the strength and<br />

durability of the concrete.<br />

As soon as the concrete has hardened sufficiently, it shall be covered either<br />

with sand, polythene sheet, hessian, canvas or similar materials and kept<br />

continuously wet for at least 14 (fourteen) days after final setting. Curing by<br />

continuous sprinkling of water will be allowed if the Engineer is satisfied<br />

with the adequacy of the arrangements made by the Contractor.<br />

If permitted by the Engineer, curing compound like "ANTISOLE (WP)"<br />

may be used for prevention of premature water loss in concrete and<br />

thereby effecting curing of concrete . This type of curing compound shall<br />

be sprayed on newly laid concrete surfaces to form thin film barrier against<br />

premature water loss without disturbances to normal setting action. The<br />

curing compound shall comply with ASTM requirements for acceptance.<br />

The curing compound shall be applied following the final finishing operation<br />

and immediately after disappearance of water sheen from concrete<br />

surface.<br />

It is important not to apply the curing compound when standing water is still<br />

present on concrete.<br />

The contractor shall arrange for the manufacturer's supervision.<br />

The Contractor shall remain extremely vigilant and employ proper equipment<br />

and workmen under able supervision for curing. The Engineer's<br />

decision regarding the adequacy of curing is final. In case any lapse on<br />

the part of the Contractor is noticed by the Engineer, he will inform the<br />

Contractor or his supervisor verbally or in writing to correct the<br />

deficiency in curing. If no satisfactory action is taken by the Contractor<br />

within 3 (three) hours of issuance of such instruction, the Engineer will be<br />

at liberty either to employ sufficient means through any agency to make<br />

good the deficiency and entirely at the discretion of the Engineer.<br />

3.16 Reinforcement<br />

Mild steel round bars, cold twisted and deformed bars as medium tensile<br />

or high yield strength steel, plain hard drawn steel wire fabric etc., will be<br />

(PCA.774.S034sca2) V.II-D2/S-III : 25


DCPL-K4A02<br />

used as reinforcement as per drawings and directions. In an aggressive<br />

environment an anti-corrosive coating on the reinforcement may be provided<br />

as per IS:9077, as shown on the drawing or as directed by the Engineer.<br />

3.16.1 Bar Bending Schedules<br />

3.16.2 Cleaning<br />

The Contractor shall submit to the Engineer for approval Bar Bending<br />

Schedules with working drawings in triplicate, showing clearly the<br />

arrangements proposed by the Contractor to match available stock of<br />

reinforcing steel, within one month of receipt of the Letter of Intent or of<br />

the receipt of the relevant design drawings, whichever is later. Upon<br />

receipt of the Engineer's final approval of the Bar Bending Schedule<br />

and drawings, the Contractor shall submit 6 (six) prints of the final drawings<br />

with one reproducible print after incorporating necessary modifications or<br />

corrections, for final record and distribution. Approval of such detailed<br />

drawings by the Engineer shall not relieve the Contractor of his<br />

responsibility for correctness nor of any of his obligations to meet the other<br />

requirements of the Contract.<br />

All steel for reinforcement shall be free from loose scales, oil, grease,<br />

paint or other harmful matters immediately before placing the concrete.<br />

3.16.3 Cutting & Bending of Reinforcement<br />

Unless otherwise specified, reinforcing steel shall be bent in accordance<br />

with the procedure specified in IS:2502 or as approved by the Engineer.<br />

Bends and shapes shall comply strictly with the dimensions<br />

corresponding to the approved Bar Bending Schedules. Bar Bending<br />

Schedules shall be rechecked by the Contractor before any bending is<br />

done.<br />

No reinforcement shall be bent when already in position in the work, without<br />

approval of the Engineer, whether or not it is partially embedded in<br />

concrete. Bars shall not be straightened in a manner that will injure the<br />

material. Rebending can be done only if approved by the Engineer.<br />

Reinforcing bars above 16 mm diameter shall be bent by machine<br />

producing a gradual and even motion. Bars of 16 mm or below may be<br />

bent by hand. All the bars shall be cold bent unless otherwise<br />

approved. Bending hot at a cherry-red heat(not exceeding 845C) may<br />

be allowed under very exceptional circumstances except for bars whose<br />

strength depends on cold working. Bars bent hot shall not be cooled by<br />

quenching.<br />

Reinforcing bars, whether high yield or mild steel shall be cut using either<br />

hand held shears, guillotines or foot operated pneumatic cutters. Cutting<br />

bars using cold chisels may be allowed by the Engineer at exceptional<br />

cases.<br />

3.16.4 Placing in Position<br />

(PCA.774.S034sca2) V.II-D2/S-III : 26


DCPL-K4A02<br />

3.16.5 Welding<br />

3.16.6 Control<br />

All reinforcements shall be accurately fixed and maintained in position<br />

as shown on the drawings by such approved and adequate means like<br />

mild steel chairs and/or concrete spacer blocks irrespective of whether<br />

such supports are payable or not. Bars intended to be in contact at<br />

crossing points, shall be securely tied together at all such points by No. 20<br />

G annealed soft iron wire. Tack welding of bars should not be done<br />

unless permitted by the Engineer. Binders shall tightly embrace the<br />

bars with which they are intended to be in contact and shall be securely<br />

held. The vertical distance between successive layers of bars shall be<br />

maintained by provision of mild steel spacer bars. They should be spaced<br />

such that the main bars do not sag perceptibly between adjacent spacers.<br />

Before actual placing, the Contractor shall study the drawings thoroughly<br />

and inform the Engineer in case he feels that placement of certain bars is<br />

not possible due to congestion. In such cases he should not start placing<br />

any bar before obtaining clearance from the Engineer.<br />

Normal bond laps in reinforcement may be placed by lap or butt welding<br />

reinforcement bars, if asked by the Engineer, under certain conditions.<br />

The work should be done with suitable safeguards in accordance with<br />

relevant Indian Standards for welding of mild steel bars used in<br />

reinforced concrete construction as per IS:2751 and IS:456. Welded mesh<br />

fabrics conforming to IS:1566 may also be used if specified in the<br />

Schedule of Items and Drawings.<br />

The placing of reinforcements shall be completed well in advance of<br />

concrete pouring. Immediately before pouring, the reinforcement shall be<br />

examined by the Engineer for accuracy of placement and cleanliness.<br />

Necessary corrections as directed by him shall be carried out. Laps and<br />

anchorage lengths of reinforcing bars shall be in accordance with<br />

IS:456, unless otherwise specified. If the bars in a lap are not of the same<br />

diameter, the smaller will guide the lap length. The laps shall be staggered<br />

as far as practicable and as directed by the Engineer. Arrangements for<br />

placing concrete shall be such that reinforcement in position do not have<br />

to bear extra load and get disturbed.<br />

The cover for concrete over the reinforcements shall be as shown on the<br />

approved drawings unless otherwise directed by the Engineer. Where<br />

concrete blocks are used for ensuring the cover and positioning<br />

reinforcement, they shall be made of mortar not leaner than 1 (one) part<br />

cement to 2 (two) parts sand by volume and cured in a pond for at least 14<br />

(fourteen) days. The type, shape, size and location of the concrete blocks<br />

shall be as approved by the Engineer.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 27


DCPL-K4A02<br />

3.17 Cold Weather Concreting<br />

When conditions are such that any operation of concreting may be<br />

expected to be done at 5 Deg.C atmospheric temperature or below the<br />

work shall conform to the requirement of Clause 14 of IS:456 and IS:7861.<br />

(Part. II).<br />

3.18 Hot Weather Concreting<br />

When depositing concrete in very hot weather, the Contractor shall take<br />

all precautions as per IS:7861 (Part-I) and stagger the work to the cooler<br />

parts of the day to ensure that the temperature of wet concrete used in<br />

massive structures does not exceed 40 Deg.C while placing. Positive<br />

temperature control by precooling, postcooling or any other method, if<br />

required, will be specified.<br />

3.19 Concreting under water<br />

3.20 Form Work<br />

3.20.1 General<br />

When it is necessary to deposit concrete under water it shall be done in<br />

accordance with the requirements of clause 14 of IS:456.<br />

Formwork shall conform to the shape, grade, lines, levels and dimension<br />

as shown on the drawings. The contractor shall prepare design & working<br />

drawings for formwork & temporary support system for important structures<br />

and get them approved by the Engineer prior to commencement of actual<br />

work.<br />

Materials used for the formwork inclusive of the supports and centering shall<br />

be capable of withstanding the working load and remain undistorted<br />

throughout the period it is left in service. All supports and scaffolds should<br />

be manufactured from structural or tubular steel except when specifically<br />

permitted otherwise by the Engineer.<br />

The centering shall be true to vertical, rigid and thoroughly braced both<br />

horizontally and diagonally. Rekers are to be used where forms are to<br />

support inclined members. The forms shall be sufficiently strong to<br />

carry without undue deformation, the dead weight of the concrete as a<br />

liquid as well as the working load, in case the Contractor wishes to adopt<br />

any other design criteria, he has to convince the Engineer about its<br />

acceptability before adopting it. Where the concrete is vibrated, the<br />

formwork shall be strong enough to withstand the effects of vibration<br />

without appreciable deflection, bulging, distortion or loosening of its<br />

components. The joints in the formwork shall be sufficiently tight to prevent<br />

any leakage of slurry or mortar.<br />

To achieve the desired rigidity, tie bolts, spacer blocks, tie wires and<br />

clamps as approved by the Engineer shall be used but they must in no way<br />

(PCA.774.S034sca2) V.II-D2/S-III : 28


DCPL-K4A02<br />

impair the strength of concrete or cause stains or marks on the finished<br />

surface. Where there are chances of these fixtures being embedded, only<br />

mild steel or concrete of adequate strength shall be used.<br />

Alternatively, except in case of water retaining structures through rods<br />

and the tie bolts shall be sleeved with PVC conduits to allow retraction of<br />

the ties on removal of the shutters. Where required, the annulus of the<br />

conduits will be filled with expanding mortar to seal the void. Bolts<br />

passing completely through liquid retaining walls/slabs for the purpose of<br />

securing and aligning the formwork shall not be used.<br />

The formwork shall be such as to ensure a smooth uniform surface free<br />

from honeycombs, air bubbles, bulges, fins and other blemishes. Any<br />

blemish or defect found on the surface of the concrete must be brought to<br />

the notice of the Engineer immediately and rectified as directed by him.<br />

For exposed interior and exterior concrete surfaces of beams, columns and<br />

wall, plywood or other approved form shall be thoroughly cleaned and tied<br />

together with approved corrosion- resistant devices. Rigid care shall be<br />

exercised in ensuring that all column forms are plumb and true and<br />

thoroughly cross braced to keep them so. All floor and beam centering<br />

shall be crowned not less than 8 mm in all directions for every 5 metres<br />

span.Unless specifically described on the drawings or elsewhere to the<br />

contrary, bevelled forms 25 mm by 25 mm shall be fixed in the form-work<br />

at all corners to provide chamfering of the finished concrete edges. The<br />

formwork should lap and be secured sufficiently at the lift joints to prevent<br />

bulges and offsets.<br />

Temporary openings for cleaning, inspection and for pouring concrete shall<br />

be provided at the base of vertical forms and at other places, where they<br />

are necessary and as may be directed by the Engineer. The temporary<br />

openings shall be so formed that they can be conveniently closed when<br />

required, during pouring operations without leaving any mark on the<br />

concrete.<br />

3.20.2 Cleaning and Treatment of Forms<br />

All parts of the forms shall be thoroughly cleaned of old concrete, wood<br />

shavings , saw dust, dirt and dust sticking to them before they are fixed in<br />

position. All rubbish, loose concrete, chippings, shavings, saw dust etc.<br />

shall be scrupulously removed from the interior of the forms before<br />

concrete is poured. Compressed air jet and/or water jet along with wire<br />

brushes, brooms etc. shall be used for cleaning. The inside surface of the<br />

formwork shall be treated with approved non-staining oil based shutter<br />

release agent like "Separol/Sika form oil/ Siparol Concentrate" before it is<br />

placed in position. Care shall be taken that oil or other compound does<br />

not come in contact with reinforcing steel or construction joint surfaces.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 29


3.20.3 Design<br />

DCPL-K4A02<br />

They shall not be allowed to accumulate at the bottom of the formwork.<br />

The oiling of the formwork will be inspected just prior to placement of<br />

concrete and redone wherever necessary.<br />

The formwork shall be so designed and erected that the forms for slabs<br />

and the sides of beams, columns and walls are independent of the<br />

soffits of beams and can be removed without any strain to the concrete<br />

already placed or affecting the remaining formwork. Removing any<br />

props or repropping shall not be done except with the specific<br />

approval of the Engineer. If formwork for column is erected for the full<br />

height of the column, one side shall be left open and built up in sections,<br />

as placing of concrete progress. Wedges, spacer bolts, clamps or other<br />

suitable means shall be provided to allow accurate adjustment and<br />

alignment of the formwork and to allow it to be removed gradually<br />

without jarring the concrete.<br />

The design of formwork shall take into account all vertical and lateral loads<br />

that the forms will carry or be subjected to during the construction<br />

process. Besides weight and pressures of reinforced concrete and<br />

weight of the forms themselves, the design shall consider loading due<br />

to unsymmetrical placement of concrete ; impact from dumping of concrete<br />

; movement of men and construction equipment ; wind action and any other<br />

imposed load during construction. The contractor shall assess the<br />

magnitude of vertical live load to be taken for design of formwork duly<br />

considering his method, sequence and rate of pouer of concrete.<br />

However, minimum design vertical live load to be considered shall be 750<br />

kg/sqm excluding weight of concrete.<br />

3.20.4 Inspection of Forms<br />

Casting of Concrete shall start only after the formwork has been inspected<br />

and approved by the Engineer. The concreting shall start as early as<br />

possible within 3 (three) days after the approval of the formwork and<br />

during this period the formwork shall be kept under constant vigilance<br />

against any interference. In case of delay beyond three days, a fresh<br />

approval from the Engineer shall be obtained.<br />

3.20.5 Removal of Forms<br />

Before removing any formwork, the Contractor must notify the Engineer<br />

well in advance to enable him to inspect the concrete if he so desires.<br />

The Contractor shall record on the drawing or in any other approved<br />

(PCA.774.S034sca2) V.II-D2/S-III : 30


DCPL-K4A02<br />

manner, the date on which concrete is placed in each part of the work and<br />

the date on which the formwork is removed therefrom and have this<br />

record checked and countersigned by the Engineer regularly.<br />

The Contractor shall be responsible for the safe removal of the formwork<br />

and any work showing signs of damage through premature removal of<br />

formwork or loading shall be rejected and entirely reconstructed by<br />

him. The Engineer may, however, instruct to postpone the removal of<br />

formwork if he considers it necessary.<br />

Forms for various types of structural components shall not be removed<br />

before the minimum periods specified herein and the removal after the<br />

minimum periods shall also be subject to the approval of the Engineer in<br />

each case.<br />

(PCA.774.S034sca2) V.II-D2/S-III : 31


DCPL-K4A02<br />

TABLE - IV<br />

SCHEDULE OF REMOVAL OF FORM<br />

________________________________________________________________________<br />

Ordinary Portland<br />

Rapid Hardening Portland<br />

Cement Concrete<br />

Cement Concrete<br />

________________________________________________________________________<br />

Part of Temperature Deg.C Temperature Deg.C<br />

Structure<br />

________________________________________________________________________<br />

Above 40 Deg.- 20 Deg.-Below Above 40 Deg.- 20 Deg.- Below<br />

40 Deg.C 20 Deg. 5 Deg. 5 Deg. 40 Deg. 20 Deg. 5 Deg. 5 Deg.<br />

________________________________________________________________________<br />

Days Days Days Days<br />

Days Days Days Days<br />

________________________________________________________________________<br />

a) Columns 2 1 1 Do not 1 1 1 Do not<br />

& Walls remove remove<br />

forms until<br />

forms<br />

b) Beam sides 3 2 3 site cured 2 1 1 until<br />

test speci-<br />

site<br />

c) Slabs, 10 7 8 men develop 7 4 5 cured<br />

125 mm at least test<br />

50% of the specimd)<br />

Slabs over specified en dev-<br />

125 mm 28 days elop at<br />

thick and strength least<br />

soffit of 18 14 16 12 8 9 50% of<br />

minor beams<br />

the specified<br />

28<br />

e) Soffit of 24 21 22 14 10 12 days<br />

main beams<br />

strength<br />

________________________________________________________________________<br />

Wherever exposed surfaces of concrete can be effectively sealed to prevent loss of<br />

water, the periods specified for temperature above 40 Deg.C can be reduced to those of<br />

the temperature range of 20 Deg.C to 40 Deg.C subject to approval of the Engineer.<br />

Construction joints in beams, if required to be provided, will be located within the middle<br />

third of span according to clause 3.13.1(b) of this specification. In such cases,<br />

however, entire span of beam shall have to be kept supported by formwork till its removal<br />

for the portion of beam, cast at a later date, is due and so approved by the Engineer.<br />

If any type of cement other than ordinary portland cement and Rapid<br />

hardening portland cement is used the time of removal or forms shall be<br />

revised as approved by the Engineer such that the strength of this cement<br />

(PCA.774.S034sca3) V.II-D2/S-III : 32


3.20.6 Tolerance<br />

DCPL-K4A02<br />

at the time of removal of forms match with strength of portland cement at<br />

the time of removal of form as mentioned above . This has to be supported<br />

by regular tests.<br />

The formwork shall be so made as to produce a finished concrete, true<br />

to shape, lines, levels, plumb and dimensions as shown on the drawings<br />

subject to the following tolerances unless otherwise specified in this<br />

Specification or drawings or directed by the Engineer :<br />

For<br />

a) Sectional dimension - + 5 mm<br />

b) Plumb - 1 in 1000 of height<br />

c) Levels - + 3 mm before any<br />

deflection has taken place<br />

The tolerance given above are specified for local aberrations in the finished<br />

concrete surface and should not be taken as tolerances for the entire<br />

structure taken as a whole or for the setting and alignment of formwork,<br />

which should be as accurate as possible to the entire satisfaction of the<br />

Engineer. Any error, within the above tolerance limits or any other as may<br />

be specially set up by the Engineer, if noticed in any lift of the structure<br />

after stripping of forms, shall be corrected in the subsequent work to<br />

bring back the surface of the structure to its true alignment.<br />

3.20.7 Re-use of Forms<br />

3.20.8 Classification<br />

Before re-use, all forms shall be thoroughly scraped, cleaned, joints<br />

and planes examined and when necessary repaired, and inside<br />

surface treated as specified hereinbefore. Formwork shall not be<br />

used/re-used if declared unfit or unserviceable by the Engineer.<br />

Generally, the 'ordinary' class formwork shall be used unless otherwise<br />

directed by the Engineer :<br />

a) Ordinary : These shall be used in places where ordinary<br />

surface finish is required and shall be composed of<br />

steel and/or approved good quality partially seasoned<br />

timber.<br />

b) Plywood : These shall be used in exposed surfaces, where<br />

a specially good finish is required and shall be made<br />

of approved brand of heavy quality plywood to<br />

produce a perfectly uniform and smooth surface<br />

conforming to the shape described in the drawing with<br />

(PCA.774.S034sca3) V.II-D2/S-III : 33


DCPL-K4A02<br />

required grain texture on the concrete. Re-use may<br />

only be permitted after special inspection and approval<br />

by the Engineer. He may also permit utilisation of<br />

used plywood for the 'ordinary' class, if it is still in<br />

good condition.<br />

c) Ornamental: These shall be used where ornamental and curved<br />

surface are required and shall be made of selected<br />

best quality well seasoned timbers or of plywood,<br />

which can be shaped correctly.<br />

3.21 Opening, Chases, Grooves, Rebates, Blockouts etc.<br />

The Contractor shall leave all openings, grooves, chases, etc. in<br />

concrete work as shown on the drawings or as specified by the Engineer.<br />

3.22 Anchor Bolts, Anchors, Sleeves, Inserts, Hangers/Conduits/Pipe and Other<br />

misc. Embedded Fixtures. The Contractor shall build into concrete work all<br />

the items noted below and shall embed them partly or fully as directed<br />

and secure the same as may be required. The materials, if required to be<br />

supplied by the Contractor, shall be as specified and be of best quality<br />

available according to relevant Indian Standards of approved manufacture<br />

and to the satisfaction of the Engineer. Exposed surfaces of embedded<br />

materials are to be painted with one coat of approved anti-corrosive paint<br />

and/or bituminous paint. If welding is to be done subsequently on the<br />

exposed surface of embedded material the paint shall be cleaned off the<br />

member to a minimum length of 50 mm beyond each side of the weld line.<br />

Necessary templates, jigs, fixtures, supports etc. shall be used as may be<br />

required or directed by the Engineer. Items to be embedded.<br />

a) Inserts, hangers, anchors, frames around openings, manhole<br />

covers, frames, floor clips, sleeves conduits and pipes.<br />

b) Anchor bolts and plates for machinery, equipment and for structural<br />

steel work.<br />

c) Steel structurals to be left embedded for future extension, special<br />

connection etc.<br />

d) Lugs or plugs for door and window frames occurring in<br />

concrete work.<br />

e) Flashing and jointing in concrete work.<br />

f) Any misc. embedments and fixture as may be required.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 34


DCPL-K4A02<br />

Correct location and alignment, as per drawings/instruction of all these<br />

embedded items shall be entirely the responsibility of the Contractor.<br />

3.23 Expansion and Isolation Joints<br />

3.23.1 General<br />

Expansion and isolation joints in concrete structures shall be provided at<br />

specific places as per details indicated on the drawings. The materials and<br />

types of joints shall be as specified hereinafter. In case of liquid<br />

retaining structures, additional precautions shall be taken to prevent<br />

leakage of liquids as may be specified on the drawings or as directed by the<br />

Engineer. All materials are to be procured from reliable manufacturers and<br />

must have the approval of the Engineer. Where it is the responsibility of the<br />

Contractor to supply the material, the Engineer may demand test<br />

certificates for the materials and/or instruct the Contractor to get them tested<br />

in an approved laboratory. Joints shall be formed true to line, level, shape,<br />

dimension and quality as per drawings and specifications. Prior<br />

approval of the method of forming the joints should be obtained from the<br />

Engineer before starting the work.<br />

3.23.2 Bitumen Board/Expanded Polystyrene Board<br />

a) Bitumen Board<br />

Bitumen impregnated fibre board of approved manufacturer as per<br />

IS:1838 may be used as fillers for expansion joints. It must be<br />

durable and waterproof. It shall be compressible and possess a<br />

high degree of rebound. The dimensions of the board should be<br />

equal to that of the joint being formed. It should, preferably be<br />

manufactured in one piece, matching the dimension of the joint and<br />

not prepared by cutting to size smaller pieces from larger boards at<br />

site. At the exposed end, the joint shall be sealed with approved<br />

sealing compound to a depth of at least 25 mm after application of<br />

an approved primer. The sealing compound and the primer shall<br />

be applied as specified by the manufacturer.<br />

b) Expanded Polystyrene Boards<br />

3.23.3 Joint Sealing Strips<br />

If required, commercial quality\of expanded polystyrene<br />

products commonly used for thermal insulations may also be used<br />

as filler material in expansion joints. The thickness may vary from<br />

12 mm to 50 mm. The material will have to be procured from<br />

reliable manufacturers as approved by the Engineer. The method of<br />

installations will be similar to that recommended by the<br />

manufacturers for fixing on cold storage walls. A coat of Bitumen<br />

paint may have to be applied on the board against which concrete will<br />

be placed.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 35


DCPL-K4A02<br />

Joint sealing strips may be provided at the construction, expansion and<br />

isolation joints as a continuous diaphragm to contain the filler material<br />

and/or to exclude passage of water or any other material into or out of the<br />

structure.<br />

The sealing strips will be non-metallic like rubber or P.V.C.<br />

Sealing strips will not have any longitudinal joint and will be procured and<br />

installed in largest practicable lengths having a minimum number of<br />

transverse joints. The material is to be procured from reputed<br />

manufacturers having proven records of satisfactory supply of joint strips<br />

of similar make and shape for other jobs. The jointing procedure shall be<br />

as per the manufacturer's recommendations, revised if necessary, by the<br />

Engineer. The Contractor is to supply all labour and material for<br />

installation including the material and tools required for jointing, testing,<br />

protection, etc. If desired by the Engineer, joints in rubber seals may have<br />

to be vulcanised.<br />

Non - metallic sealing strips will be normally in Rubber or P.V.C. Rubber<br />

or P.V.C. joint seals can be of shape having any combination of the<br />

following features :<br />

i) Plain<br />

ii)<br />

iii)<br />

iv)<br />

Central bulb<br />

Dumb-bell or flattened ends<br />

Ribbed and Corrugated Wings<br />

v) V shaped<br />

As these types of seals can be easily handled in very large lengths,<br />

transverse joints will be allowed only under unavoidable circumstances<br />

and with the specific approval of the Engineer.<br />

The method of forming these joints, laps etc. shall be as specified by the<br />

Manufacturer and/or as approved by the Engineer taking particular care<br />

to match the central bulbs and the edges accurately.<br />

a) Rubber Sealing Strips<br />

The minimum thickness of Rubber sealing strips shall be 3 mm and<br />

the minimum width 100 mm. The actual size and shape will be as<br />

shown in drawings of items and/or as directed by the Engineer. The<br />

material will be natural rubber and be resistant to corrosion,<br />

abrasion and tear and also to attacks from the acids, alkalis and<br />

(PCA.774.S034sca3) V.II-D2/S-III : 36


DCPL-K4A02<br />

chemicals normally encountered in service. The physical properties<br />

will be generally as follows. The actual requirements may be<br />

slightly different as decided by the Engineer :<br />

Specific Gravity : 1.1 to 1.15<br />

Shore Hardness : 65A to 75A<br />

Tensile Strength : 25 - 30 N/Sq.mm<br />

Maximum Safe<br />

Continuous<br />

Temperature : 75 Deg.C<br />

Ultimate Elongation : Not less than 350%<br />

b) P.V.C. Sealing Strips<br />

The minimum thickness of P.V.C. sealing strips will be 3 mm and<br />

the minimum width 100 mm. The actual size and shape will be as<br />

shown in drawings/schedule of items and/or as directed by the<br />

Engineer. The material should be of good quality Polyvinyl<br />

Chloride highly resistant to tearing, abrasion and corrosion as<br />

well as to chemicals likely to come in contact with during use.<br />

The physical properties will generally be as follows. The actual<br />

requirements, which will be directed by the Engineer, may vary<br />

slightly :<br />

Specific Gravity : 1.3 to 1.35<br />

Shore Hardness : 60A to 80A<br />

Tensile Strength : 10 - 15 N/Sq.mm<br />

Maximum Safe<br />

Continuous<br />

Temperature : 70 Deg.C<br />

Ultimate Elongation : Not less than 275%<br />

(PCA.774.S034sca3) V.II-D2/S-III : 37


DCPL-K4A02<br />

3.23.4 Joint Sealing Compound<br />

When directed, the gap in expansion joints shall be thoroughly cleaned<br />

and bitumen compound laid as per manufacturer's specifications. The<br />

compound to be used shall be of approved manufacture and shall conform<br />

to the requirements of IS:1834.<br />

Alternatively, when directed , the expansion Joints may be filled with joint<br />

sealing compound like "Sikalastic" or approved equivalent and shall be<br />

applied as per manufacturer's specification.<br />

3.23.5 Isolation Joints<br />

3.23.6 Rubber Pad<br />

Strong and tough alkathene or PVC sheet about 1 mm in thickness and as<br />

approved by the Engineer shall be used in isolation joints. It shall be fixed<br />

by an approved adhesive compound on the cleaned surface of the already<br />

set concrete, to cover it fully. Fresh concrete shall be laid against the<br />

sheet, care being taken not to damage the sheet in any way.<br />

Hard foundation quality rubber pads of required thickness and shapes shall<br />

be put below machine or other foundations as shown on the drawings or as<br />

directed by the Engineer. The rubber shall have a unit weight of 1500<br />

Kg/Cu.m, a shore hardness - 65A to 70A and be of best quality of<br />

approved manufacture, durable, capable of absorbing vibration and must be<br />

chemically inert in contact with moist or dry earth or any other deleterious<br />

material expected under normal conditions.<br />

3.24 Grouting under Machinery or Structural Steel Bases<br />

If required, grouting under base plates of machines or structural steel<br />

etc. shall be carried out by the Contractor. In general, the mix shall be 1 (one)<br />

part cement and 1 (one) part sand and just enough water to make it flow as<br />

required. The areas to be grouted shall be cleaned thoroughly with<br />

compressed air jet and/or with water in locations where accumulated<br />

surplus water can be removed. Where directed by the Engineer, 6 mm<br />

down stonechips may have to be used in the mix. Surface to be grouted<br />

shall be kept moist for at least 24 hours in advance. The grout shall be<br />

placed under expert supervision, so that there is no locked up air. Edges<br />

shall be finished properly. If desired by the Engineer, admixtures like<br />

Aluminium powder, 'Ironite' etc. may have to be added with the grout in<br />

proportions to be decided by the Engineer. Admixture, if directed to be<br />

added, will be measured and paid separately.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 38


DCPL-K4A02<br />

Alternatively non-shink , free flow, cementious grout like "Sikagrout 214/<br />

Ankor NSG" or approved equivalent specifically selected for the type<br />

of equipment to be located (vibrating, static etc.) may also be used for<br />

grouting as per manufacturer's specification with necessary approval of the<br />

Engineer.<br />

3.25 Precast Concrete<br />

The Specification for precast concrete will be similar as for the cast-in-place<br />

concrete described herein and as supplemented in this section. All<br />

precast work shall be carried out in a yard made for the purpose.<br />

This yard shall be dry, properly levelled and having a hard and even as well<br />

as well drained surface to prevent excessive uneven settlement due to<br />

softening of soil during casting & curing. If the ground is to be used as a<br />

soffit former of the units, it shall be paved with concrete or masonry and<br />

provided with a layer of plaster (1:2 proportion) with smooth neat cement<br />

finish or a layer of M.S. sheeting. Where directed by the Engineer, casting<br />

will have to be done on suitable vibrating table. The yard, lifting<br />

equipment, curing tank, finished material storage space etc. shall be<br />

designed such that the units are not lifted from the mould before 10 (Ten)<br />

days of curing and can be removed for erection after 28 (twenty eight)<br />

days of curing. The moulds shall preferably be of steel or of timber lined<br />

with G.I. sheet metal and must be rigid enough to prevent distortion during<br />

placing and compaction of the concrete.<br />

Other than normal curing by applying water through spray nozzles or<br />

perforated hose curing by high pressure steam, steam vapour or other<br />

accepted processes may also be employed to accelerate the hardening of<br />

the concrete and to reduce the curing time.<br />

Lifting hooks, where necessary or as directed by the Engineer, shall be<br />

embedded in correct position of the units to facilitate erection, even though<br />

they may not be shown on the drawings, and shall be burnt off and<br />

finished after erection.<br />

All members shall be imdelibly marked with a unique identification<br />

mark on a surface which will not be permanently exposed to show on<br />

which production line they were manufactured , their type , the class of<br />

concrete, the data of casting and if they are of a symmetrical section the<br />

face which will be uppermost when the member is in its correct position<br />

after erection.<br />

Precast concrete units, when ready, shall be transported to site by suitable<br />

means approved by the Engineer. Care shall be taken to ensure that no<br />

damage occurs during transportation. All adjustments, levelling and<br />

(PCA.774.S034sca3) V.II-D2/S-III : 39


DCPL-K4A02<br />

plumbing shall be done as per instructions of the Engineer. The<br />

Contractor shall render all help with instruments, materials and men to the<br />

Engineer for checking the proper erection of the precast units.<br />

After erection and alignment, the joints shall be filled with grout or concrete<br />

as directed by the Engineer. If centerings have to be used for supporting the<br />

precast units, they shall not be removed until the joints have attained<br />

sufficient strength and in no case before 14 (fourteen) days. The joint<br />

between precast roof planks shall be pointed with 1:2 cement : sand mortar<br />

where called for in the drawings.<br />

3.26 Waterproofing of Concrete Structure<br />

3.26.1 General<br />

Waterproofing of concrete structures shall be done by either suitable<br />

extraneous treatments like applying waterproofing paints like "Sikatop Seal"<br />

fixing bitumen felts etc. or internally by suitable design of the concrete<br />

mix, addition of suitable admixtures conforming to IS:2645 and equivalent<br />

American or British codes in the concrete or mortar at the time of mixing<br />

and/or installing water bars at the joints.<br />

The design, material and workmanship shall conform to the relevant I.S.<br />

Codes where applicable. The Engineer's approval of the materials shall be<br />

obtained by the Contractor before procurement. If desired by the<br />

Engineer, test certificates for the materials and samples shall be submitted by<br />

the Contractor. The materials shall be of best quality available indigenously,<br />

fresh clean and suitable for the duties called upon.<br />

3.26.2 Water Bar/Seal/Special Treatment of Construction Joint<br />

Water bearing structures and underground structures may have water<br />

bar/seals installed at the joints. They may be rubber or P.V.C. The<br />

materials and installation will be as described under Clause 3.23.3.<br />

Construction joint should be provided as per clause 3.13.1 with or without<br />

water bar / Seal as shown on the drawing. In case of water bars being<br />

used at the construction Joint, fixing of the same has to be done carefully so<br />

that the water bar is not disturbed during concreting. The construction joint<br />

shall also be treated by any one of the following methods :<br />

Method 1 : A surface retarder in the form of a thixotropic gel shall be<br />

applied on the joint surface of the previous pour in case of joint on the wall<br />

and in case of floor the same shall be applied on the formwork against<br />

which previous pour of concreting shall be done. The retarder may be liquid<br />

or paste form depending on the type of formwork. The formwork shall<br />

be removed within 24 hours after concreting. Within 2 hours of striking of the<br />

formwork the retarder shall be washed off with strong water jet to make<br />

surface rough and clean. Then a rich cement mortar using cement, sand<br />

and aggregates (maximum size 8 mm) along with synthetic rubber<br />

emulsion type water resistant bonding agent shall be applied for a depth of<br />

50 mm just before pouring the next stage of concreting in case of walls.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 40


DCPL-K4A02<br />

The above bonding agent will be mixed with water which will be used for<br />

making the cement mortar. The proportion of mixing of this bonding agent<br />

with water shall be as per manufacturer's specification. In case of floor<br />

joint, however, after washing of retarder a solvent free two component<br />

epoxy resin bonding agent will be used at the joint before the next pour of<br />

concrete. The above bonding agent shall have the following properties<br />

after 28 days :<br />

Compressive strength - 55 to 60 N /Sq. mm<br />

Flexural Strength - 25 to 30 N /Sq. mm.<br />

Tensile strength - 15 N Sq. mm ( approx )<br />

Bonding strength to concrete - 3 N / Sq. mm ( approx )<br />

Bonding strength to steel - 20 N / Sq. mm ( approx)<br />

The whole operation shall be done as per manufacturer's specification.<br />

The contractor shall provide manufacturer's supervision.<br />

Method 2 : One row of threaded nozzles at regular intervals not exceeding<br />

1.5 m centre to centre shall be placed in concrete along the construction<br />

joint during casting. Injection of cement water together with a suitable<br />

waterproof expanding grouting admixture of approved quality shall be<br />

done through the nozzles after the construction joint in walls and slabs.<br />

The injection shall be done under pressure of approximately 2 to 4 Kg/Sq<br />

cm . The nozzles shall be sealed off with suitable admixture after the<br />

injection is over. The whole operation shall be carried out as per<br />

manufacturer's specification and supervision.<br />

3.26.3 Waterproofing Admixtures<br />

The waterproofing admixture for concrete and cement mortar / plaster shall<br />

conform to relevant IS code. The admixture shall not cause decrease of<br />

strength of concrete / plaster at any stage and it is free from chlorides and<br />

sulphates. The admixture shall not affect the setting time by more than 5 %<br />

The maximum permissible dosage of admixture will be 3% (three<br />

percent) by weight of cement but a lower dosage will always be preferred.<br />

The product shall be stored in strong moisture proof packings.<br />

However, in case of important structures where M25 or higher grade<br />

concrete is specified, the use of melamine based, high range water<br />

resistant concrete admixture shall be used to provide a waterproof<br />

concrete around 410 Kg/ Cm.m a melamine based super plasiticizer will be<br />

preferable.<br />

a) In concrete : The approved admixture shall be based on<br />

modified lignosulphonate like "Plastocrete -<br />

(PCA.774.S034sca3) V.II-D2/S-III : 41


DCPL-K4A02<br />

N/Super" or approved equivalent. The method<br />

of application and other details shall conform to<br />

the manufacturer's specification and/or as<br />

instructed by the Engineer. The Contractor<br />

shall have the services of the manufacturer's<br />

supervisor to supervise the work, if desired by<br />

the Engineer.<br />

b) In Plaster : The concrete surface, to be plastered, shall<br />

be hacked to Engineer's satisfaction,<br />

cleaned thoroughly and kept wetted for 24<br />

hours. The plaster shall be in cement sand<br />

mortar mixed in proportion varying from 1:1 to<br />

1:4 by volume along with the approved<br />

waterproofing admixture like "Noleak CP/Sika<br />

Latex" or approved equivalent and laid in<br />

appropriate thickness and in layers not<br />

exceeding 15 mm/layer or as per<br />

manufacturer's specification. The additive shall<br />

be of quality and type approved by the<br />

Engineer. If desired by the Engineer, the<br />

Contractor shall have the work supervised by<br />

the manufacturer's supervisor. On completion,<br />

the plastered surface shall be cured<br />

continuously for a minimum period of 14 days<br />

like concrete.<br />

3.26.4 Bituminous or Tar Coating on External Surface<br />

The surface to be waterproofed shall be rendered absolutely dry, clean and<br />

dust free. The surface shall be sand papered, cleaned and completely coated<br />

with hot coal tar pitch of approved manufacturer and quality as per IS:216<br />

(not heated above 375 Deg.F) using not less than 2 Kg. per Sq.M. or with hot<br />

asphalt i.e., bitumen according to IS:73 (not heated above 400 Deg.F) using<br />

not less than 1.5 kg. per Sq.M. When the first coat has completely dried up<br />

and approved by the Engineer, the second coat shall be applied in the same<br />

manner using not less than 1.25 Kg. per Sq.M. in case of coal tar and 1 Kg.<br />

per Sq.M. in case of asphalt. Immediately after application of the second coat<br />

and before it is dried up, sand shall be spread on the surface to cover it<br />

completely. Sufficient time shall be allowed after spreading of sand before<br />

backfilling is done in order to allow the final coat to dry up completely. In<br />

place of hot application by coal tar / asphalt the coating of the outside<br />

surfaces of walls may be carried out using a ready to use liquid, bituminous<br />

emulsion/rubber protective coating of approved manufacturer.<br />

3.26.5 Protective Coating on Inside Surface<br />

Two coats or cement based to components polymer modified flexible<br />

protective and waterproofing slurry having 1 mm thick for each coat shall be<br />

(PCA.774.S034sca3) V.II-D2/S-III : 42


DCPL-K4A02<br />

applied on the walls/ floor after proper surface preparation as mentioned<br />

above. The slurry shall be applied by brush.<br />

3.26.6 Polyethelene Films : Application in Walls or base of Structures<br />

Waterproof treatment shall be applied as outlined and as per sequence<br />

given hereunder :<br />

i) the concrete surface shall be made smooth with 12 mm cement<br />

plaster 1:6<br />

ii) apply hot bitumen 80/100 grade (IS:73-1961) at the rate of 1.0<br />

Kg/Sq.m minimum<br />

iii)<br />

lay black polyethelene film 250 micron (IS:2508-1977) with cut<br />

back bitumen adhesive in overlaps over hot bitumen surface,<br />

gently pressed, taking care not to puncture the film.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 43


DCPL-K4A02<br />

Alternatively, the overlaps shall be heat sealed by an electric iron<br />

having three parallel sealing bars. A long piece of plywood is to be<br />

placed below the polyethelene film to be heat sealed. On the<br />

plywood a rubber gasket is to be laid to provide a cushion for better<br />

welding of the film. On the rubber padding, a celophane tape is to<br />

be spread and on this the LDPE film, with 100 mm overlap, is to<br />

be stretched. On the overlapped film another celophane tape is to<br />

be placed to prevent the heat sealer from sticking to the LDPE film.<br />

After this, the electric iron is to be pressed on the overlap joint for<br />

sufficient time so as to allow perfect welding. The operation is to be<br />

repeated for subsequent lengths of joints. After heat sealing, the<br />

celophane tape is to be removed and the joints are to be tested for<br />

leaks.<br />

iv)<br />

Lay 100 gm brown craft paper laminated with a layer of straight run<br />

bitumen.<br />

v) Lay hot bitument 80/100 grade (IS:73-1961) at 1.0 Kg/Sq.m<br />

minimum.<br />

vi)<br />

vii)<br />

viii)<br />

ix)<br />

Lay 250 micron polyethelene film as second layer similar to (iii) above.<br />

Lay second layer of 100 gm. brown craft paper laminated similar to<br />

(iv) above.<br />

Apply hot bitumen (straight run grade) to IS:73-1961 at 1.0 Kg/Sq.m<br />

dusted with fine sand.<br />

Protecting with a layer of 75 mm plain cement concrete M-100, or a<br />

layer of brick laid in cement mortar 1:6. In case of wall apply a 12<br />

mm thick plaster as shown on the drawing or a protective brick wall<br />

in 1:6 cement mortar as shown on the drawing.<br />

3.27 Protective coating on Concrete Surface<br />

3.27.1 On Foundation<br />

The outside faces of foundation of important structures will be protected from<br />

adverse effect of soil/ underground water, if shown on drawing or instructed<br />

by the Engineer , by using bitumen emulsion protective coating of<br />

approved manufacturer.<br />

3.28 Waterproofing by Pressure /Chemical Grouting<br />

Where required, waterproofing for underground concrete structure shall<br />

be done by injecting high polymer based non- shrink waterproof grouting<br />

compound through nozzle under pressure as per manufacturer's<br />

recommendation. The pressure during injection shall not be less than 2.5<br />

kg/Sq.cum and the thickness of epoxy resinous emulsion waterproof paint<br />

(to be applied on the external surface of walls/slabs) shall not be less than<br />

700 microns.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 44


DCPL-K4A02<br />

4.0 SAMPLING AND TESTING<br />

4.1 General<br />

4.2 Cement<br />

4.3 Aggregates<br />

4.4 Water<br />

The Contractor shall carry out all sampling and testing in accordance with<br />

the relevant Indian Standards and as supplemented herein for the<br />

following items at his own cost unless otherwise specified in this<br />

specification. The Contractor shall get the specimens tested in a laboratory<br />

approved by the Engineer and submit to the Engineer the test results in<br />

triplicate within 3 (three) days after completion of the test.<br />

Representative samples will be taken from each consignment of cement<br />

received from the manufacturer/supplier for carrying out the tests for<br />

fineness (by hand sieving), setting time and compressive strengths.<br />

Soundness Tests may also be required to be carried out if required by<br />

the Engineer. The tests shall be carried out free of charge by the Owner if<br />

cement is supplied by him. In case the Contractor is directed to arrange<br />

for the supply of cement as per the terms and conditions of the Contract the<br />

tests shall be carried out by him. In case due to any circumstances, the<br />

agency of supply is changed in the middle of the Contract, the party who<br />

bore the original contractual obligation will carry on with the test, free of<br />

charge to the other, till the end of the job. No cement from a particular<br />

consignment/batch will be used on the works unless satisfactory 3 (three)<br />

days and 7 (seven) days test results for compressive strength are known.<br />

The Owner, Engineer and Contractor will jointly associate themselves with<br />

the tests irrespective of whether they are carried out by the Owner or the<br />

Contractor. These tests are of great importance as their results will have a<br />

bearing on the acceptance of concrete or otherwise as per the terms and<br />

conditions of the Contract.<br />

The Contractor shall carry out any or all the tests aggregates as may be<br />

required by the Engineer in accordance with IS:2386 PARTS-I to VIII. The<br />

acceptance criteria of the samples tested shall be in accordance with<br />

the requirements of the relevant Indian Standards.<br />

Sampling and Testing of water being used for concrete works as per<br />

IS:3550 will be carried out by the Contractor at regular intervals and<br />

whenever directed by the Engineer. The final acceptance criteria in case of<br />

doubt will be as per IS:3025 & IS:456.<br />

4.5 Admixture<br />

(PCA.774.S034sca3) V.II-D2/S-III : 45


DCPL-K4A02<br />

4.5.1 Air Entraining Agents (A.E.A)<br />

Initially, before starting to use A.E.A., relationship between the<br />

percentage of air entrained and the cube crushing strength vis-a-vis<br />

quantity of A.E.A. used for all types of concrete will be established by the<br />

Contractor by carrying out sufficiently large number of tests. After then, at<br />

regular intervals and whenever directed by the Engineer, the Contractor will<br />

check up the actual percentages of air entrained and corresponding<br />

crushing strengths to correlate with the earlier test results.<br />

4.5.2 Other Admixtures<br />

4.6 Concrete<br />

Tests for establishing the various properties of any other admixtures which<br />

may be required to be added shall be carried out by the Contractor.<br />

The sampling of concrete, making the test specimens, curing and testing<br />

procedure etc. shall be in accordance with IS:516 and IS:1199 the size of<br />

specimen being 15 cm cubes. Normally, only compression tests shall be<br />

performed but under special circumstances the Engineer may require other<br />

tests to be performed in accordance with IS:516.<br />

Sampling procedure, frequency of sampling and test specimen shall conform<br />

to Clause 14 of IS:456.<br />

To control the consistency of concrete from every mixing plant, slump<br />

tests and/or compacting factor tests in accordance with IS:1199 and as<br />

mentioned in Clause 3.6 of this Specification shall be carried out by the<br />

Contractor every two hours or as directed by the Engineer. Slumps<br />

corresponding to the test specimens shall be recorded for reference.<br />

The acceptance criteria of concrete shall be in accordance with Clause 15<br />

of IS:456.<br />

Concrete work found unsuitable for acceptance shall have to be dismantled<br />

and replacement is to be done as per specification by the Contractor.<br />

No payment for the dismantled concrete, the relevant formwork and<br />

reinforcement, embedded fixtures, etc. wasted in the dismantled portion<br />

shall be made. In the course of dismantling, if any damage is done to the<br />

embedded items or adjacent structures, the same shall be made good to the<br />

satisfaction of the Engineer.<br />

5.0 ACCEPTANCE CRITERIA<br />

5.1 Standard Deviation<br />

(PCA.774.S034sca3) V.II-D2/S-III : 46


DCPL-K4A02<br />

Standard deviation shall be based on test results and determination of<br />

Standard deviation shall conform to clause 16 of IS:456.<br />

5.2 Acceptance Criteria<br />

The strength requirements and acceptance criteria shall conform to<br />

Clause 16 of IS:456.<br />

5.3 Inspection and Core Tests<br />

5.4 Load Test<br />

Inspection of concrete work immediately after stripping the formwork and<br />

core test of structures shall conform to Clause 17 of IS:456.<br />

Load tests of structural members may be required by the Engineer, when<br />

the strength of test specimen results fall below the required strength, as per<br />

'Load Test on Parts of Structures', Clause 17.6 of IS:456. If load testing<br />

is decided by the Engineer, the member under consideration shall be<br />

subjected to a test load equal to 1.25 (one and a quarter) times the<br />

specified live load used for design and this load shall be maintained for a<br />

period of 24 (twenty four) hours before removal. The detailed procedure of<br />

the test is to be decided by the Engineer. Load tests shall not be made until<br />

the structure is at least 56 days old.<br />

If the member shows evident failure, such changes as are necessary to<br />

make the structure adequately strong shall be made by the Contractor.<br />

Alternatively, if permitted under Statutory Regulations and at the discretion of<br />

the Engineer, the structure under test or a portion thereof may be retained<br />

as such without any modification by derating its load bearing capacity,<br />

provided the design criteria allows such derating.<br />

A reinforced concrete beam, floor or roof shall be deemed to have passed<br />

the test if the maximum deflection at the end of 24 hours does not exceed the<br />

deflection given in Clause 17.6 of IS:456.<br />

The entire cost of load testing shall be borne by the Contractor. If a<br />

portion of the structure is found to be unacceptable, it shall be dismantled<br />

and replaced by a new structure as per specification.<br />

If, in the course of dismantling, any damage is done to the embedded items<br />

and or other adjacent structures, the same will be made good by the<br />

Contractor to the satisfaction of the Engineer.<br />

6.0 LIST OF I.S. CODES AND STANDARDS FOR REFERENCE<br />

All work under this specification shall, unless specified otherwise, conform<br />

to the latest revisions and/or replacements of the following or any other<br />

Indian Standard Specifications and Codes of Practice. In case any particular<br />

aspect of work is not specifically covered by Indian Standard Specifications,<br />

(PCA.774.S034sca3) V.II-D2/S-III : 47


DCPL-K4A02<br />

any other standard practice, as may be specified by the Engineer, shall<br />

be followed :-<br />

IS : 73 - Indian Standard Specification for Paving Bitumen<br />

IS : 216 - Indian Standard Specification for Coal Tar Pitch<br />

IS : 269 - Indian Standard Specification for 33 grade Ordinary<br />

Portland Cement<br />

IS : 383 - Indian Standard Specification for Coarse and Fine<br />

Aggregates from Natural Sources for Concrete<br />

IS : 432 - Indian Standard Specification for Mild Steel and<br />

Medium Tensile Steel Bars and Hard Drawn Steel<br />

Wire for concrete Reinforcement - Part 1 & 2<br />

IS : 455 - Indian Standard Specification for Portland Slag<br />

Cement<br />

IS : 456 - Indian Standard Code of Practice for Plain and<br />

Reinforced Concrete<br />

IS : 457 - Indian Standard Code of Practice for General<br />

Construction of Plain and Reinforced Concrete for<br />

Dams and other Massive Structures<br />

IS : 516 - Indian Standard Specification for Methods of Test for<br />

Strength of Concrete<br />

IS : 737 - Indian standard specification for wrought Aluminium<br />

and Aluminium Alloy sheet and strip for general<br />

Engineering purpose. IS : 1199 - Indian Standard<br />

Specification for Methods of Sampling and Analysis<br />

of Concrete<br />

IS : 1200 - Indian Standard Specification for Method of (Part-II)<br />

Measurement Cement Concrete Works.<br />

IS : 1200 - Indian Standard Specification for Method of (Part-V)<br />

Measurement of Formwork<br />

IS : 1322 - Indian Standard Specification for Bitumen Felts for<br />

Waterproofing and Damp-proofing<br />

IS : 1489 - Indian Standard Specification for Portland -<br />

Pozzolona Cement - Part 1 & 2<br />

IS : 1566 - Indian Standard Specification for hard drawn steel<br />

wire fabric for concrete reinforcement.<br />

IS : 1609 - Code of Practice for Laying Damp-proof Treatment<br />

using Bitumen Felts<br />

(PCA.774.S034sca3) V.II-D2/S-III : 48


DCPL-K4A02<br />

IS : 1786 - Indian Standard Specification for high strength<br />

deformed Bars & wires for Concrete Reinforcement<br />

IS : 1791 - Indian Standard Specification for Batch Type<br />

Concrete Mixers<br />

IS : 1834 - Indian standard specification for hot applied sealing<br />

compound for joint in concrete.<br />

IS : 2062 - Steel for general structural purpose.<br />

IS : 2185 - Indian Standard Specification for Hollow and solid /<br />

solid light wt. Cement Concrete Blocks - Part - 1 & 2<br />

IS : 2210 - Indian Standard Specification for Design of<br />

Reinforced Concrete Shell Structures and Folded<br />

Plates<br />

IS : 2386 - Indian Standard Specification for Methods of Test for<br />

Aggregates for Concrete - Part-I to VIII<br />

IS : 2430 - Indian standard specification for method of sampling<br />

of Aggregate for concrete.<br />

IS : 2502 - Indian Standard Code of Practice for Bending and<br />

Fixing of Bars for Concrete Reinforcement<br />

IS : 2505 - Indian Standard Specification for Concrete Vibrators<br />

Immersion Type<br />

IS : 2506 - Indian Standard Specification for Screed Board<br />

Concrete Vibrators<br />

IS : 2514 - Indian Standard Specification for Concrete Vibrating<br />

Tables<br />

IS : 2645 - Integral Cement water proofing compound<br />

IS : 2722 - Indian Standard Specification for Portable Swing<br />

Weigh Batchers for Concrete (Single and Double<br />

Bucket type)<br />

IS : 2751 - Code of Practice for Welding of Mild Steel Bars used<br />

for Reinforced Concrete Construction<br />

IS : 2770 - Indian Standard Specification for Method of Testing<br />

Bond in Reinforced Concrete. Part - 1 : Pull out Test<br />

IS : 3025 - Indian Standard Specification for Methods of<br />

Sampling and Test (Physical and Chemical) for<br />

Water & waste water - art - 1 to 37<br />

IS : 3201 - Indian Standard Specification for Design and<br />

Construction of Precast Concrete Trusses and<br />

purlins.<br />

(PCA.774.S034sca3) V.II-D2/S-III : 49


DCPL-K4A02<br />

IS : 3370 - Indian Standard Specification for Code of Practice for<br />

Concrete Structures for Storage of Liquids Part 1 to 4<br />

IS : 3384 - Indian standard specification for / Bitumen primer for<br />

use in waterproofing and Danp proofing<br />

IS : 3414 - Code of practice for Design and Installation of joints in<br />

Buildings<br />

IS : 3550 - Indian Standard Specification for Method of Test for<br />

Routine Control for Water used in Industry<br />

IS : 3558 - Code of Practice for use of Immersion Vibrators for<br />

Consolidating Concrete<br />

IS : 3696 - Safety Code for Part-1 : Scaffolding and Part 2:<br />

Ladders<br />

IS : 3812 - Indian Standard Specification for Fly Ash for Use as<br />

Pozzolone & Admixture<br />

IS : 4031 - Indian Standard Specification for Method of Tests for<br />

Hydraulic Cement - Part - 1 to 14<br />

IS : 4082 - Indian Standard Specification for Recommendation<br />

on Stacking and Storage of Construction Materials at<br />

site<br />

IS : 4090 - Indian Standard Specification for Design of<br />

Reinforced Concrete Archs<br />

IS : 4634 - Indian Standard Specification for Method of Testing<br />

Performance of Batch-type Concrete Mixers<br />

IS : 4656 - Indian Standard Specification for Form Vibrators for<br />

Concrete<br />

IS : 4925 - Indian Standard Specification for Concrete Batching<br />

and Mixing Plant<br />

IS : 4926 - Indian Standard Specification for Ready Mixed<br />

Concrete<br />

IS : 4990 - Indian Standard Specification for Plywood for<br />

Concrete Shuttering work<br />

IS : 4991 - Indian Standard Specification for Blast Resistant<br />

Design of Structure for Explosion above ground<br />

IS : 4995 - Indian Standard Specification for Design (Part-I of<br />

Reinforced Concrete Bins for the Storage & II) of<br />

Granular and Powdery Materials<br />

(PCA.774.S034sca3) V.II-D2/S-III : 50


DCPL-K4A02<br />

IS : 4998 - Indian Standard Specification for Design of (Part - I)<br />

Reinforced Concrete Chimneys<br />

IS : 5512 - Indian Standard Specification for Flow Table for use<br />

in Tests of Hydraulic Cement and Pozzolanic<br />

Materials<br />

IS : 5513 - Indian Standard Specification for Vicat Apparatus<br />

IS : 5515 - Indian Standard Specification for Compaction Factor<br />

Apparatus<br />

IS : 5751 - Indian Standard Specification for Precast Concrete<br />

Coping Blocks<br />

IS : 5816 - Indian Standard Specification for Method of Test for<br />

Splitting Tensile Strength of Concrete Cylinders<br />

IS : 5891 - Indian Standard Specification for Hand Operated<br />

Concrete Mixers<br />

IS : 6452 - Indian Standard Specification for High Alumina<br />

Cement for Structural Use<br />

IS : 6909 - Indian Standard Specification for Supersulphated<br />

Cement<br />

IS : 6923 - Indian Standard Specification for Method of Test for<br />

performance of Screed Board Concrete Vibrators<br />

IS : 6925 - Indian Standard Specification for Method of Test for<br />

Determination of Water Soluble Chloride in Concrete<br />

Admixtures<br />

IS : 7242 - Indian Standard Specification for Concrete Spreaders<br />

IS : 7246 - Indian Standard Specification for Table Vibrators for<br />

Consolidating Concrete<br />

IS : 7251 - Indian Standard Specification for Concrete Finishers<br />

IS : 7320 - Indian Standard Specification for Concrete Slump<br />

Test Apparatus<br />

IS : 7861 - Indian Standard Specification for (Part-I<br />

Recommended Practice for hot and cold & II)<br />

Weather Concreting<br />

IS : 7969 - Safety Code for Storage and Handling of Building<br />

Materials<br />

IS : 8041 - Indian Standard Specification for Rapid Hardening<br />

Portland cement<br />

(PCA.774.S034sca3) V.II-D2/S-III : 51


DCPL-K4A02<br />

IS : 8043 - Indian standard specification for hydrophobic cement<br />

IS : 8112 - Indian Standard Specification for 43 grade Ordinary<br />

Portland Cement<br />

IS : 8142 - Indian Standard Specification for Determining<br />

Setting time of Concrete by Penetration Resistance<br />

IS : 8989 - Safety Code for Erection of Concrete Framed<br />

Structures<br />

IS : 9013 - Indian Standard Specification for Method of Making,<br />

Curing and Determining Compressive Strength of<br />

Accelerated - cured Concrete Test Specimens<br />

IS : 9077 - Code of Practice for Corrosion Protection of Steel<br />

Rails in RB and RCC Construction<br />

IS : 9103 - Indian Standard Specification for Admixtures for<br />

Concrete.<br />

IS : 9417 - Recommendation for welding cold worked bars for<br />

reinforced concrete construction<br />

IS : 10262 - Recommended Guideline for concrete Mix Design<br />

IS : 12269 - Indian standard specification for 53 gradeordinary<br />

portland cement<br />

IS : 12330 - Indian standard specification for sulplate resting<br />

portland cement<br />

IS : 12600 - Indian standard specification for low heat portland<br />

cement<br />

(PCA.774.S034sca3) V.II-D2/S-III : 52


DCPL-K4A02<br />

VOLUME: II-D/2<br />

SECTION-IV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FABRICATION OF STRUCTURAL STEELWORK<br />

(PCA.774.S034sca4)


DCPL-K4A02<br />

CONTENTS<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-IV : 1<br />

2.0.0 GENERAL V.II-D2/S-IV : 1<br />

3.0.0 WORKMANSHIP V.II-D2/S-IV : 11<br />

4.0.0 INSPECTION, TESTING, ACCEPTANCE V.II-D2/S-IV : 19<br />

CRITERIA AND DELIVERY<br />

5.0.0 INFORMATION TO BE SUBMITTED V.II-D2/S-IV : 24<br />

(PCA.774.S034sca4)


DCPL-K4A02<br />

VOLUME: II-D/2<br />

SECTION-IV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FABRICATION OF STRUCTURAL STEELWORK<br />

1.00 SCOPE<br />

2.00 GENERAL<br />

This specification covers supply of all raw steel materials, fabrication, testing,<br />

painting and delivery to site of structural steelwork including supply of all<br />

consumable stores and bolts, nuts, washers, electrodes and other materials<br />

required for fabrication and field connections of all structural steelwork in<br />

general covered under the scope of the contract. However, for any<br />

special structures such as rail & road bridges, steel chimney, tanks,<br />

transmission towers, furnace structures, etc., the relevant Indian Standard<br />

or IRC specification and Codes of Practices shall be given due<br />

consideration over & above this specification.<br />

2.1.0 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless otherwise<br />

specified elsewhere in the contract, shall include, but not be limited to the<br />

following :<br />

a) Preparation of complete detailed fabrication drawings and erection<br />

marking drawings required for all the structures covered under the<br />

scope of the contract based on contractor’s design drawings<br />

approved by the Owner / Consultants.<br />

b) To submit revised design with calculations and detailed fabrication<br />

drawings in case any substitution of the designed sections are to be<br />

made.<br />

c) To submit design calculations for joints and connections developed<br />

by the contractor along with detailed fabrication drawings.<br />

d) Furnish all materials, labour, tools and plant and all consumables<br />

required for fabrication and supply, all necessary bolts, nuts, washers,<br />

tie rods and welding electrodes for field connections. The field<br />

connection materials supplied by the contractor shall be in<br />

adequate quantity to avoid delay in erection.<br />

e) Furnish shop painting of all fabricated steelwork as per requirements<br />

of this Specification.<br />

f) Suitably mark, bundle and pack for transport all fabricated<br />

materials.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 1


DCPL-K4A02<br />

g) Prepare and furnish detailed Bill of Materials, Drawing Office<br />

Despatch lists, Bolt List and any other list of bought out items<br />

required in connection with the fabrication and erection of the<br />

structural steelwork.<br />

h) Insure, load and transport all fabricated steelwork field connection<br />

materials to site.<br />

2.2.0 Work by others<br />

No work under this specification will be provided for by any agency other<br />

than the contractor, unless specifically mentioned otherwise elsewhere in<br />

the contract.<br />

2.3.0 Codes and standards<br />

All work under this specification shall, unless otherwise specified in the<br />

contract, conform to the requirements of the latest revision and/or<br />

replacements of the following or any other relevant Indian Standard<br />

specifications and codes of practice. In case any particular aspect of the<br />

work is not specifically covered by any Indian Standard Specification, any<br />

other standard practice, as may be specified by the Engineer shall be<br />

followed:-<br />

LIST OF I.S. CODES -<br />

IS Codes<br />

RELEVANT TO FABRICATION OF<br />

STRUCTURAL STEEL WORK<br />

Description<br />

IS : 800 - Code of practice for general construction in steel.<br />

IS : 801 - Code of practice for use of cold formed light gauge<br />

steel structural members in general building<br />

construction.<br />

IS : 806 - Code of practice for use of steel tubes in general<br />

building construction.<br />

IS : 808 - Dimensions for rolled steel beams, channels and angle<br />

sections.<br />

IS : 812 - Glossary of terms relating to welding & cutting of<br />

metals.<br />

IS : 813 - Scheme of symbols for welding.<br />

IS : 814 - Covered electrodes for metal arc welding of carbon and<br />

carbon manganese steel.<br />

IS : 815 - Classification coding of covered electrodes<br />

for metal arc welding of mild steel and low<br />

alloy high tensile steel.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 2


DCPL-K4A02<br />

IS : 816 - Code of practice for use of metal arc welding<br />

for general construction in mild steel.<br />

IS : 817 - Code of practice for training & testing metal<br />

arc welders.<br />

IS : 818 - Code of practice for safety and health<br />

requirements in electric and gas welding and<br />

cutting operations.<br />

IS : 819 - Code of practice for resistance spot welding<br />

for light assemblies in mild steel.<br />

IS : 822 - Code of practice for inspection of welds.<br />

IS : 919 - Recommendations for limits and fits for engineering.<br />

(Part - 1&2)<br />

IS : 1161 - Steel Tubes for structural purposes.<br />

IS : 1182 - Recommended practice for Radiographic Examination<br />

of fushion welded butt joints in steel plates.<br />

IS : 1200 - Method of measurement of steel work and iron work<br />

(Part - 8)<br />

IS : 1239 - Mild steel tubes, tubulars and other wrought steel<br />

(Part - 1&2) fittings<br />

IS : 1363 - Hexagon head bolts, screws and nuts of product<br />

(Part - 1 to 3) grade C.<br />

IS : 1364 - Hexagon head bolts, screws and nuts of product<br />

(Part - 1 to 5) grade A & B.<br />

IS : 1365 - Slotted counter sunk head screws (dia. 1.6 to 20 mm)<br />

IS : 1367 - Technical supply conditions for threaded steel<br />

(Part - 1 to 18) fasteners.<br />

IS : 1608 - Method for tensile testing of steel products.<br />

IS : 1730 - Dimensions for steel plate, sheet and strip for structural<br />

and general engineering purposes.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 3


DCPL-K4A02<br />

IS : 1852 - Rolling and cutting tolerances for hot-rolled steel<br />

product.<br />

IS : 1977 - Structural steel (Ordinary quality)<br />

IS : 2016 - Plain washer<br />

IS : 2062 - Steel for general structural purposes.<br />

IS : 2629 - Recommended practice for hot-dip galvanising of<br />

iron and steel.<br />

IS : 2633 - Method for testing uniformity of coating on zinc coated<br />

articles.<br />

IS : 3644 - Code of practice for ultrasonic pulse echo testing by<br />

contact and immersion method.<br />

IS : 3757 - High Strength Structural Bolt<br />

IS : 4000 - High strength bolts in steel structure<br />

IS : 4759 - Specifications for hot-dip zinc coatings on structural<br />

steel and other allied products.<br />

IS : 4923 - Hollow steel sections for structural use.<br />

IS : 5334 - Code of practice for magnetic particle flaw detection of<br />

weld.<br />

IS : 5369 - General requirements for plain washers and lock<br />

washer.<br />

IS : 6005 - Code of practice for phosphating of iron and steel.<br />

IS : 6649 - Specification for hardened and tempered washers for<br />

high strength structural bolts and nuts.<br />

IS : 6623 - Specification for high strength structural nuts.<br />

IS : 7215 - Tolerances for fabrication of steel structures.<br />

IS : 7280 - Bare wire electrode for submerged arc welding.<br />

IS : 8500 - Structural steel micro alloyed (medium & high strength<br />

quality).<br />

IS : 8629 - Code of practice for protection of iron and (Part - I to<br />

III) steel structures from atmospheric corrosion.<br />

IS : 9595 - Recommendation for metal arc welding of carbon<br />

manganese steels.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 4


DCPL-K4A02<br />

PAINTING<br />

IS : 117 - Specification for ready mixed paint, brushing, finishing,<br />

exterior, semi-gloss, for general purposes.<br />

IS : 128 - Specification for ready mixed paint, brushing, finishing,<br />

semi-gloss for general purposes, black.<br />

IS : 1477 - Code of practice for painting of ferrons metal<br />

(Part - I & II) in building.<br />

IS : 2074 - Ready mixed paint, air-drying red-oxide zinc chrome<br />

priming.<br />

IS : 2339 - Specification for aluminium paints for general purposes<br />

in dual container.<br />

IS : 2932 - Specification for enamel, synthetic exterior type - I.<br />

IS : 2933 - Specification for enamel, synthetic exterior type - II.<br />

2.4.0 Conformity with Designs<br />

The contractor shall design all connections, supply and fabricate all<br />

steelwork and furnish all connection materials in accordance with the<br />

approved drawings and/or as instructed by the Engineer keeping in view<br />

the maximum utilization of the available sizes and sections of steel<br />

materials. The methods of painting, marking, packing and delivery of all<br />

fabricated materials shall be in accordance with the provisions of the<br />

contract and/or as approved by the Engineer. Provision of all relevant Indian<br />

Standard Specifications and Codes of Practice shall be followed unless<br />

otherwise specified in the contract.<br />

2.5.0 Materials to be used<br />

2.5.1 General<br />

All steel materials shall be free from all imperfections, mill scales, slag<br />

intrusions, laminations, pittings, rusts etc. that may impair their strength,<br />

durability and appearance. All materials shall be of tested quality only unless<br />

otherwise permitted by the Engineer and/or Consultant. If desired by the<br />

Engineer, Test Certificates of materials supplied by the contractor in<br />

respect of each consignment shall be submitted in triplicate. Whenever the<br />

materials are required to be used from unidentified stocks, if permitted by<br />

the Engineer, a random sample shall be tested at an approved laboratory<br />

from each lot of 50 tonnes or less of any particular section.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 5


