A S T O R I A<br />

G E N E R A T I N G<br />

A Draft Scope of Work was issued by NYSDEC on July 7, 2010 and Final Scope issued<br />

on November 10, 2010<br />

AGC filed an Air Permit Application on August 30, 2010<br />

AGC filed a DEIS on December 14, 2010 and revised the document on May 20, 2011<br />

and June 30, 2011<br />

AGC filed a revised Air Permit Application on May 20, 2011 and June 30, 2011<br />

NYS DEC issued a Notice of Completion of the DEIS on June 29, 2011<br />

NYSDEC issued a draft Title IV and V Air permit on June 29, 2011<br />

NYSDEC held a public hearing on the DEIS on August 24, 2011<br />

LCEP has been assigned Queue position #361 by the NYISO<br />

On May 25, 2012 AGC submitted a revised Feasibility Study to the NYISO for their<br />

review.<br />

Other<br />

considerations<br />

Key uncertainties in federal, State and local project permitting and suggestions for how such uncertainties<br />

can be addressed<br />

The project has received draft air permits and has been through the public hearing and comment<br />

period on the DEIS. The remaining items to be addressed include the CO2 PSD requirement and<br />

some minor adjustments on overall emissions to achieve a net reduction which can be readily addressed<br />

in a short period of time. There are no major uncertainties remaining.<br />

Other Considerations, if applicable<br />

Issues or challenges the proposal faces and suggestions for how these issues and challenges<br />

can be addressed for the project and future projects.<br />

There are no other issues or challenges facing the LCEP other than market conditions.<br />

Additional<br />

Information<br />

Property<br />

Ownership of the potential project location(s), and the extent to which the project would utilize<br />

existing rights-of-way and/or previously disturbed land.<br />

The LCEP will be constructed on previously disturbed industrially zoned land that is<br />

owned by AGC.<br />

Projected in-service date and project schedule<br />

Timeline for development and financing of the potential project, culminating in the commercial<br />

operation of the project, that includes preliminary engineering and licensing, detailed engineering<br />

and design, permitting, procurement of major equipment, construction, testing and commissioning.<br />

Preliminary engineering has been completed to the point required to prepare and file<br />

the applicable permit applications. The permitting process is well advanced as noted<br />

above and should be completed in less than six months. An estimated time line is appended<br />

as attachment A.<br />

<strong>THE</strong> <strong>LUYSTER</strong> <strong>CREEK</strong> <strong>ENERGY</strong> <strong>PROJECT</strong> MAY 30, 2012<br />

8