DHV Group<br />
Borehole drilling near Abong Mbang<br />
Still, during his field visit Mr. Frank Jansink observed that borehole drilling was ongoing at a site near<br />
Abong Mbang.<br />
It appears that from Phase 3 onwards 3 or 4 standard ‘designs’ are being used, with fixed unit prices:<br />
– Type A spring protection, difficult: CFA 3,900,000 9 or: € 5945 (e.g. Bartombo, <strong>Bertoua</strong> II, Ndoumbi<br />
A);<br />
– Type B spring protection, medium; CFA 2,600,000 or: € 3964 (e.g. Bonice);<br />
– Type C spring protection, easy: CFA 1,650,000 or: € 2515 (e.g. Gouverneur);<br />
– Hand-dug well: CFA 3,500,000 (€ 5336) + CFA 2,500,000 (€ 3811) <strong>for</strong> handpump (inclusive of<br />
import duties, customs, transport)<br />
Local conditions differ, however, and apparently the contractor has to fit actual costs within the fixed unit<br />
price. This has – in several cases – adversely influenced the quality of the structures, notably by the<br />
omission of rein<strong>for</strong>cement steel to save on total costs. In general, there appears to be little or no check on<br />
actual costs of construction. As a consequence, the quality of works completed recently appears to be<br />
lacking.<br />
3.5 Project implementation and management capacity<br />
The <strong>Water</strong> Committee of RC <strong>Bertoua</strong>, and specifically its Chairman, plays an important role in the local<br />
realization of the Project. The relatively small membership of RC <strong>Bertoua</strong> could be considered a risk, as<br />
replacement of members of the <strong>Water</strong> Committee in case of need may be difficult to realize. The Rotary<br />
Club <strong>Bertoua</strong> has set a target to grow from the current 6 members to 12 members in 2010 and 20<br />
members in the more distant future, but there is no indication when this could be realized – if at all.<br />
Local contractors implement the project. The first of these, Laurent Esse, worked 19 years <strong>for</strong> Care, and<br />
thus gained an extensive experience with springs and wells. He was involved from the start of the project,<br />
but was subsequently replaced by another contractor. The reason <strong>for</strong> this was mentioned to be his<br />
9<br />
A cost break-down given by Abidjane <strong>for</strong> a spring protection type A results in a total of CFA 4,180,000 or: € 6372, as<br />
follows:<br />
Preparation: CFA 30,000 (€ 46, or: 0.7%)<br />
Earthwork: CFA 800,000 (€ 1,220, or: 19.1%)<br />
Foundation, concrete, stone walls, spring tapping structure, drainage channel: CFA 1,500,000 (€ 2,287, or: 35.9%)<br />
Storage tanks, slabs, floor, stairs, laundry slab, drainage: CFA 1,700,000 (€ 2,591, or: 40.7%)<br />
Miscellaneous works: CFA 150,000 (€ 229, or: 3.6%)<br />