2.5.2 Steel<br />

2.5.3 Electrodes<br />

DCPL-K4A02<br />

The arc welding electrodes shall conform to the relevant Indian Standard<br />

Codes of Practice and Specifications and shall be of heavily coated type and<br />

the thickness of the coating shall be uniform and concentric. With each<br />

container of electrodes, the manufacturer shall furnish instructions giving<br />

recommended voltage and ampereage ( Polarity in case of D.C. supply ) for<br />

which the electrodes are suitable.<br />

All steel materials to be used in construction within the purview of this<br />

specification shall comply with any of the following Indian Standard<br />

Specifications as may be applicable :<br />

1) IS : 801 - Cold formed light gauge steel structural member.<br />

2) IS : 806 - Steel tubes in general building construction.<br />

3) IS : 1161 - Steel tubes for structural purpose.<br />

4) IS : 1977 - Structural steel (Ordinary quality)<br />

St-42-0<br />

5) IS : 2062 - Steel for general structural purpose<br />

6) IS : 8500 - Structural steel-microalloyed (Ordinary & high strength<br />

quality)<br />

In case of imported steel materials being used, these shall conform to<br />

specifications equivalent to any of the above as may be applicable.<br />

All electrodes to be used under the Contract shall comply with any of the<br />

following Indian Standard Specifications as may be applicable :<br />

2.5.4 Bolts and Nuts<br />

1) IS : 814 - Covered electrodes for metal arc welding structural<br />

steel<br />

2) IS : 815 - Classification and coding of covered electrodes for<br />

metal arc welding of mild steel and low alloy high<br />

tensile steel.<br />

3) IS : 7280 - Base wire electrode for submerged arc welding.<br />

All bolts and nuts shall conform to the requirements of Indian Standard<br />

Specification IS:1367 - Technical Supply Conditions for Threaded<br />

Fasteners.<br />

Materials for Bolts and nuts under the purview of this contract shall<br />

comply with any of the following Indian Standard Specifications as may<br />

be applicable.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 6


2.5.5 Washers<br />

2.5.6 Paints<br />

DCPL-K4A02<br />

a) Mild Steel : All mild steel for bolts and nuts when tested in<br />

accordance with the following Indian Standard<br />

Specification shall have a tensile strength of not less<br />

than 44 Kg/mm 2 and a minimum elongation of 23 per<br />

cent on a gauge length of 5.6 /A, where 'A' is the<br />

cross sectional area of the test specimen : -<br />

1) IS:1367 - Technical supply conditions for<br />

threaded fasteners.<br />

2) IS:1608 - Method for tensile testing of<br />

steel other than sheet, strip, wire<br />

and tube.<br />

b) High<br />

Tensile<br />

Steel : The material used for the manufacture of high<br />

tensile steel bolts and nuts shall have the mechanical<br />

properties appropriate to the particular class of steel<br />

as set out in IS:1367 or as approved by the Engineer.<br />

Washers shall be made of steel conforming to any of the following Indian<br />

Standard Specifications as may be applicable under the provisions of the<br />

Contract :<br />

1) IS : 1977 - Structural steel (Ordinary Quality) St-42-0<br />

2) IS : 2062 - Steel for general structural purpose<br />

3) IS : 8500 - Structural steel - microalloyed<br />

(medium & high strength quality)<br />

4) IS : 6623 - High Strength Structural Nuts<br />

5) IS : 6649 - Hardened and tampered washers for high<br />

strength structural bolts & nuts.<br />

Paints to be used for shop coat of fabricated steel under the purview of this<br />

contract shall conform to the Indian Standard Specification IS:2074 - Ready<br />

mixed Paint, Air Drying, Red Oxide - Zinc Chromate Priming.<br />

In highly corrosive environment other type of primer such as epoxy resin<br />

based zinc rich primer (such as blast steel EZ1 of Shalimer Paints Ltd., may<br />

be necessary.<br />

2.6.0 Storage of Material<br />

2.6.1 General<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 7


2.6.2 Steel<br />

2.6.3 Electrodes<br />

DCPL-K4A02<br />

All materials shall be so stored as to prevent deterioration and to ensure<br />

the preservation of their quality and fitness for the work. Any material which<br />

has deteriorated or has been damaged shall be removed from the<br />

contractor's yard immediately, failing which, the Engineer shall be at<br />

liberty to get the material removed. The Contractor shall maintain upto date<br />

accounts in respect of receipt, use and balance of all sizes and sections<br />

of steel and other materials. In case the fabrication is carried out in<br />

contractor's fabrication shop outside the plant site where other fabrication<br />

works are also carried out, all materials meant for use in this contract shall<br />

be stacked separately with easily identifiable marks.<br />

The steel to be used in fabrication and the resulting cut-pieces shall be<br />

stored in separate stacks off the ground sectionwise and lengthwise so<br />

that they can be easily inspected, measured and accounted for at any<br />

time. If required by the Engineer, the materials may have to be stored<br />

under cover and suitably painted for protection against weather.<br />

The electrodes for electric are welding shall be stored in properly designed<br />

racks, separating different types of electrodes in distinctly marked<br />

compartments. The electrodes shall be kept in a dry and warm condition if<br />

necessary by resorting to heating.<br />

2.6.4 Bolts, Nuts and Washers<br />

2.6.5 Paints<br />

Bolts, nuts and washers and other fastening materials shall be stored on<br />

racks off the ground with a coating of suitable protective oil. These shall<br />

be stored in separate gunny bags or compartments according to diameter,<br />

length and quality.<br />

Paints shall be stored under cover in air tight containers. Paints supplied in<br />

sealed containers shall be used up as soon as possible once the container<br />

is opened.<br />

2.7.0 Quality Control<br />

The Contractor shall establish and maintain quality control procedures for<br />

different items of work and materials to the extent he deems necessary to<br />

ensure that all work is performed in accordance with this specification. In<br />

addition to the Contractor's quality control procedures, materials and<br />

workmanship at all times shall be subjected to inspection by the Engineer<br />

or Engineer's representative. As far as possible, all inspection by the<br />

Engineer or Engineer's representative shall be made at the Contractor's<br />

fabrication shop whether located at Site or elsewhere. The Contractor shall<br />

co-operate with the Engineer or Engineer's representative in permitting<br />

access for inspection to all places where work is being done and in<br />

providing all necessary help in respect of tools and plants, instrument, labour<br />

and materials required to carry out the inspection. The inspection shall be so<br />

scheduled as to provide the minimum interruption to the work of the<br />

Contractor.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 8


DCPL-K4A02<br />

Materials or workmanship not in reasonable conformance with the<br />

provisions of this Specification may be rejected at any time during the<br />

progress of the work.<br />

The quality control procedure shall cover but not be limited to the following<br />

items of work :<br />

1) Steel : Quality, manufacturer's test certificates, test reports<br />

of representative samples of materials from<br />

unidentified stocks if permitted to be used.<br />

2) Bolts, Nuts : Manufacturer's certificate, dimension<br />

& Washers checks, material testing.<br />

3) Electrodes : Manufacturer's certificate, thickness and quality of flux<br />

coating.<br />

4) Welders : Qualifying Tests<br />

5) Welding sets : Performance Tests<br />

6) Welds : Inspection, X-ray, Ultrasonic tests<br />

7) Paints : Manufacturer's certificate, physical inspection reports<br />

8) Galvanizing : Tests in accordance with IS : 2633 -<br />

Method for testing uniformity of coating on Zinc<br />

Coated Articles and IS : 4759 - Specification for Hot-<br />

Dip Zinc coatings on Structural Steel and other<br />

allied products.<br />

2.8.0 Standard dimensions, forms and weights<br />

The dimensions, forms, weights and tolerances of all rolled shapes bolts,<br />

nuts, studs, washers etc. and other members used in the fabrication of<br />

any structure shall, wherever applicable, conform to the requirements of<br />

the latest relevant Indian Standards, wherever they exist, or, in the absence<br />

of Indian Standards, to other equivalent standards.<br />

2.9.0 Shop Drawings<br />

The Contractor shall submit to the Engineer the Schedule of Fabrication<br />

and delivery of structural steelwork for approval. He shall start to submit<br />

progressively for approval the shop drawings based on the approved Design<br />

Drawings and before proceeding with the fabrication work, shall get the<br />

said shop drawings approved in accordance with the contract.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 9


DCPL-K4A02<br />

The sequence of submission of shop drawings for approval shall match with<br />

the approved fabrication and delivery schedule. The approval for the shop<br />

drawings will be accorded only towards the general conformity with the<br />

design requirements as well as specification and will ensure the correctness<br />

of general arrangement for centreline dimensions and levels, Section<br />

sizes, and adequacy of connections including splice joints as to the no. of<br />

bolts, weld length, size of gusset/end plates.<br />

The correctness of all other details like cutting lengths, matching of holes,<br />

notch dimensions, match markings, bill of materials, bolt list etc. will be<br />

entirely the contractor's responsibility. The approval of the drawing however<br />

shall not relieve the contractor of his sole responsibility in carrying out the<br />

work correctly and fulfilling the complete requirements of contract<br />

documents.<br />

The shop drawings shall include but not be limited to the following : -<br />

a) Assembly drawings giving exact sizes of the sections to be used and<br />

identification marks of the various sections.<br />

b) Dimensional drawings of base plates, foundation bolt location etc.<br />

c) Details of all connections with supporting calculations.<br />

d) Comparison sheets to show that the proposed alternative section, if<br />

any, are as strong as the original sections shown on the Design<br />

Drawings.<br />

e) Complete Bill of Materials and detailed drawings of all sections as<br />

also their billing weights.<br />

f) Any other drawings or calculations that may be required for the<br />

clarification of the works or substituted parts thereof.<br />

The shop drawings shall give all the necessary information for the<br />

fabrication, erection and painting of the steelwork in accordance with the<br />

provisions of this Specification. Shop drawings shall be made in<br />

accordance with the best modern practice and with due regard to<br />

sequence, speed and economy in fabrication and erection. Shop drawings<br />

shall give complete information necessary for fabrication of various<br />

components of the steelwork, including the location, type, size and extent of<br />

welds. These shall also clearly distinguish between shop and field bolts and<br />

welds and specify the class of bolts and nuts. The drawings shall be drawn<br />

to a scale large enough to convey all the necessary information adequately.<br />

Notes on the shop drawings shall indicate those joints or groups of joints in<br />

which it is particularly important that the welding sequence and technique<br />

of welding shall be carefully controlled to minimize the locked -up stresses<br />

and distortion.<br />

Welding symbols used shall be in accordance with the requirements<br />

of the Indian Standard Specification --IS:813 - Scheme of symbols for<br />

Welding, and shall be consistent throughout. Weld lengths called for on<br />

the drawings shall mean the net effective length.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 10


DCPL-K4A02<br />

The Contractor shall be responsible for and shall pay for any alterations of<br />

the work due to any discrepancies, errors or omissions on the drawings or<br />

other particulars supplied by him, whether such drawings or other particulars<br />

have been duly approved or not in accordance with the Contract.<br />

3.0.0 WORKMANSHIP<br />

3.1.0 Fabrication<br />

3.1.1 General<br />

All workmanship shall be equal to the best practice in modern structural<br />

shops, and shall conform to the provisions of the Indian Standard IS:800 -<br />

Code of Practice for use of Structural Steel in General Building<br />

Construction and other relevant Indian Standards.<br />

3.1.2 Straightening Material<br />

3.1.3 Cutting<br />

Rolled materials before being laid off or worked, must be clean, free<br />

from sharp kinks, bends or twists and straight within the tolerances<br />

allowed by the Indian Standard Specification IS:1852 - Specification for<br />

rolling and cutting tolerance for hot-rolled steel products. If straightening is<br />

necessary, it may be done by mechanical means or by the application of<br />

a limited amount of localized heat. The temperature of heated areas, as<br />

measured by approved methods, shall not exceed 600 Deg. C.<br />

Cutting shall be effected by shearing, cropping or sawing. Use of a<br />

mechanically controlled gas cutting torch may be permitted for mild<br />

steel only. Gas cutting of high tensile steel may also be permitted provided<br />

special care is taken to leave sufficient metal to be removed by machining,<br />

so that all metal that has been hardened by flame is removed. Gas cutting<br />

without a mechanically controlled torch may be permitted if special care is<br />

taken and done under expert hand, subject to the approval of the Engineer.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 11


DCPL-K4A02<br />

To determine the effective size of members cut by gas, 3 mm shall be<br />

deducted from each cut edge. Gas cut edges, which will be subjected to<br />

substantial stress or which are to have weld metal deposited on them, shall<br />

be reasonably free from gouges. Occasional notches or gauges not more<br />

than 4 mm deep will be permitted. Gouges greater than 4 mm, that remain<br />

from cutting, shall be removed by grinding. All re-entrant corners shall be<br />

shaped notch-free to a radius of at least 12 mm. Shearing, cropping and<br />

gas cutting shall be clean, reasonably square and free from any distortion.<br />

3.1.4 Planning of edges<br />

3.1.5 Clearances<br />

Planning or finishing of sheared or cropped edges of plates or shapes or of<br />

edges gas-cut with a mechanically controlled torch shall not be required,<br />

unless specifically required by design and called for on the drawings,<br />

included in a stipulation for edge preparation for welding or as may be<br />

required after the inspection of the cut surface. Surface cut with hand-flame<br />

shall generally be ground, unless specifically instructed otherwise by the<br />

Engineer.<br />

The erection clearance for cleated ends of members connecting steel to<br />

steel shall preferably be not greater than 2 mm at each end. The erection<br />

clearance at ends of beams without web cleats shall be not more than 3 mm<br />

at each end, but where, for practical reasons, greater clearance is<br />

necessary, suitably designed cleatings shall be provided.<br />

3.2.0 Bolted construction<br />

3.2.1 Holes<br />

Holes through more than one thickness of material for members, such as<br />

compound stanchions and girder flanges, shall be drilled after the<br />

members are assembled and tightly clamped or bolted together. Punching<br />

may be permitted before assembly, if the thickness of the material is not<br />

greater than the nominal diameter of bolt plus 3 mm subject to a maximum<br />

thickness of 16 mm provided that the holes are punched 3 mm less in<br />

diameter than the required size and reamed after assembly to the full<br />

diameter.<br />

Holes for rivets or black bolts shall be not more than 1.5 mm or 2.0<br />

mm ( depending on whether the diameter of the bolt is less or more than or<br />

equal to 25 mm ) larger in diameter than the nominal diameter of the black<br />

bolt passing through them.<br />

Holes for turned and fitted bolts shall be drilled to a diameter equal to the<br />

nominal diameter of the shank or barrel subject to a tolerance grade of H8<br />

as specified in IS:919. Parts to be connected shall be firmly held<br />

together by tacking welds or clamps and the holes drilled through all the<br />

thicknesses in one operation and subsequently reamed to size. Holes not<br />

drilled through all thickness in one operation shall be drilled to a smaller size<br />

and reamed out after assembly.<br />

Holes for bolts shall not be formed by gas cutting process.3.2.2<br />

Assembly<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 12


DCPL-K4A02<br />

Drifting to enlarge unmatching holes shall not generally be permitted. In<br />

case drifting is permitted to a slight extent during assembly, it shall not<br />

distort the metal or enlarge the holes. Holes that must be enlarged to admit<br />

the bolts shall be reamed. Poor matching of holes shall be cause for<br />

rejection. The component parts shall be so assembled that they are<br />

neither twisted not otherwise damaged, and shall be so prepared that the<br />

specified cambers, if any, are maintained.<br />

Bolted construction shall be permitted only in case of field connections if<br />

called for on the Drawings and is subjected to the limitation of particular<br />

connections as may be specified. In special cases, however, shop bolt<br />

connections may be allowed if directed by the Engineer.<br />

Washers shall be tapered or otherwise suitably shaped, where necessary, to<br />

give the heads and nuts of bolts a satisfactory bearing. The threaded<br />

portion of each bolt shall project out through the nut at least one thread. In<br />

all cases the bolt shall be provided with a washer of sufficient thickness<br />

under the nut to avoid any threaded portion of the bolt being within the<br />

thickness of the parts bolted together. In addition to the normal washer, one<br />

spring washer or lock-nut shall be provided for each bolt for connections<br />

subjected to vibrating forces or otherwise as may be specified on the<br />

Drawings.<br />

3.3.0 Welded Construction<br />

3.3.1 General<br />

Welding shall be in accordance with relevant Indian Standards and as<br />

supplemented in the Specification. Welding shall be done by experienced<br />

and good welders who have been qualified by tests in accordance with<br />

IS:817.<br />

3.3.2 Preparation of Material<br />

3.3.3 Assembling<br />

Surface to be welded shall be free from loose scale, slag, rust, grease,<br />

paint and any other foreign material except that mill scale which withstands<br />

vigorous wire brushing may remain. Joint surfaces shall be free from fins and<br />

tears. Preparation of edges by gas-cutting shall, wherever practicable, be<br />

done by a mechanically guided torch.<br />

Parts to be fillet welded shall be brought in as close contact as practicable<br />

and in no event shall be separated by more than 4 mm. If the separation is<br />

1.5 mm or greater, the size of the fillet welds shall be increased by the<br />

amount of the separation. The fit of joints at contact surfaces which are<br />

not completely sealed by welds, shall be close enough to exclude water<br />

after painting. Abutting parts to be butt-welded shall be carefully aligned.<br />

Misalignments greater than 3 mm shall be corrected and in making the<br />

correction the parts shall not be drawn into a sharper slope than two<br />

degrees (2 Deg.).<br />

The work shall be positioned for flat welding whenever practicable.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 13


DCPL-K4A02<br />

3.3.4 Welding Sequence<br />

In assembling and joining parts of a structure or of built-up members, the<br />

procedure and sequence of welding shall be such as will avoid needless<br />

distortion and minimize shrinkage stresses. Where it is impossible to<br />

avoid high residual stresses in the closing welds of a rigid assembly,<br />

such closing welds shall be made in compression elements.<br />

In the fabrication of cover-plated beams and built-up members, all shop<br />

splices in each component part shall be made before such component part<br />

is welded to other parts of the member. Long girders or girder sections may<br />

be made by shop splicing not more than three sub-sections, each made in<br />

accordance with this paragraph. When required by the Engineer, welded<br />

assemblies shall be stress relieved by heat treating in accordance with<br />

the provisions of the relevant Indian Standard or any other Standard<br />

approved by the Engineer.<br />

3.3.5 Welding technique<br />

3.3.6 Temperature<br />

All complete penetration groove welds made by manual welding, except when<br />

produced with the aid of backing material not more than 8 mm thick with root<br />

opening not less than one-half the thickness of the thinner part joined, shall<br />

have the root of the initial layer gouged out on the back side before welding<br />

is started from that side, and shall be so welded as to secure sound metal<br />

and complete fusion throughout the entire cross-section. Groove welds<br />

made with the use of the backing of the same material as the base metal<br />

shall have the weld metal thoroughly fused with the backing material.<br />

Backing strips need not be removed. If required, they may be removed by<br />

gouging or gas cutting after welding is completed, provided no injury is done<br />

to the base metal and weld metal and the weld metal surface is left flush<br />

or slightly convex with full throat thickness.<br />

Groove welds shall be terminated at the ends of a joint in a manner that will<br />

ensure their soundness. Where possible, this should be done by use of<br />

extension bars or run-off plates. Extension bars or run-off plates need not<br />

be removed upon completion of the weld unless otherwise specified<br />

elsewhere in the Contract.<br />

To get the best and consistent quality of welding, automatic submerged arc<br />

process shall be preferred. The technique of welding employed, the<br />

appearance and quality of welds made, and the methods of correcting<br />

defective work shall all conform to the relevant Indian Standards.<br />

No welding shall normally be done on parent material at a temperature below (-)<br />

5 Deg.C. However, if welding is to be undertaken at low temperature, adequate<br />

precautions as recommended in relevant Indian Standard shall be taken. When the<br />

parent material is less than 40 mm thick and the temperature is between (-) 5<br />

Deg. C and 0 Deg. C, the surface around the joint to a distance of 100 mm or 4<br />

times the thickness of the material, whichever is greater, shall be preheated till it is<br />

handwarm. When the parent material is more than 40 mm thick, the temperature of<br />

the area mentioned above shall be in no case be less than 20 Deg. C. All<br />

requirements regarding preheating of the parent material shall be in accordance with<br />

the relevant Indian Standard.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 14


DCPL-K4A02<br />

3.3.7 Peening<br />

3.3.8 Equipment<br />

3.4.0 Finish<br />

Where required, intermediate layers of multiple-layer welds may be<br />

peened with light blows from a power hammer, using a round-nose tool.<br />

Peening shall be done after the weld has cooled to a temperature warm<br />

to the hand. Care shall be exercised to prevent scaling or flaking of weld<br />

and base metal from over peening.<br />

These shall be capable of producing proper current so that the operator may<br />

produce satisfactory welds. The welding machine shall be of a type and<br />

capacity as recommended by the manufacturers of electrodes or as may<br />

be approved by the engineer.<br />

Column splices and butt joints of compression members depending on<br />

contact for stress transmission shall be accurately machined and closebutted<br />

over the whole section with a clearance not exceeding 0.2 mm locally<br />

at any place. In column caps and bases, the ends of shafts together with<br />

the attached gussets, angles, channels etc., after welding together,<br />

should be accurately machined so that the parts connected butt over the<br />

entire surfaces of contact. Care should be taken that those connecting<br />

angles or channels are fixed with such accuracy that they are not<br />

reduced in thickness by machining by more than 2.0 mm.<br />

3.5.0 Slab bases and caps<br />

3.6.0 Lacing bars<br />

3.7.0 Separators<br />

Bases and caps fabricated out of steel slabs, except when cut from material<br />

with true surface, shall be accurately machined over the bearing surface<br />

and shall be in effective contact with the end of the stanchion. A bearing<br />

face which is to be grouted direct to a foundation need not be machined if<br />

such face is true and parallel to the upper face. To facilitate grouting, holes<br />

shall be provided, where necessary, in stanchion bases for the escape of<br />

air.<br />

The ends of lacing bars shall be neat and free from burrs.<br />

Rolled section or built-up steel separators or diaphragms shall be required<br />

for all double beams except where encased in concrete, in which case, pipe<br />

separators shall be used.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 15


DCPL-K4A02<br />

3.8.0 Bearing Plates<br />

Provision shall be made for all necessary steel bearing plates to take up<br />

reaction of beams and columns and the required stiffeners and gussets<br />

whether or not specified in Drawings.<br />

3.9.0 Architectural Clearances<br />

Bearing plates and stiffener connections shall not be permitted to<br />

encroach on the designed architectural clearances.<br />

3.10.0 Shop connections<br />

3.11.0 Castings<br />

3.12.0 Shop erection<br />

3.13.0 Shop painting<br />

3.13.1 General<br />

a) All shop connections shall be welded as specified on the Drawings.<br />

b) Certain connections, specified to be shop connections, may be<br />

changed to field connections if desired by the Engineer for<br />

convenience of erection and the Contractor will have to make the<br />

desired changes.<br />

Steel castings shall be annealed<br />

The steelwork shall be temporarily shop-erected complete or as directed by<br />

the Engineer so that accuracy of fit may be checked before despatch. The<br />

parts shall be shop-erected with a sufficient number of parallel drifts to<br />

bring and keep the parts in place. In case of parts drilled or punched<br />

using steel jigs to make all similar parts interchangeable, the steelwork<br />

shall be shop erected in such a way as will faciliate the check of<br />

interchangeability.<br />

Unless otherwise specified, steelwork which will be concealed by interior<br />

building finish need not be painted; steelwork to be encased in concrete<br />

shall not be painted. Unless specifically exempted, all other steelwork<br />

shall be given one coat of shop paint, applied thoroughly and evenly to<br />

dry surfaces which have been cleaned, in accordance with the following<br />

paragraph, by brush, spray, roller coating, flow-coating or dipping as may be<br />

approved by the Engineer.<br />

After inspection and approval and before leaving the shop, all steelwork<br />

specified to be painted shall be cleaned by hand-wire brushing or by other<br />

mechanical cleaning methods to remove loose mill scale, loose rust,<br />

weld slag or flux deposit, dirt and other foreign matter. Oil and grease<br />

deposits shall be removed by solvent. Steelwork specified to have no shop<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 16


DCPL-K4A02<br />

paint shall, after fabrication, be cleaned of oil or grease by solvent cleaners<br />

and be cleaned of dirt and other foreign material by through sweeping with a<br />

fibre brush.<br />

After completion of the precleaning, the metal surface shall immediately<br />

painted with red oxide zinc chromate primer conforming to IS : 2074.<br />

In highly corrosive environment, all steelwork shall be given a coat of shop<br />

paint, applied thoroughly and evenly to dry surfaces which have been<br />

cleaned by sand blasting to SA 2/1/2 grade minimum. The shop paint shall<br />

be epoxy rasin based zinc rich primer such as Blast Steel EZ1 of Shalimer<br />

Paint Limited.<br />

3.13.2 Inaccessible parts<br />

Surfaces not in contact, but inaccessible after assembly, shall receive two<br />

coats of shop paint, positively of different colours to prove application of two<br />

coats before assembly. This does not apply to the interior of sealed hollow<br />

sections.<br />

3.13.3 Contact surfaces<br />

Contact surface shall be cleaned in accordance with Sub-clause 3.13.1<br />

before assembly.<br />

3.13.4 Finished surfaces<br />

Machine finished surfaces shall be protected against corrosion by a rust<br />

inhibiting coating that can be easily removed prior to erection or which has<br />

characteristics that make removal unnecessary prior to erection.<br />

3.13.5 Surfaces adjacent to field welds<br />

3.14.0 Galvanizing<br />

3.14.1 General<br />

Unless otherwise provided for, surfaces within 50 mm of any field weld<br />

location shall be free of materials that would prevent proper welding or<br />

produce objectionable fumes while welding is being done.<br />

Structural steelwork for switchyard or other structures as may be specified in<br />

the Contract shall be hot dip galvanized in accordance with the American<br />

Society for Testing and Materials Specification ASTM-A 123 or IS : 2629 -<br />

Recommended practice for Hot-Dip Galvanising of Iron and steel. Where<br />

the steel structures are required to be galvanized the field connection<br />

materials like bolts, nuts and washers shall also be galvanized.<br />

3.14.2 Surface Preparation<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 17


3.14.3 Procedure<br />

DCPL-K4A02<br />

All members to be galvanized shall be cleaned, by the process of pickling of<br />

rust, loose scale, dirt, oil, grease, slag and spatter of welded areas and other<br />

foreign substances prior to galvanizing. Pickling shall be carried out by<br />

immersing the steel in an acid bath containing either sulphuric or<br />

hydrochloric acid at a suitable concentration and temperature. The<br />

concentration of the acid and the temperature of the bath can be varied,<br />

provided that the pickling time is adjusted accordingly.<br />

The pickling process shall be completed by thoroughly rinsing with water,<br />

which should preferably be warm, so as to remove the residual acid.<br />

Galvanizing shall be carried out by hot dip process in a proper and uniformly<br />

heated bath. It shall meet all the requirements when tested in accordance<br />

with IS:2633 - Method for testing uniformity of coating on Zinc Coated<br />

Articles and IS:4759 - Specification for Hot-dip zinc coatings on Structural<br />

Steel & other allied products.<br />

After finishing the threads of bolts, galvanizing shall be applied over the<br />

entire surface uniformly. The threads of bolts shall not be machined after<br />

galvanizing and shall not be clogged with zinc. The threads of nuts may be<br />

tapped after galvanizing but care shall be taken to use oil in the threads of<br />

nuts during erection.<br />

The surface preparation for galvanizing and the process of galvanizing<br />

itself, shall not adversely affect the mechanical properties of the materials to<br />

be galvanized. Where members are of such lengths as to prevent<br />

complete dipping in one operation, great care shall be taken to prevent<br />

warping.<br />

Materials on which galvanizing has been damaged shall be acid stripped<br />

and re-galvanized unless otherwise directed, but if any member becomes<br />

damaged after having been dipped twice, it shall be rejected. Special care<br />

shall be taken not to injure the skin on galvanized surfaces during transport<br />

and handling. Damages, if occur, shall be made good in accordance with<br />

the provisions of this Specification or as directed by the Engineer.<br />

4.0.0 INSPECTION, TESTING, ACCEPTANCE CRITERIA AND DELIVERY<br />

4.1.0 Inspection<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 18


DCPL-K4A02<br />

Unless specified otherwise, inspection to all work shall be made by the<br />

Engineer or Engineer's representative at the place of manufacture prior to<br />

delivery. The Engineer or his representative shall have free access at all<br />

reasonable times to those parts of the manufacturer's works which are<br />

concerned with the fabrication of the steelwork under this Contract and he<br />

shall be afforded all reasonable facilities for satisfying himself that the<br />

fabrication is being done in accordance with the provisions of this<br />

Specification.<br />

The Contractor shall provide such labour, materials, electricity, fuel, water,<br />

stores, tools and plant, apparatus and instruments as may be required by<br />

the Engineer to carry out inspection and/or tests in accordance with the<br />

Contract.<br />

The Contractor shall guarantee compliance with the<br />

Specification.<br />

provisions of this<br />

4.2.0 Testing and Acceptance Criteria<br />

4.2.1 General<br />

4.2.2 Steel<br />

The Contractor shall carry out sampling and testing in accordance with<br />

the relevant Indian Standards and as supplemented herein for the<br />

following items at his own cost, unless otherwise specified in the Contract.<br />

The Contractor shall get the specimens tested in a laboratory approved by<br />

the Engineer and submit to the Engineer the test results in triplicate<br />

within 3 (three) days after completion of the test.<br />

All steel supplied by the Contractor shall conform to the relevant Indian<br />

Standards. Except otherwise mentioned in the Contract, only tested quality<br />

steel having mill test reports shall be used. In case unidentified steel<br />

materials are permitted to be used by the Engineer, random samples of<br />

materials will be taken from each unidentified lot of 50 M.T. or less of any<br />

particular section for tests to conform to relevant Indian Standards.<br />

All material shall be free from all imperfections, mill scales, slag intrusions,<br />

laminations, pittings, rusts etc. that may impair their strength, durability and<br />

appearance.<br />

4.2.3 Testing Criteria for checking Lamination in raw steel plates<br />

All raw steel plate of thickness more than 20 mm supplied by the<br />

contractor shall be checked against lamination before procurement & prior<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 19


4.2.4 Welding<br />

DCPL-K4A02<br />

to commencement of fabrication work in the following ways as directed by the<br />

Engineer.<br />

a) Ultrasonic testing along the edge of specified points of the plates shall<br />

be carried out to delete lamination in the plates, if any.<br />

b) If the results of the tests in (a) are not satisfactory, the whole area of<br />

the plates shall be checked by ultrasonic testing at specified nodal<br />

points formed at equidistant grid locations. The spacing of the grids<br />

shall be determined from tests in (a) or as directed by the Engineer.<br />

If the results of the above tests are not satisfactory, the plates shall not be<br />

taken up for fabrication work. Even after fabrication at shop, if the Engineer<br />

requires any ultrasonic testing to detect lamination of plates, the same<br />

shall be carried out by the Contractor. If the plates in the fabricated item is<br />

found to be laminated, the component will be rejected.<br />

All electrodes shall be procured from reliable manufacturers with test<br />

certificates. The correct grade and size of electrode which has not<br />

deteriorated in storage shall be used. The inspection and testing of welding<br />

shall be performed in accordance with the provisions of the relevant<br />

Indian Standards or other equivalents. For every 50 tonnes of welded<br />

fabrication, the Engineer may ask for at least 1 (one) test-destructive or<br />

non-destructive including X-ray, ultrasonic test or similar. In the event of<br />

further tests as may be desired by the Engineer, if the results are found to<br />

be unsatisfactory; and if the test shows no defect. In cases of the test<br />

results showing deficiency, the Engineer shall have option to reject or<br />

instruct any remedial measures to be taken.<br />

4.2.5 Bolts, nuts and washers<br />

All bolts, nuts and washers shall be procured from reputed manufacturer<br />

approved by the Engineer and shall conform to the relevant Indian<br />

Standards. If desired by the Engineer, representative samples of these<br />

materials may have to be tested in an approved laboratory and in<br />

accordance with the procedures described in relevant Indian Standards.<br />

4.2.6 Shop painting<br />

All paints and primers shall be of standard quality and procured from<br />

approved manufacturers and shall conform to the provisions of the relevant<br />

Indian Standards.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 20


DCPL-K4A02<br />

4.2.7 Galvanizing<br />

4.3.0 Tolerance<br />

4.4.0 Acceptance<br />

All galvanizing shall be uniform and of standard quality when tested in<br />

accordance with IS:2633 - Method for testing uniformity of coating on<br />

Zinc Coated Articles and IS:4759 - specification for Hot-Dip Zinc Coatings<br />

on Structural Steel & other allied products.<br />

The tolerances on the dimensions of individual rolled steel components<br />

shall be as specified in IS:1852 - specification for rolling and Cutting<br />

Tolerances for Hot-rolled Steel Products. The tolerances on straightness,<br />

length etc. of various fabricated components (such as beams and girders,<br />

columns, crane gantry girder etc.) of the steel structures other than steel<br />

railway & road bridges, structures subjected to dynamic loading (like wind,<br />

seismic etc.) and thin walled construction (like box girders) shall be as<br />

specified in IS:7215 - Tolerances for Fabrication of Steel Structures.<br />

Should any structure or part of a structure be found not to comply with any<br />

of the provisions of this Specification, the same shall be liable to rejection.<br />

No structure or part of the structure, once rejected, shall be offered again<br />

for test, except in cases where the Engineer considers the defects<br />

rectifiable. The Engineer may, at his discretion, check the test results<br />

obtained at the Contractor's works by independent tests at an approved<br />

laboratory and should the items, so tested, be found to be unsatisfactory.<br />

When all tests to be performed in the Contractor's shop under the terms of<br />

this contract have been successfully carried out, the steelwork will be<br />

accepted forthwith and the Engineer will issue an acceptance certificate,<br />

upon receipt of which, the items will be shop painted, packed and<br />

despatched. No item to be delivered unless an acceptance certificate for the<br />

same has been issued. The satisfactory completion of these tests or the<br />

issue of the certificates shall not bind the Owner to accept the work,<br />

should it, on further tests before or after erection, be found not in<br />

compliance with the Contract.<br />

4.5.0 Delivery of materials<br />

4.5.1 General<br />

The Contractor will deliver the fabricated structural steel materials to site<br />

with all necessary field connection materials in such sequence as will<br />

permit the most efficient and economical performance of the erection work.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 21


4.5.2 Marking<br />

DCPL-K4A02<br />

the Owner may prescribe or control the sequence of delivery of materials, at<br />

his own discretion.<br />

Each separate piece of fabricated steelwork shall be distinctly marked<br />

on all surfaces before delivery in accordance with the markings shown<br />

on approved erection drawings and shall bear such other marks as will<br />

further facilitate identification and erection.<br />

4.5.3 Packing and Shipping<br />

All projecting plates or edges and all ends of members of joints shall be<br />

stiffened, all straight members and plates, shall be bundled, all screwed<br />

ends and machined surfaces shall be suitably packed and all bolts, nuts,<br />

washers, and small loose parts shall be packed separately in order to<br />

prevent damage or distortion during shipping.<br />

Shipping shall be strictly in accordance with the sequence stipulated in<br />

the agreed programme. Payment may be held up for items sent in advance<br />

of the sequence till they could be erected. The Contractor shall include<br />

and provide for in his rates, the freight and other charges for<br />

despatching the materials to the worksite and also for securely protecting<br />

and packing the materials to avoid loss or damage during transport by rail,<br />

road or water. All packings shall allow for easy removal and checking at<br />

site. Special precautions shall be taken against rusting, corrosion, breakage<br />

or damage otherwise of the materials. All parts shall be adequately braced<br />

to prevent damage in transit.<br />

Each bundle, bale or package delivered under this contract shall be<br />

marked on as many sides as possible and such distinct marking (all previous<br />

irrelevant markings being carefully obliterated) shall show the following : -<br />

a) Name and address of the consignee<br />

b) Name and address of the consignor<br />

c) Gross weight of the package in tonnes and its dimensions<br />

d) Identification marks and/or number of the package<br />

e) Custom registration number, if required<br />

All markings shall be carried out with such materials as would ensure quick<br />

drying and indelibility.<br />

Each component or part or piece of material when shipped, shall be<br />

indelibly marked and/or tagged with reference to assembly drawings and<br />

corresponding piece numbers.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 22


DCPL-K4A02<br />

Each packing case shall contain in duplicate in English a packing list<br />

pasted on to the inside of the cover in a water-proof envelope, quoting<br />

especially :<br />

a) Name of the Contractor<br />

b) Number and date of the Contract<br />

c) Name of the office placing the contract<br />

d) Nomenclature of stores<br />

e) A schedule of parts or pieces, giving the parts or piece number with<br />

reference to assembly drawings and the quantity of each.<br />

The shipping dimensions of each package shall not exceed the maximum<br />

dimensions permissible for transport over the Indian Railways/Roads.<br />

After delivery of the materials at site, all packing materials shall automatically<br />

become the property of the Owner.<br />

Notwithstanding anything stated hereinbefore, any loss or damage<br />

resulting from inadequate packing shall be made good by the Contractor<br />

When facilities exist, all shipments shall be covered by approved Insurance<br />

Policy for transit at the cost of the Contractor.<br />

The contractor shall ship the complete materials or part on board a vessel<br />

belonging to an agency approved by the Owner or on rail and/or road<br />

transport as directed. The Contractor shall take all reasonable steps to<br />

ensure correct appraisal of freight rates, weights and volumes and in no<br />

case will the Owner be liable to pay any warehouse, wharfage, demurrage<br />

and other charges.<br />

If, however, the Owner has to make payment of any of the above mentioned<br />

charges, the amount paid will be deducted from the progressive bills of the<br />

Contractor.<br />

Necessary advise regarding the shipment with relevant details shall reach<br />

the Engineer at least a week in advance.<br />

5.0.0 INFORMATION TO BE SUBMITTED<br />

5.1.0 With Tender<br />

The following information are required to be submitted with the Tender :<br />

a) Progress Schedule<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 23


DCPL-K4A02<br />

The Contractor shall quote in his Tender a detailed schedule of<br />

progress of work and total time of completion, itemizing the time<br />

required for each of the following aspects of work.<br />

1) Preparation and approval of shop drawings<br />

2) Procurement of materials<br />

3) Fabrication and shipping of all anchor bolts<br />

4) Fabrication and shipping of main steelwork<br />

5) Fabrication and shipping of steelwork for bunkers. Tanks<br />

and/ or silos as applicable.<br />

6) Fabrication and shipping of all other remaining steel work<br />

including miscellaneous steelwork<br />

7) Final date of completion of all shipments<br />

Time required for completion being one of the main criteria for selecting<br />

the successful bidder, it is desired that the bidder quotes the minimum time<br />

required by him for completing the work.<br />

b) Shop<br />

Location of the Tenderer's fabrication workshop giving details of<br />

equipment, manpower, the total capacity and the capacity that will be<br />

available exclusively for this contract shall be submitted.<br />

c) Matching Steel<br />

A rough indication of the quantities and details of matching steel<br />

sections required to start the work shall be furnished.<br />

5.2.0 After Award<br />

After award of the Contract the successful Tenderer is to submit the<br />

following :<br />

a) Complete fabrication drawings, material lists, cutting lists, bolt lists,<br />

field welding schedules based on the design drawings in accordance<br />

with the approved schedule.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 24


DCPL-K4A02<br />

b) Monthly Progress Report with necessary photographs in six (6)<br />

copies to reach the Engineer on or before the 7th day of each<br />

month, giving the upto date status of preparation of detailed shop<br />

drawings, bill of materials, procurement of materials, actual<br />

fabrication done, shipping and all other relevant information.<br />

c) Results of any test as and when conducted and as required by the<br />

Engineer.<br />

d) Manufacturer's mill test report in respect of steel materials, bolts,<br />

nuts and electrodes as may be applicable.<br />

(PCA.774.S034sca4) V.II-D2/S-IV : 25


DCPL-K4A02<br />

VOLUME: II-D/2<br />

SECTION-V<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ERECTION OF STRUCTURAL STEELWORK<br />

(PCA.775.S034sca5)


DCPL-K4A02<br />

CONTENTS<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-V : 1<br />

2.0.0 GENERAL V.II-D2/S-V : 1<br />

3.0.0 WORKMANSHIP V.II-D2/S-V : 4<br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA V.II-D2/S-V : 10<br />

5.0.0 INFORMATION TO BE SUBMITTED V.II-D2/S-V : 14<br />

(PCA.775.S034sca5)


DCPL-K4A02<br />

VOLUME: II-G/2<br />

SECTION-V<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ERECTION OF STRUCTURAL STEELWORK<br />

1.0.0 SCOPE<br />

This specification covers the erection of structural steelwork including<br />

receiving and taking delivery of fabricated structural steel materials arriving<br />

at Site and installing the same in position, painting and grouting the<br />

stanchion bases all complete as per Drawings, this Specification and other<br />

provision of the Contract.<br />

2.0.0 GENERAL<br />

2.1.0 Work to be provided for by the Contractor<br />

The work to be provided for by the Contractor, unless otherwise<br />

specified in the Contract, shall include but not be limited to the following:-<br />

a) The Contractor shall provide all construction and transport<br />

equipment, tools, tackle, consumables, materials, labour and<br />

supervision required for the erection of the structural steelwork.<br />

b) Receiving, unloading, checking and moving to storage yard at Site<br />

including prompt attendance to all insurance matters as necessary for<br />

all fabricated steel materials arriving at Site. The Contractor shall pay<br />

all demurrage and/or wharfage charges etc. on account of default on<br />

his part.<br />

c) Transportation of all fabricated structural steel materials from Site<br />

storage yard, handling, rigging, assembling, bolting, welding and<br />

satisfactory installation of all fabricated structural steel materials in<br />

proper location according to approved erection drawings and/or as<br />

directed by the Engineer. If necessary suitable temporary approach<br />

roads to be built for transportation of fabricated steel structures.<br />

d) Checking center lines, levels of all foundation blocks including<br />

checking line, level, position and plumb of all bolts and pockets. any<br />

defect observed in the foundation shall be brought to the notice of<br />

the Engineer. The Contractor shall fully satisfy himself regarding<br />

the correctness of the foundations before installing the fabricated<br />

steel structures on the foundation blocks.<br />

e) Aligning, plumbing, levelling, bolting, welding and securely fixing the<br />

fabricated steel structures in accordance with the Drawings or as<br />

directed by the Engineer.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 1


DCPL-K4A02<br />

f) Painting of the erected steel structures if required by the Contract.<br />

g) All minor modifications of the fabricated steel structures as<br />

directed by the Engineer including but not limited to the following :<br />

i) Removal of bends, kinks, twists etc. for parts damaged during<br />

transport and handling.<br />

ii) Cutting, chipping, filling, grinding etc. if required for<br />

preparation and finishing of site connections.<br />

iii)<br />

iv)<br />

Reaming of holes for use of higher size bolt if required.<br />

Welding of connections in place of bolting for which holes are<br />

either not drilled at all or wrongly drilled during fabrication.<br />

Welding in place of bolting will be permitted only at the<br />

discretion of the Engineer.<br />

v) Refabrication of parts damaged beyond repair during<br />

transport and handling or Refabrication of parts which are<br />

incorrectly fabricated.<br />

vi)<br />

vii)<br />

Fabrication of parts omitted during fabrication by error, or<br />

subsequently found necessary.<br />

Drilling of holes which are either not drilled at all or are<br />

drilled in incorrect location during fabrication.<br />

2.2.0 Work by others<br />

viii) Carry out tests in accordance with this Specification if<br />

directed.<br />

No work under this Specification will be provided for by any agency other<br />

than the Contractor unless specifically mentioned elsewhere in the Contract.<br />

2.3.0 Codes and Standards<br />

All work under this Specification shall, unless specified otherwise, conform to the<br />

latest revisions and/or replacements of the following or any other Indian Standard<br />

Specification and codes of Practice of equivalent:-<br />

IS-800<br />

IS-456<br />

IS-7205<br />

: Code of Practice for general construction in steel<br />

: Code of Practice for plain or reinforced concrete<br />

: Safety Code for erection of Structural Steel work<br />

IS-12843 : Tolerance for erection of Steel Structures<br />

2.4.0 Conformity with designs<br />

The Contractor will erect the entire fabricated steel structure, align all<br />

the members, complete all field connections and grout the<br />

(PCA.775.S034sca5) V.II-D2/S-V : 2


2.5.0 Material<br />

2.5.1 General<br />

DCPL-K4A02<br />

foundations all as per the provisions of this specification and the<br />

design criteria detailed in the approved erection drawings and/or other<br />

stated document. All work shall conform to the provisions of the relevant<br />

Indian Standard Specifications and/or the instructions of the engineer. The<br />

testing and acceptance of the erected structures shall be in accordance<br />

with the provisions of this Specification and/or the instructions of the<br />

Engineer.<br />

The Contractor will check the quantity, quality and the sizes of the fabricated<br />

materials and verify the adequacy of the same in accordance with the<br />

Drawings and Specifications. The Contractor shall make good any deficiency,<br />

if detected, either by repair or with fresh material as may be directed by the<br />

Engineer.<br />

All consumables like oxygen and acetylene gas, paints, fuels, lubricants, oil,<br />

grease, cement, sand, aggregates and any other material that may be<br />

required for the execution of the works in accordance with the contract will<br />

be supplied by the contractor for erection work and will be deemed to have<br />

been included in this rates.<br />

2.5.2 Materials to conform to Indian Standards<br />

All materials required to be supplied by the Contractor under this Contract<br />

shall conform to the relevant Indian Standard Specifications.<br />

2.6.0 Storage of materials<br />

2.6.1 General<br />

2.6.2 Yard<br />

All material shall be so stored as to prevent deterioration and to ensure the<br />

preservation of their quality and fitness for use in the works. Any material<br />

which has been deteriorated or damaged beyond repairs and has become<br />

unfit for use shall be removed immediately from the site, failing which,<br />

the Engineer shall be at liberty to get the materials removed by agency.<br />

The Contractor will have to establish a suitable yard in an approved<br />

location at site for storing the fabricated steel structures and other materials<br />

which will be delivered to him by the Owner according to the Contract. The<br />

yard shall have proper facilities like, drainage, lighting, suitable access for<br />

large cranes, trailers and other heavy equipments. The yard shall be fenced<br />

all around with security arrangement and shall be of sufficiently large area to<br />

permit systematic storage of the fabricated steel structures without<br />

overcrowding and with suitable access for cranes, trailers and other<br />

equipment for use in erection work in proper sequence in accordance with<br />

the approved programme of work. The Tenderer should visit the site prior to<br />

submission of his Tender to acquaint himself with the availability of land<br />

and the development necessary by way of filling, drainage, access roads,<br />

(PCA.775.S034sca5) V.II-D2/S-V : 3


DCPL-K4A02<br />

fences, sheds etc. all of which shall be carried out by the Contractor as<br />

directed by the Engineer.<br />

2.6.3 Covered Store<br />

All field connection materials, paints, cement etc. shall be stored on well<br />

designed racks and platforms off the ground in a properly covered store<br />

building to be built.<br />

2.7.0 Quality Control<br />

The contractor shall establish and maintain quality control procedures for<br />

different items of work and materials as may be directed by the Engineer to<br />

assure compliance with the provisions of the Contract and shall submit the<br />

records of the same to the Engineer. The quality control operation shall<br />

include but not be limited to the following items of work:-<br />

1) Erection : Lines, levels, grades, plumbs, joint characteristics including<br />

tightness of bolts.<br />

2) Grouting : Cleaning and roughness of foundation, quality of materials<br />

used for grouting, admixtures, consistency and strength of grout.<br />

3) Painting : Preparation of surface for painting, quality of primers and<br />

paints, thinners, application and uniformity of coats.<br />

The Contractor shall salvage, collect and deliver all the packing materials<br />

to the Owner.<br />

3.0.0 WORKMANSHIP<br />

3.1.0 Erection<br />

3.1.1 Plant and equipment<br />

The suitability and adequacy of all erection tools and plant and equipment<br />

proposed to be used shall be efficient, dependable, in good working<br />

condition and shall have the approval of the Engineer.<br />

3.1.2 Method and sequence of erection<br />

The method and sequence of erection shall have the prior approval of the<br />

Engineer. The Erection shall arrange for most economical method and<br />

sequence available to him consistent with the Drawings and Specifications<br />

and such information as may be furnished to him prior to the execution<br />

of the Contract.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 4


DCPL-K4A02<br />

3.1.3 Temporary bracing<br />

Unless adequate bracing is included as a part of the permanent framing, the<br />

erector during erection shall install temporary guys and bracings where<br />

needed to secure the framing against loads such as wind or seismic forces<br />

comparable in intensity to that for which the structure has been designed,<br />

acting upon exposed framing as well as loads due to erection equipment and<br />

erection operations.<br />

If additional temporary guys are required to resist wind or seismic forces<br />

acting upon components of the finished structure installed by others<br />

during the course of the erection of the steel framing, arrangement for their<br />

installation by the erector shall be made.<br />

The responsibility of the Contractor in respect of temporary bracings and<br />

guys shall cease when the structural steel is once located, plumbed,<br />

levelled, aligned and grouted within the tolerances permitted under the<br />

specification and guyed and braced to the satisfaction of the Engineer.<br />

3.1.4 Temporary floors for buildings<br />

3.1.5 Setting out<br />

It shall be the responsibility of the Contractor to provide free of cost<br />

planking and to cover such floors during the work in progress as may be<br />

required by any Act of Parliament and/or by-laws of state, Municipal or other<br />

local authorities.<br />

Positioning and levelling of all steelwork, plumbing of stanchions and<br />

placing of every part of the structure with accuracy shall be in accordance<br />

with the approved Drawings and to the satisfaction of the Engineer. Concrete<br />

foundations, where required, shall be made by other agencies. Anchor bolts<br />

and other anchor steel shall be embedded by other agencies. The<br />

Contractor shall check the positions and levels of the anchor bolts, etc.<br />

before concreting and get them properly secured against disturbance<br />

during pouring operations. He shall remain responsible for correct<br />

positioning. For heavy columns, etc. the Contractor shall set proper screed<br />

bars if desired by the Engineer, to maintain proper level.<br />

Each tier of column shall be plumbed and maintained in a true vertical<br />

position subject to the limits of tolerance allowable under this Specification.<br />

No permanent field connections by bolting or welding shall be carried out<br />

until proper alignment and plumbing has been attained.<br />

3.1.6 Field bolting<br />

All relevant portions in respect of bolted construction of the Specification for<br />

Fabrication of Structural Steelwork applicable to the Project shall also be<br />

applicable for field bolting in addition to the following :<br />

Bolts shall be inserted in such a way so that they may remain in position<br />

under gravity even before fixing the nut. Bolted parts shall fit solidly together<br />

when assembled and shall not be separated by gaskets or any other<br />

(PCA.775.S034sca5) V.II-D2/S-V : 5


DCPL-K4A02<br />

interposed compressible materials. When assembled, all joint surfaces,<br />

including those adjacent to the washers shall be free of scales except tight<br />

mill scales. They shall be free of dirt, loose scales, burns, and other defects<br />

that would prevent solid seating of the parts. Contact surfaces within<br />

friction-type joints shall be free of oil, paint, lacquer, or galvanizing.<br />

All high tensile bolts shall be tightened to provide, when all fasteners in the<br />

joint are tight, the required minimum bolt tension by any of the following<br />

methods.<br />

a) Turn-of-nut method<br />

When the turn-of-nut method is used to provide the bolt tension,<br />

there shall first be enough bolts brought to a "snug tight" condition to<br />

ensure that the parts of the joint are brought into good contact with<br />

each other. "snug tight" is defined as the tightness attained by a<br />

few impacts of an impact wrench or the full effort of a man using an<br />

ordinary spud wrench. Following this initial operation, bolts shall be<br />

placed in any remaining holes in the connection and brought to snug<br />

tightness. All bolts in the joint shall then be tightened additionally by<br />

the applicable amount of nut rotation specified in Table-1 with<br />

tightening progressing systematically from the most rigid part of<br />

the joint to its free edges. During this operation there shall be no<br />

rotation of the part not turned by the wrench.<br />

TABLE - I<br />

------------------------------------------------------------------------------------------<br />

Bolts length not Bolt length Remarks<br />

exceeding 8 x dia.<br />

exceeding 8xdia.<br />

or 200 mm<br />

or 200 mm<br />

------------------------------------------------------------------------------------------<br />

1/2 turn 2/3 turn Nut rotation is<br />

relative to bolt<br />

regardless of the<br />

element (nut or<br />

bolt) being turned.<br />

Tolerance on<br />

rotation - 30<br />

over or under.<br />

Bolts may be installed without hardened washers when tightening<br />

is done by the turn-of-nut method. However, normal washers shall<br />

be used.<br />

Bolts tightened by the turn-of-nut method may have the outer face<br />

of the nut match-marked with the protruding bolt point before final<br />

tightening, thus affording the inspector visual means of noting the<br />

actual nut rotation. Such marks can be made by the wrench operator<br />

by suitable means after the bolts have been brought up snug tight.<br />

b) Torque Wrench tightening<br />

(PCA.775.S034sca5) V.II-D2/S-V : 6


NOTE :<br />

DCPL-K4A02<br />

When torque wrenches are used to provide the bolt tensions,<br />

the bolts shall be tightened to the torques specified in TABLE - II.<br />

Nuts shall be in tightening motion when torque is measured. When<br />

using torque wrenches to install several bolts in a single joint, the<br />

wrench shall be returned to touch up bolts previously tightened,<br />

which may have been loosened by the tightening of subsequent<br />

bolts, until all are tightened to the required tension.<br />

TABLE - II<br />

------------------------------------------------------------------------<br />

Nominal Bolt<br />

Torque to be applied<br />

Diameter (mm) (Kg.M) for bolt class 8.8<br />

of IS : 1367<br />

------------------------------------------------------------------------<br />

20 59.94<br />

22 81.63<br />

24 103.73<br />

------------------------------------------------------------------------<br />

The above torque values are approximate for providing tensions of 14.7<br />

MT for 20 mm dia., 18.2 MT for 22 mm dia; and 21.2 MT for 24 mm dia.<br />

bolts under moderately lubricated condition. The torque wrench shall be<br />

calibrated at least once daily to find out the actual torque required to<br />

produce the above required tension in the bolt by placing it in a tension<br />

indicating device. These torques shall be applied for tightening the bolts on<br />

that day with the particular torque wrench.<br />

In either of the above two methods, if required, for bolt entering and<br />

wrench operation clearances, tightening may be done by turning the bolt<br />

while the nut is prevented from rotating.<br />

Impact wrenches if used shall be of adequate capacity and sufficiently<br />

supplied with air to perform the required tightening of each bolt in<br />

approximately ten seconds.<br />

3.1.7 Field Welding<br />

Holes for turned bolts to be inserted in the field shall be reamed in the field.<br />

All drilling and reaming for turned bolts shall be done only after the parts<br />

to be connected are assembled. Tolerances applicable in the fit of the bolts<br />

shall be in accordance with relevant Indian Standard Specifications. All other<br />

requirements regarding assembly and bolt tightening shall be in accordance<br />

with this sub clause.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 7


DCPL-K4A02<br />

All field assembly and welding shall be carried out in accordance with<br />

the requirements of the specification for fabrication work applicable to the<br />

project, excepting such provisions therein which manifestly apply to shop<br />

conditions only. Where the fabricated structural steel members have been<br />

delivered painted, the paint shall be removed before field welding for a<br />

distance of at least 50 mm on either side of the joints.<br />

3.1.8 Holes, cutting and fitting<br />

3.2.0 Drifting<br />

No cutting of sections, flanges, webs, cleats, bolts, welds etc. shall be done<br />

unless specifically approved and/or instructed by the Engineer.<br />

The erector shall not cut, drill or otherwise alter the work of other trades, or<br />

his own work to accommodate other trades, unless such work is clearly<br />

specified in the Contract or directed by the Engineer. Wherever such work<br />

is specified the Contractor shall obtain complete information as to size,<br />

location and number of alterations prior to carrying out any work.<br />

Correction of minor misfits and reasonable amount of reaming and cutting of<br />

excess stock from rivets will be considered as permissible. For this, light<br />

drifting may be used to draw holes together and drills shall be used to<br />

enlarge holes as necessary to make connections. Reaming, that<br />

weakens the member or makes it impossible to fill the holes properly or to<br />

adjust accurately after reaming shall not be allowed.<br />

Any error in shop work which prevents the proper assembling and fitting of<br />

parts by moderate use of drift pins and reamers shall immediately be called<br />

to the attention of the Engineer and approval of the method of correction<br />

obtained. The use of gas cutting torches at erection site is prohibited.<br />

3.3.0 Grouting of stanchion bases and bearings of beams and girders on stone,<br />

brick or concrete (Plain or reinforced)<br />

Grouting shall be carried out with Ordinary Cement grout as described<br />

below :<br />

The mix shall be one (1) part cement and one (1) part sand and just enough<br />

water to make it workable. The positions to be grouted shall be cleaned<br />

thoroughly with compressed air jet and wetted with water and any<br />

accumulated water shall be removed. These shall be placed under expert<br />

supervision, taking care to avoid air-locks. Edges shall be finished properly. If<br />

the thickness of grout is 25 mm or more, two (2) parts of 6 mm down graded<br />

stone chips may be added to the above noted cement-sand grout mix, if<br />

required, by the Engineer or shown on the drawings.<br />

Admixtures like aluminium powder, "ironite" may be required to be added to<br />

the grout to enhance certain desirable properties of the grout.<br />

Alternatively, the grouting may be done with non-shrink high strength free flow<br />

cementious grout (ready mixed) like “Sika grout - 214", or "Anchor NSG" or<br />

approved equivalent.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 8


DCPL-K4A02<br />

No grouting shall be carried out until a sufficient number of bottom lengths of<br />

stanchions have been properly lined, levelled and plumbed and sufficient floor<br />

beams are tied in position.<br />

Whatever method of grouting is employed, the operation shall not be carried<br />

out until the steelwork has been finally levelled and plumbed, the stanchion<br />

bases being supported meanwhile by steel wedges, and immediately before<br />

grouting, the space under steel shall be thoroughly cleaned.<br />

3.4.0 Painting after erection<br />

Field painting, if required to be done by the erection Contractor, shall only<br />

be done after the structure is erected, levelled, plumbed, aligned and grouted in<br />

its final position, tested and accepted by the Engineer. However, touch up<br />

paintings, making good any damaged shop painting and completing any<br />

unfinished portion of the shop coat shall be carried out by the erection<br />

Contractor to the Owner. The materials and specification for such painting in<br />

the field shall be in accordance with the requirements of the specification for<br />

fabrication of structural steelwork applicable for the project.<br />

Painting shall not be done in rainy or foggy weather or when humidity is such<br />

as to cause condensation on the surfaces to be painted. Before painting of steel,<br />

which is delivered unpainted, is commenced, all surfaces to be painted shall<br />

be dried and thoroughly cleaned from all loose scale and rust.<br />

All field bolts, welds and abrasions to the shop coat shall be spot painted with<br />

the same paint used for the shop coat. Where specified, surfaces which will be<br />

in contact after site assembling shall receive a coat of paint (in addition to the<br />

shop coat, if any) and shall be brought together while the paint is still wet.<br />

Surface which will be inaccessible after field assembly shall receive the full<br />

specified protective treatment before assembly. Bolts and fabricated steel<br />

members which are galvanized or otherwise treated and steel members to<br />

be encased in concrete shall not be painted.<br />

The specification for paint and workmanship shall be in accordance with<br />

the requirements of the specification for fabrication of structural steelwork<br />

applicable to the project.<br />

The number of coats and the shades to be used shall be as specified or as<br />

directed by the Engineer.<br />

3.5.0 Stainless Steel Plate Lining in Bunker Hopper<br />

The hopper portion of the coal bunkers shall be lined with stainless steel<br />

plates of 3 mm thickness. The stainless steel shall be of AISI-316 quality.<br />

The work includes supply, fabrication, welding and fixing of stainless steel<br />

lining plate to bunker M.S. plate as per drawing.<br />

The stainless steel liner shall be fixed to the Bunker hopper by plug welding<br />

using special electrodes (such as, Inox-CW coding AWS-310-16 ISMBOS-<br />

311 or Inox-D2 coding AWSE-309-16, ISMB 04-311 manufactured by Advani<br />

Oerlikon Ltd). Such plug welding shall be done by drilling 21.5 mm dia.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 9


DCPL-K4A02<br />

holes at 300 mm centre to centre both ways. The plug welding shall be<br />

ground flush with the lining plate.<br />

3.6.0 Final cleaning up<br />

Upon completion of erection and before final acceptance of the work by the<br />

Engineer, the Contractor shall remove all falsework, rubbish and all<br />

Temporary Works resulting in connection with the performance of his work.<br />

3.7.0 Safety Measures during Erection<br />

The safety measures to workmen and supervisors during all types of<br />

erection work (e.g., use of lifting appliances, slingning, welding, gas<br />

cutting, etc.) should be taken as per IS : 7205. When any statutory provisions<br />

exist, the same shall be complied with in addition to the provisions contained<br />

in the above code.<br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA<br />

4.1.0 General<br />

Loading tests shall be carried out on erected structures, if required by the<br />

Engineer, to check adequacy of fabrication and/or erection. Any structure or<br />

a part thereof found to be unsuitable for acceptance as a result of the test<br />

shall have to be dismantled and replaced with suitable member. In course of<br />

dismantling, if any damage is done to any other parts of the structure or to<br />

any fixtures, the same shall be made good by the Contractor responsible, to<br />

the satisfaction of the Engineer.<br />

The structure or structural member under consideration shall be loaded<br />

with its actual dead load for as long a time as possible before testing and<br />

the tests shall be conducted as indicated in the following Sub-clauses 4.1.1,<br />

4.1.2 and 4.1.3. The method of testing and application of loading shall be as<br />

approved by the Engineer.<br />

4.1.1 Stiffness Test<br />

In this test, the structure or member shall be subjected, in addition to its<br />

actual dead load, to a test load equal to1.5 times the specified superimposed<br />

load, and this loading shall be maintained for 24 hours. The maximum<br />

deflection attained during the test shall be within the permissible limit. If, after<br />

removal of the test load, the member or structure does not show a recovery<br />

of at least 80 per cent of the maximum strain or deflection shown during 24<br />

hours under load, the test shall be repeated. The structure or member<br />

shall be considered to have sufficient stiffness, provided that the recovery<br />

after this second test is not less than 90 percent of the maximum increase in<br />

strain or deflection recorded during the second test.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 10


DCPL-K4A02<br />

4.1.2 Strength Test<br />

The structure or structural member under consideration shall be subjected,<br />

in addition to its actual dead load, to a test load equal to the sum of the<br />

dead load and twice the specified superimposed load, and this load shall be<br />

maintained for 24 hours.<br />

In the case of wind load, a load corresponding to twice the specified wind<br />

load shall be applied and maintained for 24 hours, either with or without the<br />

vertical test load for more severe condition in the member under<br />

consideration or the structure as a whole. Complete tests under both<br />

conditions may be necessary to verify the strength of the structure. The<br />

structure shall be deemed to have adequate strength if, during the test, no<br />

part fails and if on removal of the test load, the structure shows a recovery<br />

of at least 20 per cent of the maximum deflection or strain recorded during<br />

the 24 hours under load.<br />

4.1.3 Structure of same design<br />

Where several structures are built to the same design and it is considered<br />

unnecessary to test all of them, one structure, as a prototype, shall be fully<br />

tested, as described in previous Sub-clauses, but in addition, during the<br />

first application of the test load, particular note shall be taken of the strain or<br />

deflection when the test load 1.5 times the specified superimposed load has<br />

been maintained for 24 hours. This information is required as a basis of<br />

comparison in any check test carried out on samples of the structure.<br />

When a structure of the same type is selected for a check test, it shall be<br />

subjected, in addition to its actual dead load, to a superimposed test load,<br />

equal to 1.5 time the specified live load, in a manner and to an extent<br />

prescribed by the Engineer. This load shall be maintained for 24 hours,<br />

during which time, the maximum deflection shall be recorded. The check<br />

test shall be considered satisfactory, provided that the maximum strain or<br />

deflection recorded in the check test does not exceed by more than 20% of<br />

the maximum strain or deflection recorded at similar load in the test on<br />

the prototype.<br />

4.1.4 Repair for subsequent test and use after strength tests<br />

4.2.0 Tolerances<br />

An actual structure which has passed the "Strength Test" as specified in<br />

Sub-clause 4.1.2 hereinbefore and is subsequently to be erected for use,<br />

shall be considered satisfactory for use after it has been strengthened by<br />

replacing any distorted members and has subsequently satisfied the<br />

'Stiffness Test' as specified in Sub-clause 4.1.1. hereinbefore.<br />

Some variation is to be expected in the finished dimensions of structural steel<br />

frames. Unless otherwise specified, such variations are deemed to be<br />

within the limits of good practice when they are not in excess of the<br />

cumulative effect of detailed erection clearances, fabricating tolerances for<br />

the finished parts and the rolling tolerances for the profile dimensions<br />

(PCA.775.S034sca5) V.II-D2/S-V : 11


DCPL-K4A02<br />

permitted under the Specifications for fabrication of structural steelwork<br />

applicable to this Project and as specified below :<br />

I. For Buildings Containing Cranes<br />

Component Description Variation<br />

Allowed<br />

Main columns a) Shifting of column axis<br />

at foundation level with<br />

respect to building line<br />

i) In longitudinal i) 3.0 mm<br />

direction<br />

ii) In lateral direction<br />

ii) 3.0 mm<br />

b) Deviation of both major<br />

column axis from vertical<br />

between foundation and<br />

other member connection<br />

levels :<br />

i) For a column upto i) 3.5 mm<br />

and including 10M from true<br />

height<br />

vertical<br />

ii) For a column greater ii) 3.5 mm from<br />

than 10M but less true vertical for<br />

than 40M height any 10M length<br />

measured between<br />

connection levels,<br />

but not more than<br />

7.0 mm per<br />

30 m length.<br />

Component Description Variation<br />

Allowed<br />

c) For adjacent pairs of<br />

columns across the width<br />

of the building prior to<br />

placing of truss.<br />

d) For any individual column<br />

deviation of any bearing<br />

or resting level from<br />

levels shown on drawings.<br />

9 mm on true<br />

span.<br />

3.0 mm<br />

(PCA.775.S034sca5) V.II-D2/S-V : 12<br />

e) For adjacent pairs of<br />

columns either across the<br />

width of building or<br />

longitudinally level


DCPL-K4A02<br />

difference allowed between<br />

bearing or seating level<br />

supposed to be at the<br />

same level.<br />

3 mm<br />

Trusses a) Deviation at centre of 1/1500 of the<br />

span of upper chord span or not<br />

member from vertical greater than<br />

plane running through 10 mm whichever<br />

centre of bottom chord. is the least.<br />

b) Lateral displacement of 1/250 of depth<br />

top chord at centre of of truss or<br />

span from vertical plane 20 mm whichever<br />

running through centre is the least.<br />

of supports.<br />

Crane<br />

a) Difference in levels of<br />

Girders &<br />

crane rail measured bet-<br />

Tracks ween adjacent columns. 2.0 mm<br />

b) Deviation to crane rail<br />

gauge<br />

c) Relative shifting of ends<br />

of adjacent crane rail in<br />

plan and elevation after<br />

thermit welding.<br />

d) Deviation of crane rail<br />

axis from centre line of<br />

web.<br />

3.0 mm<br />

1.0 mm<br />

3.5 mm<br />

Component Description Variation<br />

Allowed<br />

Setting of<br />

Expansion<br />

gaps<br />

At the time of setting of<br />

the expansion gaps, due<br />

regard shall be taken of<br />

the ambient temperature<br />

above or below 30C.<br />

The coefficient of expansion<br />

or contraction shall<br />

be taken as 0.000012 per<br />

C per unit length.<br />

II.<br />

For Building without Cranes<br />

The maximum tolerances for line and level of the steel work shall<br />

be 3.0 mm on any part of the structure. The structure shall not be<br />

(PCA.775.S034sca5) V.II-D2/S-V : 13


4.3.0 Acceptance<br />

DCPL-K4A02<br />

out of plumb more than 3.5 mm on each 10M section of height and<br />

not more than 7.0 mm per 30 M section.<br />

These tolerances shall apply to all parts of the structure unless the<br />

drawings issued for erection purposes state otherwise.<br />

Structures and members which have passed the tests and conform to all<br />

requirements specified in the foregoing Sub-clause 4.1.0, 4.1.1, 4.1.2,<br />

4.1.3 and 4.1.4 and other applicable provisions of this Specification and are<br />

within the limits of tolerances specified in Sub-clause 4.2.0 and/or<br />

otherwise approved by the Engineer shall be treated as approved and<br />

accepted for the purpose of fulfilment of the provisions of this Contract.<br />

5.0.0 INFORMATION TO BE SUBMITTED<br />

5.1.0 Before Tender<br />

Along with the Tenders the Tenderers will be required to submit the<br />

following information :<br />

5.1.1 Tentative Programme<br />

The Tenderer shall submit a tentative programme based on the information<br />

available in the Tender Document and visit to Site indicating the structurewise<br />

erection schedule proposed to be maintained by the Contractor to<br />

complete the job in time in accordance with the Contract.<br />

5.1.2 Constructional Plant and Equipment, Tools,<br />

Temporary Works & Manpower<br />

5.1.3 Erection yard<br />

A detailed list of all Constructional Plant & Equipment like cranes, derricks,<br />

winches, welding sets, erection tools etc. along with their make, model,<br />

present condition and location available with the Tenderer which he will be<br />

able to employ on the job to maintain the progress of work in accordance<br />

with the Contract shall be submitted along with the Tender. The total<br />

number of each category of experienced personnel like fitters, welders,<br />

riggers etc. that he will be able to employ on the job shall also be indicated.<br />

