23.04.2014 Views

Boring - Trenchless International

Boring - Trenchless International

Boring - Trenchless International

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Powering New York State<br />

by Nick H. Strater, Brian C. Dorwart, Brierley Associates, LLC and Lane Puls, Burns and McDonnell<br />

The recent expansion of an electric substation in rural New York State required<br />

trenchless installation of a 345 kilovolt duct bank through an existing rock slope,<br />

below live overhead wires – an optically guided, downhole hammer was selected to<br />

complete the job.<br />

North america<br />

April 2010 - <strong>Trenchless</strong> <strong>International</strong><br />

Representatives of Burns &<br />

McDonnell, Brierly Associates LLC, and<br />

Construction Drilling Inc. collaborated in<br />

the development of a plan to drill large<br />

diameter holes through the rock slope<br />

using the optically guided downhole<br />

hammers.<br />

The existing substation rests within a<br />

topographic “bowl”, and sits near the toe<br />

of a 35 foot high, vertical rock slope. With<br />

the close proximity of live electric facilities<br />

at the crest and toe of the slope, conventional<br />

rock excavation by blasting was not<br />

feasible, and a rock breaker would have<br />

been too expensive due to rock strength<br />

and work area restrictions. Therefore, it<br />

was determined that trenchless installation<br />

of the cables would be required to<br />

minimise impact to the slope and adjacent<br />

substation facilities.<br />

A powerful solution<br />

<strong>Trenchless</strong> design and construction<br />

planning was restricted by the presence of<br />

overhead, high voltage power lines at the<br />

crest and toe of the slope, and the requirement<br />

that the trenchless method could<br />

not use drilling fluid. This constraint was<br />

imposed by the substation owner, due to<br />

concerns about the impacts of inadvertent<br />

drill fluid returns on the adjacent electrical<br />

equipment. Although horizontal directional<br />

drilling (HDD) was initially considered as a<br />

possible means of completing the installation,<br />

it was eventually ruled out due to site<br />

access limitations, the need to use drill<br />

fluid, and relative cost.<br />

Based on these design constraints and<br />

the subsurface conditions, the design<br />

team recommended that the duct bank<br />

installation be completed in holes drilled<br />

with an optically guided downhole<br />

hammer, using methods perfected by<br />

Construction Drilling, Inc. (CDI), of western<br />

Massachusetts.<br />

Developing downhole hammers<br />

CDI has developed a means tracking<br />

downhole hammers during drilling.<br />

The guidance system consists of a target-mounted<br />

drill bit, theodolite, and<br />

monitor, which provides the operator with<br />

continuous, real-time information about<br />

the deviation of the desired drilling profile.<br />

Specially designed drill bits and drilling<br />

techniques permit steering. Prior to this<br />

project, CDI had used this technology to<br />

enable precision rock anchor installations<br />

in and around sensitive structures, including<br />

dams and bridge abutments.<br />

For this installation, the optimum trenchless<br />

layout was to install ducts in three<br />

holes; two at 28 inch diameter (electric<br />

ducts), and one at 18 inch diameter<br />

(grounding and communications ducts).<br />

This layout resulted in cost savings, as<br />

the tooling for holes larger than 28 inch<br />

diameter becomes significantly more<br />

expensive. Each of the holes was approximately<br />

60 feet long, located 10 feet apart<br />

(centre-to-centre), and inclined 30 degrees<br />

downward from horizontal. The holes were<br />

each drilled from the top of the rock slope<br />

downward into the substation.<br />

Ultimately, the staging and performance<br />

of the trenchless work for this project were<br />

governed by the overhead electric cables,<br />

which remained energised throughout<br />

construction. The situation was complicated<br />

by the tendency of these cables<br />

to expand and sag downward during<br />

periods of heavy energy loads. To ensure<br />

worker safety, a phased work plan was<br />

developed dictating maximum equipment<br />

