| Ground floor details<br />

Joists to be designed to service class 2<br />

GF1 <strong>STEICO</strong>joist parallel to wall<br />

Sealant<br />

DPC<br />

<strong>STEICO</strong>joist<br />

Minimum<br />

150 mm<br />

Air flow<br />

Minimum 150 mm<br />

<br />

GF2 <strong>STEICO</strong>joist bearing on external wall<br />

DPC<br />

<br />

Minimum<br />

150 mm<br />

Masonry hanger<br />

Sealant<br />

<strong>STEICO</strong>joist<br />

Granular fill<br />

Wall designed to<br />

building designer‘s<br />

requirements<br />

<br />

Perforated drain<br />

External cavity wall<br />

Min. 150 mm<br />

Span direction<br />

Treated wall plate<br />

DPC<br />

Minimum 75 mm to DPC<br />

Intermediate support with<br />

cross ventilation<br />

Subfloor ground level to fall to outlet / drain<br />

GF3 <strong>STEICO</strong>joist bearing on external wall<br />

<br />

Joists may be built in or supported<br />

on hangers. Consideration<br />

must be given to prevent ingress<br />

of water.<br />

Sealant<br />

DPC<br />

Minimum<br />

150 mm<br />

Span direction<br />

DPC<br />

DPC<br />

Minimum 150 mm<br />

Intermediate support with<br />

cross ventilation<br />

External cavity wall<br />

Subfloor ground level to fall to outlet / drain (see drainage notes)<br />

26<br />

<strong>Technical</strong> <strong>Guide</strong> <strong>STEICO</strong> <strong>construction</strong>