A site plan showing the layout and location of the erection yard proposed<br />

to be established by the Tenderer shall be attached with the Tender<br />

indicating the storage space for fabricated steel materials, site-fabrication<br />

and repair shop, covered stores, offices, locations of erection equipments<br />

and other facilities. The Engineer shall have the right to modify the<br />

(PCA.775.S034sca5) V.II-D2/S-V : 14


DCPL-K4A02<br />

arrangement and location of the proposed yard to suit site conditions and<br />

the Contractor shall comply with the same without any claim whatsoever.<br />

5.2.0 After award of the Contract<br />

After award of the contract, the Contractor shall submit the following :-<br />

5.2.1 Detailed Programme<br />

The Contractor shall submit a detailed erection programme for completion of<br />

the work in time in accordance with the Contract. This will show the target<br />

programme, with details of erection proposed to be carried out in each<br />

fortnight, details of major equipment required and an assessment of<br />

required strength of various categories of workers in a proforma approved<br />

by the Engineer.<br />

5.2.2 Fortnightly Progress Report<br />

The Contractor shall submit fortnightly progress reports in triplicate to the<br />

Engineer showing along with necessary photographs, 125 mm x 90 mm<br />

size, and all details of actual achievements against the target programme<br />

specified in Sub-clause 5.2.1 above. Any shortfall in the achievement in a<br />

particular fortnight must be made up within the next fortnight. Along with<br />

this report, the Contractor shall also furnish details of fabricated materials in<br />

hand at site and the strength of his workers.<br />

(PCA.775.S034sca5) V.II-D2/S-V : 15


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-VII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROADS AND DRAINAGE<br />

(PCA.775.S034sca7)


DCPL-K4A02<br />

CONTENTS<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0 SCOPE V.II-D2/S-VII : 1<br />

2.0 GENERAL V.II-D2/S-VII : 1<br />

3.0 EXECUTION V.II-D2/S-VII : 6<br />

4.0 TESTING AND ACCEPTANCE V.II-D2/S-VII : 30<br />

CRITERIA<br />

(PCA.775.S034sca7)


VOLUME : II-D/2<br />

SECTION-VII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROADS AND DRAINAGE<br />

1.0 SCOPE<br />

This specification covers all work required for the construction of road<br />

including box-cutting, edging, sub-base, water bound macadam, bituminous<br />

macadam, wearing course etc. and shall include all incidental items of work<br />

not shown or specified but reasonably implied or necessary for the<br />

completion of the work.<br />

This specification also includes all work required for drainage including<br />

road side drain, R.C.C. culverts, pipe-culverts, drainage pipes, manholes<br />

etc. and all other incidental items.<br />

2.0 GENERAL<br />

2.1 Work to be Provided for by the Contractor<br />

The work to be provided for by the Contractor, unless specified otherwise,<br />

shall include but not be limited to the following :<br />

a) Furnish all labour, supervision, services, materials, equipment, tools<br />

and plants, transportation etc. required for the work.<br />

b) Submit for approval detailed schemes of all operations required for<br />

executing the work e.g. material handling, placement, services,<br />

approaches etc.<br />

c) To carry out and submit to the Engineer results of tests whenever<br />

required by the Engineer to assess the quality of work.<br />

2.2 Work to be Provided for by Others<br />

No work under this specification will be provided for by any agency other<br />

than the Contractor unless specifically mentioned elsewhere in the<br />

Contract.<br />

2.3 Codes and Standards<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 1


DCPL-K4A02<br />

All work under this specification, unless specified otherwise, shall conform<br />

to the latest revision and/or replacements of the following or any other<br />

relevant I.S. Specifications and Codes of Practice.<br />

1. Specification for road and bridge works of Ministry of shipping &<br />

Transport (Roads wing) Published by the IRC.<br />

2. IRC-19 Standard specifications and Code of Practice for Water<br />

Bound Macadam.<br />

3. IRC:SP-11 Hand Book of Quality Control for Construction of Roads<br />

and Runways.<br />

4. IS:456 Indian Standard Code of Practice for Plain and<br />

Reinforced Concrete.<br />

5. IS:2212 Code of Practice for Brickwork.<br />

6. IS:783 Code of Practice for Laying of Concrete Pipes.<br />

7. Other specifications mentioned elsewhere in this specification.<br />

In case any particular aspect of work is not covered specifically by Indian<br />

Standard Specification, any other standard practice as may be specified by<br />

the Engineer shall be followed.<br />

2.4.0 Conformity with Designs<br />

The contractor shall carryout the work as per the drawings issued to him<br />

and/or contractor's drawings which are approved by the Engineer and/or<br />

the Engineer's instructions.<br />

2.5.0 Materials to be Used<br />

2.5.1 General<br />

All materials required for the work shall be of best commercial variety and<br />

as approved by the Engineer.<br />

2.6.0 Quality Control<br />

The Contractor shall establish and maintain quality control for the various<br />

aspects of the work, method, materials and equipment used. All works<br />

performed shall conform to the lines, grades, cross sections and<br />

dimensions shown on the drawings or as directed by the Engineer.<br />

Permitted tolerances for roadworks are described hereinafter.<br />

i) Horizontal Alignments<br />

Horizontal alignments shall be reckoned with respect to the centre<br />

line of the carriageway as shown on the drawings. The edges of the<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 2


DCPL-K4A02<br />

carriageway as constructed shall be correct within a tolerance of <br />

25 mm therefrom. The corresponding tolerance for edges of the<br />

roadway and lower layers of pavement shall be 40 mm.<br />

ii)<br />

Longitudinal Profile<br />

The levels of the subgrade and different pavement courses as<br />

constructed, shall not vary from those calculated with reference to the<br />

longitudinal and cross-profile of the road shown on the drawings or as<br />

directed by the Engineer, beyond tolerances mentioned below :<br />

Sub-grade<br />

Sub-base<br />

Base course<br />

25 mm<br />

20 mm<br />

15 mm<br />

Wearing course 10 mm<br />

Tolerance in wearing course shall not be permitted in<br />

conjunction with the positive tolerance for base course if the<br />

thickness of the former is thereby reduced by more than 6 mm.<br />

iii)<br />

Surface Regularity of Subgrade and Pavement Courses<br />

The surface regularity of completed sub-bases, base courses and<br />

wearing surfaces in the longitudinal and transverse directions shall be<br />

within the tolerances indicated in Table-I.<br />

The longitudinal profile shall be checked with a 3 metre long straight<br />

edge, at the middle of each traffic lane along a line parallel to the<br />

centre of the road. The transverse profile shall be checked with a set<br />

of three camber boards at intervals of 10 metres.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 3


DCPL-K4A02<br />

TABLE -I<br />

PERMITTED TOLERANCES OF SURFACE REGULARITY<br />

FOR PAVEMENT COURSES<br />

____________________________________________________________________________________________________________________<br />

Sl.<br />

No. Type of Construction Longitudinal Profile with 3 metre straight edge Cross Profile<br />

__________________________________________________________________________________________________________<br />

Maximum Permi- Maximum number of undulations Maximum permissible variassible<br />

undulation permitted in any 300 metres tion from specified profile<br />

l ength exceeding : under camber template<br />

mm mm mm<br />

___________________________________<br />

18 12 10 6<br />

1 2 3 4 5 6 8<br />

__________________________________________________________________________________________________________<br />

1. Earthen subgrade 25 30 - - - 15<br />

2. Granular subbase 15 - 30 - - 12<br />

3. Water Bound Macadam with<br />

oversize metal (40-90 mm size) 15 - 30 - - 12<br />

4. Water Bound Macadam with normal<br />

size metal (20-50 mm and 40-63mm<br />

size), Bituminous Penetration<br />

Macadam 12 - - 30 - 8<br />

5. Surface dressing ** (two coat)<br />

over WBM (20-50 mm or 40-63 mm<br />

size metal), Bituminous penetration<br />

macadam or built-up<br />

spray grout 12 - - 20 - 8<br />

____________________________________________________________________________________________________________<br />

___________________________________________________________________________________________________________________________<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 4


DCPL-K4A02<br />

Sl.<br />

No. Type of Construction Longitudinal Profile with 3 metre straight edge Cross Profile<br />

_________________________________________________________________________________________________________________<br />

Maximum Permi- Maximum number of undulations Maximum permissible variassible<br />

undulation permitted in any 300 metres tion from specified profile<br />

l ength exceeding : under camber template<br />

mm mm mm<br />

_____________________________________<br />

18 12 10 6<br />

1 2 3 4 5 6 8<br />

_________________________________________________________________________________________________________________<br />

6. Open graded premix carpet,<br />

mixseal surfacing 10 - - - 30 6<br />

7. Bituminous macadam 10 - - - 20 *** 6<br />

8. Semi-dense carpet 10 - - - 20 *** 6<br />

9. Asphaltic Concrete 8 - - - 10 *** 4<br />

_________________________________________________________________________________________________________________<br />

NOTES :<br />

1. ** For surface dressing in all other cases, the standards of surface evenness will be the same as those for the surface<br />

receiving the surface dressing.<br />

2. *** These are for machine laid surfaces. If laid manually due to unavoidable reasons, tolerance upto 50 percent above<br />

these values in this column may be permitted at the discretion of the Engineer. However, this relaxation does not apply to<br />

the values of maximum undulation for longitudinal and cross profiles mentioned in columns 3 and 8 on the table.<br />

3. Surface evenness requirements in respect of both the longitudinal and cross profiles should be simultaneously satisfied.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 5


DCPL-K4A02<br />

3.0 EXECUTION<br />

3.1.0 Shoulder Construction<br />

3.1.1 Description<br />

3.1.2 Materials<br />

This work shall consist of constructing shoulders on either side of the<br />

pavement, in accordance with the requirements of this specification and in<br />

conformity with the lines, grades and cross-sections shown on the drawings<br />

or as directed by the Engineer.<br />

Shoulder may be of selected earth or grannlar material conforming to the<br />

requirements of embankment construction or granular sub-base construction<br />

respectively.<br />

3.1.3 Construction Operations<br />

3.2.0 Kerb<br />

3.2.1 Material<br />

Except in the case of bituminous constructions, shoulders shall be<br />

constructed in advance of the laying of pavement courses. The compacted<br />

thickness of each layer of shoulder shall correspond to the compacted layer<br />

of pavement course to be laid adjacent to it. After compaction, the inside<br />

edges of shoulders shall be trimmed vertical and included area cleaned of all<br />

spilled material before proceeding with the construction of the pavement<br />

layer.<br />

In the case of bituminous courses, shouldering operations shall start only<br />

after the pavement course has been laid and compacted.<br />

Regardless of the method of laying, all shoulder construction material<br />

shall be placed directly on the shoulder. Any spilled material dragged on to<br />

the pavement surface shall be immediately removed, without damage to the<br />

pavement and the area so affected thoroughly cleaned.<br />

During all stages of shoulder construction, the required cross-fall shall be<br />

maintained to drain off surface water.<br />

Kerb, if required for construction of footpath, shall consist of precast<br />

concrete blocks with a concrete grade of M-15. The blocks shall be 100 mm<br />

wide and of suitable length. The depth of blocks unless otherwise mentioned<br />

elsewhere, shall be 375 mm considering 225 mm height of footpath from the<br />

road level.<br />

3.2.2 Laying<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 6


DCPL-K4A02<br />

The Kerb shall be laid by cutting trenches 150 mm deep. The width of the trench shall<br />

be minimum and just sufficient to insert the kerbs. The inside faces of the Kerbs<br />

shall be in plumb and the gap between the block shall not be more than 10 mm.<br />

The kerbs shall be thoroughly packed with a mixture of stone chips (50%) and<br />

moorum (50%) at the outside face. The laying and packing shall be done in a proper<br />

workmanlike manner acceptable to the Engineer.<br />

3.3.0 Sub-base (Granular Sub-base)<br />

3.3.1 Description<br />

3.3.2 Materials<br />

This work shall consist of laying and compacting well-graded material on prepared<br />

subgrade in accordance with the requirements of these specifications. The material<br />

shall be laid in one or more layers as shown on the drawings and according to lines,<br />

grades and cross sections shown on the drawings or as directed by the Engineer.<br />

The materials to be used for the work shall be natural sand, moorum, gravel,<br />

crushed stone, crushed slag, crushed concrete, brick metal, laterite, kanker etc. or<br />

combinations thereof depending upon the grading required. The mixed materials shall<br />

be free from organic or other deleterious constituents and conform to one of the three<br />

gradings given in Table-II below.<br />

TABLE-II<br />

Grading for Granular Sub-base Materials<br />

__________________________________________________________________<br />

Sieve designation<br />

Percent by weight passing the seive<br />

Grading 1 Grading 2 Grading 3<br />

__________________________________________________________________<br />

80 mm 100 100 100<br />

63 mm 90-100 90-100 90-100<br />

4.75 mm 35-70 40-90 50-100<br />

75 micron 0-20 0-25 0-30<br />

__________________________________________________________________<br />

CBR Value (Minimum) :<br />

for fraction of material<br />

passing 20 mm sieve 30% 25% 20%<br />

__________________________________________________________________<br />

Note : The material passing 425 micron sieve for all the three gradings when<br />

tested according to IS:2720 (Part V) shall have liquid limit and plasticity index<br />

of not more than 25 percent and 6 percent respectively.<br />

3.3.3 Physical Requirements<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 7


DCPL-K4A02<br />

The fraction of material passing 20 mm sieve shall give a CBR value as<br />

specified in Table-II when tested in accordance with IS:2720 (Part XVI)<br />

after preparing the samples at maximum dry density and optimum moisture<br />

content corresponding to IS:2720 (Part VII) and soaking the same in water<br />

for 4 days.<br />

3.3.4 Spreading and Compacting<br />

Immediately prior to the laying of sub-base, the subgrade already finished<br />

shall be prepared by removing all vegetation and other extraneous matter,<br />

lightly sprinkled with water, if necessary, and rolled with one pass of 8-10<br />

tonne smooth wheeled roller.<br />

The sub-base material shall be spread on the subgrade with the help of a<br />

drag spreader, motor grader or other approved means. The thickness of<br />

loose layers shall be so regulated that the maximum thickness of the layer<br />

after consolidation does not exceed 150 mm.<br />

Moisture content of the loose material shall be checked in accordance with<br />

IS:2720 (Part II) and suitably adjusted by sprinkling additional water from a<br />

hose line, truck mounted water tank or other approved means so that at the<br />

time of compaction it is from 1 percent above to 2 percent below the optimum<br />

moisture content corresponding to IS:2720 (Part VIII). While adding water,<br />

due allowance shall be made for evaporation losses. After water has been<br />

added, the material shall be processed by mechanical or other approved<br />

means if so directed by the Engineer until the layer is uniformly wet.<br />

Immediately thereafter, rolling shall be started with 8 to 10 tonne smooth<br />

wheeled rollers or other approved plant. Rolling shall commence at the<br />

edges and progress towards the centre longitudinally except that on<br />

superelevated portions it shall progress from the lower to the upper edge<br />

parallel to the centre line of the pavement. Each pass of the roller shall<br />

uniformly overlap not less than one third of the track made in the<br />

preceding pass. During rolling, the grade and camber shall be checked and<br />

any high spots or depressions which become apparent corrected by<br />

removing or adding fresh material.<br />

Rolling shall be continued till the density achieved is at least 100% of the<br />

maximum dry density for the material determined as per IS:2720 (Part VII).<br />

The surface of any layer of material on completion of compaction shall be<br />

well closed, free from movement under compaction plant and from<br />

compaction planes, ridges, cracks or loose material. All loose, segregated<br />

or otherwise defective areas shall be made good to the full thickness of layer<br />

and re-compacted.<br />

3.4.0 Water Bound Macadam Sub-base/Base Course<br />

3.4.1 Description<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 8


3.4.2 Materials<br />

DCPL-K4A02<br />

Water bound macadam shall consist of clean, crushed aggregates mechanically<br />

interlocked by rolling and bonded together with screenings, binding material, where<br />

necessary and water, laid on a prepared subgrade or sub-base, as the case may be,<br />

and finished in accordance with the requirements of these Specifications and in<br />

conformity with the lines, grades and cross-sections shown on the drawings or<br />

otherwise directed by the Engineer.<br />

3.4.2.1 Coarse Aggregates - General Requirements<br />

Coarse aggregates shall be either crushed or broken stone. The aggregates shall<br />

conform to the physical requirements set forth in Table-III.<br />

TABLE-III<br />

Physical Requirements of Coarse Aggregates<br />

for Water Bound Macadam<br />

____________________________________________________________<br />

Sl. Type of Test Test method Requirements<br />

No. Construction<br />

___________________________________________________________<br />

1. Sub-base Los Angeles IS:2386 50 percent<br />

Abrasion Value* (Part IV) maximum.<br />

or<br />

Aggregate IS:2386 40 percent<br />

Impact Value (Part IV) maximum.<br />

or<br />

IS:5640**<br />

2. Base a) Loss Angeles IS:2386 50 percent<br />

Abrasion Value* (Part IV) maximum.<br />

or<br />

Aggregate IS:2386 40 percent<br />

Impact Value Part IV) maximum.<br />

or<br />

IS:5640**<br />

b) Flakiness IS:2386 15 percent<br />

Index*** (Part I) maximum.<br />

__________________________________________________________<br />

* Aggregate may satisfy requirements of either of the two tests.<br />

** Aggregates like brick metal, kankar and laterite which get softened<br />

in presence of water, shall be tested for impact value under<br />

conditions in accordance with IS:5640.<br />

*** The requirements of Flakiness Index shall be enforced only in case of<br />

crushed or broken stone and crushed slag.<br />

3.4.2.2 Crushed or Broken Stone<br />

Crushed or broken stone shall be hard, durable and free from excess of<br />

flat, elongated, soft and disintegrated particles, dirt and other objectionable<br />

matter.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 9


DCPL-K4A02<br />

3.4.2.3 Grading Requirements of Coarse Aggregates<br />

The coarse aggregates shall conform to one of the gradings given in Table-<br />

IV, provided, however, the use of Grading No. 1 shall be restricted to subbase<br />

courses only.<br />

TABLE-IV<br />

GRADING REQUIREMENTS OF COARSE AGGREGATES<br />

__________________________________________________________________<br />

Grading Size range Sieve Percent by weight<br />

No. designation passing the sieve<br />

__________________________________________________________________<br />

1. 90 mm to 40 mm 100 mm 100<br />

80 mm 65-85<br />

63 mm 25-60<br />

40 mm 0-15<br />

20 mm 0-5<br />

2. 63 mm to 40 mm 80 mm 100<br />

63 mm 90-100<br />

50 mm 35-70<br />

40 mm 0-15<br />

20 mm 0-5<br />

3. 50 mm to 20 mm 63 mm 100<br />

50 mm 95-100<br />

40 mm 35-70<br />

20 mm 0-10<br />

10 mm 0-5<br />

__________________________________________________________________<br />

3.4.2.4 Screenings<br />

Screenings to fill voids in the coarse aggregate shall generally consist of<br />

the same material as the coarse aggregate. However, where permitted,<br />

predominantly non-plastic material such as moorum or gravel (other than<br />

rounded river borne material) may be used for this purpose provided liquid<br />

limit and plasticity index of such material is below 20 and 6 respectively and<br />

fraction passing 75 micron sieve does not exceed 10 percent.<br />

As far as possible, screenings shall conform to the gradings set forth in<br />

Table-V Screenings of Type A in Table shall be used with coarse<br />

aggregates of grading 1 in Table IV. Screenings of Type A or B, shall be<br />

used with coarse aggregates of grading 2. Type B screenings shall be used<br />

with coarse aggregates of grading 3.<br />

TABLE-V : GRADINGS FOR SCREENINGS<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 10


DCPL-K4A02<br />

__________________________________________________________________<br />

Grading Size of Sieve Percent by weight<br />

Classi- screenings designation passing the sieve<br />

fication<br />

__________________________________________________________________<br />

A 12.5 mm 12.5 mm 100<br />

10.0 mm 90-100<br />

4.75 mm 10-30<br />

150 micron 0-8<br />

B 10 mm 10 mm 100<br />

4.75 mm 85-100<br />

150 micron 10-30<br />

__________________________________________________________________<br />

3.4.2.5 Binding Material<br />

Binding material to be used for water bound macadam construction shall<br />

comprise of a suitable material approved by the Engineer having plasticity<br />

index value of less than 6 as determined in accordance with IS:2720 (Part<br />

V).<br />

Application of binding material may not be necessary, when the<br />

screenings used are of crushable type such as moorum or gravel.<br />

3.4.3 Construction Operations<br />

3.4.3.1 Preparation of Base<br />

The subgrade/sub-base to receive the water bound macadam coarse shall<br />

be prepared to the specified grade and camber and made free of dust and<br />

other extraneous material. Any ruts or soft yielding places shall be corrected<br />

in an approved manner and rolled until firm. Where water bound macadam<br />

is to be laid over an existing black topped surface, 50 mm x 50 mm furrows<br />

shall be cut at an angle of 45 degrees to the centre line of the road at 1<br />

metre intervals in the latter before laying the coarse aggregate.<br />

3.4.3.2 Inverted Choke<br />

If the water bound macadam is to be laid directly over the sub-grade,<br />

without any other intervening pavement course, a 25 mm course of<br />

screenings (Grading B) shall be spread on the prepared subgrade before<br />

application of the coarse aggregates is taken up.<br />

3.4.3.3 Spreading Coarse Aggregate<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 11


3.4.3.4 Rolling<br />

DCPL-K4A02<br />

The coarse aggregates shall be spread uniformly upon the prepared surface<br />

in such quantities that the thickness of the compacted layer is 100 mm for<br />

grading 1 and 75-100 mm for gradings 2 and 3 for each layer.<br />

The spreading shall be done from stockpiles along the side of the roadway or<br />

directly from vehicles. In no case shall the aggregate be dumped in heaps<br />

directly on the surface prepared to receive the aggregate nor shall hauling<br />

over uncompacted or partially compacted base be permitted.<br />

The surface of the aggregates spread shall be carefully checked with<br />

templates and all high or low spots remedied by removing or adding<br />

aggregate as may be required. No segregation of large or fine particles shall<br />

be allowed and the coarse aggregate as spread shall be of uniform gradation<br />

with no pockets of fine material.<br />

The coarse aggregate shall not normally be spread more than 3 days in<br />

advance of the subsequent construction operations.<br />

Immediately following the spreading of the coarse aggregate, rolling<br />

shall be started with three wheeled power rollers of 8 to 10 tonne capacity or<br />

tandem or vibratory rollers of approved type. The weight of the roller shall<br />

depend upon the type of the aggregate and be indicated by the Engineer.<br />

Except on superelevated portions where the rolling shall proceed from inner<br />

edge to the outer, rolling shall begin from the edges gradually progressing<br />

towards the centre. First the edge/edges shall be compacted with roller<br />

running forward and backward. The roller shall then move inwards parallel to<br />

the centre line of the road, in successive passes uniformly lapping<br />

preceding tracks by at least one half width.<br />

Rolling shall continue until the aggregates are thoroughly keyed and the<br />

creeping of aggregates ahead of the roller is no longer visible. During rolling<br />

slight sprinkling of water may be done, if necessary. Rolling shall not be<br />

done when the subgrade is soft or yielding or when it causes a wave-like<br />

motion in the subgrade or sub-base course.<br />

The rolled surface shall be checked transversely and longitudinally with<br />

templates and any irregularities corrected by loosening the surface, adding or<br />

removing necessary amounts of aggregate and re-rolling until the entire<br />

surface conforms to desired camber and grade. In no case shall the use of<br />

screenings be permitted to make up depressions.<br />

3.4.3.5 Applications of Screenings<br />

After the coarse aggregate has been rolled, screenings to completely<br />

fill the interstices shall be applied gradually over the surface. These shall<br />

not be damp or wet at the time of application. Dry rolling shall be done<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 12


DCPL-K4A02<br />

while the screenings are being spread so that vibrations of the roller cause<br />

them to settle into the voids of the coarse aggregate. The screenings shall<br />

not be dumped in piles but be spread uniformly in successive thin layers<br />

either by the spreading motion of hand shovels or by mechanical spreaders,<br />

or directly from trucks. Trucks operating for spreading the screenings shall<br />

be so driven as not to disturb the coarse aggregate.<br />

The screenings shall be applied at a slow and uniform rate (in three or<br />

more applications) so as to ensure filling of all voids. This shall be<br />

accompanied by dry rolling and brooming with mechanical brooms, handbrooms<br />

or both. In no case shall the screenings be applied so fast and thick<br />

as to form cakes or ridges on the surface in such a manner as would<br />

prevent filling of voids or prevent the direct bearing of the roller on the coarse<br />

aggregate. These operations shall continue until no more screenings can<br />

be forced into the voids of the coarse aggregate.<br />

The spreading, rolling and brooming of screenings shall be carried out in<br />

only such lengths of the road which could be completed within one day's<br />

operation.<br />

3.4.3.6 Sprinkling and Grouting<br />

After the screenings have been applied, the surface shall be copiously<br />

sprinkled with water, swept and rolled. Hand brooms shall be used to<br />

sweep the wet screenings into voids and to distribute them evenly. The<br />

sprinkling, sweeping and rolling operations shall be continued, with<br />

additional screenings applied as necessary, until the coarse aggregate<br />

has been thoroughly keyed, well-bonded and firmly set in its full depth and<br />

a grout has been formed of screenings. Care shall be taken to see that the<br />

base or subgrade does not get damaged due to the addition of excessive<br />

quantities of water during construction.<br />

3.4.3.7 Application of Binding Material<br />

After the application of screenings, the binding material where it is required<br />

to be used shall be applied successively in two or more thin layers at a slow<br />

and uniform rate. After each application, the surface shall be copiously<br />

sprinkled with water, the resulting slurry swept in with hand brooms, or<br />

mechanical brooms to fill the voids properly, and rolled during which water<br />

shall be applied to the wheels of the rollers if necessary to wash down the<br />

binding material sticking to them. These operations shall continue until the<br />

resulting slurry after filling of voids, forms a wave ahead of the wheels of<br />

the moving roller.<br />

3.4.3.8 Setting and Drying<br />

After the final compaction of water bound macadam course, the road shall<br />

be allowed to dry overnight. Next morning hungry spots shall be filled with<br />

screenings or binding material as directed, lightly sprinkled with water if<br />

necessary and rolled. No traffic shall be allowed on the road until the<br />

macadam has set. The Engineer shall have the discretion to stop hauling<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 13


3.5.0 Tack Coat<br />

3.5.1 Description<br />

3.5.2 Materials<br />

DCPL-K4A02<br />

traffic from using the completed water bound macadam course if in his<br />

opinion it would cause excessive damage to the surface.<br />

The work shall consist of application of a single coat of low viscosity liquid<br />

bituminous material to an existing road surface preparatory to another<br />

bituminous construction.<br />

Binder : The binder used for tack coat shall be bitumen of a suitable<br />

grade as directed by the Engineer and conforming to IS:73, 217 or 454, as<br />

applicable, or any other approved cutback.<br />

3.5.3 Construction Operations<br />

3.5.3.1 Preparation of Base<br />

The surface on which the tack coat is to be applied shall be thoroughly<br />

swept and scraped clean of dust and any other extraneous material before<br />

the application of the binder.<br />

3.5.3.2 Application of Binder<br />

Binder shall be heated to the temperature appropriate to the grade of bitumen<br />

used and approved by the Engineer and sprayed on the base at the rate<br />

specified below. The rate of spread in terms of straight-run bitumen shall be<br />

5 kg. per 10 square metre area for an existing bitumen treated surface and<br />

10 kg per 10 square metre area for an untreated water bound macadam<br />

surface. The binder shall be supplied uniformly with the aid of sprayers.<br />

The tack coat shall be applied just ahead of the on-coming bituminous<br />

construction.<br />

3.6.0 Bituminous Macadam Binder Course<br />

3.6.1 Description<br />

3.6.2 Materials<br />

3.6.2.1 Binder<br />

This work shall consist of construction, in a single course, of 50 mm / 75 mm<br />

thickness of compacted crushed aggregates premixed with a bituminous binder, laid<br />

immediately after mixing, on a base prepared previously in accordance with the<br />

requirements of these Specifications, and in conformity with the lines, grades and<br />

cross sections shown on the drawings or directed by the Engineer.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 14


3.6.2.2 Aggregates<br />

DCPL-K4A02<br />

The Binder shall be straight run bitumen of a suitable grade as directed by the<br />

Engineer complying with IS:73.<br />

The aggregates shall consist of crushed stone, crushed gravel (shingle) or other<br />

stones. They shall be clean, strong, durable, of fairly cubical shape and free of<br />

disintegrated pieces, organic and other deleterious matter, and adherent coats. The<br />

aggregates shall preferably be hydrophobic and of low porosity.<br />

The aggregates shall satisfy the physical requirements set forth in Table-VI.<br />

TABLE-VI<br />

PHYSICAL REQUIREMENTS OF AGGREGATES<br />

FOR BITUMINOUS MACADAM<br />

________________________________________________________________<br />

Sl. No. Test Test method Requirements<br />

__________________________________________________________________<br />

1. Los Angeles Abrasion * IS:2386 35% Maximum<br />

Value<br />

(Part IV)<br />

2. Aggregate Impact Value * -do- 30% "<br />

3. Flakiness Index IS:2386 35% "<br />

(Part I)<br />

4. Stripping Value IS:6241 25% "<br />

5. Water Absorption IS:2386 2% "<br />

(Part III)<br />

__________________________________________________________________<br />

* Aggregates may satisfy requirements of either of the two tests.<br />

The aggregates for bituminous macadam for different thicknesses shall conform to<br />

the grading A or B given in Tables VII & VIII.<br />

TABLE-VII<br />

AGGREGATES GRADING FOR 75 MM COMPACTED<br />

THICKNESS OF BITUMINOUS MACADAM<br />

__________________________________________________________________<br />

Sieve<br />

Percent by weight passing the sieve<br />

Designation ________________________________________<br />

Grading A<br />

Grading B<br />

__________________________________________________________________<br />

63 mm 100<br />

50 mm 90-100<br />

40 mm 35-65 100<br />

25 mm 20-40 70-100<br />

20 mm - 50-80<br />

12.5 mm 5-20 -<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 15


DCPL-K4A02<br />

4.75 mm - 10-30<br />

2.36 mm - 5-20<br />

75 micron 0-5 0-4<br />

__________________________________________________________________<br />

TABLE-VIII<br />

AGGREGATE GRADING FOR 50 MM COMPACTED THICKNESS<br />

OF BITUMINOUS MACADAM<br />

____________________________________________________<br />

Sieve<br />

Percent by weight passing the sieve<br />

Designation _________________________________<br />

Grading A Grading B<br />

____________________________________________________<br />

50 mm 100<br />

40 mm 90-100<br />

25 mm 50-80 100<br />

20 mm - 70-100<br />

12.5 mm 10-30 -<br />

10 mm - 35-60<br />

4.75 mm - 15-35<br />

2.36 mm - 5-20<br />

75 micron 0-5 0-4<br />

____________________________________________________<br />

3.6.2.3 Proportioning of Materials<br />

The binder content for premixing shall be 3.5 and 4.0 percent by weight of<br />

the total mix for aggregate grading A and B respectively, except when<br />

otherwise directed by the Engineer.<br />

The quantities of aggregates to be used shall be sufficient to yield the<br />

specified thickness after compaction.<br />

3.6.2.4 Variation in Proportioning of Materials<br />

The Contractor shall have the responsibility for ensuring proper proportioning<br />

of materials and producing a uniform mix. A variation in binder content of<br />

0.3 percent by weight of total mix shall, however, be permissible for<br />

individual specimens taken for quality control tests.<br />

3.6.3 Construction Operations<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 16


DCPL-K4A02<br />

3.6.3.1 Weather and Seasonal Limitations<br />

Bituminous macadam shall not be laid during rainy weather or when the<br />

base course is damp or wet.<br />

3.6.3.2 Preparation of Base<br />

3.6.3.3 Tack Coat<br />

The base on which bituminous macadam is to be laid shall be prepared,<br />

shaped and conditioned to the specified lines, grade and cross sections as<br />

directed by the Engineer. The surface shall be thoroughly swept and<br />

scraped clean and free from dust and foreign matter.<br />

A tack coat shall be applied over the base.<br />

3.6.3.4 Preparation and Transport of Mix<br />

3.6.3.5 Spreading<br />

Hot mix plant of adequate capacity shall be used for preparing the mix.<br />

The temperature of binder at the time of mixing shall be in the range 150<br />

Deg.- 165 Deg.C and that of aggregates in the range 125 Deg. - 150 Deg.C,<br />

provided that the difference in temperature between the binder and<br />

aggregate at no time exceeds 25 Deg.C.<br />

Mixing shall be thorough to ensure that a homogenous mixture is obtained<br />

in which all particles of the aggregates are coated uniformly.<br />

The mixture shall be transported from the mixing plant to the point of use in<br />

suitable vehicles. The vehicles employed for transport shall be clean and be<br />

covered over in transit if so directed by the Engineer.<br />

The mix shall be spread immediately after mixing by means of a self<br />

propelled mechanical paver with suitable screeds capable of spreading,<br />

tamping and finishing the mix to the specified lines, grade and cross sections.<br />

However, in restricted locations and in narrow widths, where the available<br />

plants cannot operate in the opinion of the Engineer, he may permit manual<br />

laying of the mix.<br />

The temperature of mix at the time of laying shall be in the range 110 Deg. -<br />

135 Deg.C.<br />

In multilayer construction, the longitudinal joint in one layer shall offset that<br />

in the layer below by about 150 mm. However, the joint in the topmost layer<br />

shall be at the centre line of the pavement.<br />

Longitudinal joints and edges shall be constructed true to the delineating<br />

lines parallel to the centre line of the road. All joints shall be cut vertical to<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 17


3.6.3.6 Rolling<br />

DCPL-K4A02<br />

the full thickness of the previously laid mix and the surface painted with hot<br />

bitumen before placing fresh material.<br />

After the spreading of mix, rolling shall be done by 8 to 10 tonne power<br />

rollers or other approved plant. Rolling should start as soon as possible<br />

after the material has been spread. Rolling shall be done with care to keep<br />

from unduly roughening the pavement surface.<br />

Rolling of the longitudinal joint shall be done immediately behind the paving<br />

operation. After this, the rolling shall commence at the edges and progress<br />

towards the centre longitudinally except that on super-elevated portions it<br />

shall progress from the lower to the upper edge parallel to the centre line of<br />

the pavement.<br />

The initial or breakdown rolling shall be done as soon as it is possible to<br />

roll the mixture without cracking the surface or having the mix pick up on<br />

the roller wheels. The second or inter mediate rolling shall follow the break<br />

down rolling as closely as possible and be done while the paving mix is still<br />

at a temperature that will result in maximum density. The final rolling shall<br />

be done while the material is still workable enough for removal of roller<br />

marks.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 18


DCPL-K4A02<br />

When the roller has passed over the whole area once, any high spots or depressions<br />

which become apparent shall be corrected by removing or adding fresh material.<br />

The rolling shall then be continued till the entire surface has been rolled to<br />

compaction, there is no crushing of aggregate and all roller marks have been<br />

eliminated. Each pass of the roller shall uniformly overlap not less than one third of<br />

the track made in the preceeding pass. The roller wheels shall be kept damp if<br />

necessary to avoid the bituminous material from sticking to the wheels and being<br />

picked up. In no case shall fuel lubricating oil be used for this purpose.<br />

Rolling operations shall be completed in every respect before the temperature of the<br />

mix falls below 80 Deg.C.<br />

Rollers shall not stand on newly laid material while there is a risk that it will be<br />

deformed thereby. The edges along and transverse of the bituminous macadam laid<br />

and compacted earlier shall be cut to their full depth so as to expose fresh surface<br />

which shall be painted with a thin surface coat of appropriate binder before the new<br />

mix is placed against it.<br />

The bituminous macadam shall be provided with final surfacing without any delay.<br />

If there is to be any delay, the course shall be covered by a seal coat before allowing<br />

any traffic over it.<br />

3.7.0 Open-Graded Premix Carpet<br />

3.7.1 Description<br />

3.7.2 Materials<br />

3.7.2.1 Binder<br />

3.7.2.2 Aggregates<br />

This work shall consist of laying and compacting an open-graded carpet of 2 cm<br />

thickness in a single course composed of suitable small sized aggregates premixed<br />

with a bituminous binder on a previously prepared base, to form a wearing course, in<br />

accordance with the requirements of these specifications.<br />

The binder shall be bitumen of a suitable grade, as directed by the Engineer, and<br />

satisfying the requirements of IS:73, 217, 454 or other approved cutback as<br />

applicable.<br />

The aggregates shall consist of angular fragments of clean, hard, tough and durable<br />

rock of uniform quality throughout. They shall be obtained by crushing rock, gravel or<br />

river shingle and be free of elongated and flaky pieces, soft and disintegrated<br />

materials, and vegetable or other deleterious matter. They shall preferably be<br />

hydrophobic type.<br />

The aggregates shall satisfy the quality requirements set forth in Table VI except that<br />

the Flakiness Index shall be limited to a maximum of 30.<br />

3.7.2.3 Proportioning of Materials<br />

The materials shall be proportioned as per quantities given in Table IX.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 19


DCPL-K4A02<br />

TABLE-IX : QUANTITIES OF MATERIALS REQUIRED FOR 10 SQ.M OF ROAD<br />

SURFACE FOR 2 CM THICK OPEN-GRADED PREMIX CARPET<br />

__________________________________________________________________<br />

Aggregates of Carpet<br />

a) Stone chippings - 12 mm size; passing<br />

20 mm sieve and retained on 10 mm sieve 0.18 Cu.m<br />

b) Stone chippings - 10 mm size; passing<br />

12.5 mm sieve and retained on 6.3 mm sieve 0.09 Cu.m<br />

_______________<br />

Binder for premixing (quantities in terms of straight run bitumen)<br />

Total : 0.27 Cu.m<br />

_______________<br />

a) For 0.18 Cu.m of 12 mm size stone<br />

chippings at 52 kg per Cu.m<br />

9.5 kg<br />

b) For 0.09 Cu.m of 10 mm size stone<br />

chippings at 56 kg per Cu.m<br />

5.1 kg<br />

______________<br />

Total : 14.6 kg<br />

______________<br />

__________________________________________________________________<br />

3.7.3 Construction Operation<br />

3.7.3.1 Weather and Seasonal Limitations<br />

Open-graded premix carpet shall not be laid during rainy weather or when<br />

the base course is damp or wet or when the atmospheric temperature in<br />

shade is 16 Deg.C or below.<br />

3.7.3.2 Preparation of Base<br />

The underlying base on which the bituminous carpet is to be laid shall be<br />

prepared, shaped and conditioned to the specified lines, grade and cross<br />

section in accordance with Table I as directed by the Engineer. The surface<br />

shall be well cleaned by removing caked earth and other foreign matter with<br />

wire brushes, sweeping with brooms and finally dusting with sacks as<br />

necessary.<br />

3.7.3.3 Tack Coat<br />

A tack coat complying with clause 3.5 shall be applied over the base<br />

preparatory to laying of the carpet. Application of tack coat shall, however,<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 20


DCPL-K4A02<br />

not be necessary when the laying of carpet follows soon after the provision of<br />

a bituminous course.<br />

3.7.3.4 Preparation of Premix<br />

Mixers of approved type shall be employed for mixing the aggregates with<br />

the bituminous binder.<br />

The binder shall be heated to the temperature appropriate to the grade of<br />

bitumen approved by the Engineer, in boilers of suitable design avoiding<br />

local overheating and ensuring a continuous supply.<br />

The aggregates shall be dry and suitably heated to a temperature as<br />

directed by the Engineer before these are placed in the mixer. After about 15<br />

seconds of dry mixing, the heated binder shall be distributed over the<br />

aggregates at the rate specified.<br />

The mixing of binder with chippings shall be continued until the chippings are<br />

thoroughly coated with the binder. The mix shall be immediately transported<br />

from the mixer to the point of use in suitable vehicles or wheel barrows.<br />

The vehicles employed for transport shall be clean and be covered over in<br />

transit if so directed.<br />

3.7.3.5 Spreading and Rolling<br />

The premixed material shall be spread on the road surface with rakes to<br />

the required thickness and camber or distributed evenly with the help of a<br />

drag spreader, without any undue loss of time. The camber shall be<br />

checked by means of camber boards and inequalities evened out. As<br />

soon as sufficient length of bituminous material has been laid rolling shall<br />

commence with 6 to 8 tonne power rollers, preferably of smooth wheel<br />

tandem type, or other approved plant. Rolling shall begin at the edges and<br />

progress toward the centre longitudinally, except that on the superelevated<br />

portions it shall progress from the lower to upper edge parallel to the centre<br />

line of the pavement.<br />

When the roller has passed over the whole area once, any high spots or<br />

depressions which become apparent shall be corrected by removing or<br />

adding premixed materials. Rolling shall then be continued until the entire<br />

surface has been rolled to compaction and all the roller marks eliminated.<br />

In each pass of the roller, preceding track shall be overlapped uniformly by<br />

at least 1/3 width. The roller wheels shall be kept damp to prevent the<br />

premix from adhering to the wheels and being picked up. In no case shall<br />

fuel/lubricating oil be used for this purpose.<br />

Rollers shall not stand on newly laid material while there is a risk that it will be<br />

deformed thereby.<br />

The edges along and transverse of the carpet laid and compacted earlier shall be<br />

cut to their full depth so as to expose fresh surface which shall be painted with a<br />

thin surface coat of appropriate binder before the new mix is placed against it.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 21


DCPL-K4A02<br />

3.7.3.6 Seal Coat<br />

3.8.0 Seal Coat<br />

3.8.1 Description<br />

3.8.2 Materials<br />

3.8.2.1 Binder<br />

A seal coat conforming to clause 3.8 shall be applied to the surface immediately<br />

after laying the carpet. No traffic shall be allowed on the road till the seal coat has<br />

been placed.<br />

This work shall consist of application of a seal coat for sealing the voids in a<br />

bituminous surface laid to the specified levels, grade and camber.<br />

Seal coat shall be of either of the two types below, as specified:<br />

Type A : Liquid seal coat comprising of an application of a layer of bituminous binder<br />

followed by a cover of stonee chippings.<br />

Type B : Premixed seal coat comprising of a thin application of fine aggregate<br />

premixed with bituminous binder.<br />

The binder shall be bitumen of a suitable grade as directed by the Engineer and<br />

conforming to the requirements of IS:73, 217 or 454 as applicable or any other<br />

approved cutback.<br />

The quantity of binder to be utilised, in terms of straight run bitumen shall be 9.8<br />

kg and 6.8 kg per 10 square metre area for Type A and Type B seal coat<br />

respectively.<br />

3.8.2.2 Stone Chippings for Type A Seal Coat<br />

The stone chippings shall consist of angular fragments of clean, hard, tough and<br />

durable rock of uniform quality throughout. They shall be free of elongated or flaky<br />

pieces, soft or disintegrated stone, vegetable or other deleterious matter. Stone<br />

chippings shall be of 6 mm size defined as 100 percent passing through 10 mm sieve<br />

and retained on 2.36 mm sieve. The quantity used for spreading shall be 0.09 cubic<br />

metre per 10 square metre area. The chippings shall satisfy the quality<br />

requirements spelled out in Table VI except that the upper limit for flakiness Index<br />

shall be 30.<br />

3.8.2.3 Fine Aggregate for Type B Seal Coat<br />

The fine aggregate shall be sand or fine grit and shall consist of clean, hard,<br />

durable, uncoated dry particles and shall be free from dust, soft or flaky<br />

material, organic matter or other deleterious substances. The aggregate<br />

shall pass 1.7 mm sieve and be retained on 180 micron sieve. The quantity<br />

used for premixing shall be 0.06 cubic metre per 10 square metre area.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 22


DCPL-K4A02<br />

3.8.3 Construction Operations<br />

3.8.3.1 Preparation of Base<br />

The seal cost shall be applied immediately after the laying of bituminous<br />

course which is required to be sealed. Before application of seal coat<br />

materials the surface shall be cleaned free of any dust or other extraneous<br />

matter.<br />

3.8.3.2 Construction of Type A Seal Coat<br />

The binder shall be heated in boilers of suitable design, to the temperature<br />

appropriate to the grade of bitumen approved by the Engineer and sprayed<br />

on the dry surface in a uniform manner preferably with the help of mechanical<br />

sprayers. Excessive deposits of binder caused by stopping or starting of the<br />

sprayer or through leakage or any other reason shall be suitably corrected<br />

before the stone chippings are spread.<br />

Immediately after the application of binder, stone chippings in a dry and<br />

clean state, shall be spread uniformly on the surface, preferably by means of<br />

a mechanical gritter, otherwise manually so as to cover the surface<br />

completely. If necessary, the surface shall be broomed to ensure uniform<br />

spread of chippings.<br />

Immediately after the application of the cover material, the entire surface<br />

shall be rolled with a 8-10 tonne smooth wheeled roller. Rolling shall<br />

commence at the edges and progress towards the centre except in<br />

superelevated portions where it shall proceed from the inner edge to the<br />

outer. Each pass of the roller shall uniformly overlap not less than one third of<br />

the track made in the preceeding pass. While rolling is in progress additional<br />

chippings shall be spread by hand in whatever quantities required to make<br />

up irregularities. Rolling shall continue until all aggregate particles are<br />

firmly bedded in the binder and present a uniform closed surface.<br />

3.8.3.3 Construction of Type B Seal Coat<br />

Mixers of approved type shall be employed for mixing the aggregates with<br />

the bituminous binder.<br />

The binder shall be heated in boilers of suitable design, to the temperature<br />

appropriate to the grade of bitumen approved by the Engineer. Also the<br />

aggregates shall be dry and suitably heated to a temperature directed by the<br />

Engineer before the same are placed in the mixer. Mixing of binder with<br />

aggregates to the specified proportions shall be continued till the latter are<br />

thoroughly coated with the former.<br />

The mix shall be immediately transported from the mixing plant to the point<br />

of use and spread uniformly on the bituminous surface to be sealed.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 23


DCPL-K4A02<br />

As soon as sufficient length has been covered with the premixed material,<br />

the surface shall be rolled with 6-8 tonne smooth wheeled power rollers.<br />

Rolling shall be continued till the pre-mixed material completely seals the<br />

voids in the bituminous course and a smooth uniform surface is obtained.<br />

3.8.4 Opening to Traffic<br />

In the case of Type B Seal coat, traffic may be allowed soon after final rolling<br />

when the premixed material has cooled down to the surrounding<br />

temperature. However, as regards Type A seal coat, traffic shall not be<br />

permitted until the following day.<br />

3.9.0 Repair of Existing Water Bound Macadam Surface<br />

Pot holes or patches and ruts in water bound macadam base or surface<br />

course, which is to be surface treated, shall be repaired by removal of all<br />

loose material by cutting in rectangular patches and replacing with suitable<br />

materials. The repair shall be done as under :<br />

Pot holes, patches and ruts shall be drained of water and cut to regular<br />

shape with vertical sides, and then be filled either with i) coarse aggregate<br />

and screenings conforming to the specification for water bound macadam<br />

and compacted with rollers or other approved rammer or ii) premixed material<br />

conforming to the specification for open graded premix carpet and compacted<br />

with rollers or other approved means after painting the sides and bottom of<br />

the holes with a thin application of bitumen or a combination of both as<br />

directed by the Engineer.<br />

The above is only applicable in case of damage to the existing water<br />

bound macadam surfaces. In case, however, it is found that there has been<br />

damage to the granular sub-base as well, the area of the damaged surface<br />

shall be repaired by removal of all loose materials, cut to regular shape with<br />

vertical sides and relaid with graded material as per specification of granular<br />

sub-base and then surfaced with water bound macadam as per specification<br />

for the same.<br />

3.10.0 Road Side Drains<br />

3.10.1 Formation of Drains<br />

The road side drains shall be made in sizes and slopes as shown on<br />

drawings and/or as instructed by the Engineer. The minimum side slope<br />

shall be as instructed by the Engineer. The sides and bottom shall be<br />

neatly dressed after excavation. Proper connections shall be made to the<br />

culverts, outside plant area, as per instructions of the Engineer.<br />

The excavated spoils shall be transported and filled in low areas within the<br />

plant area or in embankments as instructed by the Engineer. The lining<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 24


3.11.0 Culverts<br />

DCPL-K4A02<br />

for the drains shall be as per Dwg. and as mentioned in the Schedule of<br />

items. Lining of drains may be of bricks or cement concrete blocks of M15<br />

grade concrete as shown on drawing or as directed by the Engineer. If<br />

instructed by the Engineer or shown on drawing, drains may be of R.C.C.<br />

construction with necessary slopes.<br />

Excavation in trenches for foundation of culverts and wing walls shall be<br />

done with side slopes as per the instructions of Engineer after clearing the<br />

site, etc. as per specifications of earthwork. Backfilling with ramming and<br />

watering shall be done after construction of the foundations.<br />

The construction of culverts shall be done true to lines and levels and as<br />

shown on the drawing. The specification for Masonry and/or Plain and<br />

Reinforced Cement concrete shall be followed, as applicable.<br />

3.12.0 Pipe Culverts and Drainage Pipes<br />

3.12.1 Materials<br />

The drainage pipes unless otherwise shown on drawings or instructed by the<br />

Engineer shall be made of R.C.C. and shall be either Class NP2 or NP3.<br />

Pipe culverts shall be made of reinforced concrete pipe and shall be of class<br />

NP3 or of RDSO class for railway as decided by the Engineer or shown in<br />

the drawing. All pipes shall meet the requirements of IS:458- Latest edition<br />

and shall be procured from approved manufacturers with collars as per<br />

manufacturer's standard specifications. The tenderer shall specifically<br />

mention the particular manufacturer's product he proposes to use. Cement<br />

shall be ordinary Portland Cement as per IS:269 - Latest edition.<br />

Aggregates shall be as per IS:383 - Latest edition - Maximum size shall not<br />

exceed one third the thickness of the pipe or 20 mm whichever is smaller.<br />

Fine aggregates for concrete shall be as per IS:383 - Latest edition.<br />

3.12.2 Laying of Pipes<br />

Laying of concrete pipes shall correspond to IS:783 - Latest edition - and<br />

to specification given below :<br />

a) The foundation bed for pipe shall be excavated true to lines and<br />

grades shown on the drawings or as directed by the Engineer.<br />

When trenching is involved its width on either side of the pipe shall<br />

not be less than 150 mm nor more than one-third the diameter of pipe<br />

unless otherwise instructed/permitted by the Engineer. The sides of the<br />

trench shall be as nearly vertical as possible. Side slope, shoring,<br />

bailing out water, etc. as required shall be done by the Contractor<br />

without the Owner. Side slips, if there be any, shall be removed by the<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 25


DCPL-K4A02<br />

Contractor. After laying of the pipes are completed, backfilling of the<br />

trenches shall be done in 250 mm layers, measured loose, clods and<br />

lumps broken, watered and compacted with iron rammers to the<br />

satisfaction of the Engineer. The surplus spoils shall be transported<br />

and filled in low areas within the plant area, as instructed by the<br />

Engineer.<br />

When bed-rock or boulder strata are encountered, excavation shall be<br />

taken down to at least 200 mm below the bottom level of the pipe with<br />

prior permission of the Engineer and all rock/boulders in the area shall<br />

be removed and space filled with approved earth free from stone or<br />

fragmented material, shaped to the requirements and thoroughly<br />

compacted to provide adequate support for the pipe.<br />

Filling of trench shall be carried out simultaneously on both sides of the<br />

pipe in such a manner that unequal pressures do not occur.<br />

When two or more pipes are to be laid adjacent to each other, they<br />

shall be separated by a distance equal to at least half the diameter of<br />

the pipe subject to a minimum of 450 mm.<br />

Laying of pipes shall start from the outlet and proceed towards<br />

inlet.<br />

All pipes and fittings shall be gradually lowered into the trench or<br />

placed on the supports by approved means taking due care not to<br />

damage them. Under no circumstances the pipes shall be dropped<br />

into the trench or on supports from a height.<br />

b) Pipe bedding shall be first class projection bedding for positive projecting<br />

pipes as per IS:783 - Latest edition - having a projection ratio of not greater<br />

than 0.70, in which the pipe is carefully bedded on fine granular materials in an<br />

earth foundation carefully shaped to fit the lower part of the pipe exterior for at<br />

least ten percent of its overall height, and in which earthfilling material is<br />

thoroughly rammed and tamped in layers not exceeding 15 cm in depth<br />

around the pipe for the remainder of the lower 30 percent of its height.<br />

If the pipe is laid in trench, pipe bedding shall be first class bedding<br />

as per IS:783.<br />

When indicated on the drawings or directed by the Engineer, the pipe<br />

shall be bedded on a craddle constructed of concrete having a mix not<br />

leaner than M15. The shape and dimension of the cradle shall be as<br />

indicated on the drawing or directed by the Engineer. The pipe shall be<br />

laid on the concrete bedding before the concrete has set.<br />

c) The drop walls shall be made with first class brickwork in 1:4 cement<br />

mortar.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 26


DCPL-K4A02<br />

d) The pipe culverts shall be made with proper care regarding the invert<br />

of the pipe, gradient, if any, etc. as specified on drawings and/or as<br />

instructed by the Engineer.<br />

e) Where R.C.C. pipes are encased in concrete at road crossings or at<br />

other places the pipes need be suitably supported avoiding<br />

reinforcements of concrete blocks, joints properly done before<br />

concreting is taken up. Concreting of total height of block may be<br />

done in a single operation or may be done upto some height for<br />

pipes to be properly laid in position and remaining height of block to<br />

be concreted subsequently.<br />

f) The R.C.C. pipes shall be joined with cement mortar. Cement mortar<br />

shall consist of 1 part cement and 2 parts of clean sand with only<br />

enough water for workability. Procedure of jointing shall be as per<br />

IS:783 - latest edition.<br />

3.12.3 Relation with Water Supply Pipeline<br />

Unless specifically cleared by the Engineer, under no circumstances shall<br />

drainage pipes be allowed to come close to water supply pipelines.<br />

3.13.0 Manholes and Inspection Chambers<br />

3.14.0 Masonry<br />

3.14.1 Brick Masonry<br />

The maximum distance between manholes shall be 30 meter unless<br />

specifically permitted otherwise. In addition at every change of alignment,<br />

gradient or diameter there shall be a manhole or inspection chamber. The<br />

distance between manhole or inspection chamber and gully chamber shall<br />

not exceed 6 meters unless permitted otherwise. Manhole shall be<br />

constructed so as to be water-tight under test. The channel or drain at the<br />

bottom of chamber shall be plastered with 1:2 cement sand mortar and<br />

finished smooth to the grade. The channels and drains shall be shaped and<br />

laid to provide smooth flow.<br />

Connection to existing pipelines shall be through a manhole.<br />

Manholes shall be provided with standard covers, usually C.I. or as directed<br />

by the Engineer. The covers shall be close fitting so as to prevent gases<br />

from coming out.<br />

All bricks shall be of first class (Class A) quality, well burnt, of uniform size,<br />

shape and colour free from cracks, flaws or nodules of free lime. Bricks<br />

shall be soaked in water for at least two hours prior to use and shall be laid<br />

truly horizontal and vertical in headers and stretchers with cement mortar<br />

consisting of one part of cement and four parts of sand, unless otherwise<br />

mentioned in the schedule of Items or directed by the Engineer, in<br />

layers not exceeding 1.5 M in height. Each layer shall be allowed at least 24<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 27


3.14.2 Stone Masonry<br />

DCPL-K4A02<br />

hours to settle itself before another layer is placed on it and every layer<br />

cured with water until the starting of next layer above it.<br />

Materials for mortar such as sand and cement shall be of approved quality.<br />

Mortar shall be well mixed, first dry mixed and then by adding water slowly to<br />

have a thick workable consistency. Mortar shall be mixed in small batches<br />

consistent with the rate of consumption so that no mortar is used after one<br />

hour of mixing.<br />

Mortar joints shall be kept uniformly 10 mm thick and all joints should be full<br />

of mortar. Brickwork shall be carried up regularly in plumb every course being<br />

horizontal. No vertical joints shall come directly over one another.<br />

Joints of the brickwork shall be raked minimum 10 mm deep using raking<br />

tool while mortar is still green to provide bond for plaster or pointing.<br />

Where plaster or pointing is not provided, the joints shall be struck flush and<br />

finished immediately. The brickwork shall be kept moist for 14 days.<br />

All bricks which absorb water more than 20% of their own dry weight after<br />

being immersed in water for 24 hours shall be rejected. Brick should be as<br />

per IS:1077. Bricks shall have minimum crushing strength of 50 kg/Sq.cm.<br />

All stones shall be from approved quarries, hard, tough, durable, compact grained,<br />

uniform in texture and colour and free from decay, flaws, veins, cracks and sand<br />

holes. A stone shall not absorb more than 5 percent of its weight of water after 24<br />

hours immersion. Samples shall be submitted by the Contractor and approved<br />

samples shall be retained by the Engineer for comparison of bulk supply.<br />

Stone shall be thoroughly soaked before laying. Stones shall be laid on their natural<br />

quarry beds. Individual stones shall be fitted with mallet and properly wedged to<br />

reduce thickness of mortar joints. Thickness of joint shall not be less than 8 mm and<br />

not greater than 25 mm. At least two stones shall run the full width of the wall for<br />

every square meter of surface area.<br />

3.14.3 Pointing to Masonry<br />

After raking out of the joints, the brickwork shall be brushed down with a<br />

stiff wire brush, so as to remove all loose dust from the joints and thoroughly<br />

washed with water, mortar consisting of 1 part cement and 3 parts clean,<br />

sharp, well graded sand by volume shall be pressed carefully into the joints<br />

and finished with suitable tools to shape as shown on the drawings. Any<br />

surplus mortar shall be scraped off the wall face leaving the surface clean.<br />

The pointed surface shall be kept wet for at least three days for curing.<br />

3.15.0 Plaster to Masonry and Concrete<br />

Before application of plaster the surface shall be cleaned of all dirt, grease<br />

or loose particles by hard brush and water. The surface shall be<br />

thoroughly moist to prevent absorption of water from the base course. Any<br />

excess water shall be mopped up.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 28


DCPL-K4A02<br />

3.15.1 Finish<br />

Unless otherwise mentioned in the schedule of items plastering shall be<br />

done with cement sand mortar - 1 part by volume of cement to 4 parts by<br />

volume of clean, sharp, well graded sand. For sand cement plaster, sand<br />

and cement in the specified proportion shall be mixed dry on a watertight<br />

platform and minimum water added to achieve working consistency. For<br />

lime gauge plaster, lime putty or hydrated lime and sand in the required<br />

proportion shall be mixed on a watertight platform with necessary addition<br />

of water and thoroughly ground in mortar mill. This mix shall than be<br />

transferred to a mechanical mixer to which the required quantity of cement<br />

is added and mixed for at least 3 minutes.<br />

No mortar which has stood for more than half an hour shall be used.<br />

Plaster, when more than 12 mm thick, shall be applied in two coats. All<br />

plaster work shall correspond to IS:1661- latest edition.<br />

Generally, all plastered surfaces shall have a standard finish unless<br />

otherwise shown on the drawing or directed by the Engineer. The interior<br />

plaster shall be finished to a smooth surface by steel trowelling. The<br />

exterior surfaces shall be finished with a wooden float.<br />

However, if shown on the drawing or directed by the Engineer the plastered<br />

surface shall have a neat cement finish. Immediately after achieving a true<br />

plastered surface with the help of a wooden straight edge, the entire area<br />

shall be uniformly treated with a paste of neat and rubbed smooth with a<br />

trowel.<br />

3.16.0 Cement Concrete (Plain and Reinforced)<br />

Shall be as laid down in “Techncial Specification for Cement Concrete (Plain<br />

and Reinforced)” Section - III.<br />

4.0 TESTING AND ACCEPTANCE CRITERIA<br />

4.1 Roads<br />

All testing, as mentioned in the body of the specification and as mentioned in<br />

Clause No. 900 of Specification for Roads and Bridge Works, 1983 published<br />

by IRC on behalf of Ministry of Shipping and Transport (Roads Wing) shall<br />

be carried out by the Contractor as per direction of the Engineer. No extra<br />

payment shall be made for such tests.<br />

4.2 Masonry and Plastering<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 29


DCPL-K4A02<br />

Masonry and finish to masonry and concrete shall fully comply with the<br />

drawings, approved samples and instructions of the Engineer with respect<br />

to lines, levels, thickness and any other special criteria as mentioned in<br />

the body of the specification or as shown on drawing.<br />

4.3 Cement Concrete<br />

The strength requirements and acceptance criteria shall conform to the<br />

relevant clauses of IS:456.<br />

(PCA.775.S034sca7) V.II-D2/S-VII : 30


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-VIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

MASONRY & ALLIED WORKS<br />

(PCA.775.S034sca8)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.00.00 SCOPE V.II-D2/S-VIII : 1<br />

2.00.00 INSTALLATION V.II-D2/S-VIII : 1<br />

3.00.00 I.S. CODES V.II-D2/S-VIII : 5<br />

(PCA.775.S034sca8)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-VIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

MASONRY & ALLIED WORKS<br />

1.0.0 SCOPE<br />

This specification covers furnishing, installation, repairing, finishing,<br />

curing, protection, maintenance and handing over of masonry and allied<br />

works for use in structures and locations covered under the scope of the<br />

Contract.<br />

2.0.0 INSTALLATION<br />

2.1.0 Soling<br />

2.1.1 Brick Soling<br />

2.1.2 Stone Soling<br />

2.2.0 Brick Edging<br />

The ground shall be dressed, consolidated by ramming or by light rolling<br />

and a 12 mm thick cushion of sand laid. On the sand cushion the bricks<br />

shall be laid with fine joints and placed firmly in position by hammering<br />

with wooden mallet. The surface shall be free from undulations. The 'frog'<br />

side shall be on the underside. The joints shall be broken the in all direction<br />

and bricks cut as required. Orientation shall be as desired by the Engineer.<br />

After laying of each layer of bricks sand shall be spread over and worked<br />

into the joints to pack the bricks tight.<br />

The stones for soling shall be selected on the basis of thickness of soling<br />

as shown as the drawings. The larger stones shall be laid and the gaps<br />

filled by smaller stones. The interstices shall then be firmly packed with<br />

sand by flooding with water.<br />

Excavation shall be done close to the brick dimensions and in perfect<br />

alignment. Bricks shall be firmly placed by hammering with wooden mallets<br />

and sides and joints packed firmly with earth so that the edging is not<br />

disturbed easily. Alignment and level shall be acceptable to the Engineer.<br />

(PCA.775.S034sca8) V.II-D2/S-VIII : 1


DCPL-K4A02<br />

2.3.0 Masonry<br />

2.3.1 General<br />

2.3.2 Mortar<br />

2.3.3 Brick Masonry<br />

All masonry work shall be true to lines and levels as shown on drawings. All<br />

masonry shall be tightly built against structural members and bonded with<br />

dowels, inserts etc. as shown on drawings.<br />

Mix for mortar shall be specified in the Schedule of Items.<br />

When lime is used hydrated lime shall be mixed with water to form a putty<br />

and stored with care to prevent evaporation for at least 24 hours before<br />

use. Quick lime shall be slaked with enough water to make a cream,<br />

passed through a No. 10 seive and stored avoiding evaporation for seven<br />

days before use.<br />

Lime putty and sand in proper proportion shall be mixed on a water-tight<br />

platform with necessary addition of water and thoroughly ground in a<br />

mortar mill. This mix shall be transferred to a mechanical mix, required<br />

quantity of cement added and the content mixed for at least 3 minutes.<br />

Mixtures of lime putty and sand may be stored avoiding drying out. For<br />

cement sand mortar cement and sand in requisite proportions shall be<br />

mixed dry in a mechanical mixer and then water added and mixed further.<br />

Minimum quantity of water shall be added to achieve working consistency.<br />

Surplus mortar droppings from masonry, if received on surface free from<br />

dirt may be mixed with fresh mortar if permitted by the Engineer who<br />

may direct addition of additional cement. No mortar which has stood for<br />

more than half an hour shall be used.<br />

Bricks shall be soaked by submergence in clean water for at least two hours<br />

in approved vats before use. Bricks shall be laid in English bond unless<br />

specified otherwise. Broken bricks shall not be used. Cut bricks shall be<br />

used if necessary to complete bond or as closers. Bricks shall be laid with<br />

frogs upwards over full mortar beds. Bricks shall be pressed into mortar<br />

and tapped into final position so as to embed fully in mortar. Inside faces<br />

shall be buttered with mortar before the next bricks is placed and<br />

pressed against it. Thus all joints between bricks shall be fully filled with<br />

mortar.<br />

Mortar joints shall be kept uniformly 10 mm thick. All joints on face shall be<br />

raked to minimum 10 mm depth using raking tool while the mortar is still<br />

green to provide bond for plaster or pointing. Where plaster or pointing is<br />

not provided, the joints shall be struck flush and finished immediately.<br />

Brickworks two bricks thick or more shall have both faces in true plane.<br />

Brickwork of lesser thickness shall have one selected face in true plane.<br />

2.3.4 Exposed Brickwork<br />

(PCA.775.S034sca8) V.II-D2/S-VIII : 2


DCPL-K4A02<br />

Brickwork in superstructures which is not covered by plaster shall be as<br />

shown on drawing and executed by specially skilled mason. Courses shall<br />

be truly horizontal and vertical joints truly vertical. Wooden straight<br />

edges with brick course graduations and position of window sills and lintels<br />

shall be used to control uniformity of brick courses. Masons must check<br />

workmanship frequently with plumb, spirit level, rule and string. All brickwork<br />

shall be cleaned at the end of days work. If face bricks are specified<br />

in the drawings, the brickwork shall be in composite bricks, with face bricks<br />

on the exposed face and balance in routine bricks, but maintaining the<br />

bond fully. Where face bricks are not specified, bricks for the exposed face<br />

shall be specially selected from routine bricks. All exposed brickwork on<br />

completion of work shall be rubbed down, washed clean and pointed as<br />

specified. Where face bricks are used carborandum stone shall be used for<br />

rubbing down.<br />

2.3.5 Reinforced Brickworks<br />

Reinforcements shall be as specified in the drawings. All reinforcements<br />

shall be thoroughly cleaned and fully embeded in mortar. Where M.S. bars<br />

are used as reinforcement, these shall be laped with dowels if left in R.C.<br />

columns or welded to steel stanchions.<br />

2.3.6 Stone Masonry<br />

Stones shall be thoroughly soaked before laying. Stones shall be laid on<br />

their natural quarry beds. Individual stones shall be fitted with mallet and<br />

properly wedged to reduce thickness of mortar joints. Thickness of joint<br />

shall be not less than 8 mm and not greater than 25 mm. Al least two<br />

stones shall run the full width of the wall for every square meter of surface<br />

area.<br />

2.3.7 Exposed Stonework<br />

Stonework which is to be kept exposed shall be as shown on drawing or<br />

described in the Schedule of Items. It shall be executed by specially<br />

skilled mason. Stones used for exposed face shall be specially selected.<br />

All exposed stone faces shall be kept clean and free from mortar and<br />

pointed up neatly as the work proceeds in a manner called for in the<br />

drawings or instructions. A sample wall, 10 sq.m. in area shall be built and<br />

approved by the Engineer and all works shall match with this sample.<br />

2.3.8 Composite Masonry<br />

Where stonework facing with brick masonry backing is specified the bond<br />

between them shall be achieved by bond stones of dimensions and<br />

frequency as desired by the Engineer.<br />

2.3.9 Expansion & Separation Joints<br />

(PCA.775.S034sca8) V.II-D2/S-VIII : 3


DCPL-K4A02<br />

Location of joints shall strictly be as shown on drawings or as instructed by<br />

the Engineer. Expansion joints shall be as shown on drawings. Expansion<br />

joint filler boards and sealing strips shall have minimum transverse joints.<br />

