A S T O R I A<br />
G E N E R A T I N G<br />
A Draft Scope of Work was issued by NYSDEC on July 7, 2010 and Final Scope issued<br />
on November 10, 2010<br />
AGC filed an Air Permit Application on August 30, 2010<br />
AGC filed a DEIS on December 14, 2010 and revised the document on May 20, 2011<br />
and June 30, 2011<br />
AGC filed a revised Air Permit Application on May 20, 2011 and June 30, 2011<br />
NYS DEC issued a Notice of Completion of the DEIS on June 29, 2011<br />
NYSDEC issued a draft Title IV and V Air permit on June 29, 2011<br />
NYSDEC held a public hearing on the DEIS on August 24, 2011<br />
LCEP has been assigned Queue position #361 by the NYISO<br />
On May 25, 2012 AGC submitted a revised Feasibility Study to the NYISO for their<br />
review.<br />
Other<br />
considerations<br />
Key uncertainties in federal, State and local project permitting and suggestions for how such uncertainties<br />
can be addressed<br />
The project has received draft air permits and has been through the public hearing and comment<br />
period on the DEIS. The remaining items to be addressed include the CO2 PSD requirement and<br />
some minor adjustments on overall emissions to achieve a net reduction which can be readily addressed<br />
in a short period of time. There are no major uncertainties remaining.<br />
Other Considerations, if applicable<br />
Issues or challenges the proposal faces and suggestions for how these issues and challenges<br />
can be addressed for the project and future projects.<br />
There are no other issues or challenges facing the LCEP other than market conditions.<br />
Additional<br />
Information<br />
Property<br />
Ownership of the potential project location(s), and the extent to which the project would utilize<br />
existing rights-of-way and/or previously disturbed land.<br />
The LCEP will be constructed on previously disturbed industrially zoned land that is<br />
owned by AGC.<br />
Projected in-service date and project schedule<br />
Timeline for development and financing of the potential project, culminating in the commercial<br />
operation of the project, that includes preliminary engineering and licensing, detailed engineering<br />
and design, permitting, procurement of major equipment, construction, testing and commissioning.<br />
Preliminary engineering has been completed to the point required to prepare and file<br />
the applicable permit applications. The permitting process is well advanced as noted<br />
above and should be completed in less than six months. An estimated time line is appended<br />
as attachment A.<br />
<strong>THE</strong> <strong>LUYSTER</strong> <strong>CREEK</strong> <strong>ENERGY</strong> <strong>PROJECT</strong> MAY 30, 2012<br />