Presentation on Case I & Case II Bidding Projects ... - Infraline
Presentation on Case I & Case II Bidding Projects ... - Infraline
Presentation on Case I & Case II Bidding Projects ... - Infraline
You also want an ePaper? Increase the reach of your titles
YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.
C<strong>on</strong>cerns – <strong>Case</strong> 2 <strong>Bidding</strong><br />
‣ <strong>Case</strong> 2 Bids are not being invited by the States in expeditious manner, due<br />
to the following key issues –<br />
a. Difficulty in Land Acquisiti<strong>on</strong><br />
b. Firm Fuel arrangement<br />
c. Delay in Envir<strong>on</strong>mental Clearance<br />
Example<br />
State<br />
Karnataka<br />
Project<br />
PCKL is trying its best to select the developer for establishment<br />
of 1320 MW of Gulbarga (Jewargi) Thermal Power Plant through<br />
competitive bidding since 2007, however due to n<strong>on</strong>-availability<br />
of fuel – the bid is still <strong>on</strong> hold (after RFQ).