Transverse joints shall meet the approval of the Engineer.<br />

Separation joints shall be with standard water proof paper or with alkathene<br />

sheets about 1 mm in thickness. Length and sealing of laps shall be to the<br />

satisfaction of the Engineer.<br />

2.3.10 Mouldings, Cornices, Drip Course<br />

2.3.11 Curing<br />

These shall be made as shown in drawings. Bricks or stone shall be cut and<br />

dressed as required. If no subsequent finish is envisaged, these shall be<br />

rubbed to correct profile with carborandum stone.<br />

Masonry shall be cured by keeping it wet for seven days from the date of<br />

laying. In dry weather at the end of days work top surface of masonry shall<br />

be kept wet by ponding.<br />

2.3.12 Embedding of fixtures<br />

All fixtures shall generally be embedded in mortar and masonry units shall<br />

be cut as required.<br />

2.3.13 Encasing of Structural Steel<br />

This shall be done by building masonry work round flanges, webs etc. and<br />

filling the gap between steel and masonry by minimum 12 mm thick mortar.<br />

Encased members shall be wrapped with chicken wire mesh when shown<br />

on drawings or instructed by the Engineer. The minimum lap in chicken<br />

wire mesh shall be 50 mm.<br />

2.4.0 Damp Proof Course<br />

Unless otherwise specified Damp-proof course shall be 40 mm or as per<br />

schedule thick 'artificial stone' in proportion 1:1-1/2:3 cement sand stonechips<br />

(10 mm down) with admixture of a waterproofing compound as<br />

approved by the Engineer. The percentage of admixture shall be as per<br />

manufacturer's specifications but not less than 2% by weight of cement.<br />

The top surface shall be double chequered and cured by ponding for seven<br />

days.<br />

2.5.0 Damp Proof Membrane<br />

Damp proof treatment using fibre or hessian base bitumen felt shall be 6, 8<br />

or 10 course treatment as specified in IS:1609. The number of courses<br />

(PCA.775.S034sca8) V.II-D2/S-VIII : 4


DCPL-K4A02<br />

shall be as mentioned. Sequence or work shall be as directed by the<br />

Engineer. Extreme care shall be taken to prevent damage to felt during<br />

and after laying. The Contractor shall be obliged to rectify any leakage<br />

appearing within 5 years of installation by removing and renewing the coats<br />

at the point of leakage.<br />

Where shown on drawing, damp proof membrane with one layer bitumen<br />

paper or one layer alkathene sheet shall be laid with minimum 150 mm<br />

lap under slabs on grade.<br />

3.0.0 I.S. CODES<br />

Some of the important relevant codes for this section are :<br />

IS:1127 : Recommendations for dimensions and workmanship<br />

of natural building stones for masonry work.<br />

IS:1597 : Code of Practice for Construction of stone Masonry.<br />

IS:1609 : Code of Practice for laying Damp-proof treatment<br />

using bitumen felts.<br />

IS:2212 : Code of Practice for Brickwork.<br />

IS:2250 : Code of Practice for preparation and use of Masonry<br />

Mortar.<br />

IS:5134 : Bitumen Impregnated Paper & Board.<br />

(PCA.775.S034sca8) V.II-D2/S-VIII : 5


DCPL-K4A02<br />

VOLUME : II-D /2<br />

SECTION-IX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FINISH TO MASONRY & CONCRETE<br />

(PCA.775.S034sca9)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-IX : 1<br />

2.0.0 INSTALLATION V.II-D2/S-IX : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-IX : 6<br />

4.0.0 I.S. CODES V.II-D2/S-IX : 6<br />

(PCA.775.S034sca9)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-IX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FINISH TO MASONRY & CONCRETE<br />

1.0.0 SCOPE<br />

This Specification covers furnishing, installation, repairing, finishing, curing,<br />

testing, protection, maintenance till handing over of finishing items for<br />

masonry and concrete. This shall also include the work to be done to make<br />

the surface suitable for receiving the finishing treatment. Before commencing<br />

finishing items the Contractor shall obtain the approval of the Engineer<br />

regarding the scheduling of work to minimise damage by other trades. He<br />

shall also undertake normal precaution to prevent damage or disfiguration to<br />

work of other trades or other installation.<br />

2.0.0 INSTALLATION<br />

2.1.0 Preparation of Surface<br />

2.2.0 Plastering<br />

2.2.1 Mortar<br />

All joints in masonry walls shall be raked out to a depth of at least 10 mm<br />

with a hooked tool made for the purpose while the mortar is still green.<br />

Walls shall be brushed down with stiff wire brush to remove all loose dust<br />

from joints and thoroughly washed with water. All laitance shall be removed<br />

from concrete to be plastered.<br />

For all types of flooring, skirting and dado work, the base cement<br />

concrete slab or masonry surface shall be roughened by chipping and<br />

cleaned of all dirt, grease or loose particles by hard brush and water. The<br />

surface shall be thoroughly moist to prevent absorption of water from the<br />

base course. Any excess of water shall be mopped up.<br />

At any point, the level of base shall be lower than the theoretical finished<br />

floor level by the thickness of floor finish. Any chipping or filling to be done<br />

to bring the base in the required level shall be brought to the notice of the<br />

Engineer and his approval shall be taken regarding the method and<br />

extent of rectification work required.<br />

Prior to commencement of actual finishing work, the approval or the<br />

Engineer shall be taken as to the acceptability of the base.<br />

Mortar for plastering shall be as specified in the drawings.<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 1


DCPL-K4A02<br />

For sand cement plaster, sand and cement in the specified<br />

proportion shall be mixed dry on a watertight platform and minimum<br />

water added to achieve working consistency.<br />

For lime gauged plaster, lime putty or hydrated lime and sand in the<br />

required proportion shall be mixed on a watertight platform with necessary<br />

addition of water and thoroughly ground in mortar mill. This mix shall then be<br />

transferred to a mechanical mixer to which the required quantity of cement is<br />

added and mixed for at least 3 minutes.<br />

No plaster which has stood for more than half an hour shall be used;<br />

plaster that shows tendency to become dry before this time, shall have water<br />

added to it.<br />

2.2.2 Application of Plaster<br />

2.2.3 Finish<br />

Plaster, when more than 12 mm thick, shall be applied in two coats - a base<br />

coat followed by the finishing coat. Thickness of the base coat shall be<br />

sufficient to fill up all unevenness in the surface; no single coat, however,<br />

shall exceed 12 mm in thickness. The lower coat shall be thicker than the<br />

upper coat, the overall thickness of the coats shall not be less than the<br />

minimum thick-ness shown on the drawings. The undercoat shall be allowed<br />

to dry and shrink before applying the second coat of plaster. The undercoat<br />

shall be scratched or roughened before it is fully hardened to form a<br />

mechanical key. The method of application shall be 'thrown on' rather than<br />

'applied by trowel'.<br />

To ensure even thickness and true surface, patches of plaster about 100<br />

mm to 150 mm square or wooden screed 75 mm wide and of the thickness<br />

of the plaster, shall be fixed vertically about 2000 mm to 3000 mm apart,<br />

to act as gauges. The finished wall surface shall be true to plumb, and the<br />

Contractor shall make up any irregularity in the brickwork with plaster.<br />

All vertical edges of brick pillars, doorjambs etc. shall be chamfered or<br />

rounded off as directed by the Engineer. All drips, grooves, mouldings and<br />

cornices as shown on drawing or instructed by the Engineer shall be done<br />

with special care to maintain true lines, levels and profiles. After the<br />

plastering work is completed, all debris shall be removed and the area<br />

left clean. Any plastering that is damaged shall be repaired and left in<br />

good condition at the completion of the job.<br />

Generally, the standard finish shall be used unless otherwise shown on<br />

drawing or directed by the Engineer. Wherever any special treatment to<br />

the plastered surface is indicated, the work shall be done exactly as shown<br />

on the drawings, to the entire satisfaction of the Engineer regarding the<br />

texture, colour and finish.<br />

a) Standard Finish<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 2


DCPL-K4A02<br />

Wherever punning is indicated, the interior plaster shall be<br />

finished rough. Otherwise the interior plaster shall generally be<br />

finished to a smooth surface. The exterior surface shall generally be<br />

finished with a wooden float.<br />

b) Neat Cement Finish<br />

Immediately after achieving a true plastered surface with the<br />

help of a wooden straight edge, the entire area shall be uniformly<br />

treated with a paste of neat cement at the rate of one (1) kg. per<br />

Sq.M. and rubbed smooth with a trowel.<br />

c) Coloured Plaster Finish<br />

This shall be done in the same way as specified in Clause<br />

2.2.2 but using coloured cement in place of ordinary cement. When<br />

coloured plastering is specified in more than one coat, the top coat<br />

only shall be made with coloured cement.<br />

Coloured cement shall be either ready mixed material or may<br />

be obtained by mixing pigments and cement at site, as approved by<br />

the Engineer. The pigments to be mixed with cement shall conform<br />

to Appendix-A of IS:2114 latest edition. Samples of colouring<br />

material shall be submitted to the Engineer for approval and<br />

material procured, shall conform in all respects to the approved<br />

samples, which shall remain with the Engineer. All coloured cement<br />

and/or pigments shall be stored in an approved manner in order to<br />

prevent deteriorations.<br />

d) Pebble-dash Finish<br />

Mortar of required thickness consisting of 1 part cement and<br />

4 parts sand by volume shall be applied in the usual manner as<br />

described under plastering Clause 2.2.2. While the mortar is still<br />

plastic small pebbles or crushed stone of size generally from 10<br />

mm to 20 mm as approved by the Engineer shall be thrown on the<br />

plastered surface. The aggregate shall be lightly tapped into the<br />

mortar with a wood float or the flat end of a trowel, in order to<br />

ensure satisfactory bond between the dashing and the mortar.<br />

e) Rough-Cast Finish<br />

A wet plastic mix of 3 parts coloured cement 6 parts sand and<br />

4 parts aggregate by volume (gravel or crushed stone of size from 6<br />

mm to 12 mm as approved by the Engineer) shall be thrown on to<br />

the wall by means of a plaster's trowel and left in the rough condition.<br />

f) Scraped Finish<br />

Ordinary plaster as described under Clause 2.2.2 after being<br />

levelled and allowed to stiffen for a few hours, shall be scraped<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 3


2.2.4 Curing<br />

DCPL-K4A02<br />

with a steel straight edge to remove the surface skin. The pattern<br />

shall be as approved by the Engineer.<br />

g) Textured Finish<br />

Mortar consisting of 1 part cement and 3 parts sand by volume<br />

shall be applied in a manner as specified under "Plastering" Clause<br />

2.2.2. Ornamental treatments in the form of horizontal or vertical rib<br />

texture fan texture etc. shall be applied by means of suitable tools to<br />

the freshly applied plastered surface, as approved by the Engineer.<br />

All plastered surfaces after laying, shall be watered, for a minimum period<br />

of seven days, by an approved method, and shall be protected from<br />

excessive heat and sunlight by suitable approved means. Moistening shall<br />

commence, as soon as the plaster has hardened sufficiently and not<br />

susceptible to damage. Each individual coat of plaster shall be kept damp<br />

continuously, for at least two days, and then dried thoroughly, before applying<br />

the next coat.<br />

2.3.0 Pointing to Masonry<br />

All joints of brickwork shall be raked out to a depth of 10 mm with a<br />

hooked tool made for the purpose while the mortar is still green. The<br />

brickwork shall then be brushed down with a stiff wire brush, so as to<br />

remove all loose dust from the joints and thoroughly washed with water.<br />

Mortar consisting of 1 part cement and 3 parts clean, sharp, well graded<br />

sand by volume shall be pressed carefully into the joints and finished with<br />

suitably tools to shape as shown on the drawings. Any surplus mortar shall<br />

be scraped off the wall face leaving the surface clean.<br />

The pointed surface shall be kept wet for at least three days for curing.<br />

2.4.0 Plaster with Metal Lath<br />

The supports, hangers, brackets, cleats etc. shall be as shown on<br />

drawings and/or as approved by the Engineer. These shall have a<br />

coat of prime paint before and another coat of approved paint after<br />

erection.<br />

The metal lath shall be expanded metal, with 12 mm x 38 mm mesh,<br />

16 BG thick and 3 mm wide strands. Side laps shall be minimum 12<br />

mm and end laps 25 mm minimum. The plastering shall be minimum 20<br />

mm thick measured from the back of lath and applied in two layers.<br />

The mortar for plastering shall consist of 1 part cement, 1/2 part lime and 4<br />

parts sand by volume, or 1 part cement and 4 parts sand by volume mixed<br />

as specified in plastering, Clause 2.2.1. The application, finish etc. shall<br />

be as specified under relevant clause above. A 2 mm Plaster of Paris<br />

punning shall be applied over plaster as a finishing coat to give perfectly<br />

smooth and even finish.<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 4


DCPL-K4A02<br />

2.5.0 Lime Punning<br />

For plastered surfaces, where an even smooth surface is specified, lime<br />

punning with 5 parts of shell lime properly slaked, strained and aged, mixed<br />

with 1 part clean, washed, sieved, fine sand by volume shall be done. The<br />

thickness of lime punning shall be not less than 2 mm and more than 3 mm.<br />

The plastered surface shall be saturated with water before application of the<br />

lime punning. The punning shall be applied by skilled workman and given a<br />

smooth and even finish free from undulations, cracks etc. and to the<br />

satisfaction of the Engineer.<br />

2.6.0 Plaster of Paris Punning<br />

2.7.0 Stone Facing<br />

Plastered surfaces, where specified shall be finished with Plaster-of-<br />

Paris punning. The material shall be from approved manufacturers and<br />

approved by the Engineer. The thickness of the punning shall be 2 mm<br />

and shall be applied by skilled workmen. The finish shall be smooth, even<br />

and free from undulation, cracks etc.<br />

Before bulk work is taken in hand, a sample of punning shall be done on<br />

roughly 10 Sq.M. area and approval of the Engineer taken. The work shall<br />

then be taken in hand as per approved sample.<br />

Stone facing where specified shall be done as shown on design<br />

drawings and approved shop drawings. The stone shall be as<br />

specified on drawings. Samples of stone shall be submitted to the<br />

Engineer for approval and then bulk purchase made. The Contractor shall<br />

submit three copies of shop drawing for the Engineer's approval before<br />

commencing the work.<br />

The thickness of facing stone shall be not less than 25 mm<br />

otherwise specified on drawings.<br />

unless<br />

The stone slabs shall be cut and finished to sizes as per pattern shown on<br />

drawings. They shall be fastened to wall with suitable noncorrodable<br />

anchorage as approved by the Engineer. Where mild steel clamps, stays<br />

etc. are used for anchorage, they shall be galvanised (weight of zinc<br />

coating shall not be less than 700 gms per square meter of surface) to<br />

prevent rust stains developing on the finished surface. There shall be at<br />

least 12 mm gap between the stone and masonry, which shall be filled up<br />

and packed by a mortar of 1 part cement and 3 parts of sand by volume.<br />

After the mortar is set and cured for at least four days, the exposed<br />

surface shall be rubbed and polished as approved by the Engineer.<br />

The completed surface shall be neat, or uniform texture and<br />

acceptable to the Engineer.<br />

Where pointing is specified on drawings it shall be done by mortar as<br />

specified on drawings.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 5


DCPL-K4A02<br />

Finish to masonry and concrete shall fully comply instructions of the<br />

Engineer with respect to lines, levels, thickness, colour, texture, pattern and<br />

any other special criteria as shown on drawings.<br />

4.0.0 I.S. CODES<br />

Important relevant code for this Section :<br />

a) IS:1661 : Code of practice for cement and cement-lime<br />

plaster finish on walls & ceilings.<br />

b) IS:4101 : Code of practice for external facings and<br />

veneers.<br />

(PCA.775.S034sca9) V.II-D2/S-IX : 6


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-X<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FLOOR FINISHES AND ALLIED WORKS<br />

(PCA.775.S034sc10)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-X : 1<br />

2.0.0 INSTALLATION V.II-D2/S-X : 2<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-X : 20<br />

4.0.0 I.S. CODES V.II-D2/S-X : 21<br />

(PCA.775.S034sc10)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-X<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FLOOR FINISHES AND ALLIED WORKS<br />

1.0.0 SCOPE<br />

This specification covers furnishing, installation, finishing, curing, testing,<br />

protection, maintenance till handing over various types of floor finishes and<br />

allied items of work as listed below :<br />

a) In Situ Finishes<br />

i) Integral finish to concrete base<br />

ii)<br />

iii)<br />

iv)<br />

Red Oxide of Iron finish<br />

Terrazzo finish<br />

Granolithic finish<br />

v) Patent Stone<br />

vi)<br />

vii)<br />

viii)<br />

Metallic Hardener like "Ironite" finish<br />

Mastic Asphalt finish<br />

Chemical Resistant finish<br />

b) Tiled Finishes<br />

i) Terrazzo tile<br />

ii)<br />

iii)<br />

iv)<br />

Chequered tile<br />

Glazed tile<br />

Tesse rae (Mosaic etc.)<br />

v) Chemical Resistant<br />

vi)<br />

vii)<br />

Rubber, Vinyl etc.<br />

Stone Slab<br />

(PCA.775.S034sc10) V.II-D2/S-X : 1


DCPL-K4A02<br />

1.0.1 Base<br />

1.0.2 Sequence<br />

The base to receive the finish is covered under other relevant<br />

specifications.<br />

Commencement, scheduling and sequence of the finishing works shall<br />

be planned in detail and must be specifically approved by the<br />

Engineer in view the activities of other agencies working in that area.<br />

However, the Contractor for the finishing items shall remain fully responsible<br />

for all normal precautions and vigilance to prevent any damage whatsoever<br />

till handing over.<br />

2.0.0 INSTALLATION<br />

2.0.1 Special Materials<br />

2.0.2 Workmanship<br />

Basic materials are covered under Specification "Properties Storage and<br />

Handling of Common Building Materials". Special materials required for<br />

individual finishing items are specified under respective items. In general, all<br />

such materials shall be as per relevant I.S. Codes where available. In all<br />

cases these materials shall be of the best quality available indigenously,<br />

unless specified otherwise.<br />

The materials for finishing items must be procured from well-reputed<br />

specialised manufacturers and on the basis of approval of samples by the<br />

Engineer. The materials shall be ordered, procured and stored well in<br />

advance to avoid compulsion to use substandard items to maintain in the<br />

construction schedule.<br />

Only workers specially experienced in particular items of finishing work<br />

shall be engaged, where such workers are not readily available, with the<br />

Engineer's permission, experienced supervisors recommended by the<br />

manufacturer shall be engaged. In particular cases where the Engineer so<br />

desires the Contractor shall get the finishing items installed by the<br />

manufacturer.<br />

2.0.3 Preparation of the Base Surface<br />

The surface to be treated shall be thoroughly examined by the<br />

Contractor. Any rectification necessary shall be brought to the notice of the<br />

Engineer and his approval shall be taken regarding method and extent of<br />

such rectification work.<br />

For all types of flooring, skirting, dado and similar locations, the base to receive the<br />

finish shall be adequately roughened by chipping, raking out joints and cleaning<br />

thoroughly all dirts, grease etc. with water and hard brush and detergent if required,<br />

(PCA.775.S034sc10) V.II-D2/S-X : 2


2.1.0 In Situ Finishes<br />

DCPL-K4A02<br />

unless otherwise directed by the manufacturer of any special finishing materials<br />

or specifically indicated in this specification under individual item.<br />

To prevent of water from the finishing treatment the base shall be thoroughly soaked<br />

with water and all excess water mopped up.<br />

The surface shall be done dry where adhesives are used for fixing the finishes.<br />

Prior to commencement of actual finishing work the approval of the Engineer shall be<br />

taken as per the acceptability of the surface.<br />

2.1.1 Integral Finish To Concrete Base<br />

While the surface of the concrete laid as per specification for 'Cement Concrete'<br />

has been fully compacted and levelled but the concrete is still 'green' a thick slurry<br />

made with neat cement shall be applied evenly and worked in with iron floats.<br />

When the slurry starts to set it shall be pressed with iron floats to have a firm<br />

compact smooth surface without trowel mark or undulations.<br />

This finish shall be as thin as possible by using 2.2 kg. of cement per Sq. M. of<br />

area.<br />

The surface shall be kept in shade for 24 hours and then cured for at least 7 days<br />

continuously by flooding with water. The surface shall not be subjected to any load<br />

or abrasion till 21 days after laying.<br />

As desired by the Engineer the surface, while still 'green' shall be indented by<br />

pressing strings. the marking shall be of even depth, in straight lines and the<br />

panels shall be of uniform and symmetrical patterns.<br />

2.1.2 Red Oxide of iron Finish<br />

It shall consist of an underbed and a topping over already laid and matured concrete<br />

base.<br />

a) Thickness<br />

Unless otherwise specified the total thickness of the finish shall be minimum<br />

40 mm for horizontal and 25 mm for vertical surface of which the topping<br />

shall (not less than 10 mm) while the topping shall be of uniform thickness<br />

the underbed may vary in thickness to provide necessary slopes. The vertical<br />

surface shall project out 6 mm from the adjacent plaster or other finishes.<br />

Necessary cutting into the surface receiving the finish shall be done to<br />

accommodate the specified thickness.<br />

All junctions of vertical with horizontal shall be rounded neatly to uniform<br />

radius of 25 mm.<br />

b) Mix<br />

i) Underbed<br />

(PCA.775.S034sc10) V.II-D2/S-X : 3


DCPL-K4A02<br />

The underbed for floors and similar horizontal surfaces<br />

shall consist of a mix of 1 part cement, 2 parts coarse sand<br />

and 4 parts 10 mm down graded stone chips by volume.<br />

For vertical and similar surfaces the mix shall consist of 1<br />

part cement to 3 parts coarse sand by volume.<br />

ii)<br />

Topping<br />

For the topping cement, screened through a fine mesh and<br />

red oxide of iron pigment powder similarly screened shall<br />

be dry mixed thoroughly in right proportions to produce the<br />

desired colour when laid. The mix shall then be prepared with<br />

1 part cement (mixed with pigment) and 3 parts coarse sand<br />

volume. The whole quantity required for each visible area<br />

shall be prepared in one batch to ensure uniform colour.<br />

c) Laying<br />

The underbed shall be laid in panels of mixing area 5 Sq.M.<br />

each and no side shall be more than 2.5 along. For outdoor<br />

locations the maximum area shall be 2.0 Sq.M. The forms for the<br />

panels shall have perfectly aligned edges to the full depth of the<br />

total thickness of finish. If specified aluminium or glass dividing strips<br />

shall be used.<br />

The panels shall be laid in alternate bays or in chequered<br />

board pattern. No panel shall be cast in contact with another already<br />

laid until the contraction of the latter has taken place. The underbed<br />

shall be laid, compacted, levelled and brought to proper grade with a<br />

screed or float. The topping shall be placed after about 24 hours<br />

while the underbed is still somewhat 'green' but firm enough to<br />

receive the topping. The surface of the underbed shall be<br />

roughened for better bonding. The topping shall be rolled for<br />

horizontal areas and thrown and pressed for vertical areas to extract<br />

all superfluous cement and water to achieve a compact dense mass<br />

fully bonded with the underbed. The topping shall then be levelled<br />

up by trowelling and finished smooth with a slurry made with<br />

already prepared cement and pigment mixture. About 2.0 Kg. of the<br />

mixture shall be consumed/per Sq.M. for horizontal surface, and 1.0<br />

Kg. for vertical surface. The surface shall be cured for seven days<br />

by keeping it moist.<br />

d) Polishing<br />

About 36 hours after laying when the surface has hardened<br />

sufficiently it shall be polished with polishing stone till a smooth shiny<br />

surface to the satisfaction of the Engineer, is achieved. The finish<br />

shall be washed and cleaned just before handing over.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 4


DCPL-K4A02<br />

2.1.3 Terrazo Finish : In Situ<br />

It shall consist of an underbed and a topping laid over an already laid and<br />

matured concrete base.<br />

a) Thickness<br />

b) Mix<br />

Unless otherwise specified the total thickness of the finish<br />

shall be minimum 40 mm for horizontal and 25 mm for vertical<br />

surface of which the topping shall be not less than 10 mm. While<br />

the topping shall be of uniform thickness the underbed may very in<br />

thickness to provide necessary slopes. The vertical surface shall<br />

project cut 6 mm from the adjacent plaster or other finish.<br />

Necessary cutting into the surface receiving the finish shall be<br />

done to accommodate the specified thickness.<br />

All junctions of vertical with horizontal shall be rounded<br />

neatly to uniform radius of 25 mm.<br />

i) Underbed<br />

The underbed for floors and similar horizontal surfaces<br />

shall consist of a mix of 1 part cement, 1.1/2 parts sand<br />

and 3 parts stone chips by volume. For vertical surfaces the<br />

mix shall consist of 1 part cement to 3 parts sand by volume.<br />

The sand shall be coarse. The stone chips shall be 10 mm<br />

down well graded. Only sufficient water to be added to<br />

give a workable consistency.<br />

ii)<br />

Topping<br />

The mix for the topping shall be composed of cement,<br />

colour pigment, marble dust and marble chips.<br />

Proportions of the ingredients shall be such as to produce<br />

the terrazzo of colour texture and pattern approved by the<br />

Engineer. The cement shall be white or grey or a mixture of<br />

the two to which pigment shall be added to achieve the<br />

desired colour. To 3 parts of this mixture 1 part marble<br />

powder by volume shall be added and thoroughly mixed dry.<br />

To 1 part of this mix 1 to 1.1/2 parts of marble chips by<br />

volume shall be added and thoroughly mixed dry again.<br />

The pigment must be stable and nonfading. It must be<br />

very finely ground. The marble powder shall be from white<br />

marble and shall be finer than IS Sieve No. : 30. The size of<br />

marble chips may be between 1 mm to 20 mm.<br />

Sufficient quantity to cover each visible area shall be<br />

prepared in one lot to ensure uniform colour. Water to make<br />

(PCA.775.S034sc10) V.II-D2/S-X : 5


DCPL-K4A02<br />

it just workable shall be added to a quantity that can be used<br />

up immediately before it starts to set.<br />

c) Laying<br />

The underbed shall be laid in panels. The panels shall not be<br />

more than 5 sq.m in area of which no side shall be more than 2.5 M<br />

long. For exposed locations the maximum area of a panel shall be 2.0<br />

Sq.M. The panel shall be laid in alternate bays or chequered board<br />

pattern. No panel shall be cast in contact with another already laid<br />

until the latter has contracted to the full extent.<br />

Dividing strips made of aluminium or glass shall be used for<br />

forming the panels. The strips shall exactly match the total depth of<br />

underbed plus topping.<br />

d) Curing<br />

After laying, the underbed shall be levelled compacted and brought<br />

to proper grade with a screed or float. The topping shall be laid<br />

after about 24 hours while the underbed is still somewhat "green"<br />

but firm enough to receive the topping. A slurry of the mixture of<br />

cement and pigment already made shall be spread evenly and<br />

brushed in just before laying the topping. The topping shall be<br />

rolled for horizontal areas and thrown and pressed for vertical areas<br />

to extract all superfluous cement and water and to achieve a<br />

compact dense mass fully bonded with the underbed. The<br />

surface of the topping shall be trowelled over, pressed and brought<br />

to a smooth dense surface showing a minimum 75% area covered by<br />

marble chips in a even pattern of distribution.<br />

The surface shall be left for curing for about 12 to 18 hours<br />

and then cured by allowing water to stand on the surface or by<br />

covering with wet sack for four days.<br />

e) Grinding and Polishing<br />

When the surface has sufficiently hardened it shall be watered and<br />

ground evenly with rapid cutting coarse grade (no.60) grit blocks, till<br />

the marble chips are exposed and the surface is smooth. Then the<br />

surface shall be thoroughly washed and cleaned. A grout with already<br />

prepared mixture of cement and pigment shall be applied to fill up all<br />

pinholes. The surface shall be cured for 7 days by keeping it moist<br />

and then ground with fine grit blocks (no.: 120). It shall again be<br />

cleaned with water, the slurry applied again to fill up any pinholes that<br />

might have appeared and allowed to be cured again for 5 days.<br />

Finally, the surface is ground a third time with very fine grit blocks<br />

(no.: 320) to get smooth surface without any pinhole. The grinding<br />

shall be done by a suitable machine. Where grinding machine can not<br />

be used hand grin- ding may be allowed when the first rubbing shall<br />

be with carborundum stone of coarse grade (no.60), second rubbing<br />

with medium grade (no.: 80) and final rubbing and polishing with fine<br />

grade (no.: 120). The surface shall be cleaned with water, dried and<br />

(PCA.775.S034sc10) V.II-D2/S-X : 6


2.1.4 Granolithic Finish<br />

DCPL-K4A02<br />

covered with soil free, clean sawdust if directed by the Engineer. The<br />

final polishing shall be positioned till before handing over if desired by<br />

the Engineer. Just before handing over the surface shall be dusted<br />

with oxalic acid at the rate of 0.33 gm. per. Sq.M, water sprin- kled on<br />

to it and finished by buffing with felt or hessian bobs. The floor shall<br />

be cleaned with soft moist rag and dried. However, all excess wax<br />

polish to be wiped off and the surface to be left glossy but not<br />

slippery.<br />

Granolithic finish shall either be laid monolithically over base concrete or<br />

separately over hardened base concrete.<br />

a) Thickness<br />

b) Mix<br />

The finish shall be average 20 mm and minimum 12 mm thick,<br />

unless specified otherwise.<br />

The mix shall consist of 1 part cement : 1 part coarse sand : 2 parts<br />

coarse aggregate by volume. The coarse aggregate shall be very<br />

hard like granite and well graded between 6 mm and 12 mm.<br />

Minimum quantity of water to get workability shall be added.<br />

c) Laying of Monolithic Topping<br />

The concrete base shall be laid as per specification "Cement<br />

Concrete" and levelled upto the required grade. The form shall<br />

remain sufficiently protruding to take the finish.<br />

Within about 3 hours of laying the base while it is still fully "green"<br />

the topping shall be laid evenly to proper thickness and grade. If<br />

considered necessary the surface of the base shall roughened by<br />

wire brushing. Unless manual operation is permitted by the<br />

Engineer, mechanical vibrators of suitable design shall be used to<br />

press the topping firmly and work vigorously and quickly to secure<br />

full bond with concrete base.<br />

The laitance brought to the surface during compression shall<br />

be removed carefully without disturbing the stone chips. The surface<br />

shall then the lightly trowelled to remove all marks. When sufficiently<br />

set, hand trowelling shall be done to secure a smooth surface<br />

without disturbing the stonechips.<br />

For large areas the laying shall be in panels of maximum 25<br />

Sq.M area. The panels shall be laid in chequered board pattern.<br />

d) Laying of Topping Separately on Hardened Base<br />

(PCA.775.S034sc10) V.II-D2/S-X : 7


e) Curing<br />

DCPL-K4A02<br />

The base concrete shall be prepared as stated in clause 2.0.3 and a<br />

slurry of neat cement applied just prior to laying the granolithic<br />

concrete mix (1:1:2). The method of compaction etc. shall be same<br />

as for monolithic topping.<br />

Immediately after laying, the finish shall be protected against rapid<br />

drying. As soon as the surface had hardened sufficiently, it shall be<br />

kept continuously moist for at least 10 days by means of wet gunny<br />

bags or pounding of water on the surface. The floor shall not be<br />

exposed to heavy traffic during this period.<br />

f) Grinding<br />

If grinding is specified, it shall start only after the finish has fully<br />

set. Clause 2.1.3 (c) shall be followed. However, the ultimate polish<br />

required shall be decided upon by the Engineer.<br />

g) Finishing<br />

2.1.5 Patent Stone<br />

Where specified, sodium silicate or magnesium or zinc silico<br />

fluoride treatment shall be done. The number of coats to be applied<br />

shall be as specified. The concentration and method of application<br />

of the solutions shall be as specified in IS : 5491.<br />

It shall consist of an underbed and a topping laid on an already laid and<br />

matured concrete base.<br />

a) Thickness<br />

The patent stone finish shall have thickness as stipulated<br />

under clause 2.1.2 (a) except that the topping shall be 6 mm thick.<br />

b) Mix<br />

i) Underbed<br />

The mix shall be as stipulated under clause 2.1.3(b).<br />

ii)<br />

Topping<br />

The mix for the topping shall consist of 1 part cement<br />

and 1 part fine sand by volume.<br />

c) Laying<br />

(PCA.775.S034sc10) V.II-D2/S-X : 8


DCPL-K4A02<br />

The Patent Stone finish, including the underbed shall be laid<br />

in alternate bays or in chequered board pattern. No panel shall be<br />

cast in contact with another already laid till the contraction of the<br />

latter has already taken place.<br />

The maximum area of each panel shall be 3 Sq.M of which no<br />

side shall be more than 2 M long.<br />

A cement grout shall be applied and worked into the surface<br />

to receive the finish, the underbed then laid, compacted and levelled<br />

to proper grade with a screed or float. The topping shall be applied<br />

evenly on the underbed while it is not fully set but firm enough and<br />

rolled and pressed to get full bond.<br />

The topping shall trowelled to a dense finish to the<br />

satisfaction of the Engineer. All trowel marks shall be mopped out<br />

with a soft cloth to give a clean smooth surface.<br />

After the surface is sufficiently set, the finished floor shall be kept<br />

moist for 7 days for curing. If desired the finish shall be polished as<br />

directed by the Engineer.<br />

2.1.6 Metallic Hardener Like "Ironite" Finish<br />

This will consist of a topping (incorporating iron particles) to bond with<br />

concrete base while the latter is "Green".<br />

a) Thickness<br />

Unless otherwise specified the metallic hardener finish shall<br />

be of 12 mm depth.<br />

b) Material<br />

c) Mix<br />

The hardening compound shall be uniformly graded iron particles free<br />

from non-ferrous metal impurities, oil, grease, sand soluble alkaline<br />

compounds or other injurious materials. When desired by the<br />

engineer, actual samples shall be tested.<br />

Proportion of the metallic hardener shall be as specified or<br />

as indicated by the manufacturer. However, in absence of any such<br />

direction 1 part metallic hardener shall be mixed dry with 4 parts<br />

cement, by weight. To this mixture 6 mm nominal size stone chips<br />

shall be added in proportion of 1 part cement (mixed with<br />

(PCA.775.S034sc10) V.II-D2/S-X : 9


d) Laying<br />

2.1.7 Mastic Asphalt Finish<br />

DCPL-K4A02<br />

hardener) to 2 parts of stone chips by volume and uniformly mixed.<br />

Minimum quantity of water shall be added to make it workable.<br />

The concrete floor shall be laid as per specification "Cement<br />

Concrete" an levelled upto the required grade. The forms, if any shall<br />

remain sufficiently projecting to take the finish.<br />

The surface shall be roughened by wire brush as soon as<br />

possible.<br />

The finish shall be laid while the concrete underbed is still<br />

very "green" within about 3 hours of laying of the latter. The finish<br />

shall be of uniform thickness and even dense surface without<br />

trowel marks, pin holes etc. This topping layer shall be pressed<br />

firmly and worked vigorously and quickly to secure full bond with the<br />

concrete base. Just when the initial set starts the surface shall be<br />

finished \smoothened with steel trowel.<br />

The finished floor shall be cured for 7 days by keeping it wet.<br />

This is a one layer treatment on concrete or brick base.<br />

a) Thickness<br />

The thickness shall be as specified in the drawing<br />

b) Materials<br />

Bitumen shall be industrial bitumen of the grades 90/15 and<br />

75/15 conforming to IS: 702.<br />

Mineral filler shall be dry stone dust passing through 75-micron IS<br />

Sieve.<br />

Fine aggregate shall be crushed and graded natural lime stone<br />

or other hard-work.<br />

Coarse aggregate shall be crushed siliceous stone or other<br />

approved aggregate 6 mm stone chips shall be used for finish upto<br />

20 mm thick & 10 mm chips for thicker finish.<br />

c) Composition<br />

(PCA.775.S034sc10) V.II-D2/S-X : 10


DCPL-K4A02<br />

Bitumen mastic shall conform to IS: 1195 and shall be either<br />

brought to site in blocks weighing about 25Kg. or prepared at site. If<br />

brought in blocks, these shall be remelted in mechanically agitated<br />

mastic cookers and coarse aggregate, preferably preheated fed in<br />

successive portions until the complete change is thoroughly<br />

incorporated. At no stage during the remelting and mixing<br />

process, shall the temperature exceed 205°C.<br />

d) Laying<br />

The hot mastic shall be laid on dry base surface cleaned<br />

thoroughly by wire brushing and sweeping. The mastic shall be<br />

levelled and when cooled to some extent shall be finished with a<br />

wooden float with addition of small quantity of fine sand if required.<br />

No load shall be allowed till the finish has cooled to normal<br />

temperature.<br />

The mastic shall be laid in suitable panels of about 15 Sq.M<br />

in area each formed by formers. Succeeding panels shall be laid<br />

overlapping the finish panel so as to melt its edges and form a<br />

continuous finish without joint.<br />

2.1.8 Chemical Resistant in Situ Finish<br />

2.2.0 Tiled Finish<br />

Chemical resistant in situ finish shall be as epoxy resin with suitable filler<br />

material over a primer or called for in the Schedule of Items. The<br />

minimum thickness shall be 6 mm. About its performance the Engineer shall<br />

have to be fully satisfied by test results and examination of similar treatment<br />

already in existence.<br />

The Contractor shall get it done by a specialised manufacturer, get<br />

guarantee of performance from the organisation and pass it on to the Owner<br />

in addition to his own guarantee.<br />

These shall include finish tiles, stone slabs and similar manufactured or<br />

natural items over already laid and matured base of concrete or masonry by<br />

means of an underbed or an adhesive layer.<br />

2.2.1 Terrazzo Tile Finish<br />

The finish will consist of manufacture terrazo tile and an underbed.<br />

a) Thickness<br />

The total thickness including the underbed shall be minimum<br />

40 mm for floors 30 mm for walls unless otherwise specified.<br />

The skirting, dado and similar vertical surfaces shall<br />

project out 6 mm uniformly from the adjacent plaster or other wall<br />

finishes. The necessary cutting into the surface receiving the<br />

tiled finish, to accommodate the specified thickness shall be done.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 11


DCPL-K4A02<br />

b) Tiles : Terrazzo<br />

The tiles shall, unless specifically permitted in special cases be<br />

machine made under quality control in a shop. The tile shall be<br />

pressed hydraulically to a minimum of 140 Kg. per Sq.cm.<br />

Each tile shall bear on its back permanent and legible trade<br />

mark of the manufacturer. All angles of the tiles shall be right angles<br />

all arises sharp and true, colour and texture of the wearing face<br />

uniform throughout. Maximum tolerance allowance length and<br />

breadth shall be + 1 mm and the thickness + 3 mm. Face of the tile<br />

shall be plane, free from pin holes and other blemishes.<br />

The tiles shall be composed of a backing and topping. The<br />

topping shall be of uniform thickness not less than 10 mm.<br />

The total thickness including the topping shall be as<br />

specified but not less than 20 mm in any case.<br />

The backing shall be composed of 1 part ordinary grey cement<br />

and 3 parts of stone chips by weight mixed with water.<br />

The topping shall be as specified under clause 2.1.3 (b).<br />

The tile shall be cured at the shop for at least 14 days<br />

before delivery to the site. First grinding shall be given to the tiles at<br />

the shop before delivery. Tiles shall be packed properly to prevent<br />

damage during transit and storage. The tiles must be carefully<br />

stored to prevent staining by damp, rust, oil, and grease or other<br />

chemicals.<br />

Tiles made in each batch shall be kept and used separately so<br />

that colour of each area of the floor may remain uniform.<br />

The manufacturer shall supply along with the tiles the grout mix<br />

containing cement and pigment in exact proportions as used in<br />

topping of the tiles. The containers for the grout mix shall be suitably<br />

marked to relate it to the particular type and batch of tiles.<br />

c) Mix : Underbed<br />

d) Laying<br />

The underbed for floor and similar horizontal surfaces shall be 1 part<br />

lime putty : 1 part surkhi : 2 parts coarse sand by weight mixed with<br />

sufficient water to form a stiff workable mass. For skirting and dado<br />

and all vertical surfaces it shall be about 12 mm thick and composed<br />

of 1 part cement and 3 parts coarse sand by weight.<br />

The underbed mortar shall be evenly spread and brought to<br />

proper grade and consolidated to a smooth surface. The surface<br />

shall be roughened for better bond. Before the underbed had time to<br />

set and while it is still fairly moist but firm, cement shall be hand<br />

(PCA.775.S034sc10) V.II-D2/S-X : 12


DCPL-K4A02<br />

dusted over it or a cement slurry applied and the tiles shall<br />

immediately be placed upon and firmly pressed by wooden mallet<br />

on to the underbed until it achieves the desired level. The tiles shall<br />

be kept soaked for about 10 minutes just before laying. The joints<br />

between tiles shall be as close as possible and not more than 1.5 mm<br />

wide.<br />

Special care shall be taken to check the level of the surface<br />

and the lines of the joints frequently so that they are perfect.<br />

When tiles are required to be cut to match the dimensions these<br />

shall be sawn and edges rubbed smooth. The location of cut tiles<br />

shall be planned in advance and approval of the Engineer taken.<br />

At the junction of horizontal surface with vertical surface the tiles on<br />

the former shall enter at least 12 mm under the latter.<br />

After fixing, the floor shall be kept moist and allowed to<br />

mature undisturbed for 7 days. Heavy traffic shall not be allowed.<br />

If desired dividing strips as specified under Clause 2.1.3 (c) may be<br />

used for dividing the work into suitable panels.<br />

e) Grinding and Polishing<br />

Procedure shall be same as Clause 2.1.3 (c) 2. Grinding shall<br />

not commence earlier than 14 days after laying of tiles.<br />

2.2.2 Chequered Tile Finish<br />

The finish shall consist of manufactured grey or coloured cement tiles or<br />

terrazzo tiles with chequered face and an underbed laid over concrete or<br />

brick surface.<br />

a) Thickness<br />

Thickness shall be same as in clause 2.2.1 (a).<br />

b) Tiles : Chequered<br />

The tiles shall have chequers not less than 2.5 cm. c/c and<br />

not more than 5 cm c/c, Depth of grooves shall be not less than 5<br />

mm. The grooves shall be uniform and straight.<br />

The tiles shall conform to clause 2.2.1 (b) except that these<br />

may have the topping in terrazzo or plain grey cement or colour<br />

pigment added to cement as specified.<br />

c) Underbed<br />

As per clause 2.2.1 (c).<br />

(PCA.775.S034sc10) V.II-D2/S-X : 13


DCPL-K4A02<br />

d) Laying<br />

As per clause 2.2.1 (d).<br />

e) Grinding and Polishing<br />

2.2.3 Glazed Tiles Finish<br />

As per clause 2.2.1 (e) except that the tiles shall be ground<br />

and polished by hand after laying taking special care in polishing<br />

the grooves properly and uniformly.<br />

This finish shall be composed of glazed earthenware tiles with an<br />

underbed laid over a concrete or masonry base.<br />

a) Thickness<br />

The total thickness shall be between 20 mm and 25 mm<br />

including the underbed. The tile finish on vertical surface shall<br />

project out 6 mm uniformly from the adjacent plaster or other wall<br />

finishes. The necessary cutting into the surface receiving the finish,<br />

to accommodate the specified thickness shall be done.<br />

b) Tiles : Glazed<br />

The tiles shall be of earthenware, covered with glaze white<br />

or coloured, plain or with designs, of 150 mm x 150 mm nominal<br />

sizes and 10 mm thick unless otherwise specified. The tolerance<br />

shall be + 1.5 mm for length and breadth and + 0.5 mm for thickness<br />

specials like internal and external angles, beads, covers, cornices,<br />

corner pieces etc. shall match. The top surface of the tiles shall be<br />

glazed with a gloss or matt unfading stable finish as desired by the<br />

Engineer. The tiles shall be flat and true to shape. The colour shall<br />

be uniform and fractured section shall be fine grained in extures,<br />

dense and homogeneous. The tiles shall be strong and free<br />

from flaws like cracks, craze, specks, crawlings, etc. and other<br />

imperfections. The edge and the underside of the tiles shall be<br />

completely free from glaze and the underside shall have ribs or<br />

indentations for better anchorage with the fixing mortar.<br />

The coloured tiles, when supplied, shall preferably come from<br />

one batch to avoid difference in colour.<br />

c) Mix : Underbed<br />

The mix for the underbed shall consist of 1 part cement and 3<br />

parts coarse sand by weight mixed with sufficient water or any other<br />

mix if specified.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 14


DCPL-K4A02<br />

d) Laying<br />

Same as clause 2.2.1 (d).<br />

e) Finishing<br />

The joints shall be cleaned and flush pointed with white<br />

cement and cured for 7 days by keeping it wet. The surface shall<br />

be cleaned with soap or suitable detergent, washed fully and wiped<br />

with soft cloth to prevent scratching before handing over.<br />

2.2.4 Tesserae Finish (Mosaic etc.)<br />

This finish consists of manufactured vitreous, glass, ceramic or similar hard<br />

small pieces set in an underbed over a concrete or masonry surface, already<br />

laid.<br />

a) Thickness<br />

The total thickness including the underbed shall be between<br />

16 mm and 25 mm.<br />

b) Tesserae Finish<br />

These shall usually be 6 mm thick small piece of ceramic<br />

vitreous china, tinted glass or similar hard wearing, strong and<br />

durable material in desired shapes and sizes and patterns.<br />

The supply shall come in the desired pattern in full or<br />

sections conveniently for handling, stuck to pieces of strong thick<br />

paper on the surface to be exposed. The gum used for this purpose<br />

must be water soluble and non-staining. The sections shall be<br />

properly marked to avoid mistakes and master drawing shall be<br />

available at the site for guidance.<br />

c) Mix : Underbed<br />

d) Laying<br />

Same as clause 2.2.3 (c)<br />

The specification for laying if given by the manufacturer of<br />

the item shall be followed provided it is approved by the Engineer.<br />

Otherwise clause 2.2.3 (d) shall generally be followed. However,<br />

instead of grey cement the slurry shall be made with white cement to<br />

fix the panels. The paper mounted patterns in sections shall be<br />

carefully placed and pressed in position true to lines and levels.<br />

Earliest possible the paper shall be peeled off and surface<br />

(PCA.775.S034sc10) V.II-D2/S-X : 15


DCPL-K4A02<br />

examined and cleaned, joints flush pointed with white cement<br />

and cured for 7 days by keeping it wet.<br />

2.2.5 Chemical Resistant Tiled Finish<br />

This shall include all varieties of special tiles used for specific chemical<br />

resistance function and an underbed over already laid concrete or masonry.<br />

a) Tiles<br />

The chemical resistant tiles as detailed in the Schedule of items shall<br />

be of the best indigenous manufacture unless otherwise specified<br />

and shall be resistant to the chemical described in the Schedule of<br />

Items. The tiles shall have straight edges, uniform thickness, plain<br />

surface, uniform non-fading colour and textures.<br />

Glazed tiles if permitted to act as chemical resistant finish<br />

shall be considered under clause 2.2.3.<br />

Usually the chemical resistant tiles shall not absorb water more than<br />

2% by weight. The tiles shall have at least compression strength of<br />

700 Kg/cm2. The surface shall be abrasion resistant and durable.<br />

b) Laying<br />

The mortar used for setting or for underbed the tiles shall be durable<br />

and strong. The grout which shall be to the full depth of tile shall have<br />

equal chemical resistant properties. Joints shall be pointed if so<br />

desired. The setting and fixing shall be according to the<br />

manufacturer's specification approved by the Engineer.<br />

2.2.6 Rubber, Vinyl or Vinyl Asbestos Tiles Finish<br />

This shall include various types of tiles manufactured from rubber, vinyl,<br />

etc. set with a adhesive on concrete or masonry base. An underbed may be<br />

required to secure desirable surface and grade.<br />

a) Thickness<br />

b) Tiles<br />

The thickness of the tiles shall be mentioned in the Schedule<br />

or in drawing.<br />

Unless otherwise desired the tiles shall be squares of<br />

approved dimensions.The tolerance in dimensions shall be 1.5mm.<br />

The face of the tiles shall be free from porosity, blisters,<br />

cracks, embedded foreign matters or either physical defects which<br />

affect appearance or serviceability. All edges shall be cut true and<br />

square. The colour shall be nonfading and uniform in appearance,<br />

(PCA.775.S034sc10) V.II-D2/S-X : 16


DCPL-K4A02<br />

insoluble in water and resistant to alkalies, cleaning agents and usual<br />

floor polishes.<br />

Each tile shall be marked on the back legibly and indelibly<br />

with manufacturer’s trade mark, the thickness, sizes, batch number<br />

and date of manufacturer.<br />

Tiles shall be delivered securely packed and stored in clean, dry<br />

well ventilated place at a temperature near about to that the tiles shall<br />

be called upon to stand ultimately.<br />

Adhesive to be used for sticking the tiles shall be approved by the<br />

tile manufacturer. The adhesive shall have a short drying time and<br />

long life in addition to toughness.<br />

c) Mix : Underbed<br />

The underbed where required to make up the specified<br />

thickness or to give the required grade or to get the right type of<br />

surface shall be composed of 1 part like putty : 1 part cement : 4<br />

parts coarse sand mixed with just sufficient water to make it workable.<br />

d) Laying<br />

The tiles shall be kept in the room to be tiled for at least 24 hours to<br />

bring them to the same temperature as the room. For air<br />

conditioned space, the air-conditioning shall be completed before<br />

tiling is taken up.<br />

The surface to receive this finish shall be firm even<br />

textured but not too smooth, without undulations and other<br />

deficiencies. If an underbed is laid the same shall be cured<br />

for at least 7 days by keeping it moist and then fully dried.<br />

The surface shall be thoroughly cleaned. All loose dust<br />

particles shall be removed. Oil and grease if any shall be<br />

completely cleaned by use of detergent.<br />

The adhesive shall be applied to fully dry surface in desired<br />

thickness uniformly. The adhesive shall also be applied to the backs<br />

and edges of the tiles and allowed to surface dry. The tiles shall be<br />

placed neatly on the surface exactly to the approved pattern and set<br />

with a suitable tool. If the edges tend to curl, weights are to be used<br />

to keep the edges down. Special care shall be taken to avoid<br />

formation of air pockets under the tiles. The joints shall be very fine.<br />

Any adhesive squeezed out through the joints shall be removed<br />

immediately.<br />

e) Finishing<br />

If any adhesive mark is there on the surface a soft cloth<br />

soaked in solvent shall be used to wipe it off. The surface shall be<br />

(PCA.775.S034sc10) V.II-D2/S-X : 17


DCPL-K4A02<br />

cleaned with soft soap, dried and polished with an approved type of<br />

polish just before handing over.<br />

2.2.7 Stone Slab Finish : Marble, Stone and Similar Fine Grained Stone<br />

a) Thickness<br />

The underbed shall be minimum 12 mm and average 20 mm thick.<br />

The slabs may be 25 mm, 30 mm or 40 mm thick as specified.<br />

b) Stone Slab<br />

The stone slabs shall be made from selected stock which are<br />

hard, sound, homogeneous and dense in texture and free from<br />

flaws. Angles and edges shall be true, square, free from chipping<br />

and surface shall be plane. The slabs shall preferably be<br />

machine cut to the required dimensions.<br />

Tolerance of 5 mm in dimensions and 2 mm in thickness<br />

will be allowed. Unless specified the slabs shall be minimum 300 mm<br />

x 300 mm.<br />

The stone slabs shall come from specific regions and in<br />

specified quality with top surface fine chisel dressed. All sides shall<br />

also be fine chisel dressed to the full depth to allow finest possible<br />

joints.<br />

The slabs shall be delivered to the site well protected<br />

against damages and stored in dry place under cover.<br />

c) Mix : Underbed<br />

d) Laying<br />

Same as clause 2.2.1 (c).<br />

The sides and top surface of the slabs shall be machine rubbed<br />

or table rubbed with coarse sand stone and washed clean before<br />

laying.<br />

The underbed mortar shall be evenly spread and brought to<br />

proper level on the area under each slab. The slab shall be laid over<br />

the underbed, pressed and tapped down with wooden mallet to the<br />

proper level. The slab shall then be lifted and the underbed corrected<br />

as necessary and allowed to stiffen a little. Next, a thick cement slurry<br />

shall be spread over the surface. The edges of the slab shall be<br />

buttered with slurry of cement, grey/white/mixed with pigment<br />

matching the colour of the stone slabs. The slab shall be gently laid<br />

and tapped with wooden mallet to bed properly to a very fine joint<br />

and to the required level. All surplus cement slurry shall be<br />

removed and the surface mopped clean with wet soft cloth. The<br />

laid finish shall be cured for 7 days by keeping it wet.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 18


DCPL-K4A02<br />

e) Polishing, Finishing<br />

Fine chiselling shall be done to remove the slight undulations that<br />

usually exist at the joints. The polishing and finishing shall be done<br />

as specified under clause 2.2.1 (e). However, the joints shall be so<br />

fine in the case of stone slabs that grouting shall not be called for.<br />

2.2.8 Stone Slab Finish : Sand Stone and<br />

Similar Coarse Grained Stone Finish<br />

Generally clause 2.2.7 shall be followed except that the workmanship and<br />

finish shall not be fine as which are explained hereunder.<br />

The slabs shall be rough chiseled or fine chiseled as specified. Tolerance<br />

may be allowed upto + 6 mm for rough finish, but no sharp unevenness<br />

and shall be allowed. For fine chiseling the unevenness shall be limited to<br />

2 mm. The sides shall be chisel dressed at least to half slab depth so that<br />

the maximum deviation from straight line shall be within 25 mm. Beyond this<br />

depth the edge may be slightly splayed.<br />

The joint thickness shall be kept limited to 5 mm in case of rough finish<br />

and 3 mm in case of fine finish unless wider joints are specified. The joints<br />

shall be grouted with white or coloured cement.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

The finish shall be checked specially for :<br />

a) Level, Slope, Plumb as the case may be<br />

b) Pattern and Symmetry<br />

c) Alignment of joints, dividing strip etc.<br />

d) Colour, texture<br />

e) Surface finish<br />

f) Thickness of joints<br />

g) Details at edges, junctions etc.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 19


DCPL-K4A02<br />

h) Performance<br />

i) Precautions specified for durability<br />

4.0.0 I.S. CODES<br />

Important relevant codes for this section :<br />

IS : 777 : Glazed earthenware tiles<br />

IS : 1196 : Code of practice for laying bitumen mastic<br />

flooring<br />

IS : 1197 : Code of practice for laying of rubber floors<br />

IS : 1237 : Cement concrete flooring tiles<br />

IS : 1443 : Code of practice for laying and finishing of<br />

cement concrete flooring tiles<br />

IS : 2114 : Code of practice for laying in situ terrazzo floor<br />

IS : 3461 : PVC asbestos floor tiles<br />

IS : 4860 : Specification for acid resistant bricks<br />

IS : 5518 : Code of practice for laying of flexible PVC Sheet<br />

and tile flooring.<br />

IS : 5491 : Code of practice for laying in situ granolithic<br />

floor topping.<br />

(PCA.775.S034sc10) V.II-D2/S-X : 20


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FALSE FLOORING<br />

(PCA.775.S034sc11)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.00.00 SCOPE V.II-D2/S-XI : 1<br />

2.00.00 FALSE FLOORING SYSTEM V.II-D2/S-XI : 1<br />

3.00.00 ACCEPTANCE CRITERIA V.II-D2/S-XI : 2<br />

(PCA.775.S034sc11)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

FALSE FLOORING<br />

1.0.0 SCOPE<br />

This specification covers supplying, installation, repairing, finishing, testing,<br />

protection and maintenance till handing over of removable free access false<br />

flooring systems consisting of an assembly of panels mounted on adjustable<br />

pedestal and supporting steel grid system to provide an under floor space.<br />

2.0.0 FALSE FLOORING SYSTEM<br />

2.1.0 Base<br />

The system shall be placed over a base of R.C.C. floor slab and with<br />

necessary grouting etc. to fix the supporting structure.<br />

2.2.0 Supporting Structure<br />

2.3.0 Floor Panel<br />

The supporting structure shall comprise of fabricated jacks made out of 25<br />

mm. dia. MS rounds having 150 mm. threads at top. This jack shall be<br />

welded to 100 mm x 100 mm x 6 mm thick MS base plate pedestal.<br />

Pedestals shall be vertically true and located at 600 mm centre to centre to<br />

conform to the size of the floor panels and shall be fixed to the RCC floor slab<br />

with ARALDITE. The jack shall be equipped with locking device to prevent<br />

loss of finished elevation. Adjustment shall be provided by the threaded rod<br />

member and elevating nut. The capital shall be of aluminium alloy die cast<br />

and shall receive cold rolled MS floor supporting channels of size 40 mm x 40<br />

mm x 3.15 mm thickness as per drawings, both for main and cross runners.<br />

The pedestal shall be equipped with conducting grounding pad. All MS<br />

members shall be treated with steel protective paint as per drawing.<br />

2.3.1 The floor panels shall be made of phenol for maldehyde bonded particle<br />

board treated with fire resistant paint as per schedule items. Size of each<br />

panel shall be 600 mm x 600 mm with all panel edges finished to a tolerance<br />

of + 0.25 mm on the diagonals. The edges of the floor panels shall be<br />

covered by 4 mm. thick rigid PVC edging. The underside of the panel shall<br />

have 0.05 mm. thick Aluminium foil which shall be fixed to the particle board<br />

with resin-based adhesive.<br />

(PCA.775.S034sc11) V.II-D2/S-XI : 1


DCPL-K4A02<br />

2.4.0 Strength<br />

2.5.0 Surface Finish<br />

2.6.0 Skirting<br />

2.7.0 Installation<br />

Each 600 mm x 600 mm floor panel must be capable of supporting an<br />

uniform minimum live load of 1220 Kg/Sq.M or a concentrated minimum load<br />

of 450 Kg. applied through a phenolic caster 75 mm in diameter and 45 mm<br />

wide, or a rolling minimum load of 450 Kg. at any point with a maximum<br />

deflection of 2 mm. The ultimate strength shall be capable of carrying a 2300<br />

Kg. axial load without deformation of any part.<br />

All removable panels shall have the top surface finished with 2 mm thick<br />

Antiatatic Vinyl Flooring bonded to the surface with adhesive as per<br />

manufacturer’s specification.<br />

Skirting shall be of the same Anstistatic Vinyltiles, 150 mm. high and 2 mm.<br />

thick, completely matching with the false flooring surface and shall be fixed<br />

with the plastered wall surface as per manufacturer’s specification.<br />

All steel surface are to be protected by pointing over a primer as per<br />

schedule of items and any damage to the paint during installation shall be<br />

made good. Finished floor surface, when specified by the Engineer-in-<br />

Charge shall be protected by the Contractor with kraft paper taped and<br />

sealed at edges to prevent tearing.<br />

Any damage to the sub floor during installation of the false flooring system<br />

shall be made good by the Contractor without to the owner.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

The false flooring system shall be checked specially for :<br />

a) Level<br />

b) Alignment of joints<br />

c) Thickness of joints<br />

d) Surface finish<br />

e) Colour and texture<br />

(PCA.775.S034sc11) V.II-D2/S-XI : 2


DCPL-K4A02<br />

VOLUME : II-D /2<br />

SECTION-XII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

CARPENTRY & JOINERY<br />

(PCA.775.S034sc12)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0 SCOPE V.II-D2/S-XII : 1<br />

2.0 INSTALLATION V.II-D2/S-XII : 1<br />

3.0 ACCEPTANCE CRITERIA V.II-D2/S-XII : 3<br />

4.0 I.S. CODES V.II-D2/S-XII : 4<br />

(PCA.775.S034sc12)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

CARPENTRY & JOINERY<br />

1.0 SCOPE<br />

This shall include supply, fitting and fixing of timber frames to doors and<br />

windows with M S holdfasts, paneled or flush doors, windows, shutters,<br />

partitions, wall paneling, pelmets, shelves, furniture, etc. as shown in drawings,<br />

including a prime coat of approved paint, varnish, or fixing of decorative plastic<br />

laminate. This shall also include the supply and fixing of all hardware and<br />

fixtures shown in drawing.<br />

2.0 INSTALLATION<br />

2.1 Materials<br />

a) Timber<br />

Unless otherwise specified, all timber shall be best quality well<br />

seasoned C P teakwood free from large or loose, knots cracks or other<br />

defects. Where specified, timber shall be treated with approved wood<br />

preservative before use. Before starting the carpenters work, the<br />

Tenderer shall have the rough timber approved by the Engineer.<br />

b) Plywood<br />

Plywood shall be commercial quality with decorative surface veneer.<br />

Unless specifically permitted otherwise, the adhesive used in plywood<br />

shall be phenol-formaldehyde resin of B W R grade conforming to<br />

IS:848.<br />

c) Decorative Laminated Plastic Sheets<br />

The colour, pattern, finish and texture shall be approved by the<br />

Engineer and the bulk supply procured in sheet sizes which will ensure<br />

the least number or joints in one surface.<br />

d) Flush Doors<br />

(PCA.775.S034sc12) V.II-D2/S-XII : 1


DCPL-K4A02<br />

Flush doors shall be hollow or solid core doors with commercial or<br />

decorative faces and hardwood edges. The core for solid core doors<br />

shall be of block board or wood particle board. Manufacturer's literature<br />

and test certificates shall be submitted for the approval of the Engineer.<br />

The Contractor shall give a guarantee that the adhesive used is phenol<br />

formaldehyde of B W R grade, conforming to IS:848. The thickness<br />

shall be as specified in the drawing.<br />

e) Panel Doors<br />

Panel door shall be of teakwood shutter frame and panels of teakwood.<br />

Other considerations shall be as mentioned in item (d) above.<br />

f) Fixtures<br />

2.2 Workmanship<br />

2.2.1 General<br />

Fixtures for doors, windows, furniture, etc. shall be as shown on<br />

drawing.<br />

The work shall be done by skilled carpenters as per details shown on drawing<br />

or instructed by the Engineer.<br />

Framing timber and other work shall be close-fitting with proper wood joinery,<br />

accurately set to required lines or levels and rigidly secured in place. The<br />

surface of frames etc. which will come in contact with masonry after fixing, shall<br />

be given two coats of approved paint before fixing. Mastic caulking shall be<br />

done after fixing external door and window frames. Special care shall be taken<br />

to match the grain of timber or plywood which will be subsequently polished.<br />

Screwing or nailing will not be permitted to the edge of plywood and particle<br />

board. The edge of all plywood, blockboard and particle board shall be finished<br />

with teakwood lipping unless otherwise shown on drawings.<br />

Fixing for frames and partitions shall generally be with 40 mm x 6 mm x 300<br />

mm long M S holdfasts bifurcated at end and grouted with 1:2:4 cement<br />

concrete. The gap between masonry and external door and window frame<br />

shall be caulked with polysulphide mastic. M S grills or guard bars shall be<br />

provided to windows where called for in the drawings.<br />

2.2.2 Finish<br />

(PCA.775.S034sc12) V.II-D2/S-XII : 2


DCPL-K4A02<br />

All carpentry work after finishing shall be sand papered smooth. A prime coat<br />

paint shall be given after inspection of the Engineer to all surfaces other than<br />

those which shall be subsequently polished or covered with laminated plastic<br />

sheet.<br />

2.2.3 Surface Treatment<br />

When shown on drawings decorative ply or laminated plastic sheets shall be<br />

bonded under pressure to the surface to be finished. The adhesive used shall<br />

be of approved brand and brought to site in sealed containers. The rate of<br />

application and the length of time for which the pressure is to be applied shall<br />

be as per the manufacturer's instructions. The edge of sheets shall be<br />

protected by teak lipping or beveled as shown on drawings.<br />

3.0 ACCEPTANCE CRITERIA<br />

3.1 Door and Window Frames<br />

All frames shall be square and flat at the time of delivery and shall be checked<br />

for dimensions and corner angles. After fixing they shall be on a fine vertical<br />

plane. All external door and window frames shall be caulked with mastic.<br />

3.2 Door and Window Shutters<br />

Shall be of proper size, shape and design and free of warp. When fixed to<br />

frames, these shall operate smoothly without jamming and all latching or<br />

locking devices shall engage properly without undue pressure.<br />

3.3 Partitions, Paneling, Pelmets, Furniture, etc.<br />

3.3.1 General<br />

These shall conform to drawings in all details. No unsightly nailmarks etc. shall<br />

be permitted. Plywood grains shall be matched to give a uniform and pleasing<br />

appearance.<br />

3.3.2 Partition<br />

3.3.3 Pelmets<br />

Shall be checked for rigidity of fixing, plumb and horizontal as well as vertical<br />

alignment.<br />

Shall be checked for rigidity of fixing and adequate clearance of fixture.<br />

3.3.4 Cupboard Shutters<br />

Shall operate smoothly without jamming and locks, bolts and double ball<br />

catches shall engage securely. Single ball catches shall not be used.<br />

(PCA.775.S034sc12) V.II-D2/S-XII : 3


DCPL-K4A02<br />

3.3.5 Drawers<br />

Shall operate smoothly and have back stops to prevent them from being<br />

pushed too far. Locks shall engage securely.<br />

3.3.6 Loose Furniture<br />

When placed on a level surface tables tops etc. shall be horizontal and the<br />

pieces stand stably on legs or supports.<br />

4.0 I.S. CODES<br />

Some of the important relevant Codes for the Section are:<br />

IS:4021 - Timber door, window and ventilator frames.<br />

IS: 1003 - Timber paneled and glazed shutters.<br />

IS:2191 - Wooden flush door shutter (Cellular and hollow core type).<br />

IS:2202 - Wooden flush door shutters (solid core type).<br />

(PCA.775.S034sc12) V.II-D2/S-XII : 4


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

SUSPENDED CEILING<br />

(PCA.775.S034sc13)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XIII : 1<br />

