FUNDING OUTLOOK AND SHORTFALL<br />

Total<br />

Deferred Projects<br />

Project <strong>Budget</strong><br />

69th Street Parking Garage $22,600,000<br />

Ardmore Transportation Center, Paoli Line 15,831,000<br />

Berridge Shop Roof Replacement 12,600,000<br />

BSS Erie Station ADA 7,500,000<br />

BSS Snyder Station ADA 5,000,000<br />

Chestnut Hill West Bridge 0.35 replacement 9,869,000<br />

City Hall Station 100,000,000<br />

Elwyn to Wawa Improvements 80,000,000<br />

Exton Station, Paoli Line 5,000,000<br />

Levittown Station, Trenton Line 34,300,000<br />

Loop <strong>Program</strong> - 23rd & Venango, 33rd & Dauphin, 61st & Pine <strong>and</strong> Wycombe 8,600,000<br />

Loop <strong>Program</strong> – Parkside<br />

Funded<br />

MSFE 5th Street Station 10,100,000<br />

MFSE 40th Street Station ADA 6,000,000<br />

MFSE Margaret-Orthodox Station ADA 32,500,000<br />

New Payment Technology<br />

Loan Secured<br />

Paoli Line Amtrak Interlockings/Signals - Phase 2 44,000,000<br />

Paoli Transportation Center 40,000,000<br />

Parking Expansions / Improvements 62,600,000<br />

RRD Substation Improvements 67,000,000<br />

Vehicle Washer - Frazer <strong>and</strong> Frontier 5,090,000<br />

Villanova Station, Paoli Line 22,900,000<br />

Wayne Junction Station<br />

Funded<br />

25