height during construction. To meet the<br />

height restrictions, the surface grade in<br />

the vicinity of the drill entry was lowered<br />

by about 7 feet prior to mobilisation of<br />

the drill rig. This was done using small,<br />

low-profile equipment, including Bobcatmounted<br />

hoe rams and excavators.<br />

Using an (Egtechnology) EGT MD 3000<br />

multi-purpose anchor drill, CDI elected<br />

to use a multiple-pass approach for the<br />

drilling. This involved completing a pilot<br />

hole with an eight inch diameter hammer<br />

bit, followed by an 18 inch, and then a<br />

28 inch hammer. The rods required for<br />

this type of drilling need to be very stiff to<br />

accommodate the shallow alignment, and<br />

to withstand the stress needed to withstand<br />

the impact force imposed by the<br />

hammers. In this case, the rods ranged<br />

from 12 to 18 inches in diameter, and were<br />

equipped with a hexagonal quick-release<br />

joint.<br />

The 18 and 28 inch hammers were<br />

equipped with a leading edge extension,<br />

or “stinger”, designed to follow<br />

the pilot hole. The 28 inch hammer was<br />

designed specifically for this project, and<br />

was forged from a single block of steel.<br />

Like most downhole hammers, the tools<br />

employed by CDI are driven by air, with<br />

a velocity of about 3,000 feet per second.<br />

The air exits the hammer face, where it<br />

then serves to remove the cuttings from<br />

the hole. In an effort to protect the adjacent<br />

electric facilities, all cuttings and<br />

dust generated during drilling were captured<br />

in a stuffing box and diverted to an<br />

adjacent containment device, before the<br />

air was discharged into the atmosphere.<br />

The vibrations generated by this equipment<br />

were minimal, well below the site<br />

threshold of 0.5 inches per second, and<br />

the noise generated the hammers was likened<br />

to that an large excavator-mounted<br />

impact hammer (ie, a hoe ram).<br />

During drilling, the passage of the 8 inch<br />

pilot and 18 inch hammer were completed<br />

without issue; each appearing at the toe of<br />

the slope within 6 inches of the surveyed<br />

High Tech in <strong>Trenchless</strong> Technology<br />

35 years of Swiss Engineering<br />

Underground Piercing (Moles)<br />

from Ø 45-190 mm (1.75“-7.5“)<br />

exit point. It was noted during drilling,<br />

however, that there was a “soft” zone in<br />

the rock, approximately 30 feet from the<br />

drill entry location. The soft zone was<br />

interpreted to represent a zone of highly<br />

weathered rock, parallel the high-angle<br />

foliation observed in the rock mass. To<br />

maintain the line and grade across this<br />

zone, the heavier, 28 inch hammer was<br />

equipped with an 8 foot long, 27 inch<br />

diameter steel “barrel” shroud intended to<br />

help bridge the soft zones in the rock, and<br />

keep the bit from dropping during drilling.<br />

Drilling with the shroud proved effective,<br />

although the decreased annulus diminished<br />

the efficiency of cuttings removal,<br />

which in turn caused occasional jamming<br />

of the tools. Although drilling with the<br />

shroud was somewhat more time consuming,<br />

the 28 inch hammer ultimately exited<br />

the toe of the rock slope with six inches of<br />

the design alignment for each hole, which<br />

was well within the limits required for successful<br />

duct installation.<br />

Following completion of the holes, and<br />

duct bundles were assembled using<br />

mechanically-coupled PVC, that minimised<br />

the need for bundle lay-down room.<br />

Following installation of the duct dandles,<br />

a concrete bulkhead was cast at the bottom<br />

of each hole, and the annulus around<br />

the installed duct was tremie-grouted with<br />

a thermal grout.<br />

HDD Machines for directional bores<br />

up to 400 m (1‘300 ft) and Ø 1’000 mm (40”)<br />

TERRA AG, Hauptstrasse 92, 6260 Reiden, Switzerland<br />

phone: +41-62-749 10 10 fax: +41-62-749 10 11 e-mail: terra.ch@bluewin.ch www.terra-eu.eu<br />

Cable Bursters with pulling forces<br />

up to 40 tons (88‘000 lbs)<br />

North america<br />

April 2010 - <strong>Trenchless</strong> <strong>International</strong><br />

32<br />

33

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!