2.0.0 MATERIAL V.II-D2/S-XIII : 1<br />

3.0.0 INSTALLATION V.II-D2/S-XIII : 2<br />

4.0.0 SHOP DRAWINGS V.II-D2/S-XIII : 2<br />

5.0.0 WORKMANSHIP V.II-D2/S-XIII : 2<br />

6.0.0 SAMPLES V.II-D2/S-XIII : 2<br />

7.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XIII : 2<br />

8.0.0 I.S. CODES V.II-D2/S-XIII : 2<br />

(PCA.775.S034sc13)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

SUSPENDED CEILING<br />

1.0.0 SCOPE<br />

2.0.0 MATERIAL<br />

This specification covers the furnishing of all materials, labour, tools,<br />

equipment, supervision and services necessary for incidental to the<br />

supply, installation, finishing and completion of suspended ceiling work<br />

of various profiles and at all elevations as per drawing, specification and<br />

instruction of Architect/Owner. The work shall also include providing<br />

openings in the ceiling for lighting fixtures, air conditioning diffusers<br />

etc. as shown in drawing and instruction of Architect/Engineer.<br />

2.1.0 Aluminium Grid suspension system<br />

a) Suspender : shall be fabricated from 10 dia. M.S. rod angle, flast or<br />

as required to suit ceiling profile and suspension system with<br />

turnbuckle for adjustment of levels. All M.S. works shall have one<br />

coat of synthetic enamel paint over a coat of red lead primer.<br />

b) Frame work/grid : shall be of aluminium sections as follows :<br />

Wall angle - 25 x 25 x 1.6 mm. thick.<br />

Main Tee<br />

- 35 x 25 x 1.6 mm. thick<br />

2.2.0 Ceiling Panel<br />

Cross Tee - 25 x 25 x 1.6 mm. thick<br />

Tees shall be jointed with adequate cleats etc.<br />

Ceiling Panels shall be best quality both side laminated rigid phenolic foam<br />

insulation board similar to "PHENOTHERM" as manufactured by<br />

`Bakelite Hylam'. The thickness, size and finish shall be as per drawing.<br />

(PCA.775.S034sc13) V.II-D2/S-XIII : 1


DCPL-K4A02<br />

3.0.0 INSTALLATION<br />

3.1.0 The ceiling grid shall be suspended from structural walls slabs, beams<br />

truss structural steel etc. with suspender fabricated from M.S.rod/<br />

angles/flasts etc. to the required level. The entire suspension system shall<br />

be of sufficient strength and rigidity to allow placing of planks over the grid<br />

for movement of maintenance personnel to attend various electrical and air<br />

conditioning installation over the ceiling and to carry ceiling panels in true<br />

level and plane without exceeding a deflecting of 1/360th of their span. All<br />

ceiling panels shall be secured in position using hold down clips of sufficient<br />

number. All joints in ceiling panels shall run straight.<br />

The installation of ceiling system shall be strictly as per drawing.<br />

4.0.0 SHOP DRAWINGS<br />

4.1.0 Contractor shall prepare complete working details layout based on the<br />

conceptual layout and design of suspended ceiling and illumination and air<br />

conditioning layout shown on the drawings and obtain approval from<br />

the Architect/Owner before installation.<br />

5.0.0 WORKMANSHIP<br />

5.1.0 Shall be done in the best workmanlike manner by the manufacturer<br />

authorised agency in accordance with manufacturer standards and<br />

recommendations.<br />

6.0.0 SAMPLES<br />

6.1.0 3 (three) mock-up samples of reasonable size showing standard grid with<br />

panels and suspender etc. having desired finish, colour etc. shall be<br />

submitted to the Architect/Owner for approval before materials are<br />

Delivered at site. Installed material shall match approved samples.<br />

7.0.0 ACCEPTANCE CRITERIA<br />

Finished ceiling shall be at the correct plane and present a pleasing and<br />

uniform appearance, free from sags, warps, figures or damaged boards.<br />

Joints, exposed grids etc. shall be in true lines and symmetrically<br />

placed in manner shown on drawings. Cutouts for light fixtures, diffusers<br />

etc. shall be of exact dimensions and in exact locations.<br />

8.0.0 I.S. CODES<br />

IS:2441 : Code of Practice for fixing ceiling coverings.<br />

(PCA.775.S034sc13) V.II-D2/S-XIII : 2


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

METAL DOORS, WINDOWS, VENTILATORS, LOUVRES, ETC.<br />

(PCA.775.S034sc14)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XIV : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XIV : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XIV : 7<br />

4.0.0 INFORMATION TO BE SUBMITTED V.II-D2/S-XIV : 9<br />

5.0.0 RATES V.II-D2/S-XIV : 9<br />

6.0.0 METHOD OF MEASUREMENT V.II-D2/S-XIV : 9<br />

7.0.0 I.S.CODES V.II-D2/S-XIV : 10<br />

(PCA.775.S034sc14)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

METAL DOORS, WINDOWS, VENTILATORS, LOUVRES, ETC.<br />

1.0.0 SCOPE<br />

The work in general shall consist of supplying and/or erecting and installing of<br />

all metal doors, windows, ventilators, louvers, glazed partitions, etc. as shown<br />

on drawings with all materials complete excluding supply of glass and glazing.<br />

The scope of work shall also include the assembly and the Owner from the<br />

store at site shall supply erection of all doors, windows, louvres, glazed partitions,<br />

etc. for which fabricated materials. Supplying and/or fixing of all door and window<br />

accessories and hardware is also included in the scope.<br />

2.0.0 INSTALLATION<br />

2.1.0 Materials<br />

Steel sections used for fabrication of doors, windows etc. shall be standard<br />

rolled steel sections specified in IS:1038 and IS:1361 or as specified in drawing<br />

and schedules.<br />

Steel sheets for frames, shutters, louvre blades etc. shall be of gauge<br />

mentioned in drawings.<br />

Aluminium sections for fabricating doors, windows, partitions etc. shall be<br />

extruded sections conforming to IS:1948 and 1949 or as manufactured by<br />

Indian Aluminium Company Limited or approved equivalent. The alloy used<br />

shall conform to IS Designation HE 9-WP of IS:733.<br />

Hardware and fixtures shall be as specified in "Schedule of Fixtures" and the<br />

best quality from approved manufacturers shall only be used. The Tenderer<br />

shall specifically state the particular manufacturer's materials he proposes to<br />

use. "Schedule of Fixtures" is for the purpose of stating the minimum<br />

requirement and improper alignment or faulty operation due to inadequate<br />

strength of hardware or fixture shall entirely be the Contractor's responsibility.<br />

All hardware and fixtures shall be able to withstand repeated use. Door<br />

closures shall conform to IS:3564 and shall be suitable for doors weighing<br />

61-80 Kg. unless otherwise stated in schedule. Each closer shall be<br />

guaranteed against manufacturing defect for one year and any defect found<br />

within this period shall be rectified or the closer replaced free of .<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 1


2.2.0 Fabrication<br />

DCPL-K4A02<br />

Concealed door closers shall be either floor mounted or transom mounted,<br />

suitable for installation with metal doors. It shall conform to the performance<br />

requirements and endurance test stated in IS:3564 - Appendix A.<br />

The Contractor shall submit samples of each type of hardware to the Engineer.<br />

The approved samples shall be retained by the Engineer for comparison of<br />

bulk supply. The samples shall be returned to the Contractor towards the end<br />

for incorporation in the job.<br />

The mastic for caulking shall be of best quality from a manufacturer approved<br />

by the Engineer. In general, the mastic for fixing of metal frames shall be as<br />

per IS:1081 and/or as approved by the Engineer.<br />

2.2.1 Steel Doors, Windows, Ventilators, Louvres etc.<br />

a) Door Frames<br />

Frames shall be fabricated from 16 G sheets. They shall be mortised,<br />

reinforced, drilled and tapped for hinges and lock and bolt strikes.<br />

Where necessary, frames shall be reinforced for door closers.<br />

Welded construction with mitred corners shall be used. Rubber door<br />

silencers shall be furnished for the striking jamb. Loose "T" masonry<br />

anchors shall be provided. Frames shall finish flush with floor and<br />

adjustable floor anchors shall be supplied. Frames shall be brought to<br />

site with floor ties/weather bars installed in place.<br />

b) Double Plate Flush Door Shutters<br />

Door shutters shall be 45 mm. thick, completely flush design and shall<br />

comprise of two outer sheets or 18 G steel sheets, rigidly connected<br />

and reinforced inside with continuous vertical 20 G stiffeners, spot<br />

welded in position at not more than 150 mm on centres.<br />

Both edges of doors shall be joined and reinforced full height by steel<br />

channels placed immediately inside and welded to the door faces. Top<br />

and bottom of doors shall be reinforced horizontally as shown on<br />

drawing by steel channels running full width of door. Doors shall not<br />

have more than 2.5 mm clearance at jambs and heads, shall have<br />

proper level on lock stiles and rails to operate without binding, and shall<br />

be reinforced at corners to prevent sagging or twisting. Pairs or double<br />

doors shall have meeting-stile edges bevelled or rebated. Where<br />

shown on drawing or called for in the schedule of items the doors shall<br />

be sound-deadened by filling the inside voids with mineral wool or other<br />

suitable approved materials.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 2


Doors shall be mortised, reinforced, drilled and tapped in shop for<br />

hinges, locks and bolts. They shall also be reinforced for closers,<br />

push-plates and other surface hardwares where necessary. Any<br />

drilling and tapping required for surface hardware shall be done at site.<br />

Where shown on drawing, provision shall be made for fixing glazing,<br />

vision panels, louvres etc. glazing moldings shall be of 18 G steel or<br />

extruded aluminium sections with profiles shown on drawing and<br />

suitable for fixing 6 mm. glass. Louvres blades shall be V or Z shaped<br />

and made out of 16 G sheets.<br />

c) Single Sheet Door Shutters<br />

Single sheet doors shall be made from best quality 18 G mild steel<br />

sheets, and shall present a flush surface on the outside. The inside<br />

shall be stiffened with semi tubular edge and central stiffening rail,<br />

which shall convey the lock and other furniture. The frames shall be<br />

made from best quality 16 G mild steel sheets.<br />

Wherever required as shown on drawings, provisions for fixing glass<br />

panes, louvres etc. shall be made.<br />

The manufacturing shall be done as specified in 2.2.1.b. "Double Plate<br />

Flush Door Shutters".<br />

d) Sliding Doors<br />

DCPL-K4A02<br />

Sliding doors shall be either double plate or single plate construction as<br />

called for in drawings made out of 18 gauge steel sheets with adequate<br />

stiffeners. The Contractor shall specify the weight of the door in his<br />

shop and submit the manufacturer's catalogue of the sliding gear he<br />

proposes to use. Where shown on drawings or call for in the Schedule<br />

of Items, the Contractor shall make provision for openings to the door<br />

for mono-rail beams. Doors shall close positively to exclude rain water<br />

from seeping in. When called for in schedule, sliding doors shall<br />

withstand specified wind loads without buckling or jamming. The door<br />

shall slide freely under all ambient conditions.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 3


DCPL-K4A02<br />

e) Door Threshold<br />

Door threshold shall be provided as shown on drawing. Doors without<br />

threshold shall have bottom tie of approved type.<br />

f) Steel Windows, Sashes, Ventilators etc.<br />

These shall conform in all respects to IS:1038 and IS:1361 latest<br />

editions and as shown on drawings. The details as called for in the<br />

above codes shall be applicable for coupling mullions, transoms,<br />

weather bars, pivot arrangements for ventilators, etc. or as shown on<br />

drawings or called for in the Schedule of Items.<br />

All welds shall be dressed flush on all exposed and contact surfaces.<br />

Where composite unit openings are shown on drawings, the individual<br />

window units shall be joined together with requisite transoms and<br />

mullions as shown on drawings. All windows shall be outside glazed,<br />

fixed with putty or metal glazing beads as shown on the drawings<br />

and/or specified under Schedule of Items. Where aluminium glazing<br />

beads are specified, they shall be extruded aluminium channel 9.5 mm<br />

x 9.5 mm x 1.6 mm (Indal Section No. 2209) unless otherwise shown on<br />

drawings. Aluminium beads shall be given one coat of zinc chromate<br />

primer before fixing to windows.<br />

2.2.2 Aluminium Door, Windows and Frames<br />

Extruded sections shall have a minimum 3 mm wall thickness unless otherwise<br />

approved in samples by the architect/engineer. All sections shall be approved<br />

by the Architect/Engineer before fabrication is taken up. Doors, frames,<br />

mullions, transom etc. shall be anodized in a bath of sulphuric acid to provide a<br />

clear coating of minimum 0.6 mm thickness. The anodized materials shall then<br />

be sealed by immersing in bailing water for 15 minutes. A protective<br />

transparent coating shall be applied to the sections before shipment from the<br />

factory.<br />

All work shall be fitted and shop assembled to a first class job, and ready for<br />

erection. Shop joints shall be made to hair lines and then welded or braced by<br />

such method as will produce an uniform colour throughout the work. Work on<br />

the above, other than described, shall be carefully fitted and assembled with<br />

neat joints with concealed fasteners. Wherever possible, joints shall be made<br />

in concealed locations and on edges of doors. Field connections of all work<br />

may be made with concealed screws or other approved type of fasteners.<br />

Glazing beads shall be snap fit type without visible screws and shall be of sizes<br />

to accommodate 6 mm thick glazing or as specified in schedule of items. All<br />

work shall be adequately braced and reinforced as necessary for strength and<br />

rigidity.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 4


DCPL-K4A02<br />

2.2.3 Aluminium Structural Glazing<br />

Providing and fixing of barriered semi unitised structural glazing system at<br />

all levels through designing and selection of mullion and transoms profiles<br />

anodised (15 to 20 micron) or powder coated (50 to 70 micron), selected for<br />

their fixing on the structure depending on the structural conditions, functional,<br />

statistical requirement and should withstand the wind load criteria as per IS-875<br />

(part - III) 1987. System should provide proper rebate areas for air pressure<br />

compensation / water drainage at required stages. Double insulated hard<br />

coated toughened glass consist of 6mm outer single safety glass, 12mm inter<br />

space and 6mm inner clear glass panel glued onto the glass glazing frame<br />

profile selected according to the vision / spandrel panel (Aluminium Composite<br />

Panels) requirement with DC 995 structural sealant. Proper supporting element<br />

should be provided for taking care of the respective infill load and reliving in<br />

case of the glass bonding failure. ( The profile sections shall be Hindalco -<br />

Alupuram unit, HYDRO product or equivalent). Floor to floor height would be<br />

4.2m approx and width of glazing supporting frame would be 1.0m approx.<br />

2.3.0 Shop Coat or Paint<br />

The shop paint for steel doors, windows etc. shall be best lead or zinc<br />

chromate primer paint from approved manufacturer. All surfaces shall be<br />

thoroughly cleaned of rust, grease, loose mill scales etc. and given one coat of<br />

shop paint. Portions like mullions, transoms etc. which will be inaccessible<br />

after assembly of units shall be given an extra coat of paint before assembly.<br />

All steel doors, windows, etc. shall be hot dip galvanised to give a coating<br />

weight of 1-1/2 - 2 oz. per sft. One coat zinc chromate primer coat shall then<br />

be applied as shop paint.<br />

Portions of aluminium frame which come in contact with masonry construction,<br />

shall, before shipment from workshop, be protected with a heavy coat of alkali<br />

paint. Aluminium coming in contact with other incompatible metals shall be<br />

coated with zinc chromate primer.<br />

2.4.0 Handling & Storage of Fabricated Material<br />

All metal doors, windows, etc. shall be packed and crated properly before<br />

despatch, to ensure that there will be no damage to the fabricated materials.<br />

Loading into wagons and trucks shall be done with all care to ensure safe<br />

arrival of materials at site in undamaged condition.<br />

When taking delivery of items supplied by Owner, the Contractor shall satisfy<br />

himself that the items supplied are upto the specified standard. Any defect<br />

detected shall promptly be brought to the notice of the Engineer.<br />

All metal doors, windows etc. shall be stored under cover in a way to prevent<br />

damage or distortion. Special care shall be taken to prevent staining of<br />

aluminium products by rust, mortar etc.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 5


2.5.0 Assembly & Erection at Site<br />

DCPL-K4A02<br />

In general, the fixing of steel doors, windows, ventilators, louvres, etc. shall<br />

conform to IS:1081 and as shown on drawings. The Contractor shall assemble<br />

and install all steel doors, windows, sashes, fixed metal louvres, etc. including<br />

transoms and mullions for composite units in respective places as shown on<br />

drawing, keeping proper lines and levels, and in approved workmanlike<br />

manner, to give trouble free and leak-proof installations.The installation shall be<br />

done according to the instructions of the manufacturer, and/or as approved by<br />

the Engineer. If required by the Engineer, the installation shall have to be<br />

carried out under the supervision of the manufacturer's staff. The Contractor<br />

shall take every precaution against damage of the components during<br />

installation. Necessary holes, chases, etc. required for fixing shall be made by<br />

the Contractor and made good again as per original, after installation.<br />

After installation of steel doors, windows, etc. all abrasions to shop-coat of paint<br />

shall be retouched and made good with the same quality of paint used in shopcoat.<br />

All coupling mullions, transoms, frames, etc. in contact with adjacent steel and<br />

other members, shall be well bedded in mastic. The Contractor shall bring to<br />

the site the mastic cement in original sealed containers of manufacturer and<br />

shall apply it as per the instructions. For all frames supplied by either the<br />

Owner or the Contractor, mastic shall be supplied by the Contractor and<br />

caulking done properly as per drawings, specifications and as per instructions<br />

of the Engineer.<br />

Door shutters, partitions hardware fixtures etc. shall be fixed only after major<br />

equipments have been installed in rooms.<br />

Wherever required, nylon cords of approved quality shall be supplied along with<br />

pivoted sashes and shall be of adequate length to terminate one metres from<br />

the floor. Loose ends of cords shall end in metal or plastic pull as approved by<br />

the Engineer.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 6


DCPL-K4A02<br />

3.0.0 ACCEPTANCE CRITERIA<br />

3.1.0 For Fabricated Items<br />

a) Overall dimensions shall be within +1.5 mm of the size shown on<br />

drawings.<br />

b) Mullions, transoms etc. shall be in one length and permissible<br />

deviations from straightness shall be limited to + 1.5 mm from the axis<br />

of the member.<br />

c) Door and window shutters shall operate without jamming. The<br />

clearance at head and jamb for door shutters shall not exceed 1.5 mm.<br />

For double leaf doors, the gap at the meeting stiles shall not be more<br />

than 1.5 mm.<br />

d) Door leaves shall be undercut where shown on drawings.<br />

e) Doors, windows, frames, etc. shall be on a true planes, free from warp<br />

or buckle.<br />

f) All welds shall be dressed flush on exposed and contact surfaces.<br />

g) Correctness of location and smoothness of operations of all shop<br />

installed hardware and fixtures.<br />

h) Provision for hardware and fixtures to be installed at site.<br />

i) Glazing beads shall be cut with mitred corners.<br />

j) Glazing clips, fixing devices etc. shall be supplied in adequate numbers.<br />

k) Shop coats shall be properly applied.<br />

l) Exposed aluminium surfaces shall be free from scratches, stains and<br />

discolouration. Anodised surfaces shall present a uniform and pleasing<br />

look.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 7


DCPL-K4A02<br />

3.2.0 For Installed Items<br />

a) Installations shall be at correct location, elevation and in general, on a<br />

true vertical plane.<br />

b) Fixing details shall be strictly as shown on drawings.<br />

c) Assembly of composite units shall be strictly as per drawings with<br />

mastic caulking of transoms and mullions, gaskets, weather strips etc.<br />

complete.<br />

d) All frames on external walls shall be mastic caulked to prevent leakage<br />

through joint between frames and masonry.<br />

e) All openable section shall operate smoothly without jamming.<br />

f) Locks, fasteners etc. shall engage positively. Keys shall be<br />

non-interchangeable.<br />

g) Cutting to concrete or masonry shall be made good and all abrasions to<br />

shop paint shall be touched up with paint of same quality as shop paint.<br />

h) Aluminium doors, windows, etc. shall be free from scratches stain or<br />

discolouration.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 8


4.0.0 INFORMATION TO BE SUBMITTED<br />

DCPL-K4A02<br />

4.1.0 With Tender<br />

a) Names of manufacturers for doors, windows, etc.<br />

b) Manufacturer’s catalogue for all hardware and fixtures proposed to be used.<br />

4.2.0 After Award<br />

a) Before starting fabrication of all metal doors, windows, etc. the Contractor shall<br />

submit detailed fabrication drawings to the Engineer for approval. The<br />

fabrication shall be started only after approval of drawings.<br />

b) He shall submit a programme of work to be done for the approval of the<br />

Engineer.<br />

c) Before bulk supply, he shall submit for the approval of the Engineer samples of<br />

all bought out items and samples of each type of fabricated items. The samples<br />

shall be retained by the Engineer for comparison of bulk supply and returned to<br />

the Contractor towards the end for final incorporation in the job.<br />

5.0.0 RATES<br />

[This clause may be ignored in view of EPC mode of execution]<br />

Rates shall be unit rates for items described in the schedule.<br />

6.0.0 METHOD OF MEASUREMENT<br />

[This clause may be ignored in view of EPC mode of execution]<br />

a) Supply and installation of doors shall be measured in number of each type used.<br />

The types shall be as shown on drawings and described in Schedule of Items.<br />

b) Supply of windows shall be measured in number of each type of unit used either<br />

single or in combination.<br />

c) Installation including assembly and erection of windows shall be measured in<br />

number of types of combinations mentioned in the Schedule of Items.<br />

d) Supply and installation of louvers shall be measured for area of opening in which<br />

the louvre is to be installed.<br />

e) Supply of mullions and transoms shall be measured for net length of different<br />

types shown on drawings and described in Schedule. In computing the length, the<br />

length required for embedding in concrete or masonry shall not be considered. No<br />

extra payment shall be made for end or cover plates.<br />

f) Vision panels, louvers to doors and insulation between door faces shall be<br />

measured for actual area and paid separately over the basic rate doors.<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 9


DCPL-K4A02<br />

g) Glazed beads, weather stripping, fixing devices etc. shall not be measured<br />

separately but shall be included in the supply rate of respective items.<br />

h) And cutting or grouting to concrete and masonry or welding and drilling to steel<br />

required for installation shall be included in the installation rate. No separate<br />

payment shall be made for cauking and jamming or frames or making good to<br />

concrete or masonry.<br />

i) Glass and glazing shall be measured and paid under relevant items.<br />

j) Door and window fixtures, locks, door closures etc. shall be measured in actual<br />

number use.<br />

7.0.0 I.S. CODES<br />

Following are some of the important I.S. Codes as relevant to this section :<br />

Steel doors, windows and ventilators - IS:1038<br />

Steel windows for industrial buildings - IS:1361<br />

Aluminium doors windows and ventilators - IS:1948<br />

Aluminium windows for industrial buildings - IS:1949<br />

Steel door frames - IS:4351<br />

Code of practice for fixing and glazing of<br />

metal (steel and aluminium) doors,<br />

windows, and ventilators - IS:1081<br />

(PCA.775.S034sc14) V.II-D2/S-XIV : 10


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

GLASS AND GLAZING<br />

(PCA.775.S034sc15)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XV : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XV : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XV : 3<br />

4.0.0 I.S. CODES V.II-D2/S-XV : 3<br />

(PCA.775.S034sc15)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

GLASS AND GLAZING<br />

1.0.0 SCOPE<br />

The work in general shall consist of supplying and fixing all glass and glazing<br />

including all clips, putty, mastic cement etc. wherever required as shown on<br />

drawings and specifications, supply of metal glazing beads and neoprene<br />

gaskets shall not be included in this scope.<br />

This shall also include the fixing of all glass and glazing supplied by the Owner<br />

at his site stores.<br />

2.0.0 INSTALLATION<br />

2.1.0 General<br />

2.2.0 Materials<br />

The Contractor shall supply and install all glass and glazing as required for<br />

various doors, windows, sashes, ventilators and fixed louvres, miscellaneous<br />

glazing and partitions, unless otherwise stated from approved manufactur<br />

having uniform refractive index and free from flaws, specks and bubbles. The<br />

glass shall be brought to site in the original packing from the manufacturer and<br />

cut to size at site.<br />

a) Glare reducing or heat absorbing glass shall be of approved<br />

manufacturer and special care shall be taken to grind smooth and<br />

round off the edges before fixing.<br />

b) Glass shall be float glass of required thickness and shall be clear or<br />

tinted as indicated.<br />

c) Wired glass shall be thick rolled glass with centrally embedded 42g.<br />

wire mesh of Georgian type. This may be of clear or coloured glass, as<br />

shown on drawings.<br />

(PCA.775.S034sc15) V.II-D2/S-XV : 1


DCPL-K4A02<br />

d) Obscure glass shall have a cast surface in one side.<br />

e) Coloured and figured glass shall be as per approved sample.<br />

f) In general, the putty shall conform to IS : 400 and be of best quality<br />

from approved manufacturer. It shall be brought to site in the<br />

manufacturer's original packing. Quick setting putty glass is used where<br />

it shall be non-setting type.<br />

g) EPDM gaskets with snap-fit glazing beads shall be fixed as per<br />

manufacturer's instructions and shall sit snugly against glass to give a<br />

leakproof installation.<br />

h) Float glass<br />

i) Double glazing<br />

2.3.0 Glazing, Setting and Finish<br />

All glazing clips, bolts, nuts, putty, mastic cement etc. as required shall be<br />

supplied by the Contractor.<br />

All glass shall be thoroughly cleaned before putting in position. Each glass<br />

pane shall be held in place by special glazing clips of approved type. As<br />

specified in relevant I.S. Codes, four glazing chips shall be provided per<br />

glasspane, except for large panes were six or more clips shall be used as per<br />

Engineer's instructions. All holes that may be necessary for holding the clips<br />

glazing heads and all other attachments shall be drilled by the Contractor.<br />

Glass panes shall be set without springing, and shall be bedded in putty and<br />

back puttied, except where moulding or gasket are specified, putty, mastic<br />

cement etc. shall be smoothly finished to the even line and figured glass shall<br />

be set with smooth side out.<br />

After completion of glazing work, the Contractor shall remove all dirt stains,<br />

excess putty etc. clean the glass panes and leave the work in perfectly<br />

acceptable condition. All broken cracked or damaged glass shall be replaced<br />

by new ones.<br />

(PCA.775.S034sc15) V.II-D2/S-XV : 2


DCPL-K4A02<br />

3.0.0 ACCEPTANCE CRITERIA<br />

a) All installation shall be free from cracked, broken or damaged glass.<br />

Edges of large panes of thicker glass and heat absorbing glass shall be<br />

inspected carefully for chipped, cracked or underground edges.<br />

b) Glazing shall be carefully done to avoid direct contact with metal<br />

frames.<br />

c) All glass shall be embedded in mastic or fixed by neoprene gaskets to<br />

give a leakproof installation.<br />

d) At completion, the panes shall be free from dirt, stains, excess putty etc.<br />

to the complete satisfaction of the Engineer.<br />

4.0.0 I.S. CODES<br />

Following are some of the important I.S.Codes relevant to this Section :<br />

IS : 3548 - Code of practice for glazing in building.<br />

IS : 1083 - Code of practice for fixing and glazing metal doors, windows &<br />

ventilators.<br />

(PCA.775.S034sc15) V.II-D2/S-XV : 3


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XVI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROLLING STEEL SHUTTERS/GRILLS<br />

(PCA.775.S034sc16)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XVI : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XVI : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XVI : 3<br />

4.0.0 I.S. CODES V.II-D2/S-XVI : 3<br />

(PCA.775.S034sc16)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XVI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROLLING STEEL SHUTTERS/GRILLS<br />

1.0.0 SCOPE<br />

This specification covers the design, supply of materials, fabrication, delivery<br />

and erection of Rolling Shutters/Grills with motor drive and/or manual operation<br />

including all accessories as hereinafter specified.<br />

2.0.0 INSTALLATION<br />

2.1.0 Components<br />

a) Slats for rolling shutters shall be made from tested bright cold rolled,<br />

annealed M.S. strips, not less than 0.9 mm thick for shutters upto 4.5 M<br />

wide and not less than 2.25 mm thick for shutters 5.5 M wide and<br />

above, machine rolled at 75 mm rolling centres, interlocking with each<br />

other. The profile will be such as to prevent excessive deflection under<br />

specified wind load.<br />

b) Rolling grills shall be constructed out of 6 mm dia. rods at 35 mm on<br />

centres running horizontally flexible connected with vertical links spaced<br />

not more than 200 mm centres. Alternatively, rolling grills shall be made<br />

from perforated slats of approved design reinforced with 6 mm dia rods.<br />

c) End locks shall be heavy type M.C.I./C.I. and shall be provided at each<br />

end of alternate slats unless specified otherwise in the Schedule.<br />

d) Bottom bars shall be finished with two angles not less than 6 mm thick<br />

for external shutters. When shown on drawings, a flexible weather strip<br />

shall be applied to make tight contact with the floor.<br />

e) Guides shall be of such depth as to retain the shutter under a wind<br />

pressure of 100 Kg/Sq.M or as specified in Schedule.<br />

f) Shafts shall be of steel pipe of sufficient size to carry the torsion load<br />

with a maximum deflection of 1/360th of span.<br />

Grease packed ball bearings or bushings shall be provided for smooth<br />

trouble free operation.<br />

g) Hoods shall be formed of not less than 20 gauge steel, suitable<br />

(PCA.775.S034sc16) V.II-D2/S-XVI : 1


DCPL-K4A02<br />

reinforced to prevent sag.<br />

h) Locks shall be slide bolt and hasp, or cylinder lock operable from one or<br />

both sides. Provision securing hand chain with pad-lock, provision for<br />

removable handle for hand cranks etc. shall be made as described in<br />

Schedule or as described by the Engineer.<br />

i) Power unit shall be suitable for 3 phase, 50 cycle, 400 volt A.C. power<br />

supply and shall be either floor or wall mounted unit. The motor shall be<br />

of sufficient capacity to move the shutter in either direction at a speed of<br />

0.3 metres per second. In addition to the gear motor each standard<br />

power unit shall include a magnetic brake, a reversing starter with<br />

built-in overload protection, a geared limit switch and one push button<br />

station located inside the building unless otherwise stated drawing.<br />

It is desirable that the bottom bar of motor operated doors shall be<br />

provided with a sensitive edge, electrically connected to stop the travel<br />

of the door on meeting an obstruction.<br />

j) Operating chains shall be of tested quality, heavily galvanised and with<br />

all ends rounded to assure smooth operation and hand protection.<br />

k) Reduction gears shall be high strength gray cast iron, machine moulded<br />

from machine out patterns.<br />

2.2.0 Manually Operated Shutters/Grills<br />

Manually operated shutters shall be easily operable by one person. The speed<br />

of operation shall be about 1.3 metres per second. In general, manually<br />

operated shutters shall be push pull type for openings upto 9 Sq.metre in area.<br />

Larger shutters shall be either chain and gear operated or crank and gear<br />

operated. The crank handle shall be removable. All shutters shall be lockable<br />

from one or both sides as described as desired by the Engineer.<br />

2.3.0 Power Operated Shutters/Grills<br />

2.4.0 Shop Coat<br />

2.5.0 Erection<br />

These shall be operable from a push button station conveniently located beside<br />

the door or as shown on drawings. One emergency hand chain/crank operation<br />

shall also be provided for use in case of failure of the electric system. Where<br />

called for in Schedule, externally mounted shutters shall be operated by control<br />

mechanism located inside the building.<br />

Shutters shall be painted with one coat of red lead or zinc chromate primer.<br />

Where specified, doors shall be galvanized and subsequently painted one coat<br />

of zinc chromate for adhesion of field coat.<br />

Door shall be installed by the manufacturer or his authorised representative and<br />

(PCA.775.S034sc16) V.II-D2/S-XVI : 2


DCPL-K4A02<br />

all work shall be as per manufacturer's instructions. Any drilling or cutting to<br />

concrete, masonry etc. shall be made good after erection of shutters and all<br />

abrasion to shop coat shall be touched up. All electrical work shall be in strict<br />

accordance with the latest Indian Electricity Rules.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

3.1.0 Shop Inspection<br />

After completing the manufacture of the different components of the rolling<br />

shutter, an arrangement for shop inspection by the Engineer shall be made to<br />

check the conformity with approved shop drawings.<br />

3.2.0 Field Inspection<br />

3.3.0 Guarantee<br />

After installing the shutters, the Contractor shall test the performance of the<br />

shutter in the presence of the Engineer. The doors shall be smoothly operable<br />

under all ambient conditions. All control and locking devices shall give fault-free<br />

performance.<br />

The Contractor shall give one year's guarantee for the successful operation of<br />

the shutters. This shall be supported by a separate and unilateral guarantee<br />

from the manufacturer of the shutters.<br />

4.0.0 I.S. CODE<br />

IS : 6248 - Metal rolling shutters and rolling grills.<br />

(PCA.775.S034sc16) V.II-D2/S-XVI : 3


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XVII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

MISCELLANEOUS METAL<br />

(PCA.775.S034sc17)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XVII : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XVII : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XVII : 4<br />

4.0.0 I.S. CODES V.II-D2/S-XVII : 4<br />

(PCA.775.S034sc17)


DCPL-K4A02<br />

VOLUME : II-G/2<br />

SECTION-XVII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

MISCELLANEOUS METAL<br />

1.0.0 SCOPE<br />

This specification shall generally be read in conjunction with item nos. 6.01 &<br />

6.03.<br />

This shall include supply, fabrication and erection of miscellaneous metal items<br />

of light nature in gates, grills, balcony and stair handrails particulars, structural<br />

mullions and transoms, ladders hangers masonry anchors, shelf angles,<br />

anchor bolts, fasteners, etc. as shown on drawing or as instructed by the<br />

Engineer. The above items shall be of fabricated or cast M.S/Aluminium/Brass,<br />

cast iron, M.S. and galvanised M.S. Sheets, aluminium sheets, expanded<br />

metal, wire mesh etc. as shown on drawings and/or described.<br />

2.0.0 INSTALLATION<br />

2.1.0 Fabrication/Casting<br />

2.1.1 General<br />

All work shall be done according to approved shop drawings. All workmanship<br />

shall be equal to the best practice in modern structural or foundry shop.<br />

2.1.2 Shop Connections<br />

a) All shop connections shall be riveted or welded except when noted<br />

otherwise on drawings.<br />

b) Welding of steel shall be done in accordance with the IS : 816. Use of<br />

metal arc welding for general construction in Mild Steel.<br />

c) Welding of aluminium shall be done in accordance with IS: 2812, Arc<br />

welding of Aluminium and Alloys, Special care shall be taken to grind<br />

smooth all welded surface that shall remain exposed to view. Welds<br />

shall be electrically continuous if so required by the Engineer.<br />

2.1.3 Shop Coat<br />

(PCA.775.S034sc17) V.II-D2/S-XVII : 1


DCPL-K4A02<br />

2.2.0 Erection<br />

2.2.1 Bracing<br />

Before leaving the shop, all metal work shall be thoroughly cleaned by effective<br />

means of all loose mill/ scale, rust and foreign matter. Except where encased in<br />

concrete, all steelwork shall be given one coat of approved metal protective<br />

paint, applied by brush thoroughly and evenly, well worked into joints and other<br />

open spaces. All paint shall be applied to dry surfaces. Steel work shall be<br />

galvanised or galvanized and painted with a coat of zinc chromate primer.<br />

Aluminium surfaces which shall come in contact with masonry shall be given<br />

one coat of zinc chromate primer.<br />

The Contractor shall provide all necessary temporary guys and braces to<br />

ensure alignment and stability of the members and to take care of all loads to<br />

which the structure may be subjected including erection of equipment and<br />

operation of the same.<br />

2.2.2 Temporary Bolting-Up<br />

2.2.3 Turned Bolt<br />

2.2.4 Welding<br />

As erection proceeds the Contractor shall plumb up and level all members and<br />

shall securely bolt up to take care of all dead load, wind load and erection<br />

stresses. Wherever piles of materials, erection equipment or other loads are<br />

carried during erection, proper provision shall be made to take care of the<br />

stresses resulting from the same.<br />

For field connections where bolting is specified, holes for the turned bolts may<br />

be reamed in the field, if required. All drilling or reaming for turned bolts shall be<br />

done after the parts to be connected are assembled.<br />

Where specified on drawings, welding shall be done in accordance with IS :<br />

816 for steel and IS: 2812 for Aluminium and Alloys.<br />

2.2.5 Cutting and Fitting<br />

No cutting of sections, flanges, webs of angles shall be done without the<br />

approval of the Engineer. Where indicated on the drawings, holes, cuttings, etc.<br />

shall be provided as required for installation, to the work by the other<br />

Contractors. No additional holes or cuttings, than those shown on drawings,<br />

shall be made without the approval of the Engineer.<br />

(PCA.775.S034sc17) V.II-D2/S-XVII : 2


DCPL-K4A02<br />

2.2.6 Drifting<br />

2.2.7 Grouting<br />

Correction of minor misfits and a reasonable amount of reaming and cutting of<br />

excess stock from rivets may be permitted. For this, light drifting may be<br />

allowed to draw holes together. Twist drills shall be used to enlarge as<br />

necessary to make connections. Reaming that weakens the members or make<br />

it impossible to fill the holes properly or to adjust accurately after reaming shall<br />

not be allowed.<br />

Any error in shop work which prevents the proper assembling and fitting of<br />

parts by moderate use of drift pins or a moderate amount or reaming and slight<br />

chipping and cutting shall immediately be called to the attention of the Engineer<br />

and approval of the method of correction obtained. The use of cutting torches<br />

to enlarge or alter rivet holes shall not be permitted.<br />

All bearing plates, loose lintels and beams, etc. shall be set to proper grade<br />

and level by the Contractor and the Engineer's approval obtained before<br />

proceeding with the grouting. Grouting shall be done in 1:1.5:3 or 1:1- 1/2:3<br />

concrete with 6 mm down stone chips.<br />

2.2.8 Anchor Bolting<br />

2.2.9 Pipe Joints<br />

2.2.10 Spot Painting<br />

2.2.11 Making Good<br />

When shown on drawings, the miscellaneous metal items shall be fixed to<br />

concrete by case hardened and drawn carbonizing steel expander nut and bolt.<br />

The Contractor shall submit the manufacturer's literature showing the average<br />

pull out and average shear values for bolts of various sizes. The bolts shall be<br />

fixed strictly as per the manufacturer's instructions.<br />

M.S. Pipes shall be joined by threaded sockets or by welding. Cast iron pipes<br />

shall be socket and spigot jointed and caulked with hemp and molten lead.<br />

All field rivets and bolts and also any serious abrasion to shop paint shall be<br />

spot painted with the same materials as used for the shop paint.<br />

All cutting to concrete or masonry shall be made good to the satisfaction of the<br />

Engineer.<br />

(PCA.775.S034sc17) V.II-D2/S-XVII : 3


DCPL-K4A02<br />

3.0.0 ACCEPTANCE CRITERIA<br />

a) All items shall be of correct shape, size, weight etc. shown on drawings.<br />

b) For installed items, the tolerances shall be follows :<br />

i) Permissible deviation from straightness - 1 in 1000.<br />

ii)<br />

Seats, stiffener connections etc. shall be as per approved<br />

drawings and shall not interfere with architectural clearances.<br />

c) All castings shall be free from blow holes, cracks and other blemishes.<br />

4.0.0 I.S. CODES<br />

IS : 226 - Structural Steel (Standard Quality)<br />

IS:800 - Code of practice for use of structural steel in general<br />

building construction.<br />

IS : 816 - Use of metal arc welding for general construction in mild<br />

steel.<br />

IS : 2812 - Arc welding of Aluminium and Alloys<br />

IS : 3150 - Hexagonal Wire Netting<br />

IS : 4948 -<br />

Welded steel wire fabric for general use.<br />

(PCA.775.S034sc17) V.II-D2/S-XVII : 4


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XVIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

PAINTING, WHITE WASHING AND POLISHING ETC.<br />

(PCA.775.S034sc18)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XVIII : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XVIII : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XVIII : 8<br />

4.0.0 I.S. CODES V.II-D2/S-XVIII : 9<br />

(PCA.775.S034sc18)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XVIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

PAINTING, WHITE WASHING AND POLISHING ETC.<br />

1.0.0 SCOPE<br />

This specification covers painting, white washing, varnishing, polishing etc. of<br />

both interior and exterior surfaces of wood work, masonry, concrete plastering,<br />

plaster or paris,Punning false ceiling, structural and other miscellaneous steel<br />

items, rain water down comer, floor and roof drains, soil, waste and service<br />

water pipes, and other ferrous and non-ferrous metal items as shown on<br />

drawings, or as directed by the Engineer.<br />

Copper, bronze, chromium plate, nickel, stainless steel, aluminium and monel<br />

metal shall generally not be painted or finished except if otherwise specified.<br />

The painting Contractor shall inspect the work of others prior to the application<br />

of paint. If surface to be finished cannot be put in suitable condition for painting<br />

by customary preparatory methods, the painting contractor shall notify the<br />

Engineer in writing or assume responsibility for and rectify unsatisfactory<br />

finishing that results.<br />

Before commencing painting, the painting Contractor shall obtain the approval<br />

of the Engineer in writing regarding the schedule of work to minimize damage,<br />

disfiguration or staining by other trades. He shall also undertake normal<br />

precautions to prevent damage, disfiguration or staining to work of other trades<br />

or other installations.<br />

2.0.0 INSTALLATION<br />

2.0.1 Materials<br />

Materials shall be highest grade products or well-known approved manufacture<br />

and shall be delivered to the site in original sealed containers, bearing brand<br />

name, manufacturer's name and colour shade, with labels intact and seals<br />

unbroken. All materials shall be subject to inspection, analysis and approved<br />

by the Engineer. It is desired that materials of one manufacturer only shall be<br />

used as far as possible & paint or one shade is obtained the same<br />

manufacturing batch. All paint shall be subject to analysis from random<br />

samples taken at site from painters bucket, if so desired by the Engineer.<br />

All prime coats shall be compatible to the material of the surface to be finished<br />

as well as to the finishing coats to be applied.<br />

All unspecified materials such as shellac, turpentine or linseed oil shall be of<br />

the highest quality available and shall conform to the latest IS standards. All<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 1


DCPL-K4A02<br />

such materials shall be made by reputable recognised manufacturers and shall<br />

be approved by the Engineer.<br />

All colours shall be as per painting schedule and tinting and matching shall be<br />

done to the satisfaction of the Engineer. In such cases, where samples are<br />

required, they shall be executed in advance with the specified materials for the<br />

approval of the Engineer.<br />

a) White Washing<br />

Shall be done from pure shell lime or fat lime, or a mixture of both as<br />

instructed by the Engineer; and shall conform to IS:712 latest edition.<br />

Samples of lime shall be submitted to the Engineer for approval, and<br />

lime as per approved sample shall be brought to site in unslaked<br />

condition. After slaking, it shall be allowed to remain in a tank of water<br />

for two days and then stirred up with a pole, until it attains the<br />

consistency of thin cream. 100 grams of gum to 6 litres of white wash<br />

water and a little quantity of indigo or synthetic ultramarine blue shall be<br />

added to the lime.<br />

b) Dry distemper<br />

Shall be made from suitable pigments, extenders, lime proof tinters,<br />

water soluble binders etc. and shall conform to IS:427.<br />

c) Oil Bound Washable Distemper<br />

Shall be of oil emulsion type, containing suitable preservatives and shall<br />

conform to IS:428.<br />

d) Waterproof Cement Paint<br />

Shall be made from best quality white cement and lime resistant colours<br />

with accelerators, waterproofing agents and fungicides. The paint shall<br />

conform to IS:5410.<br />

e) Acrylic Emulsion Paint<br />

Shall be water-based acrylic copolymer emulsion with retile titanium<br />

dioxide and other selected pigments and fungicide. It shall exhibit<br />

excellent adhesion to plaster and cement surface and shall resist<br />

deterioration by alkali salts. The paint film shall allow the moisture in<br />

wall to escape without peeling or blistering. The paint, after it is dried,<br />

shall be able to withstand washing with mild and water without any<br />

deterioration in colour, or without showing flaking, blistering or peeling.<br />

f) Synthetic Enamel Paint<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 2


2.0.2 Storage<br />

DCPL-K4A02<br />

Shall be made from synthetic resins and drying oil with rutile titanium<br />

dioxide and other selected pigments to give a smooth, hard, durable<br />

and glossy finish to all exterior and interior surfaces. White and pastel<br />

shades shall resist yellowing and darkening with aging. The paint shall<br />

conform to IS:2932 and IS:2933.<br />

g) Aluminium Paint<br />

Shall be in two pack containers and shall resist weathering. The paint<br />

shall conform to IS:2339.<br />

h) Shall be best quality alkyd varnish suitable for brushing over the tint of<br />

paint or light natural wood and shall not darken or yellow with age.<br />

i) French Polish<br />

Shall be made from best quality shellac, denatured spirit and other<br />

suitable alcohol soluble ingredients and made by a well known<br />

approved manufacturer. The material shall conform to IS:348.<br />

French polish shall not be used on bare wood. It shall only be used as<br />

finishing coat on wood after the wood is pretreated with a liquid wood<br />

filler conforming to IS:345 is applied and rubbed out.<br />

The Contractor shall arrange for safe and proper storage of all materials and<br />

tools. The storage space if allotted within the building shall be adequately<br />

protected from damage, disfigurement & stains. Paint shall be kept covered at<br />

all times and mixing shall be done in suitable containers. All necessary<br />

precautions shall be taken by the Contractor to prevent fire.<br />

2.1.0 Preparation of surface<br />

2.1.1 Wood<br />

Before starting the work the Contractor shall obtain the approval of the<br />

Engineer regarding the soundness & readiness of the surface to be painted on.<br />

All surfaces shall be free from dirt and loose or peeling paints. The surface<br />

shall be rubbed down smooth. All nails & screws shall be sunk below the<br />

surface and filled with putty after applying an under coat. Small knots that do<br />

not justify cutting and sap streaks shall be covered with minimum 2 coats of<br />

pure shellac coating applied thinly & extended 25 mm beyond the area. All<br />

large, loose or resinous knots shall be removed and filled with sound wood. All<br />

work shall be done as per IS:2338.<br />

2.1.2 Masonry, Concrete and Plastered Surface<br />

Surface shall be free from all oil, grease, efflorescence, mildew, loose paint or<br />

other foreign and loose materials. Masonry cracks shall be cleaned out and<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 3


2.1.3 Metal<br />

DCPL-K4A02<br />

patch filled with mortar similar to the original surface and uniformly textured.<br />

Where this type of re- surfacing may lead to the finishing paint being different in<br />

shade from the original surfaces, the resurfaces area shall be treated with<br />

minimum one coat of cement primer, which should be continued to the<br />

surrounding area for a distance of minimum 100 mm.<br />

Surface with mildew or efflorescence shall be treated as below :<br />

a) Mildew<br />

2.2.0 Application<br />

2.2.1 General<br />

All mildewed surfaces shall be treated with an approved fungicide such<br />

as ammonia cal wash consisting of 7g of copper carbonate dissolved in<br />

80 ml. liquor ammonia and diluted to 1 litre with water, or 2.5 percent<br />

magnesium silicofluoride solution and allowed to dry thoroughly before<br />

paint is applied.<br />

All metal surfaces shall be absolutely clean, dry and free from wax, grease or<br />

dried soap films. In addition, all steel and iron surfaces shall be free from rust,<br />

surfaces shall be cleaned by mechanical power tools to remove mill scales<br />

unless otherwise approved by the Engineer for exposed chemical resistant<br />

paints, surfaces shall be blast cleaned to near white metal. All galvanised iron<br />

surfaces shall be pretreated with a compatible primer according to the<br />

manufacturer's direction. Any abrasion in shop coat shall be touched up with<br />

the same quality of paint as the original coat.<br />

The method of application shall be as recommended by the manufacturer. In<br />

case of selection of special shades and colour (not available in standard<br />

shades) the Contractor shall mix different shades and prepare test panels of<br />

minimum size 1 meter square as per instruction of the Engineer and obtain his<br />

approval prior of application of finishing paints.<br />

Proper tools and implements shall be used. Scaffoldings if used shall be<br />

independent of the surface to be painted to avoid shade differences of the<br />

freshly repaired anchor holes.<br />

Painting shall be done by skilled labours in a workmanlike manner. All<br />

materials shall be evenly applied so as to be free of sags, runs, crawls or other<br />

defects. All coats shall be of proper consistency. In case of application by<br />

brush, no brush marks shall be visible. The brushes shall be clean and in good<br />

condition before application of paint.<br />

All priming undercoats for painting shall be applied by brush only, and rollers<br />

spray equipments etc. shall not be used.<br />

No work shall be done under conditions that are unsuitable for production of<br />

good results. No painting shall be done when plastering is in progress or is<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 4


DCPL-K4A02<br />

drying. Application of paint, which seals the surfaces to moisture, shall only be<br />

done after the moisture on and below the surface has dried out.<br />

All coats shall be thoroughly dry before succeeding coat is applied. Coats of<br />

painting as specified are intended to cover surfaces perfectly. In case the<br />

surface is not covered properly by applying the specified number of coats,<br />

further coats shall be applied by the Contractor when so desired by the<br />

Engineer.<br />

All primers and undercoats shall be tinted to approximate the colour of the<br />

finishing coats. Finished coats shall be of exact colour and shade as per<br />

approved samples and all finish shall be uniform in colour and texture. All parts<br />

of mouldings and ornaments shall be left clean and true to finish.<br />

Painting on ferrous metal surface shall be done as per IS:1477 (Part 1 & 2).<br />

The total dry thickness of the film should not be less than 120 micron.<br />

2.2.2 White Washing<br />

The surface where white washing is to be applied shall be cleared of all loose<br />

materials and dirt. All holes and irregularities of the surface shall be filled up<br />

with lime putty and shall be allowed to dry up before application of the lime<br />

solution.<br />

One coat of whitewash shall consist of one stroke from top downwards, another<br />

from bottom upwards over the first stroke and another from left to right before<br />

the previous one dries up. Second coat shall be applied and in case the<br />

Engineer feels that one or more coats are required. No brush marks shall show<br />

on the finished surface.<br />

2.2.3 Dry Distemper<br />

New plastered surface shall be allowed to dry for at least two months. New<br />

lime or lime cement plastered surface shall be washed with a solution of 1 part<br />

Vinegar to 12 parts water or 1:50 sulphuric acid solution and for 24 hours after<br />

which the wall shall be thoroughly washed with clean water. For cement<br />

plastered surface, the surface shall be washed with a solution of 100 gms. of<br />

zinc sulphate to 1 litre of water and then allowed to dry.<br />

Dry distempering shall be done as per manufacturer's instruction. In applying<br />

the distempers the brush should first be applied horizontally and immediately<br />

crossed off perpendicularly. Brushing shall not be continued too long as<br />

otherwise brush marks may result.<br />

2.2.4 Oil bound washable distemper<br />

The distemper shall be applied after surface is primed with an alkali resistant<br />

primer, and followed by minimum two coats of oil bound washable distemper all<br />

as per manufacturer's instruction.<br />

2.2.5 Waterproof Cement Paint<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 5


DCPL-K4A02<br />

Surface to be coated with cement paint shall be washed and brushed down.<br />

As soon as the moisture has disappeared, the surface shall be given one coat<br />

of paint. Care shall be taken so that the paint does not dry out too rapidly.<br />

After 4 to 6 hours, the water shall be sprinkled over the surface to assist curing<br />

and prevent cracking. After the first coat has dried (24 to 48 hours) the second<br />

coat shall be applied in a similar manner. The finished surface shall be kept<br />

moist by occasional sprinkling with water for seven days after painting.<br />

2.2.6 Acrylic Emulsion Paint<br />

Lime gauged cement plastered surfaces shall not be painted for at least one<br />

month after plastering. A sample patch shall be painted to check alkali reaction<br />

if so desired by the Engineer. Painting shall be strictly as per manufacturer's<br />

specification.<br />

2.2.7 Synthetic Enamel Paint<br />

Shall be applied on properly prime red surface. Subsequential coat shall not be<br />

applied till the previous coat is dry. The previous shall be lightly sand papered<br />

for better adhesion of subsequent coats.<br />

2.2.8 Aluminium Paint<br />

The paint, supplied in two pack containers shall be mixed and applied strictly as<br />

per manufacturer's direction. When more than one coat of paint is required or<br />

indicated, the next coat shall only be applied after the previous coat become<br />

hard dry.<br />

2.2.9 Clear Synthetic Varnish<br />

The Varnish shall be applied on wood surface after (a) filling, (b) staining & (c)<br />

sealing operations are carried out. The application of a combination of filler<br />

and stain shall not be permitted.<br />

For the finishing coats of varnish, the surface shall be allowed to dry and be<br />

rubbed down lightly, wiped off and allowed to dry. Careful attention to<br />

cleanliness is required for varnishing. All dust and dirt shall be removed from<br />

the surface as well as from the neighbourhood. Damp atmosphere and<br />

draughts shall be avoided, and exposure to extreme heat or cold & dampness<br />

shall not be allowed.<br />

The varnish shall be applied liberally with a brush and spread evenly over a<br />

portion of the surface with light strokes to avoid frothing. It shall be allowed to<br />

flow on while the next section is being laid on excess varnish shall then be<br />

scrapped off the brush and the first section be crossed, recrossed and then laid<br />

off lightly. The varnish once it has began to set, shall not be retouched. In<br />

case of any mistake in application, the varnish shall be removed and the work<br />

started afresh.<br />

The varnish shall be minimum of two coats, with the first coat being a flatting<br />

varnish. This shall be allowed to dry hard and be flatted down, before applying<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 6


2.2.10 French Polish<br />

DCPL-K4A02<br />

the next coat. Sufficient time must be allowed between coats to get a hard dry<br />

surface before next coat is applied. All work shall be as per relevant IS Code.<br />

All unevenness of the surface shall be rubbed down to smoothness with sand<br />

paper and the surface shall well dusted. The pores in the wood shall be filled<br />

up with a paste of whitening in water or methylated spirit with a suitable<br />

pigment like burnt siemma or umber.<br />

After application of the filler paste, the french polish shall be applied with a pad<br />

of woolen cloth covered by a fine cloth. The pad shall be moistened with polish<br />

and rubbed hard on the surface in a series of overlapping circles so that the<br />

polish is sparingly but uniformly applied over the entire area to give an even<br />

surface. A trace of linseed oil may be used on the pad for case of application.<br />

The surface shall be allowed to dry before further coats are applied in the same<br />

manner. To finish off, the pad shall be covered with a fresh piece of clean fine<br />

cloth, slightly damped with methylated spirit and rubbed lightly and quickly with<br />

circular motions to leave the finished surface with a uniform texture and high<br />

gloss.<br />

2.2.11 Chemical Resistant Paint<br />

For chemical resistant paints, epoxy, chlorinated rubber or vinyl butyl paint<br />

system shall be used manufacturer's recommendation regarding the paint<br />

system exposed to moderately severe corrosive condition and subject to<br />

acid/alkali spillage and fumes, shall be followed.<br />

2.2.12 Epoxy coating/painting<br />

On the clean surface of concrete after properly drying of the following system is<br />

to be adopted as per manufacturers specification :<br />

One coat of primer of following proportion to be applied over clean and dried<br />

concrete surface by brush application.<br />

ARALDITE GY 250 - 100 Parts by weight<br />

HARDENER HY 840 - 50 Parts by weight<br />

Over the primer, the uneven surface of concrete should be filled with leveling<br />

putty as mentioned above. The cost of putty is included in the item rate without<br />

fixing prior limit to consumption of putty. Two top coats of the protective<br />

treatment to be applied over the prepared smooth surface in the following<br />

proportion.<br />

ARALDITE GY 250<br />

HARDENER HY 830<br />

HARDENER BY 850<br />

- 100 Parts by weight<br />

- 45 Parts by weight<br />

- 15 Parts by weight<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 7


DCPL-K4A02<br />

SILICA FLOUR<br />

FLOW CONTROL<br />

AGENT<br />

- 20 Parts by weight<br />

- 2 Parts by weight<br />

2.3.0 Protection<br />

2.4.0 Cleaning up<br />

Pigment may be added if desired by Engineer. The first top coat is applied<br />

over the primer and is left to reach a tack free state. At this stage, the final top<br />

coat is applied.<br />

Furniture and other movable objects, equipments, fittings and accessories shall<br />

be moved, protected and replaced upon completion of work. All stationary<br />

equipments shall be well covered so that no paint can fall on them. Work<br />

finished by other agencies shall be well protected. All protections shall be done<br />

as per instructions of the Engineer.<br />

In addition to provisions in general conditions the Contractor shall, upon<br />

completion of painting etc. remove all marks and make good surfaces, where<br />

paint has been spilled, splashed or splattered, including all equipments,<br />

fixtures, glass, furniture, fittings etc. to the satisfaction of the Engineer.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

a) All painted surfaces shall be uniform and pleasing in appearance.<br />

b) All varnished surfaces shall be of uniform texture and high glossy finish.<br />

c) The colour, texture etc. shall match exactly with those of approved<br />

samples.<br />

d) All stains, splashes and splatters of paints and varnishes shall be<br />

removed from surrounding surfaces.<br />

4.0.0 I.S. CODE<br />

Important relevant IS Codes for this Sections are listed below :<br />

IS:348 : Specification for French Polish<br />

IS:427 : Specification for Distemper, dry colour as required.<br />

IS:428 : Specification for Distemper oil emulsion, colour as<br />

required.<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 8


DCPL-K4A02<br />

IS:1477 : Code of Practice for painting of ferrous (I&II)metal in<br />

buildings.<br />

IS:2338 : Code of Practice for finishing of wood (I&II)and wood<br />

based materials.<br />

IS:2339 : Specification for Aluminium Paints for general purposes<br />

in dual containers.<br />

IS:2395 : Code of Practice for painting concrete, masonry and<br />

plaster surface.<br />

IS:2932 : Specification for enamel, synthetic, exterior, type-I.<br />

IS:5410 : Specification for cement paint, colour as required.<br />

(PCA.775.S034sc18) V.II-D2/S-XVIII: 9


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROOF WATER PROOFING, INSULATION<br />

AND ALLIED WORKS<br />

(PCA.775.S034sc19)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XIX : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XIX : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XIX : 5<br />

4.0.0 I.S. CODES & STANDARDS V.II-D2/S-XIX : 5<br />

(PCA.775.S034sc19)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XIX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ROOF WATER PROOFING, INSULATION<br />

AND ALLIED WORKS<br />

1.0.0 SCOPE<br />

This specification covers furnishing, installation, repairing, finishing, curing,<br />

testing,, protection, maintenance till handing over of roof water-proofing,<br />

insulation and allied work for buildings and at locations covered under the<br />

scope of the Contract.<br />

2.0.0 INSTALLATION<br />

2.1.0 Grading Underbed<br />

The surface to receive the underbed shall be roughened and thoroughly<br />

cleaned with wire brush and water. Oil patches if any shall be removed with<br />

detergent. The surface shall be soaked with water and all excess water<br />

removed just before laying of the underbed.<br />

The underbed shall not be laid under direct hot sun and shall be kept in shade<br />

immediately after laying so as to avoid quick loss of water from the mix and<br />

separation from the roof surface. The underbed shall be cured under water for<br />

at least 7 days.<br />

The underbed shall be laid to provide an ultimate run off gradient not less than<br />

1 in 120 and as directed by the Engineer. Upto an average thickness of 25 mm<br />

the underbed shall usually be composed of cement and sand plaster. For<br />

higher thickness the underbed shall be made with cement concrete.<br />

The underbed shall be finished to receive the waterproofing treatment direct<br />

or insulation as the case may be.<br />

2.1.1 The grading plaster shall be average 25mm thick maximum. It shall consist<br />

of cement and coarse sand in the ratio 1:4 nominal by volume. The same<br />

and cement shall be throughly mixed dry and them water added. Each batch<br />

of mix shall be consumed before the initial set starts.<br />

The plaster shall be fully compacted to the desired grade in continuous<br />

operation. The surface shall be even and reasonably smooth.<br />

2.2.0 Concrete<br />

(PCA.775.S034sc19) V.II-D2/S-XIX : 1


DCPL-K4A02<br />

2.3.0 Insulation<br />

The concrete shall be used where the subgrade is more than average 25mm<br />

thick. It shall consist of cement concrete 1:2:4 nominal mix by volume with<br />

12mm down stone chips and coarse sand. The aggregate shall be mixed<br />

dry and minimum quantity of water shall be added to make the mix workable.<br />

The mix shall be laid to proper grade, fully consolidated and surface shall be<br />

smooth and even.<br />

The Tenderer shall along with the tender send specification of insulating<br />

materials he proposes to use and the proposed method of laying. Before<br />

bulk supply, the contractor shall send samples of insulating material to the<br />

Engineer, and after approval of the samples, the Contractor shall procure and<br />

transport the bulk material to the site. Whenever asked by the Engineer, the<br />

Contractor shall furnish test certificates from testing laboratory on the<br />

insulating and other properties of the materials.<br />

After laying the insulation the surface shall be made ready as required to<br />

receive the waterproofing treatment. If any plastering is used it shall be not<br />

leaner than 1:4 cement sand by volume and not thiner than 12mm and it shall<br />

be cured for seven days.<br />

2.3.1 Foam Concrete<br />

This shall be of light weight foam concrete of average 50 mm thickness or as<br />

specified or as shown on drawings. This may be laid in situ in suitable panels<br />

or in precast blocks. The insulating properties shall be such that the thermal<br />

conductivity shall not exceed 0.125 Kcl m/m degree C. The weight of the<br />

insulating material shall be from 0.3 to 0.5 gm/cm.<br />

Before starting the laying of foam concrete samples shall be prepared at site<br />

and got tested for approval of the Engineer.<br />

The foam concrete laid shall be sufficiently strong to make the usual work<br />

load and standard loads expected on the roof. Any damaged portion shall be<br />

removed and replaced forthwith. Approval of the Engineer shall be taken<br />

before laying the waterproofing over the insulation.<br />

While laying the foam concrete, samples from each batch of the mix shall be<br />

kept for test if so desired by the Engineer.<br />

2.3.2 Expanded Polystyrene Blocks<br />

The expanded polystyrene block insulation shall be fire retardant quality and<br />

shall have a maximum thermal conductivity of 0.026 KCl m/m degree C. It<br />

must be strong enough to withstand without deformation the workload and<br />

standard loads expected on the roof.<br />

The Contractor shall lay the expanded polystyrene block as per<br />

manufacturer’s approved specification. Only specifically experienced workers<br />

shall be used for this work. If the Engineer is not satisfied about the<br />

(PCA.775.S034sc19) V.II-D2/S-XIX : 2


2. 4.0 Fillets<br />

DCPL-K4A02<br />

efficiency of the workers the Contractor shall have to secure manufacturer’s<br />

supervision.<br />

Either of above items (cl. No. 2.03.01 or 2.03.02) can be adopted subject to<br />

approval of engineer.<br />

Fillets at junction of roofs and vertical walls shall be provided with the same<br />

insulating material as provided for the main roof insulation. The fillets shall<br />

be 150 mm x 150 mm in size unless otherwise shown on drawings or<br />

instructed by the Engineer.<br />

Where there is no insulation over roof slab, fillets shall be cast-in-situ cement<br />

concrete (1:2:4) nominal mix by volume.<br />

2.5.0 Water proofing by epoxy resin based application<br />

2.6.0 Flashing<br />

Exposed surfaces of cement concrete, lime concrete or brickwork to be<br />

treated for waterproofing by the resin based application shall be throughly<br />

cleaned and the epoxy resin based material to be applied as directed by the<br />

manufacturer. The material shall not have any adverse effect on the surface<br />

on which it is applied and must stick to it uniformly to make a strong durable<br />

bond. It shall not be affected by short duration from fire, sun, light traffic.<br />

The application shall be resistant to growth of fungus and proof against<br />

saltpetre action. If desired by the Engineer, a sample shall be prepared in<br />

advance and tested for waterproofness for 48 hours under 300 mm depth of<br />

standing water. The Contractor shall arrange the demonstration by providing<br />

free the materials and labours for the application.<br />

Unless otherwise stated flashing shall be done in the same way as the<br />

waterproofing except that the last layer, instead of being finished with peasized<br />

gravel, shall be finished with two coats of bituminous primer. The<br />

flashing shall be extended up the vertical surfaces as shown on drawing. The<br />

flashing shall end in grooves in vertical walls. The grooves shall be at least<br />

65 mm deep and caulked with waterproof mastic cement. The minimum<br />

overlap with horizontal roofing felt shall be 100 mm.<br />

Where specified on drawings or directed by the Engineer, metal flashing shall<br />

be provided. The metal flashing shall be done as shown on the drawings.<br />

The materials shall be 18g or 22g G.I. sheets, as specified on the drawings<br />

and/or as directed by the Engineer.<br />

2.7.0 Elastromeric Membrane<br />

2.7.1 Primer Coat<br />

(PCA.775.S034sc19) V.II-D2/S-XIX : 3


DCPL-K4A02<br />

It shall consist of polyurethane (P.U.) or any other equivalent material.<br />

Primer coat shall be a special blend of moisture curing urethane pre-polymers<br />

in solvent. A single coat of this primer shall be applied by brush /spray with<br />

airless spray equipment over the prepared bed as an adhesion coat with an<br />

application rate of 6-8 sq.m per litre depending on the surface porosity.<br />

The primer shall be allowed to dry for a minimum period of 2 to 4 hours time<br />

before the successive finishing coats of P.U. liquid membrane are applied. In<br />

any case successive finishing coat shall be applied within 24 hours.<br />

The substrate shall be properly prepared by removing all loose materials by<br />

vigourous brushings, fungal growth with proprietary fungitide as<br />

recommended. Priming coat shall not be applied to damp substrate.<br />

2.7.2 Finishing Coats<br />

2.7.3 Surface Finish<br />

The finishing coats shall consist of two successive liquid coatings of high<br />

solid content urethane pre-polymers material to form an elastomeric<br />

membrane. Application shall be with brush or spray to form an uniform<br />

jointless elastomeric membrane. The overall dry film thickness shall be 1.5<br />

mm subject to minimum 750 gm per sq.m per coat application rate.<br />

Each coat shall be allowed to dry for minimum 12 hours before applying the<br />

next coat. The surface should be dry and smooth before application.<br />

The coating shall be continued up the parapets/walls for minimum of 150 mm<br />

over the finished roof surface or fillet with suitable tucking into the vertical<br />

wall surface. It shall be continued into rain water pipes by atleast 100 mm.<br />

The final coat of PU liquid when tacky shall be sprinkled with the sand.<br />

For edges, expansion joints and any vulnerable points a layer of polyscrim<br />

cloth/fabric are to be embedded between 2 finishing coats.<br />

The entire work shall be carried out under the supervision of approved<br />

authorized agency.<br />

Areas of roof treatment shall be provided with wearing course consisting of<br />

minimum 25 mm thick PCC 1:11/2:3(using 12.5 mm size aggregate) cast in<br />

panel of maximum size of 1.20 m x 1.20 m and reinforced with 0.56 mm<br />

diameter galvanized chicken wire mesh and sealing of joints using sealant or<br />

elastomeric compound.<br />

When the roof surface is subjected to foot traffic or used as a working area, a<br />

cement mortar (1:4) shall be applied over the top most layer of roofing<br />

treatment. Over this, a layer of chequered cement concrete flooring tiles<br />

conforming to IS:13801 shall be provided. The tiles shall be laid as per IS<br />

1443.<br />

(PCA.775.S034sc19) V.II-D2/S-XIX : 4


DCPL-K4A02<br />

3.0.0 ACCEPTANCE CRITERIA<br />

The surface level shall be such as to allow quick draining of rains without<br />

leaving any pool anywhere. The finishing course shall be fully secured and<br />

shall have an even density. There shall not be any bubble formation or<br />

crushed or squeezed insulation or underbed.<br />

The Contractor shall give a guarantee in writing for all work executed under<br />

this specification supplemented by a separate and unilateral guarantee from<br />

the specified agency for the roof water-proofing treatment work. The<br />

guarantee shall be for materials and workmanship for a period of minimum<br />

10 years. The mode of execution of the guarantee shall be acceptable to the<br />

