INFRASTRUCTURE SAFETY RENEWAL PROGRAM<br />

Signals <strong>and</strong> Communications Systems<br />

• Installation of st<strong>and</strong>ard communications infrastructure, consisting of lateral copper <strong>and</strong> fiber optic cables, on the Airport<br />

Regional Rail Line.<br />

• Replacement of the existing copper-connected communications modems in all field Remote Terminal Units (RTU) with fiber<br />

optics units between 16 th Street Interlocking <strong>and</strong> "K" Interlocking on the Regional Rail Main Line.<br />

• Refurbishment of public address control units at all passenger stations on the Doylestown Regional Rail Line.<br />

• Replacement of computer-based remote train control equipment (TCE) on the Market-Frankford Line <strong>and</strong> on the Regional Rail<br />

System.<br />

<strong>FY</strong> <strong>2012</strong> FUNDING SOURCE: FTA ___ FHWA ___ STATE ACT 44 _X_ LOCAL _X_<br />

CAPITAL INVESTMENT CATEGORY: STATE OF GOOD REPAIR _X_ NORMAL REPLACEMENT ___ SYSTEM IMP. ___ SYSTEM EXPANSION ___<br />

SERVICE AREA: BUCKS, CHESTER, DELAWARE AND MONTGOMERY COUNTIES AND THE CITY OF PHILADELPHIA<br />

PRIOR FUNDING <strong>FY</strong> <strong>2012</strong> FUNDING <strong>FY</strong> 2013-2015 <strong>FY</strong> 2016-<strong>2023</strong> TOTAL COST<br />

$0 $34,400,000 $103,700,000 $276,000,000 $414,100,000<br />