A. Program Update<br />

Schedule (cont.)<br />

A few ways to accomplish this goal of expediting the<br />

Construction Schedule of the Program include:<br />

1. Supplement Construction Management staff<br />

a. Outside CM firm is being reviewed<br />

2. Group projects together<br />

a. Bid out 4-5 projects to the same contractor<br />

3. Utilize the closed schools for interim housing<br />

a. Currently gaining information from the <strong>School</strong><br />

Closure Transition team<br />