Owner.<br />

4.0.0 I.S. CODES AND STANDARDS<br />

a) IS:73 : Paving Bitumen<br />

b) IS:702 : Industrial Bitumen<br />

c) IS:1203 : Methods of testing tar and bitumen<br />

d) IS:1322 : Bitumen felts for waterproofing and damp proofing<br />

e) IS:1346 : Code of Practice for waterproofing of roofs with<br />

bitumen felts<br />

f) IS:3384 : Bitumen primer for use in waterproofing and damp<br />

proofing.<br />

(PCA.775.S034sc19) V.II-D2/S-XIX : 5


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

SHEETING WORK IN ROOF AND SIDING<br />

(PCA.775.S034sc20)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XX : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XX : 1<br />

3.0.0 ACCEPTANCE CRITERIA V.II-D2/S-XX : 2<br />

4.0.0 I.S. CODES V.II-D2/S-XX : 2<br />

(PCA.775.S034sc20)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XX<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

SHEETING WORK IN ROOF AND SIDING<br />

1.0.0 SCOPE<br />

This specification covers the erection of asbestos, C.G.I., aluminium or other<br />

sheet covering to roof and side walls at various elevations and the fabrication<br />

and/or installation of asbestos, C.G.I or aluminium gutters, flashings etc., as<br />

shown on drawings.<br />

2.0.0 INSTALLATION<br />

2.1.0 Storage of Materials<br />

2.2.0 Workmanship<br />

All materials shall be stored by the Contractor in proper way to prevent all<br />

damage. If the materials are issued at site by the Owner, the Contractor shall at<br />

the time of issue, satisfy himself about the condition of issued sheets, gutters,<br />

etc. and no complaints shall be entertained later.<br />

The workmanship shall be according to best construction practice to give a<br />

water tight finish to the satisfaction of the Engineer fixing of gutters and down<br />

pipes shall be according to IS:2527.<br />

2.2.1 Asbestos Sheeting<br />

Asbestos sheets of profiles as stated in the Schedule of Items, shall be fixed<br />

with minimum 150 mm end lap and side laps as per manufacturer's<br />

specification Hook bolts or J-bolts shall be 8 mm dia. at 305 centres 6 mm dia<br />

galvanised iron seam bolt and nut with G.I. flat washers and bitumen washers<br />

shall be used for stitching ridge capping, corner pieces, ventilators, north light<br />

curves etc.<br />

2.2.2 C.G.I. Sheeting and Aluminium Sheeting<br />

Side laps shall be 2 corrugations for roof and one corrugation for side sheeting.<br />

End laps shall be minimum 150 mm for roof and 100 mm for side sheeting. In<br />

ridges and hips where plain sheets are used the end laps shall be minimum<br />

100 mm. Holes in C.G.I sheets shall prefer.h1 Sheeting work in ably be made<br />

on the ground the sheets should be placed on trestles and holes punched in<br />

the ridge of the corrugation from the outside inward for obtaining proper seating<br />

of limpet washes. Sheets shall be secured to sheet framing by 8 mm dia.<br />

galvanised iron hooks or J-bolts and maximum 305 mm apart. The length of the<br />

(PCA.775.S034sc20) V.II-D2/S-XX : 1


DCPL-K4A02<br />

hook or J- bolts shall be to suit the sections of the bearers. Sheets shall also be<br />

bolted at the ends at every third corrugation with 6 mm dia. galvanised iron<br />

seam bolts and G.I. flat washers and bituminous washers.<br />

2.2.3 Firbre Glass Reinforced Plastic Sheeting<br />

This shall be of thickness and profile as mentioned in the drawing. Colour<br />

and light transmittance shall be as mentioned in drawings and or schedules.<br />

Where used in conjunction with C.G.I. or asbestos sheeting the end and side<br />

laps and fixing device shall be same as used for general sheeting. Where<br />

used in lieu of glass, the fixing shall be by means of timber or metal glazing<br />

beads as mentioned in drawing. In all cases, the installation shall be<br />

completely watertight and able to withstand the designed wind-pressure.<br />

3.0.0 ACCEPTANCE CRITERIA<br />

The installations shall present a neat appearance and shall be checked for<br />

water tightness. The following shall be checked :<br />

a) Side and end laps<br />

b) Absence of cracks, holes or damages in sheet<br />

c) Spacing of bolts<br />

d) Provision of double washers (G.I. and asbestos or bituminous washers)<br />

e) Proper installation of flashing<br />

4.0.0 IS CODES<br />

The following are some of the important IS Codes relevant to this sections :<br />

IS : 3007<br />

IS : 2527<br />

IS : 1626<br />

IS : 277<br />

: Code of practice for laying of asbestos cement sheets.<br />

: Code of practice for fixing rain water gutters and down pipes<br />

for roof drainage.<br />

: Specification for asbestos cement building pipes gutters and<br />

fittings.<br />

: Specification for galvanised steel sheets (plain and corrugated).<br />

(PCA.775.S034sc20) V.II-D2/S-XX : 2


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

WATER SUPPLY<br />

(PCA.775.S034sc21)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XXI : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XXI : 2<br />

3.0.0 TESTING AND ACCEPTANCE V.II-D2/S-XXI : 7<br />

4.0.0 I.S. CODES V.II-D2/S-XXI : 8<br />

(PCA.775.S034sc21)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXI<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

WATER SUPPLY<br />

1.0.0 SCOPE<br />

1.0.1 Materials<br />

This section includes supply of all materials, labour and incidentals for water<br />

supply for residential, business and industrial and other types of buildings.<br />

The water supply system of a building or premises covers service pipes and<br />

the necessary connecting pipes, fittings, control valves and all<br />

appurtenances in or adjacent to the building or premises.<br />

All materials, fittings, fixtures and appliances shall be of the best quality<br />

conforming to relevant Indian Standard and shall be procured from<br />

approved manufacturers. Unless specifically allowed by the Engineer, the<br />

Contractor shall submit samples of fittings and fixtures which will be<br />

retained by him for comparison when bulk supplies are received at the site.<br />

Ultimate choice of type, model and manufacturer lies completely with the<br />

Engineer.<br />

It shall be the responsibility of the Contractor to procure the materials<br />

selected by the Engineer. Hence order are to be placed with the<br />

manufacturers in time, so that the materials are available at the site well<br />

ahead of their requirement.<br />

The materials brought to the site, shall be stored in a separate secured<br />

enclosure away from the building materials. Pipe threads, sockets and<br />

similar items shall be specially protected till final installation. Brass and<br />

other expensive items shall be kept under lock and key. Fragile items shall<br />

be checked thoroughly when received at the site and items found damaged<br />

shall not be retained at the site.<br />

1.0.2 Pipes and Pipe Fittings<br />

Under scope of this specification, pipes and pipe fittings may be any or a<br />

combination of the following types :<br />

a) Cast Iron<br />

b) Steel : lined, coated with bituminous composition, out coated with<br />

cement concrete or mortar or galvanised.<br />

c) Reinforced Concrete<br />

d) Prestressed Concrete<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 1


DCPL-K4A02<br />

e) Lead (Not to be used for potable water)<br />

f) P. V. C.<br />

g) Copper<br />

h) Brass<br />

i) Wrought iron<br />

1.0.3 Water Reservoirs<br />

Water reservoirs like pressed steel tanks and G.I. tanks shall come under<br />

scope of this specification. Reservoirs made of concrete masonry or<br />

fabricated steel shall be covered by respective work specifications.<br />

1.0.4 Related Works<br />

1.0.5 Regulation<br />

All works, like earthwork, masonry, concrete, steelwork, cutting holes,<br />

chases, repairs and rectification associated directly with installation of water<br />

supply systems shall come under scope of the Contractor unless specifically<br />

excluded.<br />

The work which is required to be carried out under the scope of this section,<br />

shall be executed by a licensed plumber only (engaged by the Contractor)<br />

and he shall obtain all necessary sanctions, permissions, certificates etc.<br />

from Municipal and/or other Local Authorities and shall abide by all the<br />

rules of such Authorities.<br />

2.0.0 INSTALLATION<br />

While basic layouts may be available in the drawings provided by the<br />

Owner, the details might have to be supplemented by the Contractor for<br />

approval of the Engineer.<br />

Special attention shall be given by the Contractor to economy. Symmetry<br />

of layout is very important. Fittings meant for operation shall be located and<br />

oriented to allow easy reach and operation. Maintenance, repairs and<br />

replacements of pipes, fittings and fixtures must be conveniently possible.<br />

2.1.0 Pipe Lines<br />

2.1.1 Laying<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 2


DCPL-K4A02<br />

2.1.2 Back Flow<br />

In addition to fulfilling the functional requirements all pipelines shall be laid<br />

true to line, plumb and level. Any deviation shall need approval of the<br />

Engineer. Meticulous care shall be taken to avoid chances of airlock and<br />

water hammer.<br />

Pipes shall be laid on continuous unyielding surface or on reliable supports<br />

at least one near each joint and spacings as directed by the Engineer. The<br />

support must be strong, neat and shall have provisions for securing the<br />

pipes in every direction and easy maintenance. Pipes shall be encased or<br />

concealed in masonry or concrete if shown on drawing or directed by the<br />

Engineer.<br />

The layout of pipe work shall be such that there is no possibility of back<br />

flow towards the source of supply from any cistern or appliances, whether<br />

by siphonage or otherwise. All pipe works shall be so laid or fixed and<br />

maintained as to be and to remain completely water-tight, thereby avoiding<br />

waste of water, damage of property and the risk of contamination of the<br />

water conveyed.<br />

2.1.3 Contamination<br />

There shall be no cross connection whatsoever between a pipe or fitting for<br />

conveying or containing wholesome water and a pipe or fitting for containing<br />

impure water or water liable to contamination or of uncertain quality of water<br />

which has been used for any purpose.<br />

No piping shall be laid or fixed so as to pass into or through any sewer,<br />

scour outlet or drain or any manhole connected therewith.<br />

2.1.4 Underground Pipings<br />

Underground piping shall be laid at such a depth that it is not likely to be<br />

damaged by traffic and other loads and frost, where applicable.<br />

The size and depth of the trench shall be as approved by the Engineer.<br />

Back-filling shall be done with selected fine earth, unless otherwise<br />

permitted in 150 mm layers and carefully consolidated. Special care shall<br />

be taken while filling in the vicinity of the pipe to avoid damage. Before<br />

backfilling the laid pipe shall be fully tested and approved.<br />

Where the pipe rests on rock it may be bedded on a layer of fine selected<br />

material or concrete to avoid local point support.<br />

The trench shall be so treated by gradient and filling in the area that it does<br />

not act as a drainage channel.<br />

2.1.5 Concealed Piping<br />

Where desired by the Engineer or shown on the drawings the pipes shall be<br />

concealed in masonry or concrete of the structure. The Contractor may co-<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 3


DCPL-K4A02<br />

ordinate with the building Contractor for leaving the chases, openings,<br />

conduits as necessary. However, the Contractor will rectify if required the<br />

chases, openings and conduits, supplement and make good after laying<br />

and testing of the concealed pipelines.<br />

2.1.6 Jointing of Pipes<br />

Jointing of pipes shall be completely leakproof and durable. Instruction of<br />

the manufacturer shall be followed unless desired otherwise by the<br />

Engineer. However, usually recommended practices are stated below for<br />

guidance :<br />

a) Cast Iron<br />

i) Spigot and Socket Joints<br />

Lead joint : The joint is made by first caulking in clean spun<br />

yarn upto half depth and filling the reminder by running in<br />

molten lead taking care that no dross enters the joint and<br />

then thoroughly caulking the lead. The lead need not extend<br />

into the joint further than the back of the groove formed in the<br />

socket. After completing the joint it shall not be allowed to<br />

move. For rectification the joint shall be completely redone.<br />

ii)<br />

Flanged Joints : Flanged joints shall be made by jointing<br />

rings of good quality, smooth and hard compressed fibre<br />

board of thickness not less than 1.5 mm and of such width as<br />

to fit inside the circle of bolt. Diagonally opposite bolts shall<br />

be tightened in pairs and in stages so that degree of all bolts<br />

in a joint are similar. Damaged gaskets shall be replaced.<br />

b) Steel<br />

Plain ended steel pipes may be jointed by welding. Screwed and<br />

socketed joints shall be carefully tightened. Care shall be taken to<br />

remove any burr from the ends of the pipes. Jointing compound, if<br />

used, shall be lead free and approved by the Engineer. Once a<br />

joint has been screwed up it shall not be backed off unless threads<br />

are recleaned and new compound applied.<br />

c) GI Pipes<br />

Threads shall be cut with sharp tools, and before jointing all scales<br />

shall be removed from pipes by suitable means. The screw / threads<br />

of the pipe shall be cleaned out and the joint made by screwing the<br />

fittings after treating the threads with approved pipe jointing<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 4


DCPL-K4A02<br />

d) Lead<br />

2.1.7 Painting<br />

compound. Once a joint has been screwed up it shall not be backed<br />

off unless threads are recleaned and new compound applied.<br />

Lead and lead alloy pipes shall be jointed with wiped solder joints.<br />

e) Concrete<br />

Concrete pipes may be socket and spigot ended collar or band<br />

jointed. Joints shall be effected by caulking with 1:3 cement sand<br />

mortar.<br />

f) P. V. C.<br />

Manufacturer’s instruction shall be followed. For heating approved<br />

equipment with adequate control shall be used.<br />

g) Tyton Joint<br />

The manufacturer’s instruction shall be strictly followed in making<br />

such joints. Tyton joints shall be made by push-on type specification<br />

stipulated by the pipe manufacturer. The tools specified by the pipe<br />

manufacturer shall be used to secure the joint fully.<br />

Where mentioned in the Schedule, underground steel and cast iron pipes shall be<br />

given 2 coats of bituminous paint on the outside after laying, when painting is to be<br />

done above ground G.I. pipes shall be given a coat of zinc chromate primer, C.I. and<br />

M.S. pipes shall be given one coat of red lead or zinc chromate primer. Top coats<br />

shall be minimum 2 coats of best quality paint.<br />

2.2.0 Storage Tank - Pressed Steel Tank<br />

Unless otherwise mentioned, water storage tanks shall be pressed steel tanks of<br />

nominal size and capacity as mentioned in the Schedule and fabricated with all<br />

flanges external, all flanges internal, or bottom flange internal and side flanges<br />

external, as shown on drawings or schedule of items. The fabricator shall supply 6<br />

prints of fabrication drawings to the Engineer for prior approval showing thickness of<br />

plates, method of jointing the plates, all supports, stays, gussets etc. Pads, cleats<br />

etc. required for supporting the tanks shall be supplied by the manufacturer. Inlet,<br />

overflow vent pipes, manholes etc. shall be arranged and provided as shown on<br />

drawing or mentioned in the schedule. Unless otherwise specified, the outlet pipe<br />

shall be 50 mm above the bottom of the tank and there shall be a 150 mm free<br />

board at the top of the tank.<br />

All tanks shall be supplied with mosquito-proof covered top with manhole<br />

not less than 450 mm diameter. Tanks deeper than 1.00 Metre shall be<br />

provided with m.s. internal access ladder adjacent to the manhole. Water<br />

level indicator shall be provided if asked for. Two coats of anti-corrosive<br />

paint over a suitable primer shall be applied to both internal and external<br />

surface of tanks. Such paint if used shall not impart any taste or odour to<br />

water and be of lead free composition..<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 5


DCPL-K4A02<br />

Erection of tanks shall be in accordance with detailed drawings and<br />

manufacturer’s instructions. The two finishing coats of paint shall be<br />

applied to outside after erecting is complete.<br />

2.2.1 G. I. Water Tank<br />

G. I. water tanks shall be procured from a reputed manufacturer. The<br />

design shall be good enough to withstand the loads safely. Galvanised iron<br />

water storage tank shall be made of minimum 2 mm thick galvanised iron<br />

sheet. Plain sheets shall be fixed at the corner to angle iron frames by<br />

means 6 mm rivets at 40 mm pitch for tanks upto 1000 litres capacity and 8<br />

mm rivets at 35 mm pitch for tanks above 1000 litres capacity. Tanks<br />

above 1000 litres shall have 20 mm dia. galvanised / iron stay rods, one<br />

fixed to angle framing at top and two in the body of the tank for extra<br />

strength. Holes for rivetting shall be drilled and not punched. White lead<br />

shall be applied to the joints before rivetting.<br />

In case it is desired by the Engineer that corners of tank should be welded<br />

instead of rivetted then the sheets shall be welded to form a tank will not<br />

have angle iron frame.<br />

Tanks shall have 400 mm dia. holes at the top with hinged covers. The<br />

covers shall be made of galvanised iron sheet with angle iron frame. The<br />

cover shall be just loose but close fitting to keep out dust and mosquito and<br />

will not be airtight. It shall be complete with lockable arrangement.<br />

Tanks shall be provided with rising main inlets of 40 mm dia. galvanised iron<br />

pipe or as shown on Drawing and 25 mm dia. G.I. overflow pipe. The<br />

rising main shall be connected to the tank with a ball valve near the top<br />

which disconnects the supply when tank is full up to the point of overflowing.<br />

The ball valve permits the entry of water when the tank is empty and disconnects the<br />

supply when the tank is full. It consists of a hollow floating ball made of copper,<br />

plastic or hand Tubber, 110 mm in diameter, attached to an arm which is so pivoted<br />

that the end near the pivot closes the orifice of the main when the ball is raised to<br />

the required height of water in the tank and opens the main as soon as the ball<br />

drops with the fall of water level as it is drawn off through the distribution pipes. The<br />

ball valve shall be fixed to the tank independent of the inlet pipe and set in such a<br />

position that the body of the ball valve cannot submerge when the tank is full upto<br />

the water line. The ball valve shall be so adjusted as to limit the level of the water<br />

line. The level of the water in the tank to 75 mm below the lip of the overflow pipe.<br />

Free surface shall be about 150 mm above the maximum water filled level.<br />

2.3.0 Valve, Cocks, Taps<br />

2.4.0 Protection<br />

All valves, stop cocks, taps etc. shall conform to relevant Indian Standard<br />

Specification and shall be of best quality from approved manufacturers.<br />

These shall be suitable for working pressures mentioned in the Schedule.<br />

Nominal size and material shall be as per schedule.<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 6


DCPL-K4A02<br />

Open end of each pipe shall be protected during installation by suitable<br />

covers or plugs so that the ends, threads, sockets or spigot are not<br />

damaged and no foreign material can find its way into the pipe line.<br />

Fittings and fixtures liable to be misused or stolen during the construction<br />

phase shall be fitted only before testing and handing over.<br />

3.0.0 TESTING AND ACCEPTANCE<br />

3.1.0 Inspection Before Installation<br />

All pipes, fittings and appliance shall be inspected, before delivery at the<br />

site to see whether they conform to accepted standards. The pipes and<br />

fittings shall be inspected on site before laying and shall be sounded to<br />

disclose cracks. Any defective items shall be clearly marked as rejected<br />

and forthwith removed from the site.<br />

3.2.0 Testing of Mains After Laying<br />

After laying and jointing, the main shall be slowly and carefully charged with water,<br />

so that all air is expelled from the main by providing a 25 mm inlet with a stop cock,<br />

allowed to stand full of water for a few days if time permits, and then tested under<br />

pressure. The test pressure shall be 5 Kg/CM 2 or double the maximum working<br />

pressure, whichever is greater. The pressure shall be applied by means of a<br />

manually operated test pump, or in the case of long mains or mains of a large<br />

diameter, by a power driven test pump, provided that the pump is not left<br />

unattached. In either case due precaution shall be taken to ensure that the required<br />

test pressure is not exceeded. Pressure gauges shall be accurate and shall<br />

preferably have been recalibrated before the test. The pump having been stopped,<br />

the test pressure shall maintain itself without measurable less for at least five<br />

minutes. The end of the main shall be closed by fitting a water-tight expanding plug<br />

and the plug shall be secured by struts to resist the end thrust of the water pressure<br />

in the mains.<br />

3.3.0 Testing of Service Pipes and Fittings<br />

The service pipes shall be slowly and carefully charged with water allowing all air to<br />

escape avoiding all shock or water hammer. The service pipe shall then be<br />

inspected under working conditions of pressure and flow. When all draw-off taps<br />

are closed, the service pipes shall be absolutely water-tight. All pipings, fittings and<br />

appliances shall be checked for satisfactory support and protection from damage,<br />

corrosion and frost.<br />

4.0.0 I.S. CODES<br />

Important relevant IS Codes for this Specification are listed below :<br />

Latest editions shall always be consulted.<br />

IS:2065 : Code for Practice for water supply in buildings<br />

IS:1172 : Code of basic requirements for water supply, drainage<br />

and sanitation<br />

IS:1200<br />

(Pt. XVI)<br />

: Laying of water and sewer lines including appcurtnant<br />

items.<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 7


DCPL-K4A02<br />

IS:1239<br />

(Pt. I & II)<br />

: Specification for Mild Steel Tubes and Mild Steel Tubulars<br />

and other wrought steel pipe fittings (10 mm to 15 mm<br />

nominal diameter)<br />

IS:1536 : Specification for Centrifugally cast (Spun) iron pressure<br />

pipes for water gas and sewage<br />

IS:1537 : Specification for vertically cast iron pressure pipes for<br />

water, gas and sewage.<br />

IS:3486 : Specification for Cast iron spigot and socket drain pipes<br />

(80 mm to 250 nominal diameter)<br />

IS:3589 : Specification for Electrically welded steel pipe for water,<br />

gas and sewage (200 mm to 2000 mm nominal diameter)<br />

IS:784 : Prestressed concrete pipes<br />

IS:458 : Concrete pipes (with or without reinforcement)<br />

IS:783 : Code of Practice for laying of concrete pipes<br />

IS:1592 : Asbestos cement pressure pipes<br />

IS:1626 : Asbestos cement pressure pipes, gutters and fittings<br />

(Spigot and Socket types)<br />

IS:404 : Lead pipes<br />

IS:3076 : Low density polyethylene pipes for potable water supplies<br />

IS:4984 : High density polyethylene pipes for potable water supplies<br />

IS:2501 : Copper tubes for general engineering purposes<br />

IS:407 : Brass tubes for general purposes<br />

IS:1230 : Cast iron rain water pipes and fittings<br />

IS:804 : Rectangular pressed steel tanks<br />

(PCA.775.S034sc21) V.II-D2/S-XXI : 8


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

DRAINAGE AND SANITATION<br />

(PCA.775.S034sc22)


DCPL-K4A02<br />

CONTENT<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D2/S-XXII : 1<br />

2.0.0 INSTALLATION V.II-D2/S-XXII : 1<br />

3.0.0 TESTING AND ACCEPTANCE V.II-D2/S-XXII : 9<br />

4.0.0 CODES AND STANDARDS V.II-D2/S-XXII : 11<br />

(PCA.775.S034sc22)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

DRAINAGE AND SANITATION<br />

1.0.0 SCOPE<br />

1.1.0 This section covers the layout and construction of drains for roof water, surface<br />

water and sewage together with all fittings and fixtures and inclusive of ancillary<br />

works, such as connections, manholes and inspection chambers used within the<br />

building and from the building to the connection to a public sewer or to treatment<br />

work, septic tank and soak pit dispersion trenches.<br />

2.0.0 INSTALLATION<br />

2.0.1 General<br />

All pipe lines, locations of fittings and fixtures, etc. shall be as per drawings or as<br />

directed by the Engineer. Correctness of lines, plumb, orientation, symmetry and<br />

levels shall be strictly ensured. All items shall be fully secured against movement in<br />

any direction and so located as to allow easy maintenance.<br />

All pipe lines, fittings and fixtures shall be installed leakproof. When the works under<br />

scope of this specification linked up with works executed by others, the<br />

connections shall be such as to prevent any splashing or spilling or emission of<br />

foul odour and gases.<br />

2.1.0 Rainwater Downcomers<br />

2.2.0 Gutters<br />

Rainwater downcomers shall be standard Cast Iron Pipes. In case where<br />

specifically desired, M.S. pipes may also be used. M.S. pipes shall be painted<br />

outside with two coats of anticorrosive paints under a coat of primer.<br />

Rainwater downcomers shall run along and be secured to walls, columns etc. where<br />

desired by the Engineer these may have to be installed in chases cut in the structure.<br />

All pipes shall be well secured and supported by adequately strong brackets.<br />

The brackets may be wrought iron clevis type, split ring type or perforated strap<br />

iron type as approved by the Engineer. For vertical runs each pipe shall hang<br />

freely on its brackets fixed just below the socket. Suitable spacer blocks shall be<br />

provided against the vertical surface to which the pipe is fixed.<br />

All bends and junctions shall be supplied with watertight cleanouts.<br />

Roof and floor drains and yard gullies shall be installed, if required, by cutting<br />

into the structure and grouted with 1:2:4 cement concrete. All gutters shall be<br />

provided with removable gratings.<br />

All horizontal pipes shall have a minimum fall of 1 in 100.<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 1


DCPL-K4A02<br />

The gutters shall be made of G.I. All gutters shall be supplied by reputable<br />

specialised firms. Each section shall be sufficiently rigid, edges and<br />

corners straight and the slopes perfectly uniform. G.I. gutters shall have the<br />

edges strengthened by suitable means.<br />

Unless noted otherwise the gutters shall have a minimum fall of 1 in 120.<br />

Adequate number of string supports shall be provided so that there is no<br />

reflection even when the gutter is full. Each joint must have a support.<br />

Unless otherwise specified the supports shall be fabricated M.S. brackets.<br />

All junctions shall be thoroughly watertight. The joints may be made by<br />

rivetting, bolting or soldering. All joints between successive lengths of<br />

gutters shall have on overlap of at least 5 cm. The drop in the overlap shall<br />

always be in the direction of the fall of the gutter. Ends of gutters shall<br />

be closed watertight. Junction with rainwater down comers shall be made<br />

fully watertight and secured.<br />

2.3.0 Soil and Drainage Pipes<br />

2.3.1 Gradients<br />

If not specified the minimum gradients of soil and drainage pipe line shall<br />

be as follows :<br />

100 mm nominal dia : 1 in 35<br />

150 mm nominal dia : 1 in 65<br />

230 mm nominal dia : 1 in 120<br />

300 mm nominal dia : 1 in 200<br />

2.3.2 Relation with water supply pipe lines<br />

2.3.3 Laying<br />

Unless specifically cleared by the Engineer, under no circumstances shall<br />

special drainage and soil pipes be allowed to come close to water supply<br />

pipelines.<br />

Each separate pipe shall be individually set for line and for level. Where<br />

lengths of sewer or drain pipes are laid in trench, properly painted sight<br />

rails shall be fixed across the trench at a height, equal to length of the<br />

boning rod to be used, above the required invert level of the drain or sewer<br />

at the point where the sight is fixed. More sight rails shall be required at<br />

manholes, change of gradient and intermediate positions if the distance for<br />

sighting is more than 50 ft. apart. The excavation shall be boned in at least<br />

once in every 6 ft. The foot of the boning rod shall be set on a block of<br />

wood of the exact, thickness of the wall of the pipe. Each pipe shall be<br />

separately and accurately boned between sight rails.<br />

2.3.4 Support and Protection on Pipelines<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 2


DCPL-K4A02<br />

All pipes shall be laid with sockets leading uphill. Preferably the pipe shall<br />

rest on solid and even foundations for the full length of the barrel. However,<br />

the pipe manufacturer's instruction as approved by the Engineer shall be<br />

followed in the matter of support and jointing.<br />

To achieve full and continuous support, concrete for bedding and packing<br />

is the best. Where pipes are not bedded on concrete, the floor shall be<br />

left slightly high and carefully placed so that the pipe barrels rest on<br />

undisturbed ground. If anywhere the excavation has been carried too low<br />

packing shall be done in concrete. Where laid on rock or very hard ground<br />

which cannot be easily excavated to a smooth surface, the pipes shall be<br />

laid on a cradle of fine concrete floor of gravel and crushed stone over<br />

laid with concrete or on a well consolidated gravel and crushed stone bed as<br />

desired by the Engineer. PVC or similar pipes shall be laid directly on<br />

stable soil and packed with selected soil.<br />

The minimum support and protection for glazed stoneware pipes shall be as<br />

follows :<br />

a) When cover is less than 2 metre below ground level and where<br />

pipes are unavoidably exposed above ground surface, the pipes<br />

shall be completely encased or surrounded with concrete.<br />

b) Where pipes are laid on soft soil with the maximum water table<br />

laying at the invert of the pipe, the sewer shall be bedded on<br />

concrete.<br />

c) Where the pipes have to be laid on soft soil with the maximum water<br />

table rising above the invert of the pipe, but below the top of the<br />

barrel, the pipe sewer shall be haunched.<br />

d) Where maximum water table is likely to rise above the top of the<br />

barrel or wherever the pipe is laid on soft soil the pipe sewers shall<br />

be completely encased or surrounded with concrete.<br />

Cast iron pipes and concrete pipes may be supported on suitable<br />

concrete or brick support, where specified. The supports shall be<br />

unyielding and strong enough. At least one support shall be located<br />

close to ends. Spacing of intermediate supports shall be as decided<br />

by the Engineer. Pipes shall be secured to the supports by approved<br />

means.<br />

Anchoring of pipes where necessary shall be achieved by suitable<br />

concrete encasing designed for the expected thrust.<br />

2.3.5 Entry into structures<br />

For entry of the pipe lines into any building of structure suitable conduits<br />

under the structure or sleeves shall be used. The conduits and sleeves shall<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 3


2.3.6 Ducts<br />

DCPL-K4A02<br />

be such as to allow easy repairs and replacement of the pipes. When<br />

openings or chases are required to be made in the structure for entry of pipe<br />

lines, locations and sizes shall be marked and checked by the Engineer.<br />

After laying of the pipeline the openings and chases shall be mended.<br />

Where solid, waste and ventilating pipes are accommodated in ducts,<br />

access to cleaning areas shall be provided. Connection to drain shall be<br />

through a gully with sealed cover to guard against ingress of sewer gas,<br />

vermin or backflow.<br />

2.3.7 Traps and Ventilating Pipes<br />

Pipes are carrying off the waste from water closets and waste water and<br />

overflow water from baths, wash basins, sinks to drains shall be trapped<br />

immediately beneath such fixtures. Traps shall have minimum water seal of<br />

50 mm and shall be ventilated whenever such ventilation is necessary to<br />

maintain water seal of the trap.<br />

Ventilating pipes shall be carried up vertically from the drain to a height of<br />

at least 600 mm above the outer covering of the roof of the building or as<br />

shown on drawings. All vertical ventilating, anti-syphonage and similar pipe<br />

shall be covered on top with a cowl. The cowl shall be made of C.I. unless<br />

desired otherwise by the Engineer.<br />

2.3.8 Manhole and Inspection Chambers<br />

The maximum distance between manholes shall be 30 meter unless<br />

specially permitted otherwise. In addition, at every change of alignment<br />

gradient or diameter there shall be a manhole or inspection chamber. The<br />

distance between manhole or inspection chamber and gully chamber shall<br />

not exceed 6 metres unless desired otherwise.<br />

Manhole shall be constructed so as to be watertight under test. The bending<br />

at the sides shall be carried out in such a manner as to provide no<br />

lodgement for any splashings in case of accidental flashing of the chamber.<br />

The channel or drain at the bottom of chamber shall be plastered with 1:2<br />

cement, sand mortar and finished smooth to the grade. The channels and<br />

drains shall be shaped and laid to provide smooth flow.<br />

Connecting to existing sewer lines shall be through a manhole.<br />

Manholes shall be provided with standard C.I. covers. The covers shall<br />

be close fittings so as to prevent gases from coming out. Suitable heavy<br />

duty covers shall be used where necessary as decided by the Engineer.<br />

2.3.9 Cutting of Pipes<br />

Manufacturer's instructions shall be followed for cutting of pipes where<br />

necessary. Suitable and approved tools shall be used for the cutting so as<br />

to leave surface clean and square to the axis of the pipe.<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 4


DCPL-K4A02<br />

2.3.10 Jointing<br />

Jointing of laid pipes shall be so planned as to avoid completely any<br />

movement or strain to the joints already made. If any joint is suspected to be<br />

damaged it shall be opened out and redone.<br />

All joints between pipes, pipes and fittings and manholes shall be gas-tight<br />

when above ground and water-tight when underground. Method of jointing<br />

shall be as per instructions of the pipe and fittings manufacturer and as<br />

approved by the Engineer. However, in the absence of any instruction<br />

available from the manufacturer the methods as detailed hereunder shall be<br />

used.<br />

a) Cast Iron Pipes<br />

Socket and spigot pipes shall be jointed by the cast lead joints. The<br />

spigot shall be centered in the socket of the next pipe by tightly<br />

caulking in sufficient turns of tarred gasket or hemp yarn to have<br />

unfilled half the depth of socket. When the gasket or hemp yarn<br />

has been caulked tightly a jointing shall be placed round the barrel<br />

and tightened against the face of the socket to prevent airlock.<br />

Molten lead shall then be poured in to fill the remainder of the socket<br />

and caulked with suitable tools right round the joint to make up for<br />

shrinkage of the molten metal on cooling and shall be finished 3 mm<br />

behind the socket face.<br />

Joints in cast iron pipes with special jointing arrangements like 'Tyton'<br />

joints etc. shall follow the instructions of the manufactures.<br />

In special cases if flanged joints are accepted by the Engineer the<br />

joints shall be made leakproof by inserting approved type of rubber<br />

gaskets. The bolts shall be secured in stages to avoid uneven strain.<br />

b) Concrete Pipes<br />

Care shall be taken to place the collar centrally over the joint.<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 5


DCPL-K4A02<br />

2.4.0 Trenches and other excavations<br />

2.5.0 Fixtures<br />

Width of the trench at the bottom shall be such as to provide 200 mm<br />

clearance on either side of the pipe for facility of laying and jointing.<br />

Excavated material shall be stacked sufficiently away from the edge of the<br />

trench and the side of the spoil bank shall not be allowed to endanger the<br />

stability of the excavation. Spoil may be carted away and used for filling the<br />

trench behind the work.<br />

Turf, top soil or other surface material shall be set aside, turf being carefully<br />

rolled and stacked for use in reinstatement.<br />

All excavation shall be properly timbered, where necessary.<br />

Efficient arrangements for dewatering during excavation and keeping it dry<br />

till backfilling shall be made to the satisfaction of the Engineer. Sumps for<br />

dewatering shall be located away from the pipe layout.<br />

Where the excavation proceeds through roads necessary permissions shall<br />

be secured by the Contractors from the appropriate authorities.<br />

Special care shall be taken not to damage underground services, cables<br />

etc. These when exposed shall be kept adequately supported till the trench<br />

is backfilled.<br />

The backfilling shall be done only after the pipeline has been tested and<br />

approved by the Engineer. Special care shall be taken under and sides of<br />

the pipe during handpacking with selected material. At least 300 mm over<br />

the pipe shall also be filled with soft earth or sand. Consolidation shall be<br />

done in 150 mm layers. The surface water shall be prevented from getting<br />

into the filled up trench. Traffic shall not be inconvenienced by heaping up<br />

unduly the backfilling material to compensate future settlement. All future<br />

settlements shall be made good regularly to minimise inconvenience of traffic<br />

where applicable.<br />

The Tenderer shall mention in his bid the type and make of the fixtures he<br />

intends to use enclosing manufacturer's current catalogues. In the absence<br />

of any such agreement, the Engineer shall be at liberty to choose any type<br />

and make.<br />

All fixtures and fittings shall be of approved quality and type manufactured by<br />

well known manufacturers. All items brought to the site must bear<br />

identification marks of the type of the manufacturer. Procurements shall<br />

be made well in advance and inspected and approved immediately by the<br />

Engineer. All fixtures shall be adequately protected, covered and plugged<br />

till handed over.<br />

All fittings, gratings, fasteners, unless specified otherwise, shall be chromium<br />

plated. The connecting lead pipes and bends shall weigh at least 3 kg. per<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 6


2.5.1 Water closet<br />

2.5.2 Urinals<br />

DCPL-K4A02<br />

25 mm dia per meter length. Where PVC or similar pipes are allowed the<br />

Contractor shall produce the test reports and convince the Engineer about<br />

their durability.<br />

Unless specified in the contract the fixtures shall be as specified hereinafter.<br />

a) Raised type<br />

It shall include glazed vitreous china basin with siphon, open front<br />

solid plastic seat and plastic cover, low level glazed stoneware<br />

flushing cistern with valveless fittings, supply connections and<br />

necessary fittings. All fittings shall be chromium plated. Colour of<br />

basin, cistern, seat and cover shall be as desired by the Engineer.<br />

b) Squatting type<br />

2.5.3 Wash basin<br />

2.5.4 Sink<br />

It shall include glazed vitreous china pan with foot rests and high<br />

level cast iron flushing cistern with valveless fittings, supply<br />

connections and necessary fittings. All fittings shall be chromium<br />

plated. The foot rests shall be made of white glazed vitreous china<br />

with chequered surface. The flushing cistern shall be painted as<br />

desired by the Engineer.<br />

It shall consist of wall type glazed vitreous china urinals, cast iron automatic<br />

flushing cistern complete with supply connections, flush pipe, lead<br />

pipes, gratings, traps and all other necessary fittings. Automatic flushing<br />

shall be approximately once every five minutes. For a number of urinals<br />

located together may be served by one cistern of adequate capacity. All<br />

fittings shall be chrome plated. In Technical Building automatic flushing<br />

cistern based on photo electric effect should be installed.<br />

It shall be made of glazed vitreous china. The basin shall be flat back, wall<br />

hung by painted cast iron brackets and complete with pattern with hot and<br />

cold brass faucets with nylon washers, waste chain, waste washers, lead<br />

waste pipes with traps, perforated waste complete with necessary fittings.<br />

All fittings including faucets shall be chromium plated.<br />

It shall be made of Marble or Granite . It shall be wall hung by painted cast<br />

iron brackets and complete with one brass faucet with nylon washers,<br />

waste chain, waste washers, lead waste pipes with traps, perforated waste<br />

with necessary fittings. All fittings including faucets shall be chromium<br />

plated.<br />

2.5.5 Bathroom mirror<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 7


2.5.6 Glass shelves<br />

2.5.7 Towel rail<br />

2.5.8 Soap holder<br />

DCPL-K4A02<br />

It shall be made of the best quality 6 mm thick glass and produced by a reputed<br />

mirror manufacturer. It shall be wall mounted with adjustable revolving brackets. The<br />

brackets, screws and other fittings shall be chromium plated.<br />

Glass shelves shall consist of 6 mm thick clear glass with guard rails and shall<br />

be wall mounted with brackets. All brackets, guard rails and screws shall be<br />

chromium plated.<br />

Towel rails shall be 20 mm dia chromium plated MS pipes wall mounted with steel<br />

brackets. The brackets, screws etc. shall also be chromium plated.<br />

It shall be made of chromium plated strong members. The holders shall be wall<br />

mounted with chromium plated screws.<br />

2.5.9 Liquid soap dispenser<br />

It shall be round and easily revolving with removable threaded nozzle. The body,<br />

bracket for wall mounting and screws shall be chromium plated.<br />

2.5.10 Toilet roll holder<br />

It shall be made of glazed vitreous china with suitable cover cum cutter.<br />

mounting screws shall be chromium plated.<br />

Wall<br />

2.5.11 Installation<br />

All plumbing fittings and fixtures shall be installed in most workmanlike manner by<br />

skilled workers. These shall be perfect in level, plumb, plane, location and<br />

symmetry. All items shall be securely anchored to walls and floors. All cuttings in<br />

walls and floors shall be made good by the Contractor.<br />

2.6.0 Septic tank & effluent disposal<br />

2.6.1 Septic tank<br />

Septic tank shall consist of the tank itself with inlet and outlets therefrom complete<br />

with all necessary earthwork and backfilling. The details of septic tank shall be as<br />

shown on drawings. This item shall also include ventilating pipe of at least 100 mm<br />

dia whose top shall be provided with a suitable mosquito proof wiremesh and<br />

cowl. Ventilating pipe shall extend to a height of about 2 meter when the septic tank is<br />

at least 15 meter away from the nearest building and to a height of 2 meter above<br />

the top of building when it is located closer than 15 meter. Ventilating pipes can be<br />

connected to the normal soil ventilating system of the building where allowed.<br />

2.6.2 Effluent Disposal<br />

The effluent from the septic tank shall be disposed by allowing it into an<br />

open channel or a body of water if the concerned authority approves or into<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 8


DCPL-K4A02<br />

a soak pit for absorption by soil or shall be allowed to be absorbed by soil<br />

through open jointed CI pipes laid in a trench filled with broken bricks.<br />

2.6.3 Soak pit / Chlorination Chamber<br />

The soak pit shall be complete as shown on drawing. It shall consist of a<br />

900 mm dia pit 1000 mm in depth below the invert level of the inlet pipe. The<br />

pit shall be lined with stone, brick or concrete blocks set in cement mortar<br />

(1:6) and filled with brick bats. Inlet pipe shall be taken down to a depth of<br />

900 mm from the top as an anti-mosquito measure.<br />

2.6.4 Joining C.I. Pipes / dispersion trenches<br />

Minimum dia of the CI pipe shall be 150 mm nominal. The trench for<br />

laying the pipes shall be minimum 600 x 600 mm pipes. The joints of the<br />

pipes shall be made with lead. The entire length of the pipe within the<br />

trench shall be buried in a 250 mm layer gravel or crushed stone of<br />

uniform size. On top of gravel/crushed stone layer is a 150 mm bed of<br />

well graded coarse aggregate. Ordinary soil is used for filling the top of<br />

trench.<br />

2.6.5 Commissioning septic tank and Soak pit/Chlorination Chamber<br />

After the septic tank has been proved watertight and the sewage system is<br />

checked the tank shall be filled with water to its outlet level before the<br />

sewage is let into the tank. It shall be seeded with well digested sludge<br />

obtained from septic tank or sludge digestion tank. In the absence of<br />

digested sludge a small quantity of decaying organic matter such as digested<br />

cow-dung may be introduced.<br />

3.0.0 TESTING AND ACCEPTANCE<br />

3.1.0 Inspection before installation<br />

All pipes, fittings and fixtures shall be inspected, before delivery at the site<br />

to see whether they conform to accepted standards. The pipes shall again<br />

be inspected on site before laying by sounding to disclose cracks. All<br />

defective items shall be clearly marked and forthwith removed from the site.<br />

3.2.0 Testing of Pipelines<br />

Comprehensive tests of all pipe lines shall be made by simulating conditions<br />

of use. The method of actual tests shall be decided by the Engineer. All<br />

test data shall be recorded and submitted to the Engineer for review and<br />

instruction. The Engineer's discretion regarding tolerance shall be final.<br />

General guidance for the tests are given below :<br />

a) Smoke test<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 9


DCPL-K4A02<br />

All soil pipes, waste pipes and vent pipes and all other pipes when<br />

above ground shall be approved gastight by a smoke test conducted<br />

under a pressure of 25 mm of water and maintained for 15 minutes<br />

after all trap seals have been filled with water. The smoke is produced<br />

by burning oily waste or tar paper or similar material in the<br />

combustion chamber of a smoke machine. Chemical smokes are not<br />

satisfactory.<br />

b) Water test<br />

For pipes other than Cast Iron<br />

Glazed ware and concrete pipes shall be subjected to a test pressure<br />

of at least 1.5 m head of water at the highest point of the section<br />

under tests. The tolerance figure of two litres per centimeter of<br />

diameter per kilometer may be allowed during a period of 10 (ten)<br />

minutes. The test shall be carried out by suitably plugging the low<br />

end of the drain and the ends of connections, if any, and filling the<br />

system with water. A knuckle bend shall be temporarily jointed in at<br />

the top end and a sufficient length of the vertical pipe jointed to it<br />

so as to provide the required test head or the top end may be<br />

plugged with a connection to a hose ending in a funnel which could be<br />

raised or lowered till the required head is obtained and fixed suitably<br />

for observation.<br />

Subsidence of test water may due to one or more of the following<br />

cases :<br />

a) Absorption by pipes and joints<br />

b) Sweating of pipes or joints<br />

c) Leakage at joints or from defective pipes<br />

d) Trapped air.<br />

Allowance shall be made for (a) by adding water until absorption<br />

has ceased and after which the test proper should commence. Any<br />

leakage and the defective part of the work shall be cut out and<br />

made good.<br />

For cast iron pipes<br />

Cast iron sewers and drains shall be tested as for glazedware and<br />

concrete pipes. The drain plug shall be suitably strutted to prevent<br />

their being forced out of the pipe during the test.<br />

c) For straightness<br />

i) By inserting at the high end of the sewer or drain a smooth<br />

ball of a diameter 13 mm less than the pipe bore. In the<br />

absence of obstruction, such as yarn or mortar projecting<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 10


DCPL-K4A02<br />

through the joints, the ball with roll down the invert of the<br />

pipe end emerge at the lower end; and<br />

ii)<br />

By means of a mirror at one end of the line and lamp at the<br />

other. If the pipe line is straight, the full circle of light may<br />

be observed. The mirror will also indicate obstruction in<br />

the barrel if the pipe line is not straight.<br />

3.3.0 Testing Septic Tank<br />

3.4.0 Fixtures etc.<br />

The septic tank shall be tested for watertightness. It shall be filled up with<br />

water and allowed to soak for 24 hours. Then, it shall be topped up and<br />

allowed to stand again for 24 hours and loss of level recorded. The fall shall<br />

not be more than 15 mm.<br />

All fixtures and fittings shall be connected by watertight joints. No dripping<br />

shall be accepted.<br />

4.0.0 CODES AND STANDARDS<br />

Some of the important Codes and Standards relevant to this specification<br />

shall be followed : Latest editions shall always be consulted.<br />

IS:1172 -<br />

IS:1200 -<br />

(Pt. XVI)<br />

IS:1239 -<br />

(Pt. I & II)<br />

IS:1536 -<br />

IS:1537 -<br />

IS:3486 -<br />

IS:1742 -<br />

Code of basic requirements for water supply drainage and<br />

sanitation.<br />

Laying of water and sewer lines including appurtenant items.<br />

Mild Steel Tubes and Mild Steel Tubulars and other<br />

wrought steel pipe fittings.<br />

Centrifugally cast (Spun) iron pressure pipes for<br />

water gas and sewage.<br />

Vertically cast iron pressure pipe for water, gas & sewage.<br />

Cast Iron spigot & socket drain pipes.<br />

Code of Practice for building drainage.<br />

IS:5329 - Code of Practice for sanitary pipe work above ground for<br />

buildings.<br />

IS:2470 - Code of Practice for designs and construction of septic tank<br />

for small and large installations.<br />

IS:3076 -<br />

IS:4984 -<br />

Low density polythelene pipes for potable water supplies.<br />

High density polythelene pipes for potable water supplies.<br />

IS:1537 - Vertically cast iron pressure pipes for water, gas and sewage.<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 11


DCPL-K4A02<br />

IS:1538 -<br />

IS:1230 -<br />

IS:3889 -<br />

IS:1729 -<br />

IS:1626 -<br />

Cast Iron fittings for pressure pipes for water, gas & sewage.<br />

Cast Iron rain water pipes and fittings.<br />

Centrifugally cast (spun) iron spigot & socket soil waste and<br />

ventilating pipes, fittings and accessories.<br />

Sand cast iron spigot & socket soil, waste and ventilating<br />

pipes and accessories.<br />

Asbestos cement building pipes, gutters and fittings (spigot<br />

& socket types).<br />

IS:458 - Concrete pipes (with and without reinforcement)<br />

IS:783 - Code of Practice for laying of concrete pipes.<br />

IS:784 - Prestressed concrete pipes.<br />

IS:651 - Salt glazed stoneware pipes & fittings.<br />

IS:4127 -<br />

Code of practice for laying of glazed stoneware pipes.<br />

IS:1726 - Cast Iron manhole covers and frames intended for use in<br />

drainage works.<br />

IS:5961 -<br />

Cast Iron gratings for drainage purposes.<br />

IS:5219 - 'P' & 'S' traps.<br />

(Part-I)<br />

IS:771 - Glazed earthen-ware sanitary appliance.<br />

IS:772 - General requirements of enamelled cast iron sanitary appliances.<br />

IS:774 - Flushing cistern for water closets & urinals (valveless<br />

siphonic type).<br />

IS:775 - Cast Iron brackets & supports for wash basins and sinks.<br />

IS:2548 -<br />

IS:2527 -<br />

Plastic water closet seats & covers.<br />

Code of Practice for fixing rain water gutters and down-pipes<br />

for roof drainage.<br />

(PCA.775.S034sc22) V.II-D2/S-XXII : 12


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ANTI-TERMITE TREATMENT<br />

(PCA.775.S034sc23)


DCPL-K4A02<br />

CONTENTS<br />

CLAUSE NO. DESCRIPTION PAGE NO.<br />

1.00.00 SCOPE V.II-D2/S-XXIII: 1<br />

2.00.00 EXECUTION V.II-D2/S-XXIII : 1<br />

3.00.00 ACCEPTANCE CRITERIA V.II-D2/S-XXIII : 3<br />

4.00.00 RATES V.II-D2/S-XXIII : 3<br />

5.00.00 METHOD OF MEASUREMENT V.II-D2/S-XXIII : 3<br />

6.00.00 I.S. CODES V.II-D2/S-XXIII : 3<br />

(PCA.775.S034sc23)


DCPL-K4A02<br />

VOLUME : II-D/2<br />

SECTION-XXIII<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

ANTI-TERMITE TREATMENT<br />

1.00.00 SCOPE<br />

The scope of work is to set up a chemical barrier against attack by<br />

subterranean termites while the building is under construction.<br />

2.00.00 EXECUTION<br />

2.01.00 General<br />

All work shall in general be executed as specified in IS: 6313 Part II-1981 and<br />

as per approved specification of the agency having special know-how for the<br />

job.<br />

All necessary work to ensure uniform distribution and proper penetration of<br />

treatment of treating solution shall be done according to the instruction of the<br />

Engineer.<br />

Soil treatment shall not be done when it is raining or when the soil is wet with<br />

rain or subsoil water. Once formed, the treated soil barrier shall not be<br />

disturbed.<br />

2.02.00 Chemicals and Rate of Application<br />

Any of the following chemicals (conforming to relevant Indian Standards) in<br />

water emulsion shall be applied by pressure pumps, uniformly over the area<br />

treated.<br />

Chemicals<br />

Concentration by Weight,<br />

Percentage<br />

Chlorpyrifos Emulsifiable<br />

(IS 8944 - 1978) : 1.0<br />

Heptachlor Emulsifiable<br />

Concentrate (IS: 6439 - 1978) : 0.5<br />

Chlordane Emulsifiable<br />

Concentrate (IS: 2682 - 1984) : 1.0<br />

(PCA.775.S034sc23) V.II-D2/S-XXIII : 1


2.02.01 Treatment of Column Pits, Wall Trenches and Basement Excavations<br />

DCPL-K4A02<br />

Foundations, basements etc. may either be fully enveloped by the chemical<br />

barrier or the treatment may start 500 mm below ground level. The bottom<br />

surface and sides of excavation (upto a height of about 300 mm) for column<br />

pits, walls trenches and basements shall be treated with chemicals at the rate<br />

of 5 litres / M 2 of surface area. Backfills around columns, walls etc. shall be<br />

treated at the rate of 7.5 litres / M 2 of the vertical surface. Chemical<br />

treatment shall be done in stages following the compaction of earth in layers.<br />

The treatment shall be carried out after the ramming operation is done by<br />

rodding the earth at 150 mm centres close to the wall surface and spraying<br />

the chemicals in the specified dose.<br />

2.02.02 Treatment of Top Surface of Plinth Filling<br />

Holes 50 mm to 75 mm deep at 150 mm centres both ways shall be made<br />

with crowbars on the surface of compacted plinth fill. Chemical emulsion at<br />

the rate of 5 litres / M 2 of surface shall be applied prior to laying soling or subgrade.<br />

Special care shall be taken to maintain continuity of the chemical<br />

barrier at the junction of vertical and horizontal surfaces.<br />

2.02.03 Treatment of Soil Surrounding Pipes, Wastes and Conduits<br />

Special care shall be taken at the points where pipes and conduits enter the<br />

building and the soil shall be treated for a distance of 150 mm and a depth of<br />

75 mm at the point where they enter the building.<br />

2.02.04 Treatment of Expansion Joints<br />

These shall receive special attention and shall be treated in a manner<br />

approved by the Engineer.<br />

2.02.05 Treatment at Junction of the Wall and the Floor<br />

Special care shall be taken to establish continuity of the vertical chemical<br />

barrier on inner wall surfaces from ground level up to the level of the filled<br />

earth surface.<br />

A small channel 30 x 30 mm shall be made at all the junctions of wall and<br />

columns with the floor. Rod holes made in the channel up to the ground level<br />

150 mm apart and the chemical emulsion poured along the channel at the<br />

rate of 7.5 litres per square meter of the vertical wall or column surface. The<br />

soil should be tamped back into place after this operation.<br />

3.00.00 ACCEPTANCE CRITERIA<br />

(PCA.775.S034sc23) V.II-D2/S-XXIII : 2


DCPL-K4A02<br />

The Contractor shall give a 10-year service guarantee in writing<br />

supplemented by a separate and unilateral guarantee from the specialised<br />

agency for the job to keep the building free of termites for the specified<br />

period.<br />

4.00.00 RATES<br />

Rates shall be of complete work per unit area as stated in the Schedule.<br />

5.00.00 METHOD OF MEASUREMENT<br />

Complete work of anti-termite treatment shall be measured for plinth area<br />

treated.<br />

This includes treatment, to foundations, walls, trenches, basements, plinth,<br />

burried pipes, conduits etc. The extended portions of foundation and like<br />

beyond plinth limit shall be the part of complete work.<br />

6.00.00 I.S. CODE<br />

Relevant code applicable for this Specification.<br />

IS: 6313 (Part-II) 1981 : Code of Practice of Anti-Termite Measures in<br />

Buildings<br />

Pre-constructional chemical treatment<br />

measures.<br />

(PCA.775.S034sc23) V.II-D2/S-XXIII : 3


VOLUME : II-D/2<br />

ANNEXURE A


DCPL-K9A01<br />

CONTENT<br />

d.AUSENO. DESCRIPTION PAGE NO.<br />

1.0.0 SCOPE V.II-D21S-XXIV: 1 <br />

2.0.0 GENERAL V.II-D2IS-XXIV: 1 <br />

3.0.0 EXECUTION V.II-02/S-XXIV : 12 <br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA V.II-D2IS-XXIV: 34 <br />

5.0.0 INFORMATION to BE SUBMlnED V.II-D2IS-XXIV: 35 <br />

-<br />

808 . <br />

.<br />

(PCA.co.oQ3.S805CSA24.doc.doc)


j<br />

{<br />

f.<br />

\<br />

DCPl-K9A01<br />

VOLUME: II-Dj2<br />

SECTION-XXIV<br />

TECHNICAL SPEC<strong>IF</strong>ICATION<br />

FOR<br />

REINFORCED CONCRETE MULT<strong>IF</strong>LUE STACK<br />

1,0.0 SCOPE<br />

{ This specification covers plain and reinforced cement concrete work, steel<br />

,<br />

flues and Insulation work. painting and protective treatment work, connected<br />

wIIh construction of RCC MuItif\ue Slack.<br />

2.0.0 GENERAl<br />

2,1.0 Work to be provided for by the Contractor<br />

Work to be provided by the Contractor, unless speCified otherwise, shall<br />

include but shall !lot be limited to the following :<br />

t<br />

'.<br />

a) Furnish all labour, supervision, services, Insurance, material, power,<br />

fuel forms, templates, supports, scaffolding, tools, plants, construction<br />

equipment, approaches, transportation etc.' required for the entire<br />

work.<br />

b) Design and prepare working dniwings for formworks, scaffoldings.<br />

suPPQl1s, staging,hoisting arrangement for men and material etc. and<br />

submlt them'for approval.<br />

t c) Prepare and submit for approval, as per approved schedule, detailell<br />

'J<br />

drawings for RCC work In shell, platforms at various levels, roof and<br />

ground floor arid bending schedules for reinforcement bars, showing<br />

the positions and details' of spacers, chairs,' supports, hangers.<br />

openings etc, ',.. ' " " "<br />

t<br />

{<br />

,(:~.<br />

C'<br />

(<br />

d) Prepare detailed fabrication and erection marking drawings for steel<br />

flues including flue expansion compensators, steel flue supports and<br />

restraint arrangements along wIIh fittings and aocessories and sIJhm['<br />

them for approval.<br />

e) Prepare and submit for approval detailed shop drawings, with list of<br />

materials and material specifICations for load Bearing Insulation<br />

Blocl(Sjji'ld Lateral Restraint Insulation Blocks,<br />

(PCAC[)'o03.se05CSA24.doc.doc) V.II-02JS.XXIV: 1<br />

309


DCPL-K9A01<br />

f) Prepare and submit for approval detailed schemes for operations like<br />

material handUng, placement of concrete erection of steel nues, fIXing<br />

of Insulations, Installation, dismantling and maintenanCe of nue<br />

expansion compensator etc. and for items like approaches, services<br />

etc.<br />

g) Design and sUbmit for approval mix proportions for concrete to be<br />

adopted on job.<br />

h) Fumish samples and submit for approval the results of tests for<br />

various properties of the following materials:<br />

i) Ingredients of concrete, (iI) Concrete,<br />

IiQ<br />

AcidlChemical Resistant Tiles, (iv) Castable refractories, (v)<br />

Insulation materials, (vi) Paints. (vii) SIS liner.<br />

i) ,. Provide all incidental itelTls not specified or shown on drawings in<br />

particulars but reasonably implied or necessary for successful<br />

.. completion of the work in accordance with drawings and<br />

specifications.<br />

j) Produce, if directed by the Engil)eer, a guarantee, in approved<br />

proforma, for satisfactory performance, for a speciflEld period. of<br />

material manufactured by specialist firms.<br />

2..2.0 Work .by Others<br />

No work under this specification will be provided fpr by agency other than the<br />

Contractor for this Contract unless specifically mentioned otherwise in the<br />

Contract.<br />

2.3.0<br />

Codes and Standards<br />

All works under this Specification, unless specified otherwise, shall conform<br />

to the latest revIsion&lreplacements of the following Indian Standard Codes,<br />

Cljteri8, SpecifICations, along with those mentioned therein. . In case any<br />

particular aspect. of work Is. not ~red by IrlC:jian.. Slandafds, other s.tanill!rd<br />

specificatiOn, as may be specified.by-tIIe Engineer; sh,,11 be followed.<br />

Specification" shall mean Codes, Criteria etc. of lSI.<br />

"IS<br />

IS:6<br />

IS:t04<br />

IS:158<br />

Moderate heat duty fireclay refractories, Group-A.<br />

Ready mixed paint, brushing, zinc chrome, priming.<br />

Ready mixed paint, brushing, bituminous, black, lead free, acid,<br />

alkali, water and heat resisting for general purposes.<br />

IS:195<br />

SpecifICation for fire clay mortar for laying fireclay refractory<br />

bricks.<br />

(PCA.CO-O03.S805CSA24.doc.doc) V.lI-D2IS-XXIV : 2<br />

810 . \<br />

"<br />

• • '.' I ,:.;<br />

'lI•.. -••'<br />

i.',­<br />


OCPl·K9A01<br />

,i<br />

IS:269<br />

IS:383<br />

15:432<br />

15:456<br />

IS:516<br />

IS:732<br />

IS:800<br />

IS:813<br />

IS:814<br />

IS:816<br />

IS:817 <br />

Ordinary, and low heat Portland cement<br />

Coarse and fine aggregates from natural· sources for concrete.<br />

Mild steel and medium tensile steel bars.<br />

Code of practice for plain and reinforced concrete.<br />

Methods of test for strength of concrete.<br />

Code of practice for electrical wiring. Installallons (System<br />

Voltage not exceeding 650 Volts).<br />

\<br />

Code of practice for general construction in steel: <br />

Scheme of symbols for welding. <br />

Covefed electrodes for metal arc welding of structural steel. <br />

Code of practice for use of metal arc welding for general <br />

construcllon in mild steel.<br />

. <br />

Code of practice for training and testing of metal arc welders. <br />

t<br />

c.<br />

4­<br />

".~.<br />

k." _<br />

~,;r. .<br />

( <br />

(", <br />

t<br />

t<br />

{. <br />

(.,<br />


DCPL-K9AOl<br />

15:1554 cables. <br />

15:1566 Hard-


DCPL-K9A01<br />

18:2386<br />

(Part-VIII)<br />

18:2502<br />

18:2505 <br />

18:2506 <br />

18:2633 <br />

18:2722<br />

t8:2750<br />

18:2751<br />

Petrographic examination.<br />

Code of practice for bending and fixing of bars for concrete <br />

reinforcament. <br />

Concrete vibrators, immersion type. <br />

Screed board concrete vibrators. <br />

Methods of testing uniformity of coating on linc coaled <br />

articles. <br />

Portable swing weighbatchers for concrete <br />

(single and double bucket type). <br />

Steel scaffoldings. ,<br />

Code of practice for welding of mlld, steel ,bars used for<br />

reinforcad concrete construction.<br />

", <br />

t <br />

( <br />

( <br />

lJ <br />

(; <br />

f· <br />

t <br />

t <br />

{; <br />

to:,<br />

t,<br />

18:2950<br />

18:3025<br />

18:3043 <br />

18:3144 <br />

18:3346 <br />

18:3495<br />

(Part-I to IV)<br />

18:3550 .<br />

IS:3558<br />

IS:38n <br />

18:4014 <br />

, (Part-l&II)<br />

18:4031 <br />

IS:4457 <br />

Code of practice for design and 'construction of raft<br />

foundations.<br />

Methods of sampNng and test (Physical and Chemical) for<br />

water used in Induslty.<br />

Code of Earthing.<br />

Methods of Test for Minelli! Wool Thermal Insulation Material<br />

Method for the determination of thermal conductivity of thermal<br />

Insulation materials (M slab, guarded hot- plate method.!<br />

Method of test for clay building bricks.<br />

Methods of tes/for routine control for water u~<br />

.... -­<br />

in indust""<br />

Code of practice for use of immersion vibratorn<br />

consotidating concrete.<br />

Unbonded rock and slag wool for thermal insulation.<br />

Code of practice for steel tubular scaffolding.<br />

Method of physical tests for hydraurlC cament. <br />

Ceramic Unglazed Vitreous acldresislent tiles. <br />

IS:4634 ' Method for testing performance of batch-type concrete mixe <br />

(PCA.C~03.S805CSA24.doc-doe) V.lI-D2IS-XXIV : 5<br />

313<br />

fOI


DCPL·K9A01<br />

15:4687 Gland packing asbestos.<br />

15:4832 Chemical Resistant mortars.<br />

15:4860 Acid-reslstant bricks.<br />

15:4990 Plywood for concrete shuttering wolll.<br />

15:4998 Criterte for design of reinforced concrete chimneys.<br />

(Part·Q<br />

15:5410 Cement paint, colour as required.<br />

15:5445 Long ftuted machine reemers with Morse taper shanks.<br />

15:5495 Sizes and shapes for firebrick (300 mm. and higher series).<br />

15:6911 stainless Steel plate, sheet and strip.<br />

15:8f12 High slrength ordinary portland cement.<br />

15:8183 Bonded Mineral Wool.<br />

15:9595 Recommendation for Metal Arc Welding of Carbon and<br />

Carbon Manganese steels.<br />

CP326·<br />

British Standard • Protection of structures against lightning.<br />

NEPA NO. 78 Code of protection against lightning.<br />

The Indian Electricity Rules.<br />

The,requirements of Department of CMI Aviation, Gov!. of India.<br />

2.4.0 Con(ormlty with Drawings and Spedficatlons<br />

. . . .<br />

The Contractor Shalfcarry oUt' ali the weill h strict lICCoRlance 'willi the drawings<br />

Stamped "Released for Construction" and'speCification Issued to him and as per<br />

Conlradg~s detailed drawings approved by the Consulting Engineer. Prior to<br />

concreting, the Contractor shall prepare a check list on a set format of all items of<br />

wolll involved, and lnform the Engineer well in advance so that the Engineer<br />

shail have the opportunity of satisfying himself if the works mentioned in the<br />

fom1at are dOne according to drawings and specification, and he can allow the<br />

Contractor in writing to start pouring of concrete. The entire operation of<br />

concreting shall be can1ed on as per specification, to the complete sa6sfaction of<br />

the Engineer. fIIOde'IIation from the drawings wUl be allowed unless otherwise<br />

directed by the Engineer In writing.<br />

For Load Bearing Thennal Insulation block assembly and lateral ,estralnt<br />

InsUlation block assembly, Contractor shall design sizes of all components of the<br />

(PCA.CI).OO3.S905CSA24.4oc.doc) V.U-02JS.XXIV: 6<br />

"<br />

".: " .


i<br />

DCPL-K9AOl<br />

blocks and details of their connectJons, supply and fabricate the same in<br />

accordance with the approved shop drawings prepared by him.<br />

For steelwOrk and meta! work, the Contrector shall deslgn all connections, inserts<br />

for scaffolding, supply and fabricate all steelwork and metal work and fumish all<br />

connection materials In accordance with approved shop drawings prepared by<br />

him and/or as instructed by the Engineer, keeping in view the maximum utilisationof<br />

the available sIZes ,!nd shapes for metal components.<br />

2.5.0 Mateials to be used<br />

2.5.1 General Requirement<br />

2.5.2 Cement<br />

All materials. whether to be inCOlPOlated in the work or to be used temporalily for<br />

the construction. shall conform to the relevant IS specfflcations unless stated<br />

otherwise and shall be of the quality approved by the Engineer.<br />

Portland Cement shallpe as per the requirements laid down in IS:269.<br />

2.5.3 Coarse Aggregate<br />

Coarse aggregate shall be graded crushed or brok,en slone from approved<br />

sources, free from Impurities and shall be screened free of dust and other<br />

deleterious matter. It shall conform to IS:383 or IS:515 and shall be washed<br />

clean, If nec:essaty:<br />

The maximum sIZe of coarse aggregate for stack<br />

superstructure shall be 25 mm down graded, unless otherwiSe stated (vide serial<br />

5(b) of clause 3.03'cljl). Grading for a particular size shalf confonn to relevant IS<br />

Codes and shall be such as to produce a dense Concrete of specified proportion<br />

and strength and shall be of consistency that will work raadlly Into position<br />

( without segregation. •<br />

2.5.4 AneAggregate<br />

(: Fine aggregate shall be river or pit sand. free from any clay, eerth. vegetable<br />

matters, salt or oIherimpurities and shall be dean and fit for use, to the<br />

~:,<br />

satisfaction of the EngIneer. Sand ~ for the Wort< shall nomnally<br />

.:" have a grading faDIng wiIIlin tile ~mils ~f one .of 1I1e thrae {/1'8de!l: Illentloned .<br />

in the relevant.1S Specifications. . ..... '. '. '. • _'_<br />

( 2.5.5 Water<br />

t'<br />

I>'<br />

t. 2.5.6 Reinforcement<br />

t<br />

The water for both mixing and curing of concrete shall be clean. free from 011,<br />

·acld, alkali. organic or olher deleterious substances. Contractor shall test Ihe<br />

water as end when required by the Enginaer. .<br />

Mild steel or Medium or High Tensne steel defonned bars specified for<br />

reinforcement shall confonn to the latest relevant IS Specifications and shall<br />

be of tested quartly under lSI CertifICation Scheme. The reinforcement shall<br />

t. be free from any oil. foraign material or mill or rust scales. . .<br />

,-:.,1<br />

(PCACO-OO3.S805CSA24.dOe.doe) V.U-02lS-XXIV : 7<br />

• r • "<br />

315


DCPl-K9AOl<br />

2.5.7 steel Rue<br />

a) All mild steel material to be used in construction of steel flue, shall<br />

comply with 15:2062, 15:1239,15:1367, 15:1608, 15:800 and with other<br />

relevant IS 5pec1flCllllons. The ultimate tensile strength of this steel<br />

shall notbe less than 410 NISq.mm.<br />

b) Stainless steel liners shall be fabric:ated using materials conforming to<br />

the requirements of relevant IS Specifications and/or AISI 316l or<br />

85:1449 Part-2. Gredeof S1a1ntess steel shall be equivalent to<br />

85:1449 (Part-2) 3165.12. '<br />

c) Materials to be used for fabrication of Flue expansion compensator<br />

shall be 'sultable for the flue gas tempeeture and shall be acid resisting,<br />

The expansion compensator shall comprise severa! layers of<br />

maieI1aIs gillen below in order from the gas side.<br />

. .<br />

Ij<br />

Two. layer of insulation, each consisting of heavy weight<br />

texturized glass cloth Impregnated with graphite suspension,<br />

having an approximate weight of 1.00 KgISq.m<br />

• iI)<br />

A continuous filament glass cloth coated both sides with a<br />

fIouro-elastomer having an approximate weight of 1.5<br />

KglSq.m. '<br />

Two layers of PTFE (Poly Tetra Fiouro-Ethylene) film of<br />

minimum thickness 0.15 mm each.<br />

Iv)<br />

A layer of glass felt of minimum thickness 10 mm and an<br />

approximala weight of 1.5 Kg/Sq.M.'<br />

2.5.S<br />

Paints<br />

Paints to be used for shop


DCPl-K9A01<br />

2.5.10 Insulations<br />

a) On Exterior Surface of Aues<br />

The nonnal flue gas temperature Inside the flue shall be 145 Deg.C<br />

wfth momentary rise upto 400 Deg.C (Maximum) occasionally. The<br />

insulation material shall lie able to withstand this temperature without<br />

any deterioration in thennal properties or breakdown. The thermal<br />

conductivity of the Insulating material shan not exceed 0.06 W/M<br />

Deg.C at a mean temperature of 150 Deg.C. The insulation shall also<br />

not be affected by any acid condensation from flue gas and shall be<br />

free from any impurities which may cause corrosion to the tlue<br />

material.<br />

For steel flues 65 mm thick semi rigid resin bonded fibrous mineral<br />

wool or. density not less than 96 KgICu.m as per IS:8183 or resin<br />

bonded fibrous crown glass YIOOl (high temperature) of same<br />

thickness and density not less than 36 KglCu.m capable of sustaining<br />

temperature to the tune of 540 Deg.C without any loss of material<br />

thermal property, may be used. The mineral wool for eXPOsed top<br />

portion of flue ehall be semi-rigid .with minimum density of 200<br />

KglCu.M or the glass wool for expoeed top portion of flue shall have<br />

minimum density of 75 KglCu;M.<br />

Slag wool insulation. shall not be accepted.<br />

t<br />

(<br />

The insulation free from shots should be supplied in the form of mat to<br />

be foxed with staggered joints on outer surface of.the flue with suitably<br />

spaced stud by galvanlsed wire mesh. Insulation on the top portion<br />

of flue shan be covered by stainless steel claddln9.<br />

b) AI load Bearing and SIde Restraints of Rues<br />

( .": Load bearing insulation assembly 10 have (i) a properly mechined mild<br />

.'<br />

steel plate with recess at Its top tor seating PTFE (Poly Tetra Fluoro<br />

Ethylene) sheets confot:mIng to 8S:5400 (Ii) saddle plate (MS) in the<br />

l~ middle having stalnIes$ steel plate fIXed at Its bottom surface and<br />

leacf/elasto.mt!Iie· sheet at top, an


DCPL-K9A01<br />

ii)<br />

iii)<br />

Iv)<br />

Minimum shear strength of 30 NlSq.mm when tested in<br />

accordance with 85:3497-1979.<br />

Thermal conductivity shan not exceed 0.67 W/m Deg.C at a<br />

. mean temperature of 200· Deg.C and its coeff. of linear<br />

expansion not to exceed 1.2 x 10" per Deg.C.<br />

Adhesive used for bonding purposes shall be of material with<br />

equivalent high temperature properties as approved by the<br />

engineer. II may beef "Fortafix Flborclad Adhesive" as<br />

manufactured by Fortafix Ltd •• England.<br />

2.6.0 Stol!lge of Materials<br />

2.6.1 General<br />

2.6.2 Cement<br />

All materials shall be so stored as to prevent deterioration and intrusion of<br />

foreign matter and. to ensure the preservation of their quality and<br />

characteristics for the work. Ani material. which is deteriorated or Is<br />

damaged or Is otherwise considered defective by the Engineer, shall not be<br />

used for construction arfd shall be removed from site immediately, failing<br />

which the Engineer shal~ be. at liberty to get the lI)aterials removed. The<br />

ContraCtor shall maintain an upto date accounts of receipt, issue and balance<br />

ef all materials Issued by the Owner. .<br />

Contractor shall stOre cement In water-tight and properly designe.d stores so<br />

. that the Cement can be kept dry and the stock can be handled in rotation,<br />

The doors of stores shall be at least 30 em. above G. L. Deteriorated cement<br />

shall be removed Immediately from the site. Not more than ten bags of<br />

cement shall be stacked one above the other.<br />

2.6,3 Aggregate<br />

Different materials shan be transported, handled and stored separately in<br />

sUch a manner as to pre,vent damage, deterioration or contamination. Stock<br />

pUes of fine and 'coarse !lggregates. shaD be alloWed to ,drain, so that .<br />

. aggregates'do,notcoritain too much· water. '<br />

2.6.4 Reinforcement<br />

Reinforcement shall be stored preferably under cover and stacked off ground<br />

In size 'and grade-wise separate stacks for easy identification.<br />

2.6.5 Steel, Metal and fittings<br />

All steel, metal and fittings to be ui8d for fabrication and erection shall be<br />

stored sectionwise and lengthwise In separate stacks, off ground, so that they<br />

cal'! be handled, inspected, measured and accounted for easily at any time,<br />

If required by the Engineer, the materials may have to be stored In a covered<br />

shed.<br />

(PCA.CO-O03,S805CSA24.doc.doc) V.II-D2IS-XXIV: 10<br />

....'1-,',.


