A. Program Update<br />
Schedule (Construction: Fall 2009 – 2013)<br />
A. Projects Completed: 2<br />
B. Projects in Construction: 5<br />
C. Projects out to Bid: 2<br />
D. Projects in Planning for Bid: 2<br />
E. Projects Approved by DSA: 11<br />
F. Projects in DSA for approval: 7<br />
G. Projects in Design: 2<br />
Entering Year 4, there are eleven projects ready for<br />
construction with none of those projects approved to<br />
go out to bid. It is our recommendation that the<br />
<strong>Bond</strong> Program be expedited in order to meet the<br />
original goal of a 2013 completion date and also to<br />
take advantage of a financially advantageous bid<br />
climate.<br />
4