EXECUTIVE SUMMARY<br />
The Electricity Generation Customer Choice and Competition Act<br />
mandates that the <strong>Pennsylvania</strong> <strong>Public</strong> <strong>Utility</strong> <strong>Commission</strong> (<strong>Commission</strong>) ensure<br />
that levels of reliability that existed prior to the restructuring of the electric utility<br />
industry continue in the new competitive markets. Act of December 3, 1996, P.L.<br />
802, No. 138, 66 Pa.C.S. Sec. 2801 et. seq.<br />
In response to this mandate, the <strong>Commission</strong> adopted reporting<br />
requirements designed to ensure the continuing safety, adequacy and reliability<br />
of the generation, transmission and distribution of electricity in the<br />
Commonwealth. 1 The <strong>Commission</strong> also established reliability benchmarks and<br />
standards to measure the performance of each electric distribution company<br />
(EDC). 2 Given the uncertainty of weather and other events that can affect reliability<br />
performance, the <strong>Commission</strong> has stated that EDCs should set goals to achieve<br />
benchmark performance in order to prepare for those times when unforeseen<br />
circumstances push the indices above the benchmark. 3 In recognition of these<br />
unforeseen circumstances, the <strong>Commission</strong> set the performance standard as the<br />
minimum level of EDC reliability performance. The standard is the level of<br />
performance beyond which the company must either justify its poor performance<br />
or provide information on the corrective measures it will take to improve<br />
performance. Performance that does not meet the standard for any reliability<br />
measure may be the threshold for triggering additional scrutiny and potential<br />
compliance enforcement actions.<br />
In 2005, two of the 11 EDCs failed to meet their rolling 12-month<br />
performance standards for the average duration of service outages per affected<br />
customer, while six EDCs performed better than the benchmark. Four EDCs<br />
failed to meet their rolling 12-month performance standards for the average<br />
frequency of service outages per customer, while five EDCs performed better<br />
than the benchmark. Five EDCs petitioned the <strong>Commission</strong> to amend their<br />
performance benchmarks and standards. The <strong>Commission</strong> adjusted<br />
benchmarks and standards for four of these EDCs. 4 As of the release of this<br />
document, the <strong>Commission</strong> has not yet issued a final decision on the remaining<br />
petition. 5<br />
1 Docket No. L-00970120; 52 Pa. Code §§ 57.191-57.197.<br />
2 Docket No. M-00991220.<br />
3 Docket No. M-00991220, page 25.<br />
4 Docket No. M-00991220F0003 and P-00042115.<br />
5 Docket No. M-00991220F0002.