(<br />

t<br />

DCPL·K9A01<br />

2.6.6 Paints<br />

2.6.1 Steel Flue<br />

,r 2.6.8 Insulation Material<br />

Paints shall be stored under cover, in air-tight containers. Paints supplied in<br />

sealed containers shall be used as soon as possible once the container is<br />

opened. Left over paints shall be kept in air-tight containers.<br />

Fabricated pieces of steel (Rue) liner shall be stored systematically for ease<br />

of handling.<br />

All insulation materials fike beaiing insulation blocks, restraint Insulation<br />

blocks, glass or mineral wool. asbestos ropes etc. shall be stored In paddng<br />

boxes, under covered shed, avoiding Ifleir coming in contact with<br />

objectionable matter.<br />

2.1.0 Quality Q:mtrol<br />

. ,<br />

Conltactor shall' establish and maintain quality controf for different items or<br />

work and materials as Il'lIY be directed by the Engineer to assure compliance<br />

with contract requirement and submit to the Engineer .records of the same.<br />

The Contrector shall submit all records and test resuHs in original to the<br />

Engineer for his approval, Ifso desired by him.<br />

The quality control operation shan include but shall'not be limited to the<br />

. following items of work :<br />

a) Cement<br />

b) Aggregate<br />

c,.<br />

.Water<br />

d) Reinforcement<br />

e) Structural<br />

f) Steel Rue<br />

Test to satisfy relevant IS Specifications if<br />

supplied by the Contractor.<br />

Physical, Chemica! and Mineralogical<br />

qualities; grading, moisture contents and<br />

impurities.<br />

,'tmpuritles Tesl ' '<br />

. " .. ,<br />

Miiterial tests or certificates to satisfy relevant<br />

IS Specification If suppned by the Contractor.<br />

Material tests or certificate to satisfy<br />

Steelrelevant IS Specification If supplied by the<br />

Contractor.<br />

Material tests or certificate to satisfy relevant IS<br />

Speciftcation If supplied by the Contractor.<br />

g) Stainless<br />

Material tests or certificale to satisfy<br />

£;<br />

(,"<br />

(PCA.C[).Q03,5B05CSA24,doc.doe) V.II-02IS-XXIV: 11<br />

319<br />

'it'


DCPL·K9A01<br />

relevant IS Specification if supplied by the<br />

Contractor.<br />

h) Acid<br />

Resistant<br />

Compressive and tensile strength. acid tiles&<br />

mortar resistance and water absorption test.<br />

i) Mortar Compressive and tensile strength. adhesion<br />

and acid resistance test. .<br />

j) Insulation TIIemIaI conductivity. densily. heat and acid<br />

resistance tests. Bearing capacity will be tested<br />

for bearing/restraint insulation blocks.<br />

3.0.0 ~~<br />

3.1.0 CIJn(;rete<br />

3.1.1. TriaL Mix, Grades of Concrete<br />

At klsst three weeks befOre commencing aoy concreting in the work the<br />

ConllactOf shall make trial mixes using samples of


DCPL-K9AOl<br />

MIX PROPORTIONS (BY WEIGHT) EXPECTED TO GIVE DIfFERj:NT DEGREES <br />

OF WORKABILITY WI11i D<strong>IF</strong>FERENT VALUES OF WATER - CEMENT RATIO <br />

(FOR GUIDANCE) <br />

CEMENT[TOTAL AGGREGATES RATIOS <br />

WorkabUity Waterl Ratio by Weight of Cement Ratio by Weight of Cement to<br />

Cement to Gravel Aggregate Crushed Stone Aggregate<br />

Ratio 20 mm. Size I 38 mm. size 20 ITU'I!. size I 38 mm. size<br />

i<br />

Very Low<br />

slump<br />

G-25mm.<br />

"<br />

Low<br />

slump<br />

25-50mm<br />

Medium<br />

slump<br />

5G-100mm.<br />

4, High<br />

slump<br />

100 ­<br />

( 175 mm.<br />

0.4 01:04.8 01:05.3 01:04.5 1:05<br />

0.5 01:07.2 01:07.7 01:06.5 ()1:07·,<br />

0.6 01:09.4 1:10 01:07.8 01:09.6<br />

0.7 1:10 1:12 01:08.7 01:10.6<br />

0.4 01:03.9 01:04.5 01:03.5 1:04<br />

0.5 01:05.5 01:06.7 1~05 01:05.5<br />

0.6 01:06.8 01:07.4 • 01:06.3 1:07<br />

0.7 1:08 01:08.5 01:07.4 1:08<br />

0.4 01:03.5 01:03.8 01:03,1 01:03,6<br />

0.5 01:04.8 01:05.7 01:04,2 1:05<br />

0.6 1:08 01:07.3 01:05,2 01:06.2<br />

0.4 01:03.2 01:03.5 (l1:02.9 01:03.3<br />

0,5 01:04.4 01:05.2 01:03.9 01:04,6<br />

0.6 01:05.4 01:06.7 ' 01:04.7 01:05.7<br />

0.7 01:06.2 01:07.4 01:05.5 01:06.5<br />

t NO'I'E-l :<br />

'* (c<br />

CD<br />

t.><br />

l<br />

,:,<br />

&,;.:i<br />

t~,<br />

NOTE-2:<br />

Notwithstanding anything mentioned above. the cement I Total aggregatE!<br />

ratio is not to be increased beyI;lnd 1:9 without specific permission of the<br />

Engineer.' "<br />

, It should be n6ied tha!such high aggregate cement ratlos will be required for<br />

concretes of very low slump and high _ter-cement ratios which may be<br />

required to be used in mass concrete work only.<br />

The above figures are for guidance only, the actual cemenV aggregate ratios<br />

are to be wor1


DCPL-K9AOI<br />

slreng1h of the concrete cubes falls below 1he requirement, 1he method<br />

described IIbove shall be repeated till acoepIabIe msults are obtained. The<br />

method may haVe 10 be repeated whenever there is a significant change In the<br />

quality of any of 1he ingredients for concrete, at the discretion of1he Engineer.<br />

3.1.2 Batchlng of Concrete<br />

For !=Ofltrolled collCl8te, only weigh balchlng shall be allowed. All concre1e<br />

ingredients, except water, shall be balched by weight, using an approved'.<br />

rnakil of weigh betcher. Batchlng shall be accurate to 112 Kg. The batcher \<br />

shall be tested for 8CCU11IeY of calibration, fU'Sl before commencement of<br />

work and at least once a fortnight or as directed by 1he Engineer 1hereafter.<br />

Water shall be batchad by weight or by volume measures. as approved by<br />

the Engineer.. •<br />

3.1.3 Mixing of Concrete<br />

Materials for concre1e shall be empt1ed in rotation into the mixer. When all<br />

1he ingredients are In tha drum. 1he drum ~II rot8te for one, minute for dry<br />

mixing. Af1er 1hat "'(aIer shall be edded In measured quantities in the manner<br />

specified. The mixer shaH 1hen rotate for at least two minutes. or at least<br />

forty revolutions or unUl,1here Is apparent uniform distribution of the materials<br />

and tiU 1he masil is unilOrm In colour. The entire content of the drum shall be<br />

discharged before 1he Ingredients for 1he'succeeding batch are fed Into 1he<br />

drum. The mixer shall be 1horoughly cleaned to the satisfaction of 1he<br />

Engineer, before a different quality of concrete is put through the mixer and<br />

also at the end of day's wolk.<br />

3.1.4 Workability of Concrete<br />

The' degree of workability necessary to allow the concrete to be well<br />

consolidated and to be wolked Into 1he comers of formwolk and around 1he '<br />

reinforcement and embedments. and to give 1he required surface finish shall<br />

depend on 1he type and nature of &tructure and shall be based on experience<br />

and tests. 15 mm. to 40 mm. slump In chimney works shall be adopted<br />

~ to Engineer's ap,proval unless stated o1herwise (vide serial 1 (d) of·<br />

~use np. 3.3.6). The usuat ~miIs' of consistency for various types of<br />

structure are given below ; " . .<br />

".


UMITS Of CONSISTENCY<br />

DCPL-K9A01<br />

Degree of Slump In mm. with Use for which Concrete is suitable<br />

Workability<br />

Standard Concrete<br />

Min.<br />

Max.<br />

Very Low o 15 large mass concrete work with heavy<br />

compac:tion equipment.<br />

Medium 35 65 Deep and wide RCC structures with<br />

congestion of reinforcement and inserts.<br />

High 65 100 Very narrow and.deep RCC structures<br />

with congestion due to reinfor


DCPL-K9A01<br />

Vibration shall begin as soon as one batch 0( concrete has been placed and<br />

shalf continue tin the entire section being poured has been thoroughly<br />

consolidated.<br />

To secure even and dense surfaces, free from aggregate pockets, vibration<br />

shan be supplemented by tamping or rodding by hand in the comers of forms<br />

and along the form surfaces whllelhe c:oncrele Is plastic, without damaging<br />

or endangering the stabUity 0( the formwork.<br />

A suffICient number of spare vibrators Including petrol vibrators shall be kept<br />

reedily accessible to the place 0( deposition of the concrete to assure<br />

adequate vibration In case 0( breakdown of those in use.<br />

3.1.6 CurI/Ig of Concrete<br />

Curing 0( exposed surface 0( concrete shaU commence immediately after the<br />

concrete has. set. Exposed sides shall be covered with canvas etc.<br />

immediately afieF ·sltlpping 0( forms, and curing shall be continued for a<br />

period 0( not less than 14 days. reckoned from the date and hour 0(<br />

completion of concreting.' All surfaces of the. pour shaD be kept wet with<br />

water at all times after concreting and lUI the curing period Is over. The<br />

Contracior shaD plan and employ proper equipment and sufficient labour<br />

considered adequate by the Engineer under able supervisor for curing.<br />

3.1.7 Construction Joints<br />

In concreting the chimney shell one full ring lift shall be completed in a day's ,<br />

pour. Before the forrnwork for the following pour starts the horizontal surface<br />

of the Chimney shell shall be chipped, cleaned and washed with water, and<br />

when the forrnwork Is complete, the surface shall be cleaned and washed<br />

again and covered with 1:2 sand cement slurry before fresh concrete is<br />

plaoed. The horizontal construction joints shall be so arranged and made<br />

that, they are regular and neat. No vertical joint shall be allowed. No<br />

separate paYment shaU be allowed to the Contrador for forming JOints or<br />

chipping and cleaning them or cover with slurry prior to concreting. The<br />

nlimber ofCX)nstruction joint shall be kept minimum and the spacing should<br />

not exceed three (3) melers. The Conlractor shall submit to the Engineer,<br />

any proposai of ·providing constflJllllon Joints to facilitate his work, for .the<br />

study end approval of the Engineer well In adVance. ".<br />

3.1.8 Ordinary Concrete<br />

Ordinary concrete Ilke lean concrete shall be of nominal mix as per relevant<br />

cl8I!ses 0( 15:456.<br />

,<br />

(PCA.CO.oo3.SS05CSA24.doc.doc) V.lI-D2JS..XXIV: 16<br />

824


OCPl-K9A01<br />

3.2.0 Reinforcement<br />

3.2.1<br />

Bending of Reinfortement<br />

t<br />

{<br />

3.2.2 Pladng<br />

All bars shall be carefuny and accurately bent by the Contractor in<br />

accordance with approved Drawings and ber bending schedules. Special<br />

care shall be taken to ensure correct lengths of laps. The bars shall not be<br />

bent or straightened in any manner that wiN Injure the bara or impair the bond<br />

between reinforcement & conae1e. Bends and hooks are to be provided as<br />

laid down in the IS:2502.<br />

All reinforcement shell be placed and maintained in the position shown in the<br />

drawings. Contractor shaR provide approved type of cover blocks to sUit the<br />

requirement of the Drawings. Where reinforcement Is to be provided on two<br />

faces of the shell, the Contractor shell provide adeqoate number of<br />

separators, with the approval of the Engineer. Any additional supporHo the<br />

re1nforcing cage. if required at the time of concreting, shall alSO: be provided,<br />

to the satisfaction of the Engineer. lapping of reinforcemenl as specified in<br />

the drawings or as directed by the Engineer, shall be provided. laps shall be<br />

staggered and too many laps shan be.avoided. Welded laps shall be<br />

provided only when directed or approved by the Engineer. '<br />

3.2.3 Fixing of Reinforcement<br />

18 SWG annealed steel wire shall be used as binding wire. 8ar crossing one<br />

another and contact laps shall be bound with this wire, twisted tight to make<br />

the skeleton or network rigid so that the reinforcement is not displaced during<br />

placing of concrete.<br />

3.10 Fonns<br />

( Construction by Slip-form Method<br />

." 1;.­<br />

Slip-fonm construction 'shaA !:le for constructioiI of the )oYind shield. Type of<br />

,~ Sfip-form proposed should be Indicated In the offer with sketches, drawings<br />

and. constnlCtioo ' statement ·aselCplained herein;;d'ter; !'lumber, type and '<br />

capacities of Jacks, the' control system and achievable rate of progress in<br />

t.:<br />

mmIhour should also be indicated. The chosen scheme shell be of a psst<br />

proven design. A certified perfonmance record of the scheme should be<br />

submitted with the offer to guarantee woikability of the scheme both from<br />

execution time and safety point of view. .<br />

t, ,<br />

t<br />

t:, '<br />

The Tenderer shQuld fumish a brief but commprehensive statement<br />

indicating the planning & programme and method of work to be followecUor<br />

the approval of Owner at the time of submitting Tender. This slstement shall<br />

include the following Hems:<br />

i) Type and description of SUp:form eq';lipment and its accessories.<br />

(PCA.CD-003.S60SCSA24,doc.dac) V.II-02lS-XXIV: 17<br />

L~ . ,., "<br />

325<br />

l'<br />

; .<br />

~,'..


Ii)<br />

Design of scaffolding and staging.<br />

DCPL-K9A01<br />

il1) Description of materials inCluding admixtures 10 be used for<br />

consltudion.<br />

iv) Manpower ptennlng, conl;truction spaces required , standby<br />

arrangement:<br />

vi)<br />

vii)<br />

viii)<br />

be)<br />

Rate of Slip-fonning.<br />

Proposed workabilitY requirement of concrete and type of cement &<br />

admixture to be used.<br />

Quality assurance programme.<br />

Method ofTraansportalion of melerial<br />

x) Method of curing and rectification of defects.<br />

xi)<br />

xii)<br />

xiii)<br />

Planned'intemlption, if proposed, and activilies during planned<br />

interruption. T reelment of consltuction joint. .<br />

. .<br />

COntingency solution for unptannad interruptions.<br />

Time of completion.<br />

While selecting the COntractor, due consideration will be given to the merit of<br />

the above mentionad statement proposed by the Tenderer.<br />

Not withstanding what have been specified In earlier clauses, following guide<br />

lines are being presented whk:h should be kept In view by Intending<br />

Tenderers. whUe quoting for Slip-fonn method of consltuction :<br />

1. Care to be taken to prevent dragging of concrete aiongwith upward<br />

movement of the shuttering. For this purpose following' steps are<br />

advisable : .<br />

a) ,Shutter··P\ate$ have to be smooth and should be 'thoroughly<br />

clean. BefO/B fildng them in position all the surfaces which Will<br />

be coming in contact with COIICI1Ite to have a coat of epoxy<br />

paint.<br />

b) In arees where concrete thickness Is 750 mm or more rate of<br />

pouring should be such that minimum slipping of shuttering is<br />

100 mm per hour.<br />

c) Mix design should be so done that it will be self: lubricant at<br />

the contact face of shutter and (XlIlCrete and thus reduce<br />

friction. Suitable cement of approved manufacturer<br />

(conforming to relevant I.S. SpecIfication) may be used for the<br />

purpose. An optimum ratio of coarseJllne aggregate should be<br />

(PCACO-O03.S805CSA24.doe.doe) V.II-02IS-XXIV: 18<br />

\ .. ';. ~; .


, ( OCPL-K9A01<br />

established to suit the purpose depending on availability of<br />

aggregates.<br />

d) M"IX design also should be so done that II has a slump of 50<br />

mm at the point where concrete is placed under an ambient<br />

temperatura of around 40 Oeg.C. This wlll also keep vibration<br />

by needle vibrators to required minimum. Slump should 'not<br />

drop down to zero In less than 45 minutes. Suitable ratarding<br />

agent and plasticizer of approved manufaCture may be added<br />

in mix to achieve this purpose. These admlxturas to be<br />

properly Identified by praliminary tests both for pedormance<br />

and for compatibility with particular type Qf cement propoSed 1(,<br />

be used.<br />

Additlonal steps Ike spraying of water over tha shutters and<br />

keeping down the temperatura of coarse aggregates by<br />

continuous spraying of water over those may be rasorted 10 kl<br />

ambient temperatura is more than 40 Oeg.C.<br />

,<br />

3.<br />

t.<br />

2. Cere must be taken to pravent twist. which predominantly occur in the<br />

initial stages because of low ,tipping rate, in the horizontal plane of<br />

Slip-form assembly. A thorough check on this aspect must be kept at<br />

every 15 minutes interval. One person should exclusively be assigned<br />

this work together wfth rectifying any defect.<br />

Every endeavour has to be made so as not to occur any tilt in the<br />

shutter assembly. To achieve thls following steps need be1aken :<br />

a) Performance of jacks has to be closely observed and any<br />

defective one needs Immediate replacement. Difference' In<br />

levels of opposite jaclls at any instant of time should not<br />

exceed 5 mm.<br />

(: b) Loading on Stip-form Inlsslyokes has to be fairly equal.<br />

•<br />

c) Sleeve through whlOn jacking rod passes has to be of<br />

sufficient length so' that· later gets an uniform clearance· and<br />

. does not get any chance to bll SJeeveshouldhavea minimum<br />

wan thickness of 3.25 mm and should' bE! such that jacking<br />

#:.:: rod gats a maximum clearance of 1 mm to 1.5 mm alround.<br />

,~"'<br />

(j:<br />

4. For taper walled chimneys ovellapping of shutt!)rs which are kept te<br />

efIact the tapering. needs careful attention otherwise these may be<br />

ruled with concrete slurry.<br />

t<br />

5. . In designing the mix fOllowing aspects should be borne in mind :<br />

t<br />

a) Cement used should have an initial selting time of not less<br />

than 50 minutes and preferably should have a specifIC surface<br />

around 3600 Sq.Cm.per gram.<br />

t:. .;, b) Coarse and fine aggregates should be well graded a<br />

42~,~<br />

(PCA,C0-003.S80SCSA24.dOC.dOC) V.U-02lS-XXIV: 19<br />

t;<br />

327<br />

(;


OCPL·K9AOl<br />

rounded aggregates offer better performance in SUp-form<br />

technique. These help 10 keep down water/cement ratio and<br />

also offers better lubrication between concrete and shutter<br />

surface. 40 mm down size of coarse aggregates should<br />

. praferably be used unies6 ralnforcement detailing calls for<br />

I_r size aggregates.<br />

c) From the point of view of craeP. shrinkage as well as initial<br />

selting property of conaete. cement content should not<br />

p!8ferabiy be more than 40Q Kg. per Cu.M of concrete.<br />

d) Minimum compressive elrength (after 4 to 6 hours of mixing) of<br />

concrete immediately below the shutter as slipform proceeds<br />

should be between 0.1 10 0.2 Newtonl Sq.mm ..<br />

e) It Is advi6able to use cement from a single source during the<br />

entire operation of sIIpform technique since once the .system<br />

starts. there might not be any time left for conducting trial<br />

mixes if the source of procurement of cement changes.,<br />

6. Large diameter YI'bIator needles should not be' used for vibrating<br />

concrete. Sizes of these needles should preferably be restricted to<br />

25 mm diameter and to 40 mm diameter - only in eXCeptional cases.<br />

At least two nos. standby Vibrator units should always be maintained<br />

.on top of worldng deck at all time during the entire period of slipform<br />

operation.<br />

7. It Is preferable to have membrane curing compounds sprayed. on<br />

fresh surfaces emerging out of shutter panels for ensuring proper<br />

curinng at great heights.<br />

In case such spreying is not envisaged then elaborate arrangement<br />

has to be made for adequate supply of water both on Inside and<br />

outslde vertical surfaces with spraying arrangement. necessary<br />

length of pipelines and pump of adequate head to serve the purpose.<br />

It is always advisable to have a stand-by pump for effective utilisation<br />

of the system. .<br />

.8. .' If StipfOrming In::acried. out in summer•.rate of sUpPing should· be .. " ..<br />

around 400 mm per hour. If I_rvalue Is eontemplated appropriate<br />

retarders should be spec:ifled.<br />

9. Exact number and capacity of jlldca as well as spacing of yoke frames<br />

are to be determined taking Into acoount various loadings including<br />

self weight of the system. dead and live loads on working and other<br />

platforms. horizontal load on formwork. wind load etc.<br />

It is desirable that jacking system. based on which the entinrsUpform<br />

system works, should consist of jacks 3 Tonne/6 Tonne capacity and<br />

a hydrautic pump with necessary pipe connections.<br />

Spacing of yoke tegs should preferably be kept within 2 metres to<br />

(PCA.C0-003.SS05CSA24.doc.doc) V.II-02lS-XXIV : 20


.} ,.<br />

DCPL·K9A01<br />

prevent overioading on jacks and consequent faHure resulting In twist<br />

of the formwork.<br />

! 'i.<br />

Jacking rods should be of 25 mm diameter for 3 Tonne Jacks and 32<br />

mm diameter for 6 Tonne Jacks.<br />

,(<br />

10. At least 30% spare jacks and Jacking rods should be kept ready<br />

during the entire operation. His obligatory to maintain spare hydraulic<br />

pump aIongwith a set of loose pipes In perfect working condition on<br />

top of working dad(.<br />

11. In sections where thickness Is 500 mm or more it Is prudent It, .;0 if:<br />

for two nos. ofjacks for each sllpfonm yoke,<br />

12. For effective utHity of this technique following areas need careful<br />

attentions at the very conceptual stage :<br />

a) DetaDed quality assurance programme.<br />

b) Advance Planning and preparations.<br />

c) Arrangement for on site supervision and adequate access<br />

'facUities. .<br />

13. Construction methods Including description and types of different<br />

equipment proposed to be used. structural errangement and analysis<br />

of the system, description and type of different materials. planned<br />

(<br />

interruptions, description and frequency of various checks and tests<br />

for Sllpfomn lechnlque as well as for material, method of preparing,<br />

transporting and pouring of concrete, solution for probable defects<br />

(<br />

~,,' 4llring slipping, sequence of operations during planned Interruptions<br />

elc. should be prepared beforehand by executing agency and to be<br />

apprOlled by Engineer before starting the actual ~rk.<br />

14. Pladng and binding of reinforcement is also a very critical item and<br />

needs special attention. From·pmctical·conslderations· not more than<br />

1:.:,,'<br />

two, or three layers of horizontal· Steel


OCPL-K9A01<br />

For movement of personnel supervising the work a seperete hoist<br />

must be arranged for.<br />

17. The system being operative round the clock it is obligatory to have<br />

adequate lighting arrangement both on various platform levels as well<br />

as on ground below. Arrangement has to be made for facilitating<br />

continuous upward movement of the entire system alongwith sllpform,<br />

18. Winches for lifting men and material and mixers, if located within<br />

unnsafe area around chimney, should be protected by adequate<br />

shelter from possible damage.<br />

19. Proper tele-communication system has to be established between<br />

the personnel working on top of Chimney and control room below,<br />

20. A small laboratory should be maintained at site for testing different<br />

materials like cement. coarse and fine aggregates, A cube testing ­<br />

machine may also be installed at site for getting quick feed back<br />

results.<br />

Apart -from using ,plumb bobs, level and theodolite Instruments for<br />

survey purpose arrangement should also be kept for lasers,<br />

21. In case of interruption in the course of Slipping of formwork following<br />

measures should be taken :<br />

. a) Provision of a key and additional reinforcement at the Junction<br />

of new and old concrate,<br />

b) Slipforrn system should be brought up freely to have a<br />

minimum overlap of 100 mm or so oyer previously cast<br />

concrete.<br />

c) Washing of old c:oncrate surface with compressed air and<br />

, water jet and thereafter pouring a layer of neat cement grout.<br />

d) Clearing of shuttering panels of loose materials, concrate etc.<br />

by compressed air and· applying a coat of epoxy paint, if felt<br />

necessary' by. Engineer. . _ .<br />

- e) Neatly finishing the interface of old or new 90ncrate as soon as<br />

It comes out of shuller panel.<br />

22, It is preferable to suspend the construction work und~r high wind<br />

condition,<br />

23.'<br />

It is of utmost importance that for effective impiamentatlon of this<br />

system an Engineer fully conversant with Slipform technique with<br />

enough experiern:e In planning and control of formwork should be In<br />

overall command of the site and he should be ably supported by well<br />

trained mid IeVeisupervisory staff, &killed workers and operators.<br />

(PCA.CD-003,S805CSA24,doc.doc) V.U-02lS-XXIV: 22


(<br />

f<br />

OCPL-K9A01<br />

24. Operation of sllpfonn method of construction Is a continuous one and<br />

it demands continuouslintennediate inspection of accuracies in line,<br />

level, dimensions and position and Immediate rectification of any<br />

noticed delllation. All these ask for personnel of high quality having<br />

constant vigilance over the construction activity.<br />

t<br />

25. While all the activities in effective Implementation of the work needs<br />

utmost care keeping safety of men and material in mind tt Is obligatory<br />

that all activities should be carried out under Ihe. guidance of a<br />

qualified and trained safety Engineer.<br />

Safety measures as listed below must be adhered to but shoul,! ,,,;\<br />

be limited to only thasa :<br />

a) Safety helmets and betts to be provided 10 all supervising staff<br />

and workers. .<br />

b) Safety nels to be provided below both inside and oulside<br />

platforms as instructed by Engineer.<br />

c) Handrailing and 1010 guard 10 be provided around all openings<br />

and platforms. .<br />

d) Regular maintenance of equipmenl, checking of hoists,<br />

scaffoldings etc.<br />

e) Passenger hoist must have muHiple ropes with adeauate<br />

factor of safety.<br />

f) Emergency lights, coloured lamps to be. provided in<br />

(, accordance with relevant Indian Standards' and as<br />

supplemented in Ihe Specification and I!) be operative In case<br />

of sudden power failure Emergency standby generator must<br />

( be kept ready during the enlire period of slipform method 01<br />

construction.<br />

·t~;':.: g) Emergency vehicles; first aid facilities must be kept reedy<br />

.".<br />

duriog .the entire period of Work: .<br />

...<br />

.'<br />

( ,".'- 26. Permissible construction tolerances should be limited to \he following.<br />

'"<br />

(j<br />

t""<br />

Verialion in wall thickness<br />

Variation from Design Diameter<br />

(-) 5 mm,(+) 25 mm<br />


OCPL-K9AOl<br />

3.4.0<br />

3.4.1<br />

steel Flues<br />

General<br />

Fabrication and erec\lon of Steel Flues shall conform to "Technical<br />

Specification for Fabrication and E«ICtion of Structural Steelworks· furnished<br />

in this Specification.<br />

3.4.2<br />

Fabrication<br />

Plates out of which flues will be fabricated, shoukl be bent to the required<br />

shape on an appropriate machine. No smithy process shall be adopted for<br />

the purpose. Plates are to be prevented from distorling by more than the<br />

tolerances specified during tralispollation, storage, handBng, erection and<br />

jointing. All components should be correr,:lly Io


DCPL-K9A01<br />

a) Inlemal diameter shall not<br />

vary by more than '. ±12mm<br />

b) Centre of any section shall nOI<br />

be eccentric from vertical centre<br />

line'by more than<br />

c) Centre of any section at<br />

height 'h' is in mm.<br />

above GL shall<br />

10 mm In any 15 metre<br />

height<br />

(hI2500 + 10 )mm,<br />

Dot be verticat centre<br />

where line by more than<br />

, f.<br />

d) Local deviation from a true circular fonn should not exceed the shell<br />

thid


3.5.2 Cement Paint<br />

OCPL-K9AOl<br />

and ihe drying lime between consecutive coals shall not be less than 5 hours.<br />

The overall combined thickness of paint shall be a minimum of 230 microns.<br />

The outside face of the Chimney shall. unless specified othelWise. shall be<br />

painted with Cement water proof paint. The quality shall be approved by the<br />

Engineer. Necessary samples shall be submitted to the Engineer for his<br />

approval. The sUrfece of the shaH shall be prepared as per paint<br />

manufacturer's specjficalion. In addItion. care shall be taken thai the surface<br />

Is free from stain. honey comb and any rough and uneven surface. The joints<br />

between two shuttering and two lifts of shuttering shall be so prepared that<br />

any uneveness. if by chance exists. shall be removed. If one coat of paint Is<br />

not suffICient to give. the required finish. the Contractor sha. repaint the<br />

surfece. until the engineer is satisfjed with the Workmenship. The paint shall<br />

conform, unless othelWise slated, to 15:5410. Necessary samples, test<br />

certificates and manufacturer's literature shall be submitted.to the Engineer<br />

for approval. . .<br />

3.5.3 Insulation and Packing<br />

AU insulation material should be of dimension and type, shown in the drawing.<br />

Load· bearing insulations at supports and side restraints of Steel liners should<br />

be an assembly of M.S. Plates, Stainless Steel Plates, PTFE (Poly Tetra<br />

Fluoro Ethylene) sheets and or/asbestos fibre reinforr.ed boards (SINOANYO<br />

BLOCKS). Insuliltion to be fIXed on outer surface of steel flues should be<br />

mede of glass or mineral wool.<br />

a) load Bearing Insulation Block<br />

~oad bearing assembly should consist of three units and be fabricated<br />

according to approved drawings. It would be fabricated from mild steel<br />

units with a stainless steel sheet bearing plate and load bearing<br />

insulation blocks as indicated in drawing.<br />

The first unit is bolted to the. supporting beam. 11 consists of a M.S.<br />

base plate with bolt holes on which:a ffiachined M.s. 'plate is welded.<br />

This plate IS. provided with receSs.for .PTFE sheet (conf9rming io. BS :<br />

... 5400) to seal. being lubricaled.with sllicbn grease.'<br />

'.<br />

;.<br />

#<br />

The second unit also consists of a M.S. plate having adequate size &<br />

thickness as shown in drawing. While one surface of the plate is<br />

provided with a stainless steel bearing plate the other surface has a<br />

thin layer of lead! elastomeric sheet. The side having stainless steel<br />

surface is placed on PTFE surface of First unit.<br />

The third unit consists of two layers of load bearing insulation blocks<br />

each having a minimum thickness of 50 mm and factory bonded to<br />

top & bottom M.S. plates. These are separated by 100 nnm. long load<br />

bearing insulation dowels as shown in the drawing. These plates are<br />

In tum welded to two additional M.S. plates. Of the two surfaces thus<br />

(PCA.CQ.OO3.SIlO5CSA24.doc.doc) V.iI-02lS-XXIV : 26<br />


DCPL-K9A01<br />

created one shall be welded to bracket assembly while the other<br />

should rest on the lead sheet of second unit. Bearing assembly, thus<br />

formed, should be levelled by using suHable M.S. shims.<br />

Support afTllngement typically consists of flue support shoe (a part of<br />

flue), flue support bracket connected to the shoe by precision bolted<br />

connection. The bracket in tum Is welded to the bearing assembly,<br />

which in tum is bolted to available supporting beams.<br />

Support brackets and bearing assembly are welded to locally<br />

thickened area of flue. These support ihe flue on support platfrnm at<br />

suitable locations indicated on the drawing.<br />

The arrangement described above should cater for easy and' smooth<br />

thermal mowments of linear element Suitable restraint brackets and<br />

M.S. stop plates need be provided as shown In drawings to prevent<br />

excessive movement and thus keeping different units of bearing<br />

assembly in proper position.<br />

b) lnsulation Block at Lateral Restraints<br />

At flue restraint platforms, necessary restraint arrangement with load<br />

bearing Insulation blocks and stainless steel bearing plates fixed to<br />

the Insulation blocks should be provided as indicated in drawing's.<br />

Restraint and support brackets need be provided for the bottom<br />

supported portion of the flue which rests on the support platform<br />

( provided at the base to cater for bearing and restraint requirements.<br />

{<br />

•( c) Glass or Minerai Wool<br />

Insulation thickness of 65 mm as Is specified in clause 2.05.10 shall<br />

be built up using two (2) layers composed of 40mm and 25 mm thick<br />

insulation blocks. Thicker layer shall be put as first layer around the<br />

flue on its exterior surface .<br />

The insulation on the flue shall be fIXed using Chicken G.1. wire<br />

:~:<br />

mesh,<br />

.' .. G.I. wire .lies, inSulation. retaining' studs, wasti~ etc. 'AIljoints shall <br />

be staggered. The Insulation shall be lightly secured to the exterior <br />

~.<br />

surfaca of the flue by Impaling on the studs and fixing in place by<br />

't~4"<br />

means of 63mm round or square metal plated speed washers: 20<br />

gauge galvanized wire netting shaP be wrepJled continuously over the<br />

(;: entire exterior of insulation. The wire mesh shall be 25mm hexagonal<br />

. pattern conforming to IS:1566. All joints in the mesh shall be tapped a<br />

minimum of 150 mm tied by 16 gauge soft annealed wire at 300 mm<br />

spacings. lacing' at joints shan not be used. The Contractor before<br />

t"<br />

application of Insulation, shall take prior approval of actual fixing<br />

arrangement from the Engineer.<br />

t.<br />

The insulation shalf be able to sustain structural vibrations and shall<br />

not setue under such conditions during erection, construction &<br />

,~~ operation. The Insulation shan be suitably tied to prevent dislocation-",<br />

(PCA.C[)'oo3.Sl105CSA24.doc.doc) V.lI·D2IS-XXIV: 27 .I; I<br />

Ii<br />

4;;'<br />

~~'<br />

335


DCPl-K9A01<br />

under adverse conditions.<br />

The cladding of slafnless steel &heet over the insulation shall be well<br />

SeaJred using pins. fasteners etc.<br />

d) Vermiculite Concrete<br />

VeniliculKe conCtete shall be made by mixing exfofiated verrnicul~e.<br />

portland cement and water. It &flail be of Grade-B. having a density of<br />

210 Kg./Cu.M. The vermiculite aggregate size shall be maximum 6<br />

mm. The mix shall be 1 cement and 8 vermiculite by volume.<br />

3.6.0 Add-Proof/Olemical Resistant Protedlon to Roof Slab .<br />

. AckI-ProofiChemical Resistant tiles· bedded on acid prooflcheinical resistant<br />

mortar shall be provided for the protection of roof slab. The intervening<br />

space between the tiles shall also be filled up by chemical reslstantiacid-proof<br />

epoxy mortar grouts. The. mortar·sha. be used Imrnadiately after mixing.<br />

Jiles shall be made of clay. feldsper or quartz and· vitrified at a high<br />

temperature in


l<br />

':.i.<br />

(<br />

f<br />

DCPl-K9A01<br />

additional safety another inner cover or other approved methods may be<br />

adopted. The manhole cover shall be distinctively coded to indicate the type<br />

of drainage involved.<br />

f<br />

t<br />

·3.6.0 Root Drainage<br />

3.6.1 ·General<br />

3.6.2 Pipe Joints<br />

Inside manholes necesS!lry channels and benchings finished smooth by neat<br />

cement in cement concrete (1:2:4) and foot rungs made from 20mm round<br />

bars at 300mm centres and staggered shOuld be provided. Rungs should<br />

project 100mm from wall face and be embedded 200mm Inside cement<br />

concrete block made In that location of brick work. These foot rests shall be<br />

painted with coal tar in 'the projected portions and cement slurry In the<br />

embedded parl Joint of any pipe with brick work shall be rendered perfectly<br />

leak proof.<br />

Pipes and fittings in the connection pipe to the main drainage system shan be<br />

vitrItIed clayware conforming to relevant IS and laid to the line and level<br />

indicated In the drawi"lls.<br />

Rainwater ouUets and down comers to run along inner face of stack wall. shall be<br />

made of standard cast Iron rainwater pipes confonning to IS:1230. The brackets<br />

used to hold the pipes alongside the walls shall be wrought iron clevis type. split<br />

ring type or of perforated strap fron as approved by the Engineer. Each vertical<br />

pipe shall hang freely on Its bracket fixed just below the socket Suitable spacer<br />

blocks are to be kept in between the pipe and wall surface for fixing the pipe. All<br />

bends and junctions shall be provided with water tight ciean-outs.<br />

All joints between pipes. pipes and fittings and manholes shall be gas-tight<br />

when above ground and water tight when under ground. Method of pipe<br />

cutting and jointing shall be as per instruction of the pipe and fittings<br />

(<br />

manufacturer or as approved by the Engineer. However folloWing guidelines<br />

may be followed in absence of any Instruction available from the<br />

manufacturer.<br />

(~<br />

sOcket arid Spigot 'pipes sh311 be pined'by cast lead jOintS. Spigot of the<br />

following pipe should be centred In the SOCket d the preceding pipe by lightly<br />

t> caulking in suffICIent turns of tarred gasket or hemp yam to have unfiUed half<br />

the depth of SOCket After the gasket or hemp yam has been caulked lightl"<br />

.':,<br />

a jointing ring shall be placed round the barrel and tightened against the face<br />

t···· "/<br />

of the SOCket to prevent air lock. Molten lead shall then be placed round the<br />

barrel and tightened against the face of the socket. Thereafter molten lead<br />

should be poured in to fill the remainder of the .socket and caulked wiltl<br />

;J<br />

suitable tools tight round the joint to malee up for shrinkage of the molten<br />

metal on cooling and should be finished 3mm behind the socket face. If any<br />

Joint Is suspected to be damaged it has to be opened out & redone.<br />

~,<br />

Joints in cast iron pipes with special JOinting arrangements like "Tyton" joints<br />

etc. shalt follow the instructions of the menufacturer.<br />

(4<br />

,:<br />

IJ (PCA.CO-003.S805CSA24.doC.doe) V.lI-D2IS·XXIV: 29<br />

'~ (<br />

, , .


DCPl·K9AOl<br />

3.9.0 Interi1allllumination System<br />

3.9.1 Lighting fixlures.6haII be j!rovided at the ground lloar and at each interior<br />

platform. .<br />

3.9.2 High pressure sodium vapour lamps of 7011501250 Watt rating with suitable<br />

fittings shall be provided under intenial illumination.<br />

3.9.3 Fixtures installed in rows &hall be aligned veriically and horizontally.<br />

3.9.4 All Ighting flXlures 6haII be suitable for 240 V ± 10%. 50 HZ :t: 5%. single<br />

phase. AC Supply.<br />

3.9.5 The following minimum illumination level shall be achieved and guaranteed by<br />

the Contractor : .<br />

Minimum Illumination Level<br />

Ground lloor. Platforms, stalIt:ase,<br />

landings<br />

Area of diff. Dis\, boards<br />

50 Lux<br />

150 lux<br />

3.10.0 ObsIrud.1on Ughtlog System<br />

3.10.1 The Contraclor shaD supply and Insfallthe aviation obstruction lighting system<br />

on the chimney shall consist of the following items :<br />

a) 4 sets of single obstruction Ilghl!l with fIXtures at each floor level.<br />

b) Complete G.I. conduits, PVC insulated wires, G.I. grounding conductor,<br />

weatherproof outdoor juootlon box and aD accessories viz. supports,<br />

damps, junction boxes, etc. to make the installation complete In aM<br />

respects<br />

3.10:1 Aviation obstriJction lighting system shaD conform 10 the requirements of the<br />

lateiIllndian Standard. the Intemational Civil Aviation organisation (ICAO), the<br />

inSlnx:lioil ismied bY theOlreclcf . Genenll . of ;clvH AviatIoo.oJndi" . and th~<br />

Directoratii of Air'Routeir& Aerodromes' (DARA) ciroularNo, 3 of '987.<br />

3.10.2 The obstruction lights shall be provided at the levels indicated in the drawing.<br />

3.10,3 All aviation obstruction lights at EL (+) 150 M and above shall be high intensity<br />

llashing white light having an effective Intensity of not less than 4000 candelas.<br />

The flash frequency shall be between 4O-6OImin.<br />

. .<br />

3.10.4 All aviation obstruction lights below EL. 150 M shall be medium intensity llashlng<br />

red light having an effective intensity of not less than 1500 candel"s. The IIMh<br />

frequency SMII be 4O-G0imin.<br />

(PCA.CO-()03.S80SCSA24.d"",doc) V.1I-D2IS·XXIV : 30<br />

838<br />

"'


DCPL-K9A01<br />

3.10.5 All avialion fixtures and accessories shaa be weatherproof, outdoor type<br />

capable of withstanding highly humid and flue-laden almO$phere and generally<br />

conforming to degree of protection IPW-55.<br />

3.10.6 Obstruction lighting system shaU be operated by the Contractor for not less<br />

lhan 60 days. Equipment and work which fails during the test period shall be<br />

repaired or replaced. System performance win be considered satisfactory when<br />

the obstruction rtghting system has operated continuously for a period of at<br />

least sixty (60) days.<br />

3.11.0 Temporary Obstrud:lon lighting<br />

3.11.1 Temporary obstruction lighting shall be provided by the Contractor during<br />

construdlon. Obstruction lights shan be provided at the uppermost part of the<br />

stack or the SUtTOUnding scaffolding as constructiOn proceeds upwants. As<br />

such level spedfied to have permanent obstruction fights Is passed, that level<br />

shall be provided with temporary lighting: For. Temporary obstruction l.ighting.<br />

fixture as per G!§C catalogue "2A750 (l) neon" shaD be used.<br />

3.11.2 Power for operation. of the temporary obstruCtion right shall be obtaineti from<br />

the Construction Power System. Supply circuit for these lights shall be<br />

furnished. installed and maintained by the Contractor.<br />

3.11.3 The temporary ob$Iruction Dghting system shall be operated & maintained by<br />

the Contractor from Sun set to Sun rise. tnl pennanent obstruction Lighting<br />

system is Installed and commissioned.<br />

( 3.11.4 Contractor shall supply six (6) nos. lighting fixtures simftar to the type used by<br />

him for Temporary Obstruction Lighting for Client's use in the event of outage,<br />

if any, of Pennanent Obstruction' lighting fIXtures.<br />

(<br />

3.12.0 Wiring<br />

( 3.12.1 Wires for lightirlg system shaH be PVC insulated. 650 V Ilrade.<br />

l:·"<br />

(.<br />

3.12.2 WIIl!S shall be run in GI conduits suitable for outdOOr installation., Maximum<br />

conduit fill shall be asfollOW$ :<br />

Cable Size<br />

Conduit Size<br />

20 rom 25 mm 32 mm 40 mm 50 Ill'"<br />

If<br />

a) 2.5 Sq. mm Cu 3 5 9<br />

ti<br />

1;', '<br />

...:r<br />

(;<br />

• e<br />

b) 10.0 Sq. mm AI 2 5 7 8<br />

Maximum no. of COJIductors admissible for<br />

conduit<br />

Suitable pull boxes shall be provided at convenient locations.<br />

(PCA.CD.Q03.StlO5CSA24.doc.doc) V.II-D2IS-XXIV: 31<br />

, 339


DCPL·K9A01<br />

3.12.3 lighting fixtures. conduits and junction boxes shall be properly earthed using<br />

galvan~ wire of 14 SWG. Earth wire wiD run along the entire length of the<br />

condult between fixtwes and lighting panels. lighting panels Will be connected<br />

to the grounding system.<br />

3.13.0 Ughtning Protection System<br />

3.13.1 ~I<br />

3.13.2 Air Termlnals<br />

. "<br />

The fighlning protection system to be Installed on the flue duct by the<br />

Contractor shaU be strictly as per specifIcsIioos and shaR satisfy the folloWing<br />

requirements.<br />

The ,flue shall be provided IIIIIth pointed air \enninals uniformly distributed along<br />

the top rim of )he flue. The projected length of the air terminals above the top of<br />

the flue shaU nol be less than 1000 mm. The air terminals shaH be made of lead<br />

coated solid copper rods having a minimum diameter of 20 mm.<br />

3.13,3 Down Conductors<br />

3.14.0 Grounding ,<br />

There WiU be two separate system of varfical down conductors of 50 x 6 mm<br />

Ilats. S(lBI:ed as shown in the drawings. One system. envisaged for lightning<br />

protection. II1II11 have two numbers of down conductors per flue duct starting<br />

from • the top enclreling band leading to the ground: The other system.<br />

envisaged tor earthing of various electrical equipment etc. on the stack. Will<br />

also !lave ground conductors'originating below the platform and leading to<br />

ground.<br />

The connections of the galvanized steel down conductors tQ the nearast<br />

grou,nding grid at the bottom shaH be arc welded. Connection between any two<br />

galvanized steel fIaIs/l)ands shaA be made by arc welding.<br />

A suitable boiled test piece shall be provided at each down conductors at a<br />

convenient height near the bottom of the stack. The galvanization of steel flat<br />

sheH be~at least 610 gmper aq.mIt. of Zinc and m\lSicon1ply with 184759.<br />

3.14.1 Grounding system shaft Include complete grounding for stack electrical<br />

equipment. non current carrying metallic parts including a buried grid around<br />

the stack. All grounding materials shall be suppl'led aod Installed In accordance<br />

with the reterence codes and standards. this SpecifICation and the draWings.<br />

3.14.2 Grounding materials required shall be furnished new and undamaged in<br />

accOrdance with the following requirEments:<br />

i). Grounding EJectrodas 40 rnm diameter 3 metre long<br />

mild steel rods.<br />

(PCA.CO-OO3.S805CSA24.dac.doc) V.II·D2IS-XXIV : 32


!<br />

OCPL-K9A01<br />

ii) Ground Conductor 40 mm diameter mild steel rod.<br />

(<br />

iii) Distribution Boards 50 x 6 mm GS Flat<br />

-<br />

iv) Lighting Panels, Local panels 35 x6mmGS Flat<br />

v) Push Button Station Junction 8SWGGlWire<br />

Box etc.<br />

Distribution Boards<br />

3.15.1 The following distnbution boards have been enVisaged :<br />

a) One (1) No. 415 V AC Distribution Board located at Ground level having<br />

2 Nos. 415 V, 3 ph, 4 wire incamers & castle-key interlock to prevent<br />

paralleling of two supplies. ThiS Distribution Board shall feed two (2)<br />

Nos..L1ghting Distribution Boards.and 63 Amps Receptacles.<br />

b) One (1) No. 415 V AC Emergency Distribution Board located at Ground<br />

level from which emergency supply for staircase and platform lighting of<br />

stack, elevator and aviation lighting panel shall be taken.<br />

This emergency distribution board shall be fed from two different<br />

serVices - one from the above mentioned 415 V AC Nonnal distribution<br />

board and the other from Owne(s 415 V AC e(T1ergency switchgearl<br />

MCC through one 415 V, o"n11 dry type transformer. On failure of<br />

nonnal AC supply, the emergency power will take over by means 01<br />

4 automatic switching.<br />

c) One (1) No.Avtation lighting Panel located suitably from which supply<br />

t<br />

to aviation lights at different elevations have been taken through<br />

conduits. .<br />

t<br />

d) Lighting Distribution Board No. 1 at Ground level shall feed all stairoase<br />

lights and platforms inside staCk upto-IooNer middle half of the stack.<br />

t,<br />

. e) Lighting Distributiol) Board No. 2 suit8b1y·locatedshall feed all staircase<br />

(.<br />

lights and platform at remslning upper portion ofthe stade<br />

(: All bought out electrical equipment shall be from reputed manufacturers who<br />

have manufactured and supp6ed equipment of the type & rating specified and<br />

these equlpments shall have been in successful operation in power plants for at<br />

least three (3) years.<br />

l<br />

t<br />

.::-~<br />

c';>~<br />

~<br />

Ci <br />

3.16.2 . The Contractor shall design and prepare detaUed drawings of various electrical<br />

system like Power distribution arrangement, lighting, lightning protection<br />

grounding system etc. and shall submit the same to the OwnerfConsul fot<br />

their review approval.<br />

(PCACO-OO3.se05CSA24.doe.doc) V.lI-D2fS-XXIV : 33<br />

341


DCPL·K9A01<br />

4.0.0 TESTING AND ACCEPTANCE CRITERIA<br />

4.1.0 General<br />

4.2.0 Cement<br />

4.3.0 VVater<br />

4.4.0 Concrete<br />

The Contractor shall cany out aU sampling end testing in accordance with the<br />

relevant IS SpeCifications and as supplemented herein, for the following items<br />

or any other item as may be required by the Engineer unless otharwise<br />

specified in this specification. Tha Contractor shall get the specimens tested<br />

in labolatofy. approved by the Engioeer and shall submit to him, the original<br />

test results in triplicate, within seven days after the completion of the test.<br />

Engineer may present himself while such tests are being carried out.<br />

Representative samples shall be tAken as per the relevant IS SpecifICation<br />

from each consignment of Cement received from the<br />

PurchaserlManufacturerlSupplier for canying out the tests for fineness (by<br />

hand sieving), setting time, compressive strength and soundn~ss tests, and<br />

the Contractor shall cany out the. above tests as per relevant Indian<br />

Standard. If the cement Is suppfled by the Contractor the test shan be carried<br />

out by him. The Contractor shaD cany oljt any or aU the tests on aggregates<br />

as may be required by the Engineer, in accordance with IS:2386 Parts-I to<br />

VIII. The aoceptance crfteria of the samples tested shall be in accordance<br />

withthe requlremenis of the relevant IS specifications..<br />

Sampling and testing of water being used for concrete works shall be carried<br />

out as per IS:3550, by the Contractor, at regular Intervals and whenever<br />

directed by the Engineer. ThiI final acc;eptance crfterion In case of doubt<br />

shan be as per IS:3025.<br />

The Contractor shall take cubes for worXs test as per requirement laid down<br />

,.<br />

in 1$:516 regularly from the day's pour. The.number of test cubes to be taken<br />

~.<br />

.. sheU be. as per 15:456. The. Engineer may also ~ his discretion In deciding .<br />

,.<br />

the rate of cubeS' to be: taken. The. aeeeptance criteria is 'to meet tlie<br />

~~< requirement of 15:456. If the cube test results indicate that some portions or<br />

the work is below the required strength, the Engioeer may order demolition of<br />

f<br />

that portion of work which is below strength and ask the Contractor to<br />

'1<br />

;:. rebuild, provided e satisfactory method of load testing Is not possible. Such<br />

{ testing or demolishing and rebuilding shall be carried out by the Contractor.<br />

?,.<br />

:1<br />

4.5.0 Steel Rue<br />

All site and shop welded joints shaH be inspected and tested in accordance<br />

.£<br />

.: $1<br />

"'<br />

,.<br />

i<br />

I<br />

F:<br />

."<br />

with clause 4.00.00 of Technical specification for Feb. and Eraction of<br />

structural steel work.<br />

(PCACO-OO3.S805CSA24.doc.doc) V.U..o2lS-XXIV : 34<br />

8~2 :..<br />

." I. l'


4.6.0 Insulations<br />

DCPL-K9A01<br />

The Insulating materials shall be tested for its stipulated characteristics and<br />

properties In accordance with the latest editions of IS:3144 and IS:3346<br />

andlor as directed by the Engineer.<br />

(' <br />

5.0.0 INFORMATION TO BE SUBMllTED<br />

5.1.0 WlthTender<br />

.~<br />

a)<br />

The following technical Information are required with the tender. <br />

Source and arrangement of processing of aggregates proposed to be<br />

adopted.<br />

b) Type of plant and equipment proposed to be used.<br />

c) Names of firms with which association is sought for to execute the<br />

special Hems of work e.g. nue expansion dlmpensator, load bearing<br />

insulation blocks etc. in the contract. .<br />

d) Types of formwork proposed to be used. All details as per clause no.<br />

3.03.!l6 to be submitted, if slip form method is proposed to be used.<br />

.<br />

-~ e) Shop proposed for fabrication of steel (Rue) liners. Detailed write-up<br />

on procedure of-erection of complete liner system including details of<br />

equipment proposed for the same.<br />

f) For insulating material tests to be offered for inspection & tests for<br />

which test certifICates will be submitted. A drawing showing the<br />

( details of fixing insulation on the nues at bearings, lateral restraints<br />

,<br />

and exterior surface.<br />

(<br />

g) Proposal for lifting of men and material in constructing the chimney.<br />

5.2.0 After Award<br />

.The f


5:2.2 Samples<br />

5,2.3 Deslfin Mix<br />

OCPL-K9A01<br />

The master programme may have to be reviewed and updated by the<br />

Contractor quarterly or at more frequent intervals as may be directed by the<br />

Engineer depending on the exegencles of the work.<br />

Oetalled day to day programme of every month is to be submitted by the<br />

Contractor betore the commencement ot the month.<br />

Samples ot aU materials proposed to be used shall be submitted as directed<br />

by the Engineer, in sufficient quantities. tor approval. All samples shall be<br />

submitted _II In advance of starting work at site. Approved samples wilt be<br />

preserved by tha Engineer for tuture reference. The approval ot the Engineer<br />

shall not, in any _y, relieve the Contractor of his responsibility ot supplying<br />

materiaI'ot specified quaQty.<br />

Design mix as per details of this specifICation giving proportions" ot<br />

ingredients, sources ot aggregates and cement along with accompanying test<br />

results of trial mixes as per relevant IS Specifications shall be submitted to<br />

the Engineer, for his approval, before it can be used on the work.<br />

5.2.4 Detail Drawings<br />

Following items shall be provided by the Contractor which are to be approved<br />

by lIle OWner and Consultant.<br />

a) Detail drawings and destgns of torm work includin9 scaffolding to be<br />

used. If sllpform method of construction is adopted. then detail<br />

drawings showing all the arrangements for slipform technique<br />

including methods tor reducing Internal diameter and providing<br />

raquired slopes on outer diameter.<br />

b) Detail drawings and bar bending schedules for concrete components.<br />

c) Shop drawings forstructunll.steel and 'metai work. including inserts<br />

'. etc. The Contractor shan submit his proposal for testing site and shop<br />

. joints provided insteel·lilembenI. ....... . ' ...<br />

d) Detail drawings for templates and temporary supports tor<br />

embedments.<br />

e) Category wise raql,lirements of MS, tor and structural steel including<br />

GI fiats of various sizes for procurement.<br />

f} Detailed drawings of steel llues indicating details of joints, supports<br />

and restraints including insulation blocks. and details of expansion<br />

compensator.<br />

g} Detailed drawing of hoisting arrangement tor men and material<br />

satisfying statutory regulations laid down tor safety purpose.<br />

(l'CA.C0.()()3.S80SCSA24,doc.doe) V.lI·02l5-XXIV : 36 .<br />

" ('


{<br />

DCPL·K9A01<br />

5.2.5 Reports<br />

Following Test Reports shall be furnished by the Contractor:<br />

a) Mill Test Report for cement and reinforcing steel If Ihe materials are<br />

supplied by the Contractor.<br />

b) Inspection Report of bought ouillems.<br />

c) Inspedlon Report of formworl< and reinforcemenl, insulations ..Ie,<br />

d) Reports of tests of various malerial and concrete.<br />

e) Radiographic lests on welded joints in steel flues.<br />

d) Any other data or report or test result required by the relevant IS<br />

SpecifICations and if required by the Engineer for satisfactory Quafity<br />

control of the worl


VOLUME : II-D/2<br />

ANNEXURE B


OCPL-K9AOI <br />

CONTENT<br />

aAUSENO. DESCRIPTION PAGE NO.<br />

1.00.00 GENERAL V.U-02IS-XIX : 1 <br />

2.00.00 .PRODUCTS V.U-02lS-XIX : 2 <br />

3.00.00 DOUBLE SKIN INSULATED METAL V.II-D21S-XIX : 4 <br />

-CLADDING <br />

4.00.00 EXECUTION V.II-D2I5-XIX ; 4 <br />

268<br />

(PCA.CQ.OO3.Sap5CSA19.doc)


OCPL·K9A01 <br />

VOLUME: II-D/2 <br />

SECTION·XIX <br />

TECHNICAL SPEC<strong>IF</strong>ICATION <br />

FOR <br />

SANDWICH METAL ClADDING <br />

1.00.00 GENERAL<br />

1.01.00 . Description<br />

{<br />

,. <br />

t <br />

{ <br />

tv <br />

f <br />

t·; <br />


DCPL-K9AOl<br />

iii) Fabricated sandwich melal cladding. Sample size shall be 300<br />

x 300 mm three nos.<br />

iv)<br />

Edge r;eaJing and flashing.<br />

b) Manufacture~s literature indicating the nature of preformed profiled,<br />

colour coating. manufacturer's recommended Installation, Instructions<br />

and maintenanca procedure.<br />

c) Manufacturer's certifICation of compliance with each delivery.<br />

d) Shop Drawings<br />

Showing fabrication details of sandwich/double skin metal cladding<br />

with Insulation, preformed sheet profde and total colour thickness for<br />

profiled top skin and slighlly ribbed bottom skin. thickness and nature<br />

of insulation. inslallationand erection; anchorage. fasteners and<br />

details of acoassories. metal flashing and its fixing including various<br />

openings for doors. windows,louvres, pipes etc,<br />

•<br />

1.03.02<br />

Test Reports<br />

Two copies ofTest Reports and Souroa of Quafity Control Tests.<br />

1.03.03<br />

Supplier Ceitlftcates<br />

Two copies of tedlnic:al data showing that the proposed finish product is<br />

suitabre for the environmental conditions ofthe job site and that the materials<br />

meet specific:ation requirements.<br />

1.04.00<br />

1.04.01<br />

Product Handling<br />

Delivery of Materials to Job site In manufactur~s<br />

packaging .<br />

original unopened<br />

1.04.Q2<br />

1.04.03<br />

. Identify contents with /lame of,mimufacturer. brand name, thermal value and<br />

.appllaitile siandllt'd. .<br />

" ., .....<br />

Store materials In an area protected from adverse ctimStic conditions.<br />

,moisture and open flame or spark and shall be stored off the ground with one<br />

end elevated for drainage. The sheets shall be protected from inclement<br />

weather with a waterproof covering with ventilation to avoid condensation.<br />

2.00.00<br />

2.01.00<br />

Ull.01<br />

PRODUCTS<br />

General<br />

All goods and products covered by these specifications shall be procured<br />

from manufacturer duly approved by the owner<br />

(PCA,CI).OO3.S805CSA19.docl V.tI-02IS-XIX : 2<br />

.' .<br />

270


DCPL·K9A01<br />

2.01.02<br />

2.01.03<br />

2.01.04<br />

Roof insulation shall have a ·mlnlmum R-velue of 2:083 M" "KiWatt.<br />

Thickness of sandwich cladding shall be as required to meet the specified<br />

"R"values. .<br />

Sandwich material shan be of "Rib and Flute" design to ensure wide spanning<br />

and quick recovery after being subjected to excessive load. Double skin<br />

materials shall be interlocking type 150mm wide strip and inner sheet shall be<br />

mild rib & flute type profile to ensure quick recovery after being subjected to<br />

excessive load.<br />

Matel1al<br />

t<br />

t<br />

t <br />

l


DCPL-K9AOl<br />

3.00.00<br />

3.01.00<br />

3.01.01<br />

3.01.02<br />

DOUBu: SKIN INSULAlE> METAL a.ADOING<br />

General<br />

Metal cladding may be of double skin separated by an approved insulation <br />

in between. External sheet shall be of in,terlocklng type. <br />

Double skin wall cladding shaH be comprising ofl50F external panels<br />

manufactured out of 0.6 mm TCT (TomJ coated thickness) aluminium alloy<br />

AA310515050 with stove enameled coil coaled finish, sufficient to withstand<br />

most aggressive climate. on both sides of approved shade. The 150mm wide<br />

panels (150F) shall be clipped on 10 the concealed runners and shall be<br />

interlocked with e8!fi other. The inner sheelingshall be Hi Rib 0.5mm TCT<br />

siuoon modified polyesler coated galvalume steel (AZ-l5Q gsm aluminium­<br />

Zinc alloy metal metallic coaling of total 550 Mpa yield stress as per AS-<br />

1397).The extemal panels shall be 1S0mm wide 17mm deep. The inner sheet<br />

shall have 1000-1020 mm cover width 28-30. mm high crests @2S0-25Smm ,<br />

cJc with side laps. The Inner sheet shall be fixed to structural system by<br />

means of corrosion projected ,\IeIf-drilU!lg. Self-tapping fasteners. The· sub<br />

girts of size 5Ommx50mmx50mm manufactured out of 16 G G.I (1.6mm) 'Z'<br />

shape shall be fixed 10 inner sheeting on face side at purune locations. The<br />

external panels shaH I?e fixed with the help of concealed runners 34.5 wide<br />

x48mm deep ou1 of 0.95 mm thick atuminlum strip with cut outs to hold the<br />

panels In a module of 150mm al1600mm clc and fastened on side girts. The<br />

runners shall be concealed and no fasteners are to penetrate the panels. An<br />

insulation of 50mm thick resin bonded fiberglass roll Insulation .of density<br />

16kg/m s shSll be fixed In \he cevity between two sheets. Contractor shall<br />

make cut oul of doors, windows. louvres. pipe. ducts or other cut outs as<br />

reqUIred as per contract drawings along with flashing. leak proof sealing etc<br />

as required for these cut outslwall openings.<br />

4.09.00<br />

4.01.00<br />

'·4.01'.!)1<br />

4.01.02<br />

4.02.00<br />

·, 4.02.01<br />

4.02.02<br />

EXEOJTION<br />

. Inspection<br />

the .:ontraetor iIhali exernlile UJe area. wtiiilh will be covered; lindlhe· <br />

masOnry wall where the edge of the s8ndwichldouble skin cladding will be <br />

fixed and the structural alignments. <br />

Contractor shall correct any unsatisfactory cond~ions prior to start of work.<br />

Installation<br />

Sandwich panel shail be fixed over structural members with jOints overlapped <br />

and· fastened using stainless steel fasteners self-drilling type or as <br />

reccmmended by the manufacturer. <br />

Double skin wall cladding shaU be installed slriclly as per manufacturer <br />

specifICation and details. <br />

V.II-D2IS-XIX : 4<br />

272


f· <br />

DCPl-K9A01<br />

4.02.03 All ~nd laps of profiled sheeling and jOints of fiashing shall be /jealed properly<br />

wffh non-hardening natural cure smcon sealant or as recommended bV the<br />

manufacturer. .<br />

4.02.04 Accessorles like fasteners, tape, and foam fillers, flashing etc. as required<br />

shall be provided as per recommendation of manufacturer.<br />

4.03.00 Oean-lJp<br />

Remove sealant splatters and smears remove steel particles generated by<br />

drilling to avoid damage.<br />

t -.<br />

,,-." •••<br />

\i<br />

·e::<br />

.~,;-<br />

,,­<br />

L'<br />

(.<br />

t<br />

r ...<br />

~~.<br />

{.,<br />

c<br />

(PCAC()"oo3.S80SCSA19.doe) V.I!..o2lS-XIX : 5 273


TITLE: 1X250 MW EXTENSION UNIT-8 AT<br />

DURGAPUR PROJECTS POWER STATION<br />

SPEC<strong>IF</strong>ICATION FOR ELECTRICAL WORKS<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-360-620-C001<br />

VOLUME - II B<br />

SECTION - D SUB SECTION :II<br />

REV.NO. 0<br />

SHEET<br />

OF<br />

THE DURGAPUR PROJECTS<br />

LIMITED<br />

DURGAPUR PROJECTS POWER STATION<br />

1 x 250 MW EXTENSION UNIT- 8<br />

VOLUME – II B<br />

SECTION – D<br />

SUB SECTION II<br />

<br />

<br />

Bharat Heavy Electricals Limited<br />

Project Engineering Management<br />

PPEI Building, Power Sector,<br />

Plot No. 25, Sector 16A,<br />

Noida (U.P.)-201301


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

1.0 GENERAL<br />

1.1 This section includes the design, fabrica tion, supply, installation and testing of<br />

Lightning Protection system for the Chim ney(s). The requirem ents of this specification<br />

shall be complied with in relation to the requirements set out in Data Sheet-A & Section-<br />

C.<br />

1.2 The contractor’s scope, besides m aterial s upply shall include com plete installation of<br />

Lightning Protection System , protective coating application, and testing of the system .<br />

All m aterials, consum ables, erection equipm ent etc. as required for the com pletion of<br />

installation and testing facilities shall be supplied.<br />

2.0 CODES & STANDARDS<br />

2.1 The latest revisions of the following codes & standards shall be applicable:<br />

IS:2309 Code of practice for protection of bu ildings & allied structures against<br />

lightning.<br />

IS:3043 Code of Practice for earthing<br />

IS:4759<br />

Hot-dipped galvanised coating on structural steel<br />

IS:2629<br />

Recommended practice for Hot-dipped galvanising for Iron & Steel.<br />

IS:2633<br />

Methods of Testing Uniformity of Coating on zinc-coated Articles.<br />

IS:1731<br />

Dimensions for Steel flats for structural & General Engineering Purposes.<br />

IS:1752<br />

Electroplated Coatings of Cadmium on Iron & Steel<br />

Indian Electricity Rules, 1956,<br />

Indian Electricity Act, 1960.<br />

IS:4990(Part-I) Criteria for Design of Reinforced concrete Chimney.<br />

3.0 DESIGN REQUIREMENTS<br />

3.1 Lightning Protection system for the chim ney shall consist of air-term ination network<br />

comprising requisite num ber of vertical coppe r rods, 20m m in dia, projecting at least<br />

1000mm above the top of the chim ney and th e flues, spaced uniform ly along the top<br />

periphery of the outer shell of the Chim ney and that of the flues. A ring of 75x6m m GI<br />

strip shall be laid along the top periphery of the flues and the Chim ney, form ing the


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

annular horizontal air term inations. The vertical air term inations shall be electrically<br />

connected (Brazed) to the horizontal air term inations, the vertical term ination of the<br />

flues and those of the Chim ney to the hor izontal term ination of the Chim ney. The<br />

vertical terminations shall be spaced not more than 3m apart from each other.<br />

3.2 The air term inations shall be secured to the top of Chim ney top by an arrangem ent of<br />

substantially strong construction to withstand high wind pressure prevalent in the area<br />

commensurate with the height involved. A ll m aterials for the securing arrangem ent<br />

shall be of the sam e grade as the conductors and must be galvanised. The vertical air<br />

terminals at the top of the shell shall also be secured to the guard ring at the top of the<br />

shell.<br />

3.3 A minimum of two num bers of equally spaced conductors, each consisting of 50x6m m<br />

GI strip, shall be brought down from their connecting points on the annular rings at the<br />

top of the Chim ney/flues. The down-conductors originating at the top of the flues shall<br />

be brought down along the walls of the flues a nd electrically connected (welded) to the<br />

annular ring at the top of the outer sh ell of the Chim ney. The down conductors<br />

(minimum two num bers) from the chim ney top shall be brought down to the bottom of<br />

the Chimney all along the exterior Chimney wall.<br />

3.4 A test link of copper black/phosphor bronze gunm etal bolted to the conductor for the<br />

purpose of isolation & testing shall be provided on each down conductor 1000mm above<br />

ground level.<br />

3.5 Down conductors shall be cleated to the wall at an interval of 1500m m all along the<br />

length of the Chimney.<br />

3.6 Down conductors near ground level shall be protected against m echanical injuries by<br />

means of wood-m oulding or non-m etallic cove r. A rem ovable cover of the sam e<br />

material shall be provided over the test- link for easy access.<br />

3.7 The connection between the downconductor from the test link onwards upto an annular<br />

ring of galvanised steel running around the en tire periphery of the chimney bottom shall<br />

be provided through risers which shall be of 40mm dia MS rods.<br />

3.8 The risers shall be term inated on the annular ring of 40m m dia MS rod running around<br />

the periphery of the chim ney buried 1 m etre deep in the ground and clearing all<br />

foundation by at least 2 metres.<br />

3.9 From the term ination points of the downconductors on to this underground ring, m ild<br />

steel rods shall terminate at test pits complete with test-links and electrodes.<br />

3.10 The test pits at para 3.9 shall in turn be connected to the m ain earthmat of the power<br />

house through 40mm dia MS rod.<br />

3.11 All joints, except for testing purposes, shall be welded type lap joints with an overlap of<br />

100mm. The welding shall be com plete around the joint and not tack welded. Electric<br />

arc welding shall be used for all joints.<br />

3.12 After welding, two coats of anti-corrosive (red-oxide) paint followed by a coat of<br />

bituminous paint shall be applied to each joint.<br />

3.13 The 40m m dia MS rods shall be protected against corrosion by applying a coat of<br />

barium chromate paint and two coats of bitumen below the test link.


