DHV Group<br />
4.1.2 Interviews and meetings<br />
A number of meetings, visits and introductions were held:<br />
– in<strong>for</strong>mal meetings with the Chairman and members of RC <strong>Bertoua</strong>’s <strong>Water</strong> Committee;<br />
– meetings with Mutcare and GIC/Rasaad;<br />
– workshop with Mutcare and users of water points;<br />
– meeting with the Mayor of <strong>Bertoua</strong>;<br />
– introduction to the <strong>Water</strong> Administration <strong>for</strong> East Province;<br />
– various discussions with Mr. Medou, the Engineer notably <strong>for</strong> Phase 1;<br />
– visit to the water supply company of <strong>Bertoua</strong>.<br />
4.2 Location with respect to latrines and solid waste dumping places<br />
The location of latrines or solid waste dumping places appears not to be considered in locating the water<br />
points at all. Also otherwise, the selection of sites appears to be based on <strong>for</strong>ce of habit rather than<br />
technical of geohydrological surveys. Protected springs appear to be more vulnerable to contamination by<br />
such places than dug wells, as the water is collected at very shallow depths. This aspect should be taken<br />
into account more seriously when weighing the pros and cons of spring tappings versus wells with<br />
handpumps.<br />
Waste dump in immediate surroundings<br />
of well site<br />
4.3 Appropriateness of design<br />
The method of construction of the water points during phases 4 and 5 mostly resembles a Design &<br />
Construct approach, however without proper checks on the design, with a lack of design drawings and<br />
tender documents, bills of quantities, etc., and without proper supervision. Even though the results appear<br />
to be reasonable, the vast knowledge and expertise of an engineer like Mr. Medou is hardly used.<br />
Currently used designs are of a sketchy nature at best.<br />
4.4 Maintenance period<br />
The contract <strong>for</strong> the construction of water points as used <strong>for</strong> the earlier phases envisages a maintenance<br />
period of half a year. The contract document stipulates that 5% of the contract sum is retained, and that<br />
after 6 months a check is carried out on the status of the water point, and any deficits need to be<br />
addressed by the contractor. It is unclear whether the maintenance period applies to the later phases<br />
(from phase 4 onward) as well.<br />