ERICKSON-HALL<br />

P R O G R A M M A N A G E M E N T<br />

Measure R 20<strong>06</strong> <strong>Bond</strong><br />

Program Update Presentation<br />

<strong>Rowland</strong> <strong>Unified</strong> <strong>School</strong> <strong>District</strong><br />

June <strong>22</strong>, 20<strong>10</strong><br />

Khary Knowles, Program Manager<br />

© 2009 <strong>Erickson</strong>-<strong>Hall</strong> 500 Corporate Drive Escondido, CA 92029 USA Phone (760) 796-7700 Web www.ericksonhall.com


Measure R 20<strong>06</strong> <strong>Bond</strong><br />

Program Update: AGENDA<br />

Program Update – June <strong>22</strong>, 20<strong>10</strong><br />

1. Scope<br />

2. Schedule<br />

a. Master Schedule (to date)<br />

3. Budget<br />

a. Consolidated Expenditure <strong>Report</strong><br />

b. Budget Summary <strong>Report</strong>s<br />

c. “Underfunded” projects and CM service<br />

fees<br />

2


A. Program Update<br />

Scope<br />

Current Projects: 31<br />

A. 21 schools<br />

B. 4 CTE projects<br />

• Nogales HS: Autoshop and Business<br />

• <strong>Rowland</strong> HS: Culinary Arts/JAR and Business<br />

C. 3 Portables projects<br />

1. Ybarra Academy<br />

2. Blandford ES<br />

3. Nogales HS<br />

D. NHS Library<br />

E. Trailer Projects<br />

1. Giano IS (3)<br />

2. Oswalt Academy (3 trailers for 5 classrooms)<br />

3


A. Program Update<br />

Schedule (Construction: Fall 2009 – 2013)<br />

A. Projects Completed: 2<br />

B. Projects in Construction: 5<br />

C. Projects out to Bid: 2<br />

D. Projects in Planning for Bid: 2<br />

E. Projects Approved by DSA: 11<br />

F. Projects in DSA for approval: 7<br />

G. Projects in Design: 2<br />

Entering Year 4, there are eleven projects ready for<br />

construction with none of those projects approved to<br />

go out to bid. It is our recommendation that the<br />

<strong>Bond</strong> Program be expedited in order to meet the<br />

original goal of a 2013 completion date and also to<br />

take advantage of a financially advantageous bid<br />

climate.<br />

4


A. Program Update<br />

Schedule (cont.)<br />

A few ways to accomplish this goal of expediting the<br />

Construction Schedule of the Program include:<br />

1. Supplement Construction Management staff<br />

a. Outside CM firm is being reviewed<br />

2. Group projects together<br />

a. Bid out 4-5 projects to the same contractor<br />

3. Utilize the closed schools for interim housing<br />

a. Currently gaining information from the <strong>School</strong><br />

Closure Transition team<br />

5


A. Program Update<br />

Schedule (cont.)<br />

Master Schedule (to date)<br />

Original<br />

Actual<br />

Project<br />

Duration<br />

Start Date<br />

Finish Date<br />

6


A. Program Update<br />

Budget: $138,200,000 (Ideal: $145,700,000)<br />

Budget Status <strong>Report</strong>s:<br />

1.Consolidated Expenditure <strong>Report</strong><br />

2.Budget Summary<br />

a. With graphics<br />

7


A. Program Update<br />

Budget (cont.)<br />

Consolidated Expenditure <strong>Report</strong>:<br />

• BUDGET<br />

• COMMITTED<br />

CONTRACTS<br />

• EXPENDITURES<br />

• CONTRACT<br />

BALANCE<br />

• % EXPENDED<br />

• BUDGET<br />

VARIANCE<br />

8


Budget Status<br />

Summary <strong>Report</strong>:<br />

• BUDGET<br />

• COMMITTED CONTRACTS<br />

• EXPENDITURES<br />

• REMAINING FUNDS<br />

• BUDGET VARIANCE<br />

A. Program Update<br />

Budget (cont.)<br />

State Auditing<br />

Category<br />

Object Code<br />

#6250:<br />

Construction<br />

Amount<br />

9


A. Program Update<br />

Budget (cont.)<br />

“Unfunded” Construction Costs v. Possible Fund Sources<br />

Sources Amt. Needed Poss. Funds<br />

Unreleased State Funds<br />

$ <strong>10</strong> million<br />

Construction Management Services $ 3-6 million<br />

Bid Climate Savings (ave. 33%;<br />

conservative = <strong>10</strong>% of $90M)<br />

<strong>School</strong> Consolidation Remaining<br />

Budget (conservative)<br />

Approx. Total $ 16 million<br />

Approx. Total<br />

$9 million*<br />

$7 million<br />

$ 16 million*<br />

*Note: Bid Savings dollars are “at risk” because they are not dollars<br />

“in hand”. Bid Climate Savings may be dependent upon timing and<br />

speed of construction.<br />

<strong>10</strong>


A. Program Update<br />

Summary<br />

In summary, there are two (2) topics that require<br />

attention in order to maintain the fiduciary<br />

responsibilities of the <strong>Bond</strong>. It is our opinion that:<br />

1.The Program schedule should be expedited through<br />

the construction process and<br />

2.Budget decisions should be made regarding<br />

underfunded projects and CM Service fees.<br />

11


ERICKSON-HALL<br />

P R O G R A M M A N A G E M E N T<br />

THANK YOU<br />

June <strong>22</strong>, 20<strong>10</strong><br />

Khary Knowles, Program Manager<br />