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

3.14 The com plete lightning protection system arrangem ent including air-term inations,<br />

conductors, connections, fittings etc. and m aterials located on the exterior within 10m<br />

from the top of the chimney shall have lead coating of 2.0mm thickness.<br />

3.15 All exposed m etal structures such as ha nd rails, platform s, ladders/stairs shall be<br />

connected to the downconductors through earthing band rings, of 50x6m m GI strip<br />

located 2000mm above each platform . Ladders and platforms shall be bonded together<br />

for electrical continuity. A strip of 25x3 mm GI shall be used for connection between<br />

equipment and earthing band rings. Similarly, all lighting fixtures shall be earthed.<br />

3.16 Temporary lightning protection system shall have to be provided and m aintained during<br />

the construction of chimney or till f inal lightning protection system is installed by the<br />

contractor free of cost and in line with IS:4998(Part-I).<br />

3.17 For general reference and guidance, Below Ground Earthing Typical Details drg.no.<br />

PE-DG-XXX-509-0004 & drg.no.PE-DG-XXX-509-003 may be used.<br />

4.0 GALVANISING<br />

4.1 All steel strips and m aterials requiring ga lvanisation shall be hot-dip galvanised<br />

according the IS:2629 & IS:4759. Galvanising shall be done at a place where<br />

galvanising and testing facilities conforming to the relevant Indian Standards exist. The<br />

galvanising shall be sm ooth, clean, uniform , continuous & free from acid spots. The<br />

thickness of zinc deposit at any spot shall not be less than 75 m icrons. The purchaser<br />

reserves the right to m easure the thickness of zinc deposit and reject any com ponent<br />

which shows thickness of zinc at any loca tion less than 75 m icrons. Should the<br />

galvanising of the sample be found defective, the entire batch of the steel will have to be<br />

re-galvanised at the seller’s cost.<br />

4.2 All nuts, bolts and washers, wherever used, shall be cadmium coated or zinc passivated,<br />

the thickness of plating conforming to the relevant Indian Standards.<br />

5.0 INSPECTION & TESTING<br />

5.1 The following stages of manufacture/installation shall be stage inspected by purchaser or<br />

his duly authorised representative:<br />

5.1.1 Inspection of all material such as vertical ai r terminals, steel strips, electrodes, test links<br />

including hardware items such as bolts, nuts etc.<br />

5.1.2 Inspection of m anufacturing processes su ch as shearing, punching, beinding, welding,<br />

galvanising, painting etc.<br />

5.1.3 Inspection of installation procedures<br />

The actual inspection will be carried out as per the agreed Quality Plan.<br />

5.2 TESTING<br />

5.2.1 The supplier shall perform all tests nece ssary to ensure that the m aterial and<br />

workmanship conform to relevant standard s and that such tests are adequate to


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

demonstrate that the equipm ent shall co mply with the requirem ents of this<br />

specification.<br />

5.2.2 The tolerance in dimensions shall be in accordance with appropriate Indian Standards.<br />

5.2.3 Forged steel below 10mm thick is subject to Magnetic Particle Testing.<br />

6.0 DRAWINGS, DATA & DOCUMENTS<br />

6.1 Data sheet-A of this specification gives th e details of m aterials to be used for the<br />

Lightning Protection system for Chimney.<br />

6.2 The tenderer shall subm it his design(s) a nd drawings for Dir ect stroke Lightning<br />

Protection System of Chimneys for purchaser’s evaluation/scrutiny and approval.<br />

6.3 The contractor shall furnish his design(s) and installation drawings for approval.<br />

6.4 The contractor shall furnish the requisite num ber of prints & RTF’s of all drawings as<br />

specified elsewhere in this specification.<br />

6.5 The site modifications/deviations shall be m arked on the latest revision of the drawings<br />

& submitted as ‘As Built’ drawings to the purchaser after completion of installation.<br />

6.6 Tenderer shall submit all filled up schedules as per <strong>Volume</strong>-III.<br />

6.7 The tenderer shall subm it reports on Type tests & Special tests conducted on lightning<br />

protection materials & accessories.<br />

7.0 COMPLETENESS<br />

7.1 The offer for supply and erection shall be co mplete in all respects & shall include all<br />

materials, tools and appliances, whether speci fied or not, required for the com pletion of<br />

the job.<br />

7.2 Supply/arrangements of all accessories and material etc. shall be the responsibility of the<br />

contractor.


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENTS<br />

MATERIALS & SIZES<br />

The following are the m inimum sizes of m aterial to be used for lightning protection<br />

system:<br />

S.No. Material<br />

Minimum Size<br />

1. COPPER RODS (Lead Coated)(for vertical air<br />

Terminations projecting 1000mm above the Chimney/<br />

flues)<br />

20mm dia<br />

2. GI STRIP<br />

(for annular horizontal band ring at the top of the<br />

Chimney/flues) 75x6m m<br />

3. GI STRIP<br />

(for downconductor) 50x6m m<br />

4. GI STRIP<br />

(for earthing band ring each platform)<br />

50x6mm<br />

5. MS ROD<br />

(for risers) 40m m dia<br />

6. TEST LINK<br />

com<br />

patible with size at<br />

Sl.No.3<br />

& 5 above<br />

7. MS ROD<br />

(for annular ring buried 1 metre in the ground around<br />

the chimney) 40m m dia<br />

8. MS ROD<br />

(for electrodes) with Test Pits<br />

40mm dia<br />

9. MS ROD<br />

(for connection between test pit and customer’s<br />

earthmat)<br />

40mm dia<br />

10. GI STRIP/WIRE<br />

(for connection between equipment and earthing<br />

band rings) 25x3m m/As required<br />

1.0 GUARANTEED TECHNICAL PARTICULARS:


TITLE SPEC<strong>IF</strong>ICATION NO. PES-509-02A<br />

LIGHTNING PROTECTION &EARTHING<br />

OF CHIMNEY<br />

(SUPPLY & INSTALLATION)<br />

VOLUME<br />

II B<br />

SECTION<br />

D<br />

REV NO. 0 DATE 08.02.2002<br />

SHEET 3 OF 4<br />

The tenderer shall fill up and submit the following technical particulars:<br />

1.01 Name of Manufacturer :<br />

1.02 Place and country of Manufacture :<br />

1.03 Standards applicable :<br />

i/ For materials & sizes :<br />

ii/ For galvanisation/Electroplated coating :<br />

iii/ For testing uniformity of Galvanization :<br />

iv/ For code of practice :<br />

v/ For hexagonal bolts, nuts washers :<br />

vi/ For welding :<br />

1.04 Thickness of galvanizing on steel :<br />

1.05 Thickness of Electriplated coatings :<br />

1.06 Thickness of Lend coating on copper :<br />

1.07 Materials and sizes offered :<br />

i/ Below ground conductor :<br />

ii/ Electrodes :<br />

iii/ Risers :<br />

iv/ Down Conductors :<br />

v/ Air terminations (Vertical) :<br />

vi/ Air termination (Horizontal) :<br />

vii/ Test Pits :<br />

viii/ Test Links :<br />

1.08 Whether all type test certificates furnished<br />

1.09 Whether all schedules of Vol.III filled up and submitted.


TITLE:<br />

LIGHTING NOTES AND DETAILS<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-0004<br />

VOLUME - II<br />

SECTION - C Sub Sec -II<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

LIGHTING NOTES AND DETAILS<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-0004


TITLE:<br />

LIGHTING NOTES AND DETAILS<br />

LIGHTING NOTES<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-0004<br />

VOLUME - II<br />

SECTION - C Sub Sec -II<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

1.0 These lighting notes and details shall be read and construed in conjunction with the<br />

lighting specifications and drawings<br />

2.0 Contractor shall develop final conduit/cable routings based on fixture location and<br />

other site conditions.<br />

3.0 Unless otherwise shown, the mounting heights of lighting fixtures and accessories<br />

shall generally be as follows.<br />

3.a. Lighting fixture in general areas of powerhouse, miscl. Pump house etc.<br />

3.a.i. Low bay type : 3000 mm to bottom.<br />

3.a.ii. Medium bay type : bet 3500 mm to 8000 mm to bottom.<br />

3.a.iii. High bay type : above 8000mm to bottom.<br />

3.b. Bracket lights over door opening : 300 mm bot of fixture above opening.<br />

3.c. Receptacles<br />

3.c.i. In control room office : 450 mm floor to center.<br />

3.c.ii. Elsewhere : 900 mm floor to center.<br />

3.d. Local switches<br />

: 1500 mm floor to center<br />

3.e. Lighting panels<br />

: 1800 mm floor to top<br />

4.0 All outdoor illumination fixtures unless it fed from photocell/tank-switch controlled<br />

lighting panel shall be provided with outdoor type local switches.<br />

5.0 Separate neutral wire shall be provided for each circuit. Wiring throughout the<br />

installation shall be such that there is no break in the neutral wire in the form of switch<br />

or fuse.


.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 1 O 3<br />

CHARACTE-<br />

RISTIC<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-558-00-Q-001 / 01 TITLE<br />

SYSTEM ITEM ILLUMINATION SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

1.0 CABLES & WIRES 1. SURACE MA VISUAL SAMPLE BHEL SPEC., BHEL SPEC., INSPN. 3/2 2 1 TO BE PROCURED<br />

DEECTS IS:694 , IS:694 , REPORT & TEST ROM APPROVED<br />

IS:1554 IS:1554 REPORT ROM SOURCE<br />

MANUACTURER<br />

2.0 JUNCTION BOXES, LIGHTING<br />

PANELS AND DISTRIBUTION BOARDS<br />

2.DIMENSIONS MA MEASUREMENT SAMPLE -DO- -DO- -DO- 3/2 2 1<br />

3. TYPE CR ELEC. ONE/TYPE BHEL SPEC., BHEL SPEC., TEST CERT. 3 2 1<br />

TESTS TESTS & SIZE IS:694, IS:694,<br />

IS:1554<br />

IS:1554<br />

4. ACCEP- MA -DO- SAMPLING -DO- -DO- -DO- 3 2 1<br />

TANCE<br />

TESTS<br />

5. ROUTINE MA -DO- 100% -DO- -DO- -DO- 3 - 2,1<br />

TESTS<br />

6. RLS CR RLS TESTS SAMPLES BHEL SPEC. BHEL SPEC. -DO- 3 2 1<br />

PROPS.<br />

2.1 JUNCTION BOXES 1.DIMENSIONS MA MEASUREMENTS 100% BHEL DRG. BHEL DRG. INSP. REPORT 3 - 2 COMPONENTS TO BE O<br />

APPROVED MAKE.<br />

2.PAINT SHADE/ MA VISUAL / MEAS. SAMPLE BHEL SPEC./DRG. BHELSPEC./DRG. -DO- 3 - 2<br />

THICKNESS<br />

3.HV / IR / HV MA ELECT. TESTS 100% 2KV AC OR 2KV AC OR -DO- 3 - 2<br />

1 MINUTE 1 MINUTE<br />

4.DEGREE O MA TESTS 1/SIZE IS:2147 IS:2147 TEST CERT. - - 2,1<br />

PROTECTION<br />

5.SPECIAL TESTS MA -DO- -DO- IS :2148 IS:2148 -DO- - - 2,1<br />

I ANY, EXPLOSION<br />

PROO ETC.<br />

2.2 LIGHTING PANELS AND LIGHTING 1. DIMENSIONS MA MEASUREMENT SAMPLE BHEL DRG. BHEL DRG. INSPT. REPORT 3 2,1 - COMPONENTS TO BE O<br />

DISTRIBUTION BOARDS<br />

APPROVED MAKE.<br />

11<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE


.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 2 O 3<br />

CHARACTE-<br />

RISTIC<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-558-00-Q-001 / 01 TITLE<br />

SYSTEM ITEM ILLUMINATION SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

2. PAINT SHADE/ MA VISUAL/ -DO- BHEL SPEC./DRG. BHEL SPEC./DRG. INSPT. REPORT 3 2,1 -<br />

THICKNESS<br />

MEASUREMENT<br />

3.DEGREE O MA TESTS 1/SIZE BHEL SPEC./ BHEL SPEC./ TEST CERT. - - 2,1<br />

PROTECTION RELEVANT IS RELEVANT IS<br />

(INCLUDING<br />

EXPLOSION<br />

PROO I ANY)<br />

4.PERORMANCE MA ELEC. 100% BHEL SPEC. BHEL SPEC. INSPT. REPORT 3 2,1 - BHEL SHALL WITNESS ON<br />

TESTS<br />

RANDOM ONE SAMPLE,<br />

THOUGH EACH ITEM SHALL<br />

BE CHECKED BY THE<br />

MANUACTURER.<br />

5.HV/IR/HV MA ELEC. 100% 2.5 KV AC OR 2.5 KV AC OR -DO- 3 2,1 - -DO-<br />

1 MINUTE 1 MINUTE<br />

6. TEMP. RISE MA ELEC. 1/RATING BHEL SPEC. BHEL SPEC. -DO- 3 2 1<br />

TEST (OR COM-<br />

PLETE ASSEMBL-<br />

ED LDB)<br />

3.0 TUNGSTEN ILAMENT LAMPS, 1. - ACCEPTANCE MA TESTS SAMPLE BHEL SPEC./ BHEL SPEC./ TEST CERT. 3,2 - 1<br />

TUBULAR LUORESCENT LAMPS, TESTS RELEVANT IS RELEVANT IS<br />

H.P. MERCURY VAPOUR LAMPS,SODIUM<br />

VAPOUR LAMPS,BALLASTS, LUMINAIRES<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE


.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET O 3<br />

CHARACTE-<br />

RISTIC<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-558-00-Q-001 / 01 TITLE<br />

SYSTEM ITEM ILLUMINATION SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

4.0 CONDUITS 1. MATERIAL MA VISUAL, MECH. AS PER SPEC./ IS:9537 IS:9537 INSPT. REPORT 3 2 1<br />

AND CHEMICAL IS : 9537<br />

6<br />

2. DIMENSIONS MA MEASUREMENT AS PER SPEC./ IS:9537 IS:9537 -DO- 3 2 1<br />

IS : 9537<br />

3. OTHER TESTS MA TESTS AS PER SPEC./ AS PER SPEC./ IS:9537, -DO- 3 2 1<br />

IS:9537,<br />

IS:9537,<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

5.0 ELECTRIC POLES<br />

5.1 MATERIAL 1. CHEMICAL MA CHEM. ANALYSIS SAMPLE IS:2713, IS:2713 -DO- 3/2 - 2,1<br />

COMP.<br />

IS:228 &IS:228 &<br />

IS:1894<br />

IS:1894<br />

2. PHYSICAL MA PHYS. TESTS -DO- -DO- -DO- -DO- 3/2 - 2,1<br />

PROP.<br />

5.2 INAL INSPECTION 1. WORK- MA VISUAL & MEAS. SAMPLES BHEL DRG./IS:2713 BHEL DRG./IS:2713 -DO- 3/2 2,1 -<br />

MANSHIP<br />

& INISH<br />

2. DIMENSIONS MA -DO- -DO- -DO- -DO- -DO- 3/2 2,1 -<br />

3. WEIGHT MA -DO- -DO- -DO- -DO- -DO- 3/2 2,1 -<br />

4. TESTS AS MA -DO- -DO- IS:2713 IS:2713 -DO- 3/2 2,1 -<br />

PER IS:2713<br />

NOTE : IN CASE TYPE TEST CERTIICATE OR DEGREE OPROTECTION /EXPLOSION PROONESS ROM INDEPENDENT LAB. IS NOT<br />

AVAILABLE, THE ITEM SHALL BE TESTED AT AN INDEPENDENT LAB.<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENT<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-Q11-600-C051<br />

VOLUME - IIB<br />

SECTION “C”<br />

Sub Sec-II<br />

REV. 00 DATE: 22 – 10 - 2003<br />

SHEET 1 of 3<br />

1.00.00 CODES AND IS:1554, IS:7098, IEC:502, IS:6380, IS:9968<br />

STANDARDS<br />

2.00.00 TYPE All cable shall be Flame retardent low smoke type<br />

3.00.00 RATING As p er requirement specified in Gen eral Electrical<br />

Requirements.<br />

4.00.00 OPERATIONAL REQUIREMENTS<br />

All cable s shall be suita ble for high ambient, hig h humid tro pical India n climati c<br />

conditions. All cabl es shall be d esigned to withstand the me chanical, ele ctrical and<br />

thermal stresses under the foreseen st eady state and tr ansient/fault conditions, and<br />

shall be suitable for the proposed method of installation.<br />

5.00.00 DESIGN AND CONSTRUCTIONAL FEATURES<br />

5.01.00 Parameters of the cables are as follows :<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

Particul ars Power cables Control cables Trailing cables<br />

------------------------<br />

XLPE PVC<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

a<br />

) Conductor<br />

b) Main Insulation<br />

i) Material Stranded Stranded plain Tinned copper of<br />

Aluminium annealed copper class 5 of IS:8130<br />

ii) Size As required, but As required, but As required, but<br />

Min. 6 sq.mm min. 1.5 sq.mm. min. 1.5 sq.mm.<br />

size. size. size.<br />

iii) Shape Circular/ Circular/<br />

sector sector<br />

shaped. shaped<br />

Circular<br />

only for<br />

HT cables<br />

i) Material XLPE PVC PVC Heat resistant elastomeric<br />

compound<br />

based on Ethylene<br />

Propyline Rubber<br />

(EPR)


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENT<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-Q11-600-C051<br />

VOLUME - IIB<br />

SECTION “C”<br />

Sub Sec-II<br />

REV. 00 DATE: 22 – 10 - 2003<br />

SHEET 2 of 3<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

Particul ars Power cables Control cables Trailing cables<br />

------------------------<br />

XLPE PVC<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

ii)<br />

Continuous<br />

withstand 90 70 70 90<br />

temperature<br />

(deg.C)<br />

iii) Short circuit<br />

withstand 250 160 160 250<br />

temperature<br />

(deg.C)<br />

iv) Colour identification<br />

As per relevant codes and standards<br />

c) Inner Sheath All armoured and multicore unarmoured cables have distinct<br />

extruded inner sheath<br />

i) Material PVC PVC PVC Heat resistant<br />

elastomeric<br />

compound.<br />

ii) Colour Black Black Black Black<br />

d) Armour, wherever provided<br />

i) Material Aluminium wire for GS wire/flat as Nylon cord<br />

single core cable per relevant IS. reinforcemenet<br />

and GS wire/flat for Min. coverage<br />

multi-core cables of 90%.<br />

as per relevant IS.<br />

Minimum Coverage<br />

of 90%<br />

ii) Breaking 95% of normal 95% of normal armour<br />

load of armour<br />

joint<br />

e) Outer sheath All power & control cable shall have extruded outer sheath.<br />

i) Material PVC PVC PVC Heat resistant,<br />

(Polyethe-<br />

oil resistant &<br />

lene based<br />

flame retardant<br />

halogen free<br />

heavy duty elastmaterial<br />

not<br />

tomeric<br />

accepta ble) compound


TITLE:<br />

SPEC<strong>IF</strong>IC TECHNICAL REQUIREMENT<br />

SPEC<strong>IF</strong>ICATION NO. PE-TS-Q11-600-C051<br />

VOLUME - IIB<br />

SECTION “C”<br />

Sub Sec-II<br />

REV. 00 DATE: 22 – 10 - 2003<br />

SHEET 3 of 3<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

Particul ars Power cables Control cables Trailing cables<br />

------------------------<br />

XLPE PVC<br />

-- -----------------------------------------------------------------------------------------------------------------<br />

ii) Colour Black Black Grey Black<br />

5.01.02 HT cables<br />

iii) Marking - Cable size & Same as for Same as for<br />

voltage grade Power Cables Power Cables<br />

(by embossing)<br />

- Word “FRLS”<br />

@ m 5by<br />

(<br />

embossing)<br />

- Sequential marking<br />

@1m<br />

f) FRLS Oxygen Index : Min. 29 (As per ASTMD 2863)<br />

properties on Acid gas generation: Max. 20% (As per IEC754-I)<br />

outer sheath Smoke density rating: 60% (As per ASTMD 2843)<br />

g) Flamability As per Swedish chimney test F3 as per SEN 4241475<br />

test on all As per IEC 332 Part-3 (Category B)<br />

types of cables<br />

For HT ca bles cond uctor scree n and insulatio n scre en shall b e of extrude d semi -<br />

conducting compou nd an d shall b e a pplied al ongwith XLPE insul ation in a singl e<br />

operation by triple extrusion process. Method of curing for 11kV/6.6kV cables shall be<br />

“Dry cu ring/gas curing/steam cu ring” whereas fo r 3 3KV cable s i t shall be " Dry/Gas<br />

curing". 11kV/6.6kV cables shall be provided with copper metallic screen suitable for<br />

carrying allo wable earth f ault current for 2 secs. All other voltag e grad e HT cables<br />

shall be provided with cop per metallic screen suitable for carrying earth fault current<br />

as per E0. For single core armoured cables, the a rmouring shall co nstitute th e<br />

metallic part of screening.<br />

5.01.03 LT Cables of size 150 sq.mm. and above shall be with XLPE insulation.<br />

5.01.04 Core identification<br />

5.01.05 Armouring<br />

For cables having more than five (5 ) cores, each core shall be identified by number<br />

marking. However, for cables upto five (5) cores, the sam e shall be by col our as pe r<br />

IS.<br />

Cables buried direct in ground and cables in switchyard shall be armoured.


Clause No.<br />

POWER AND CONTROL CABLES<br />

...........................................................<br />

(Bidder's Name)<br />

POWER AND CONTROL CABLES<br />

(Use separate sheet for each type and size of cables)<br />

1.00.00 Make ............................ .....................<br />

1.02.00 Country of Manufacturer ............................ .....................<br />

1.03.00 Type & designation ............................ .....................<br />

1.04.00 Applicable standard ............................ .....................<br />

1.05.00 Cable size & no. of cores ............................ .....................<br />

1.06.00 Rated voltage ............................ .....................<br />

1.07.00 Catalogue attached as Annexure No. ............................ .....................<br />

1.08.00 Continuous current rating ............................ .....................<br />

for max. conductor temperature<br />

a) When laid in air at an ambient ............................ .....................<br />

temperature of 50 deg. C<br />

b) When buried in soil having ............................ .....................<br />

thermal resistivity of 150 deg.C<br />

cm/n at a depth of 1000 mm<br />

at ground ambient temperature<br />

of 40 deg. C<br />

1.09.00 Short circuit withstand capacity and ............................ .....................<br />

duration for<br />

a) Conductor ............................ .....................<br />

b) Screen ............................ .....................<br />

c) Armour ............................ .....................<br />

1.10.00 Conductor ............................ .....................<br />

a) Material ............................ .....................<br />

b) Nominal cross section ............................ .....................<br />

area in sq. mm<br />

TECHNICAL DATA REQUIREMENT SHEETS VOLUME - III BOOK 2 PAGE<br />

FOR POWER PLANT TURNKEY PACKAGE SECTION - DE-3 1 OF 2<br />

DOC. NO. : CW-9272-C-O-M-003


Clause No.<br />

POWER AND CONTROL CABLES<br />

...........................................................<br />

(Bidder's Name)<br />

1.11.00 Insulation<br />

c) Shape of conductor ............................ .....................<br />

d) DC resistance at 20 o C ............................ .....................<br />

a) Material ............................ .....................<br />

b) Nominal thickness (in mm) ............................ .....................<br />

c) Type of curing (for XLPE) ............................ .....................<br />

1.12.00 Metallic screen (wherever applicable)<br />

a) Material ............................ .....................<br />

b) Type ........................... ....................<br />

c) Rating KA, Sec<br />

1.13.00 Material & Type of Inner sheath ............................ .....................<br />

1.14.00 Armour material & shape ............................ .....................<br />

1.15.00 Outer sheath material & type ............................ .....................<br />

1.16.00 Over all dia of cable (in mm) ............................ .....................<br />

1.17.00 Guaranteed value of minimum ............................ .....................<br />

oxygen index of outer sheath<br />

1.18.00 Maximum acid-gas generation ............................ .....................<br />

by weight (%) of outer sheath<br />

1.19.00 Smoke Density rating of outer sheath ............................ .....................<br />

TECHNICAL DATA REQUIREMENT SHEETS VOLUME - III BOOK 2 PAGE<br />

FOR POWER PLANT TURNKEY PACKAGE SECTION - DE-3 2 OF 2<br />

DOC. NO. : CW-9272-C-O-M-003


.<br />

.<br />

44<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 1 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

1.0 RAW MATERIAL<br />

1.1 PVC COMPOUND (FOR INSULATION- 1. PHYSICAL PRO- MA PHYS TESTS SAM- IS:5831/ IS:5831/ LOG BOOK 3/2 - 2<br />

AND SHEATH) PERTIES PLE BHEL SPEC- BHEL SPEC /TEST<br />

<strong>IF</strong>ICATION <strong>IF</strong>ICATION CERT<br />

2. ELEC. PROPER- MA ELEC TEST -DO- -DO- -DO- -DO- 3/2 - 2<br />

TIES<br />

3.MAKE & TYPE MA VISUAL 100 % PLANT STD. PLANT STD. DO 2 - -<br />

1.2 GALVANIZED STEEL WIRE / STRIP 1. PHY. AND ELEC MA PHY. ELEC.TESTS SAM-* IS:3975, IS:3975 -DO- 3/2 - 2 * SAMPLE FROM EACH<br />

PROPERTIES PLE BHEL SPEC BHEL SPEC BATCH / LOT<br />

2. DIMENSION MA MEASUREMENT -DO- -DO- -DO- -DO- 3/2 - 2<br />

3. GALVANIZAT- MA GALV. TESTS -DO- -DO- -DO- -DO- 3/2 - 2<br />

ION QUALITY<br />

1.3 COPPER / ALUMINIUM RODS / WIRES 1. PHYSICAL MA PHY.TESTS -DO- IS:613 IS:613 -DO- 3/2 - 2<br />

PROERTIES. IS:5484 IS:5484<br />

IS:8130<br />

IS:8130<br />

AND BHEL AND BHEL<br />

SPEC.<br />

SPEC.<br />

2.CHEM COMPOS- MA CHEM ANALYSIS -DO- -DO- -DO- -DO- 3/2 - 2<br />

ITION & PURITY<br />

3. ELECTRICAL MA ELECTRICAL -DO- -DO- -DO- -DO- 3/2 - 2<br />

PROPERTIES<br />

TESTS<br />

4. DIMENSION MA MEASURMENT -DO- -DO- -DO- -DO- 3/2 - 2<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


.<br />

.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 2 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

2.0 IN PROCESS<br />

2.1 WIRE DRAWING, TINNING 1. PHYSICAL, CR PHY. & ELECT- SAMPLE BHEL SPEC., BHEL SPEC., LOG BOOK 2 - 1<br />

AND ANNEALING ELECT. FINISH TESTS IS-8130 IS-8130<br />

& DIMEN.<br />

VISUAL, MEAS.<br />

2. CHEMICAL CR CHEMICAL -DO- -DO- -DO- -DO- 2 - -<br />

TEST FOR<br />

TEST<br />

TINNING<br />

2.2 STRANDING OF WIRES 1. NO. OF WIRES MA COUNTING SAMPLE VENDORS/ VENDORS/ LOG BOOK 2 - -<br />

BHEL SPEC. BHEL SPEC.<br />

& APPD.<br />

& APPD.<br />

DATA SHEET & DATA SHEET &<br />

RELEVANT IS RELEVANT IS<br />

2 SEQUENCE,LAY MA VISUAL, -DO- -DO- -DO- -DO- 2 - -<br />

LENGTH AND<br />

MEAS<br />

DIRECTION<br />

3. SURFACE<br />

FINISH MA VISUAL -DO- -DO- -DO- -DO- 2 - -<br />

4. DIMENSION MA MEASURE- -DO- -DO- -DO- -DO- 2 - -<br />

MENT<br />

FREE FROM -DO- 2 - 1<br />

2.3 CORE - INSULATION 1 SURFACE MA VISUAL 100% - BULGING, BURNT<br />

(NO REPAIR PERMITTED) FINISH PARTICLES<br />

LUMPS, CUTS &<br />

SCRATCHES<br />

2. INSULATION CR MEASUREMENT SAMPLE APPD.DATA SHT. APPD.DATA SHT. -DO- 2 - -<br />

THICKNESS IS : 1554 IS : 1554<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


.<br />

.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 3 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

3. CONCENTRI- CR MEASUREMENT SAMPLE MFR. STD. MFR. STD. -DO- 2 - 1 # TO BE CHECKED<br />

CITY. # ./APPD. DATA /APPD. DATA AT STARTING & FINISH<br />

SHEET. SHEET. END OF EXTRUDED LENGTH<br />

4. DIA OVER INS- MA MEASUREMENT SAMPLE -DO- -DO- -DO- 2 - -<br />

ULATION<br />

11<br />

5. SPARK TEST CR ELECTRICAL 100% MFR. STD. MFR. STD. -DO- 2 - 1<br />

OR WATER<br />

IMMERSION TEST<br />

6. CORE IDENT<strong>IF</strong>- MA VISUAL 100% IS:1554 IS:1554 -DO- 2 - -<br />

ICATION.<br />

2.4 CORE - LAYING 1.DIA OVER LAID MA MEASUREMENT SAMPLE -DO- -DO- -DO- 2 - -<br />

UP CORE<br />

2.SEQUENCE OF MA VISUAL & MEAS. SAMPLE MFR. STD/ MFR. STD/ LOG BOOK 2 - -<br />

LAY, LAY LENGTH RELEVANT IS RELEVANT IS<br />

& DIRECTION<br />

UP CORE<br />

2.5 INNER SHEATH EXTRUSION 1. SURFACE MA VISUAL 100% _ FREE FROM -DO- 2 - -<br />

FINISH<br />

BULGING,BURNT<br />

PARTICLES,<br />

LUMPS CUTS &<br />

SCRATCHES<br />

2. SHEATH MA MEASUREMENT SAMPLE IS:5831 & IS:5831 & -DO- 2 - -<br />

THICKNESS DATA SHEET DATA SHEET<br />

IS-1554<br />

IS-1554<br />

3. DIA OVER INN- MA -DO- -DO- -DO- -DO- -DO- 2 - -<br />

ER SHEATH<br />

2.6 ARMOURING 1. NO. OF WIRES/ MA COUNTING AT THE START BHEL SPEC./ BHEL SPEC./ -DO- 2 - -<br />

STRIPS OF THE APPD.DATA SH. APPD.DATA SH.<br />

PROCESS IS:3975 & IS:1554 IS:3975 & IS:1554<br />

2. LAY DIRECTION MA VISUAL -DO- -DO- -DO- -DO- 2 - -<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


.<br />

.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 4 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

3. LAY LENGTH MA VISUAL, MEAS. -DO- -DO- -DO- -DO- 2 - -<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

4. COVERAGE MA MEASUREMENT -DO- -DO- -DO- -DO- 2 - -<br />

5. DIA OVER - MA MEASUREMENT -DO- -DO- -DO- -DO- 2 - -<br />

ARMOURING<br />

2.7 OUTER SHEATH EXTRUSION 1. SURFACE MA VISUAL 100% - FREE FROM BUL- LOG BOOK 2 - -<br />

FINISH GING, BURNT PA-<br />

RTICLES, LUMPS<br />

CUTS & SCRATC-<br />

HES.<br />

2. SHEATH THICK- MA MEASUREMENT SAMPLE IS:5831 & IS:5831 & -DO- 2 - -<br />

NESS IS-1554 IS-1554<br />

DATA SHEET DATA SHEET<br />

3.DIA OVER OUT- MA -DO- -DO- -DO- -DO- -DO- 2 - -<br />

ER SHEATH<br />

4. MARKING MA VISUAL 100% IS:1554 & IS:1554 & TEST REPORT 2 - - SEQUENTIAL MARKING<br />

BHEL SPEC. BHEL SPEC. SHALL BE DONE BY<br />

PRINTING.<br />

2.8 FINISHED CABLE 1. ROUTINE TEST CR ELEC. & MEAS. 100% IS:1554 & IS:1554 & TEST REPORT 2 - 1<br />

BHEL SPEC. BHEL SPEC.<br />

2.TYPE AND FRLS CR ELEC. PHY SAMPLE * -DO-/APPD. DATA -DO-/APPD.DATA -DO- 2 - 1 *ONE DRUM / SIZE / LOT<br />

TESTS & MEAS SHEET. SHEET.<br />

3.0 FINAL INSPECTION 1. FINISH & MA VISUAL (SEE REMARK ) BHEL SPEC. FREE FROM -DO- 2 1 - ONE DRUM EACH FOR<br />

LENGTH IS: 1554 BULGING,BURNT POWER AND CONTROL<br />

PARTICLES LUMPS CABLES IN A LOT<br />

CUTS & SCRATC-<br />

HES.<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


.<br />

.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 5 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

2. DIMENSION MA MEASUREMENT AS PER IS APPD.DATA APPD.DATA -DO- 2 1 -<br />

SHEET.<br />

SHEET.<br />

IS:1554<br />

IS:1554<br />

IS:10810<br />

IS:10810<br />

3. ARMOURING- MA VISUAL & MEAS. AS PER IS -DO- -DO- -DO- 2 1 -<br />

COVERAGE<br />

NO.OF WIRES<br />

/STRIPS<br />

4.MARKING/COL- MA VISUAL -DO- -DO- -DO- -DO- 2 1 -<br />

OUR CODING<br />

5 ACCEPTANCE CR PHY. & ELECT. -D0- -DO- -DO- -DO- 2 1<br />

TESTS<br />

TESTS<br />

6. TYPE & FRLS CR MEASUREMENT (SEE REMARK) BHEL SPEC. , BHEL SPEC. -DO- 2 1 - TYPE TEST SHELL BE<br />

TESTS APPD. DATA APPD. DATA WITNESSED ON ONE<br />

SHEET SHEET SAMPLE PER TYPE<br />

(POWER / CONTROL)<br />

OF EVERY LOT.<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


.<br />

.<br />

S.<br />

NO.<br />

1<br />

COMPONENT / OPERATION<br />

2<br />

QUALITY PLAN<br />

SHEET 6 O 6<br />

CHARACTE-<br />

RISTICS<br />

CHECK<br />

3<br />

CAT.<br />

4<br />

TYPE/<br />

METHOD O<br />

CHECK<br />

5<br />

CUSTOMER PROJECT SPECIICATION<br />

TITLE<br />

NUMBER<br />

BIDDER / QUALITY PLAN SPECIICATION<br />

VENDOR NUMBER PED-507-00-Q-002 / 02 TIITLE<br />

SYSTEM ITEM PVC POWER & CONTROL CABLE SECTION VOLUME III<br />

EXTENT O<br />

CHECK<br />

6<br />

REERENCE<br />

DOCUMENT<br />

7<br />

ACCEPTANCE<br />

NORM<br />

8<br />

ORMAT O<br />

RECORD<br />

9<br />

AGENCY<br />

P W V<br />

10<br />

ORM No. PEM — 6041-0<br />

REMARKS<br />

11<br />

NOTES:<br />

A) JOINTS IN WIRES SHALL BE AS PERMITTED BY IS/BHEL SPEC<strong>IF</strong>ICATION. VENDOR TO CERT<strong>IF</strong>Y THE SAME<br />

B) NO REPAIR OF CORE INSULATION FERMITTED.<br />

C) CABLE ENDS SHALL BE SEALED AS PER BHEL SPEC<strong>IF</strong>ICATION.<br />

D) PURCHASER SHALL HAVE RIGHT TO WITNESS THE SPARK TEST AT CORE STAGE.<br />

E) RECORD OF RAW MATERIAL, PROCESS & ALL STAGES SHALL BE CERT<strong>IF</strong>IED BY VENDOR’S Q.C. AND ARE LIABLE TO AUDIT CHECK BY PURCHASER.<br />

F) FILLERS / DUMMY CORES ETC. SHALL BE AS PER BHEL SPEC<strong>IF</strong>ICATION.<br />

G) WHEREVER EXTENT OF CHECK FOR STAGE IS MENTIONED AS SAMPLES, THE SAME SHALL BE AS PER VENDOR’S SAMPLING PLAN.<br />

H) VENDOR SHALL FURNISH COMPLIANCE CERT<strong>IF</strong>ICATE TO THE INSPECTION AGENCY CONFIRMING THE PACKING AS PER BHEL SPEC<strong>IF</strong>ICATION.<br />

LEGEND :- P - PERORMER : W-WITNESSER : V - VERIYER:<br />

1-BHEL/BHEL'S CUSTOMER : 2- VENDOR : 3-SUB VENDOR<br />

BHEL PARTICULARS BIDDER / VENDOR<br />

NAME<br />

SIGNATURE<br />

DATE<br />

BIDDER’S / VENDOR’S COMPANY SEAL


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

GENERAL TECHNICAL REQUIREMENTS<br />

OF<br />

LIGHTING DISTRIBUTION BOARD<br />

&<br />

LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-559-01A


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.2.3 Independent gasketted hinged door with operating handle shall be provided for<br />

access to transformer & its taps. Operating handle shall have built-in key locking<br />

arrangement.<br />

3.2.4 Suitable ventilation arrangement for the transformer compartment to dissipate the<br />

heat of the transformer shall be provided. The arrangement shall be in the form of<br />

louvers and the same shall be provided with galvanized wire mesh with dust catchers<br />

on the inside.<br />

3.2.5 The degree of protection for transformer compartment shall be IP:42 unless<br />

mentioned otherwise in Data Sheet A.<br />

3.2.6 Connections between transformer secondary terminals and the busbars shall be<br />

made by using PVC insulated flexible copper cables or busbars.<br />

3.2.7 Warning plate shall be provided on transformer enclosure. The inscription of warning<br />

plate shall be as given below:<br />

- DO NOT OPEN DOORS WHEN ENERGISED<br />

- KEEP TAPS AT SAME POSITION FOR ALL PHASES<br />

3.2.8 Transformer enclosure shall be provided with a danger plate.<br />

3.3 Lighting Transformer<br />

3.3.1 Lighting transformer, where specified shall form an integral part of lighting distribution<br />

board.<br />

3.3.2 Lighting transformer shall be dry type, natural air cooled and suitable for mounting<br />

inside the lighting distribution board. Transformer shall be non-encapsulated type,<br />

unless specified otherwise in Data Sheet A.<br />

3.3.3 Rating of transformer shall be 50 kVA as per type of LDB.<br />

3.3.4 Voltage rating shall be given in Data Sheet A.<br />

3.3.5 Percentage impedance shall be 3% for 50kVA and 4% for 100 kVA transformers,<br />

unless specified otherwise in Data Sheet A.<br />

3.3.6 Off circuit tap changers/links shall be provided for + 5% in steps of 2.5%.<br />

3.3.7 Transformer winding insulation shall be class “F” or better.<br />

3.3.8 Transformer shall be of vector group Dynl.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.3.9 Winding shall be of copper material maximum winding temperature at full load and<br />

under site conditions shall not exceed 120 Deg. C.<br />

3.3.10 Transformer shall be suitable for cable connections on the primary side and flexible<br />

cable or busbar connectin on the secondary side.<br />

3.3.11 The secondary neutral of the transformer shall be brought out for getting a grounded<br />

4 wire supply system.<br />

3.3.12 The transformer neutral shall be brought outside the LDB for earthing. The neutral<br />

busbar shall be insulated from the LDB enclosure.<br />

3.3.13 Transformer shall be provided with the rollers, pulling holes, lifting lugs, jacking<br />

positions etc.<br />

3.4 Busbars, Connections and Joints<br />

3.4.1 Busbars shall be made of aluminium grade E 91E or high conductivity copper (ETC),<br />

Busbar material shall generally be aluminium unless mentioned otherwise in Data<br />

Sheet A.<br />

3.4.2 Busbars shall be supported on non-hygroscopic and non-inflammable insulators of<br />

material such as glass reinforced moulded plastic material, epoxy cast resin etc.<br />

Separate supports shall be provided for each phase of the busbars, Insulation level<br />

of neutral busbar shall be same as that of phase busbars.<br />

3.4.3 Busbars shall be contained in a separate vermin-proof compartment within the LDB<br />

and shall have bolted sheet steel covers for providing suitable access.<br />

3.4.4 Busbar clearances in the air shall be as per applicable standard for 500V, 3 phase<br />

system.<br />

3.4.5 Temperature of busbars, droppers and connections shall not exceed 90 Deg. C for<br />

an ambient of 50 Deg. C while carrying maximum continuous current.<br />

3.4.6 The busbar, busbar connections and supports shall have sufficient strength to<br />

withstand thermal and electromechanical stresses produced by the specified short<br />

circuit level of the system.<br />

3.4.7 Busbars (including neutral busbar) shall be capable of carrying the short-time current<br />

specified in Data Sheet A. The duration of short-time current shall be 1 sec unless<br />

mentioned otherwise in Data Sheet A. For the specified current and duration, there<br />

shall be no damage to the equipment.<br />

3.4.8 The neutral bus shall be rated same as phase bus.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.4.9 Main busbars and connections shall be prominently marked and displaced for<br />

standard sequence counting from rear to front top to bottom, or left to right as viewed<br />

from the switching device operating mechanism side.<br />

3.4.10 Busbars and connections shall be provided with colour coded PVD sleeves. All live<br />

parts shall be properly shrouded with insulating material.<br />

3.4.11 Earth busbar shall be provided separately. Material of earth busbar shall be GI<br />

unless mentioned otherwise in Data Sheet A.<br />

3.4.12 Busbar Joints<br />

a) Busbar and tap off joints shall be bolted type.<br />

b) Busbars shall be thoroughly cleaned before jointing. Suitable contact greae<br />

shall be applied to remove oxide film just before jointing.<br />

c) For copper busbars, the connecting portion shall be tinned or silver plated.<br />

3.5 Wiring and Terminals<br />

3.5.1 All internal wiring for connections to remote equipment shall be brought to terminal<br />

boards. Spare contacts of devices shall also be wired upto terminal board as per<br />

schemes. Wires shall not be jointed or teed-off except at terminal points.<br />

3.5.2 Wiring shall be made by 1000 volt grade three / seven strand PVC insulated copper<br />

wire having a cross-sectional area of not less that 1.5 sq.mm. All connections from<br />

CT leads upto instruments, terminals shall be made by copper wires of minimum 2.5<br />

sq.mm. size.<br />

3.5.3 All wiring shall be made with the Colour Codes specified below:<br />

a) 3 phase AC Connections<br />

Phase 1 ( R )<br />

Phase 2 ( Y)<br />

Phase 1 ( B )<br />

Neutral Black<br />

Red<br />

Yellow<br />

Blue<br />

b) 1 phase AC Connections<br />

Phase Red/ Yellow / Blue<br />

(as per associated circuit)<br />

Neutral Black<br />

c) DC Connections


Positive<br />

Negative<br />

TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

While<br />

Grey<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

d) Earth Connection Green<br />

3.5.4 Where wiring passes from one compartment to another, the aperture shall be<br />

‘Bushed’ to prevent damage to wires against sheet metal edges. Bushes may<br />

comprise of good quality rubber/ PVC grommets.<br />

3.5.5 Every wire end shall be fitted with numbered ferrules of white or yellow colour having<br />

glossy finish with identification number engraved in black, Ferrules shall be made of<br />

moisture and oil resisting insulating material. Ferrules shall be or interlocked type or<br />

tight fitting type. Ferrules shall be so fitted that they will not get detached, when the<br />

wire is removed from the terminal.<br />

3.5.6 System of marking of wiring shall be as per applicable standard.<br />

3.5.7 All wires used internally shall have crimped on tinned copper lugs for terminations.<br />

3.5.8 Terminal boards shall be stud type with insulating barriers of adequate height.<br />

3.5.9 Terminal boards shall have separate terminals for incoming and outgoing wires with<br />

not more than two wires connected to any one terminal.<br />

3.5.10 Terminal boards shall be mounted vertically or in the horizontal rows and properly<br />

spaced to have clean wiring arrangement, adequate access for putting ferrules,<br />

making terminations etc. It shall be possible to read the ferrule numbers when the<br />

wiring is complete. Where terminals may be live when the equipment is isolated from<br />

the main supply, these shall be clearly marked near the terminal boards.<br />

3.6 Controls<br />

The controls shall be provided as per purchaser’s requirements covered in the<br />

specification and control schemes.<br />

3.7 Switch Fuse Units<br />

3.7.1 These units shall preferably comprise of switches having integral fuses, called<br />

composite units. Alternatively, combination units of separate switch and fuse may<br />

also be acceptable.<br />

3.7.2 These units shall be provided for general purpose i.e. incoming or outgoing units.<br />

3.7.3 The units shall be of the air break air insulated type and designed to ensure safety to<br />

operating personnel.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.7.4 Composite units shall have integral fuses i.e. fuse carrier with fuse link (fuse link<br />

forming the moving contact). The design shall ensure that the moving contact is not<br />

live when switch is open i.e. in OFF position, so as to facilitate removal of fuse.<br />

3.7.5 The switch shall be capable making and carrying the system prospective fault<br />

current, but limited in magnitude and duration by the cut off characteristics of the<br />

largest HRC fuse link that may be fitted to that unit.<br />

3.7.6 The fixed contact shall be so shrouded that maintenance of the unit can be carried<br />

out in safety with the busbars live.<br />

3.7.7 Where one isolating switch is used as the incoming device, the incoming side fixed<br />

contacts shall be shrouded to ensure that maintenance can be carried out with the<br />

remote fuse and switch closed.<br />

3.7.8 Composite switch-fuse or the combination of switch and fuse shall meet the<br />

requirements of its components as follows:<br />

3.7.9 Isolating Switch<br />

a) Switches shall be air-break, quick make, quick break heavy duty type<br />

conforming to applicable standard.<br />

b) All switches shall have visible ON / OFF position indication and shall be<br />

padlockable in any (ON /OFF) position.<br />

c) Switches shall be door interlocked such that it shall not be possible to gain<br />

access to inside the unit unless the isolating switch is in OFF position.<br />

d) The switches shall be suitable for independent manual operation.<br />

e) The switch contacts shall be of silver alloy or silver plated copper and springs<br />

of non corrosive material.<br />

f) Inter-phase barriers shall be provided to prevent possibilities of phase to<br />

phase fault in the switch. The switch shall also be shrouded from all sides to<br />

prevent access to live parts on the switch after opening the unit door. The<br />

barriers and shrouding shall extend upto the height of switch to fully enclose<br />

both side terminals of the device. The arrangement shall permit easy<br />

maintenance.<br />

3.7.10 High Rupturing Capacity (HRC) Fuses<br />

a) The fuse serving as the short-circuit protective device in isolating fuse-switch<br />

units shall be of HRC cartridge, current limiting and plug-in non-deteriorating<br />

type.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

b) The fuse carriers shall be easily withdrawable for replacement of fuse,<br />

Insulated fuse pullers shall be provided where fuses are not mounted in<br />

insulating carriers to remove and replace fuses in live conditions.<br />

c) Fuses shall preferably be fitted with a device to indicate operation (i.e. when<br />

the fuse has blown).<br />

d) Live terminals of fuse bases shall be shrouded to prevent contact with<br />

personnel where fuse links are not mounted in carriers and are directly<br />

plugged into the fuse base. Inter-phase barriers extending throughout the<br />

length of the fuse base shall be provided to prevent inter-phase short circuit.<br />

They shall be shrouded from all sides to prevent accidental contact.<br />

e) Fuse carriers and bases shall be of good quality moulded insulating material.<br />

Porcelain fuse bases and carriers will not be accepted.<br />

3.8 Cable Terminations<br />

3.8.1 All cable, either incoming or outgoing to the LDB, shall be terminated in a cable<br />

chamber. For each panel, there shall be a cable chamber on the side. The door of<br />

cable chamber should open or be locked with the help of a tool. Unless stated<br />

otherwise in Data Sheet A, all cables shall enter from the bottom.<br />

3.8.2 Removable undrilled gland plates of sheet steel shall be provided in the cable<br />

chamber for entry of cables. Minimum thickness of gland plate shall be 3mm. The<br />

gland plate shall be of adequate size for connecting requisite number of cable glands<br />

for power and control cables.<br />

3.8.3 Heavy duty bolt-on termination tinned copper lugs of compression type shall be used<br />

in for power cable termination.<br />

3.8.4 For supporting and clamping of cable cores at regular interval in cable alleys,<br />

suitable slotted angle upto the respective terminal blocks shall be provided.<br />

3.8.5 The supply of tinned copper cable lugs for power cables from part the supply of<br />

equipment.<br />

3.9 Earthing<br />

3.9.1 An earth busbar of adequate size of galvanized MS shall be provided at the bottom<br />

for the entire length of the LDB.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.9.2 Every metal part other than those forming parts of an electrical circuit shall<br />

connected to the earth bus by means of high conductivity copper wire of size not less<br />

than 2.5 sq. mm cross-sectional area.<br />

3.9.3 Doors shall have a flexible copper wire for earth connection to fixed unit.<br />

3.9.4 Each LDB shall be fitted with two earthing studs located in accessible position on<br />

sides for connection of internal earth busbar to the external earthing connection.<br />

3.9.5 Earth busbar shall be brought outside LDB for making external connections.<br />

3.10 Type of LDBs<br />

The LDBs shall be of following type:<br />

a) LDB-H (n) - AC LDB with 100 kVA transformer<br />

b) LDB-F (n) - AC LDB with 50 kVA transformer<br />

c) LDB-N (n) - AC LDB with no transformer<br />

d) LDB-D (n) - DC LDB<br />

NOTE: (n) indicates number of outgoing feeders.<br />

3.10.1 AC LDBs (LDB-H, LDB-F, LDB-N)<br />

Each LDB shall comprise of the following and comply with the enclosed single line<br />

diagrams:<br />

a) One lighting transformer (LDB-H & LDB-F)<br />

LIGHTING SYSTEM<br />

b) One incomer of TP / TPN switch-fuse unit or MCCB / MCCB with neutral link<br />

as per Data Sheet A. It shall be provided on the primary side of transformer<br />

for LDB type LDB-H & LDB-F.<br />

c) Set of busbars with 3 phase and neutral.<br />

d) TPN switchfuse units for each outgoing circuit.<br />

e) Three indicating lamps with fuses for indicating bus supply ON.<br />

f) CT operated ammeter with selector switch.<br />

g) VT operated voltmeter with selector switch.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

h) Power & control terminals, earth-stud, earth busbar, designation labels,<br />

internal wiring, power cable lugs, glands etc. shall be provided to complete<br />

the LDB in all respects.<br />

3.10.2 DC LDBs (LDB-D)<br />

Each LDB shall comprise of the following and comply with the enclosed single line<br />

diagrams:;<br />

a) One incomer of two pole switch-fuse unit.<br />

b) Two pole DC contactor on the incoming circuit for changeover to DC in case<br />

of AC normal supply failure.<br />

c) One under voltage relay of suitable range, if specified in Data Sheet A.<br />

d) One ON delay timer.<br />

e) One test push button.<br />

f) Set of busbars for positive and negative.<br />

g) Two pole switch-fuse units / MCB for outgoing feeders.<br />

h) Two indicating lamps with fuses for indicating but supply ON.<br />

i) Power & control terminals, earth busbar, designation labels, internal wiring,<br />

power cable lugs, glands etc. shall be provided to complete the LDB in all<br />

respects.<br />

4.0 LIGHTING PANELS (LPs)<br />

4.1 General Requirements of Lighting Panels<br />

4.1.1. LPs shall be totally enclosed, suitable for electrical system data as specified ind Data<br />

Sheet A.<br />

4.1.2 Panels shall be suitable for indoor / outdoor application as per Data Sheet A and<br />

BOQ. Outdoor panels shall have a sloping canopy.<br />

4.1.3 LPs shall be constructed from CRCA sheet. Sheet thickness shall be 2.0mm, unless<br />

mentioned otherwise in Data Sheet A. The construction of LPs shall ensure<br />

adequate rigidity.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

4.1.4 All components of the LP shall be fully mounted inside the panel, LPs shall have only<br />

one operational front. Door shall be provided to give full access to all the<br />

components. Door shall have padlocking arrangement.<br />

4.1.5 LPs shall consist of dust and vermin proof cubicles without the use of louvers.<br />

4.16 Good quality synthetic rubber / neoprene gaskets shall be put around the door. The<br />

door when closed, shall compress the gasket uniformity.<br />

4.17 Unless mentioned otherwise in Data Sheet A, degree of protection for completed LPs<br />

shall be IP:52 for indoor LPs and IP:55 (with weather-proof protection & canopy) for<br />

outdoor LPs.<br />

4.1.8 The LPs shall be designed to prevent contact with live parts when the front door is<br />

open.<br />

4.1.9 All busbars (phase, neutral, positive, negative as applicable) within a panel shall be<br />

of the same size.<br />

4.1.10 All control wiring inside the panels shall be carried out with 1100 V grade, PVC<br />

insulated flexible copper wire of 2.5 sq.mm size.<br />

4.1.11 The rated continuous current of the equipment and components<br />

4.1.12 Each LP shall be fitted with MS. Mounting brackets.<br />

4.1.13 Panel shall be suitable for top / bottom cable / conduit entires. However, outdoor<br />

LPs shall have bottom cable / conduit entry. Removable undrilled undrilled gland<br />

plate of sheet steel shall be provided for entry of cables. Minimum thickness of gland<br />

plate shall be 3 mm. The gland plate shall be of adequate size having knock-outs for<br />

requisite number cable connections. Gland plate shall be provided with gasket.<br />

4.1.14 The lighting panel shall be complete with copper busbars, and shall incorporate<br />

switch fuse or MCB on the incoming side, single pole miniature circuit breakers<br />

(MCBs) for AC outgoing circuits and double pole MCBs for DC outgoing circuits.<br />

Number of outgoing circuits shall be as per BOQ.<br />

4.1.15 Each lighting panel shall be fitting with two GI earth studs located in accessible<br />

position on the outside of the panel on opposite sides.<br />

4.1.16 All metal parts of the panel except current carrying parts shall be bonded together<br />

electrically to the earthing stud.<br />

4.1.17 Each panel shall be fitted with phase barriers of fireproof insulating material in such a<br />

manner that it is not readily possible for personnel to touch the phase busbars.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

Insulating sheet shall be fitted around the MCBs such that only the surface and<br />

toggle of the MCBs are available on the front.<br />

4.1.18 The supply of cable lugs for power and control cable connections forms part the<br />

supply of equipment.<br />

4.1.19 Each panel shall be provided with a circuit directory plate with inscriptions neatly<br />

typed and laminated fitted on the inside of door.<br />

4.2 Type of Lighting Panels<br />

a) LP-A (n) - AC Lighting Panel<br />

b) LP-D (n) - DC Lighting Panel<br />

c) LP-F (n) - Fancy Lighting Panel (Decorative)<br />

d) LP-V (n) - Aviation Lighting Panel<br />

NOTE: (n) indicates number of outgoing circuits.<br />

4.3 AC Lighting Panel (LP-A)<br />

4.3.1 LPs shall be provided with TPN switch as incomer.<br />

4.3.2 Requisite number of single pole MCBs shall be provided for outgoing circuits.<br />

4.3.3 Separate neutral shall be available at terminal block for each outgoing circuit.<br />

4.3.4 Construction of AC Normal and AC Emergency panels shall be same.<br />

4.4 DC Lighting Panels (LP-D)<br />

4.4.1 LPs shall be provided with double pole switch as incomer.<br />

4.4.2 Requisite number of double pole MCBs shall be provided for outgoing circuits.<br />

4.5 Decorative Type Lighting Panels (LP-F)<br />

4.5.1 Decorative lighting panels shall be designed for use in areas like administrative<br />

building, service building, canteen, residential premises etc.<br />

4.5.2 Thickness of sheet steel shall be as per manufacturer’s practice.<br />

4.5.3 LPs shall be of tone colour with elegant finish.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

4.5.4 LPs shall be provided with TPN switch as incomer and requisite number of MCBs<br />

shall be provided for outgoing circuits.<br />

4.5.5 LPs shall be suitable for either surface or flush mounting as per Data Sheet A and<br />

BOQ. Flush mounted panels shall have the collared door suitable for matching with<br />

the wall.<br />

4.5.6 Lighting Panels may be provided with transparent acrylic cover for operation of<br />

MCBs, if asked for in Data Sheet A.<br />

4.5.7 LPs shall be provided with knockouts on the top, bottom and sides.<br />

4.6 Aviation Lighting Panel (LP_V)<br />

4.6.1 Aviation Lighting Panels shall be provided for feeding power supply to Aviation<br />

obstruction luminaries.<br />

4.6.2 Each Aviation Lighting Panel shall comprise of the following:<br />

a) One TPN door interlocked switch-use unit. Interlock defeat feature shall also<br />

be provided.<br />

b) Three pole AC Contactor<br />

c) 00-24 hrs timer and a photo-electric switch for automatic switching of<br />

contactor<br />

d) Three phase & neutral busbars<br />

e) Single pole or three pole MCBs for each outgoing circuit as per Data Sheet A<br />

f) Two lamps for bus supply ON & OFF indications<br />

g) Complete wiring arrangement as per control scheme.<br />

h) Auto-Manual selector switch<br />

i) ON push button<br />

j) OFF push button<br />

k) Photo switch<br />

4.6.3 Switching ON and switching OFF shall be through both 00-24 hrs timer and light<br />

sensor in automatic mode.<br />

4.6.4 One number light sensor in weather proof enclosure having IP:55 degree of<br />

protection shall be supplied loose along with each SLP.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

4.6.5 Internal power wiring shall be done with PVC insulated Cu wire of suitable size. All<br />

control wiring inside the panel shall be carried out with 1100 V grade, PVC insulated<br />

flexible copper wires.<br />

5.0 Guaranteed Performance Requirements<br />

5.1 The vendor shall guarantee satisfactory performance of the equipment under all<br />

conditions and requirement as laid down by this specification.<br />

5.2 For the general requirements of performance guarantees refer to other parts of the<br />

specification.<br />

6.0 PAINTING<br />

7.0 TESTS<br />

(All metal surface shall be cleaned, phosphated and given two coats of rust-resistant<br />

primer followed by two coats of synthetic enamel paint in light grey shade (IS:5 shade<br />

631).<br />

Each panel shall be completely assembled, wired, adjusted and tested at the factory<br />

prior to shipment. The test shall include wiring continuity tests, insulation tests and<br />

functional tests to ensure satisfactory operation and control of individual equipment.


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

1.0 SYSTEM DESIGN DATA<br />

1.1 Design Ambient : 50 Deg.C<br />

1.2 Relative humidity :<br />

a) Average : As per project synopsis<br />

b) Maximum : -do-<br />

1.3 Details of Operating parameters<br />

a) AC Supply<br />

i. Rated voltage : 415 V<br />

ii. Rated frequency : 50 Hz<br />

iii. Voltage variation : + 10 %<br />

(Permissible)<br />

iv. Frequency variation : + 5 %<br />

(Premissible)<br />

v. Combined voltage & : 10%<br />

Frequency variation<br />

(sum of absolutes<br />

permissible)<br />

vi. System fault level : 50 kA for 0.25 sec.<br />

At rated voltage<br />

vii. System grounding : Solidly<br />

b) DC Supply Not applicable<br />

i. Rated voltage : V<br />

ii. Voltage variation : %<br />

(Permissible)<br />

iii. System fault level :<br />

at rated voltage<br />

c) AC Emergency luminaries : Not applicable %<br />

as per percentage of total luminaries<br />

2.0 APPLICABLE STANDARDS : As per Annexure I


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

3.0 LIGHTING DISTRIBUTION BOARDS<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

3.1 Sheet thickness : 2.0 mm<br />

3.2 Degree of protection :<br />

a) Main panel : IP 54<br />

b) Transformer cubicle : IP 33<br />

3.3 Type of Incomer : Switch-Fuse<br />

3.4 Type of Outgoing Feeders : Switch-Fuse<br />

3.5 Voltage rating of transformer : 415 V<br />

3.6 Whether transformer is encapsulated: No<br />

3.7 Transformer impedance<br />

a) 100 kVA : - %<br />

b) 50 kVA : 4.0 %<br />

3.8 Bus bar material : Aluminium<br />

3.9 Earth busbar material : GI (50X6 mm)<br />

3.10 Cable entry : Bottom<br />

3.11 Whether under voltage relay : Not applicable<br />

required in DC LDB<br />

4.0 LIGHTING PANEL<br />

4.1 Application : Both Indoor & outdoor<br />

4.2 Sheet thickness : 2.0 mm<br />

4.3 Degree of protection<br />

a) Indoor : IP : 54<br />

b) Outdoor : IP : 55<br />

(weather-proof<br />

protection with canopy)<br />

4.4 Type of Incomer : Switch-Fuse<br />

4.5 No. of poles for Aviation lighting : 1 / 3<br />

panel MCBs


TITLE:<br />

LIGHTING DISTRIBUTION BOARD<br />

& LIGHTING PANEL<br />

SPEC<strong>IF</strong>ICATION NO. PES-558-01A<br />

VOLUME - II B<br />

SECTION - D<br />

REV.NO. 0 DATE<br />

SHEET 1<br />

OF<br />

4.6 Type of mounting of decorative : Not applicable<br />

lighting panel<br />

4.7 Whether decorative lighting panel : Not applicable<br />

required with acrylic panel<br />

5.0 LABELING : As per specification<br />

6.0 PAINTING :<br />

6.1 Shade (as per IS:5)<br />

Interior Exterior<br />

a) LDBs : Glossy white 631 of IS:5<br />

b) LPs : -do- -do-<br />

6.2 FINISH<br />

a) Interior : Semi-glossy<br />

b) Exterior : Semi-glossy<br />

6.3 Paint thickness (min.) : 50 microns<br />

7.0 MAKE OF COMPONENTS : Shall be subject to BHEL approval

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!