Little Sackville River Digger Log Installation 2009 - The Atlantic ...
Little Sackville River Digger Log Installation 2009 - The Atlantic ...
Little Sackville River Digger Log Installation 2009 - The Atlantic ...
Create successful ePaper yourself
Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.
<strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> <strong>Digger</strong> <strong>Log</strong><br />
<strong>Installation</strong> <strong>2009</strong><br />
Prepared for the <strong>Atlantic</strong> Salmon Conservation<br />
Foundation 2008 Restoration Contract<br />
September 1 st , <strong>2009</strong><br />
Kate MacPhee, John‐William Brunner and Cyndi LeBlanc<br />
0 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Table of Contents<br />
Table of Contents ............................................................................................................................ 1<br />
Acknowledgements ......................................................................................................................... 2<br />
Introductory Information for <strong>2009</strong> <strong>Digger</strong> <strong>Log</strong> <strong>Installation</strong> and Maintenance ............................... 4<br />
Work Area <strong>2009</strong> ............................................................................................................................... 6<br />
<strong>Digger</strong> <strong>Log</strong> Schematic ...................................................................................................................... 7<br />
Structure Descriptions ..................................................................................................................... 8<br />
Electro‐Fishing Survey on <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> July 2 <strong>2009</strong> .......................................................... 25<br />
Concluding Remarks ...................................................................................................................... 29<br />
Appendix A – Budget ..................................................................................................................... 30<br />
Appendix B – Press Release ........................................................................................................... 31<br />
Appendix C – Press Coverage ........................................................................................................ 32<br />
1 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Acknowledgements<br />
Kate MacPhee<br />
I would like to thank the <strong>Sackville</strong> <strong>River</strong>s Association for the opportunity to work with them this<br />
summer. This is my first summer working with the SRA, and I have been a member/volunteer<br />
with the association for about a year. I graduated from <strong>Sackville</strong> High School in 2004 and I<br />
graduated from Dalhousie University in May <strong>2009</strong> with a B.Sc. in Marine Biology, and am<br />
interested in ecology. I am employed with the <strong>Sackville</strong> <strong>River</strong>s Association through the Nova<br />
Scotia Youth Conservation Corps. This summer my main project was to oversee the installation<br />
of digger logs along the Lower <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong>. I have also taken part in the <strong>Sackville</strong> <strong>River</strong>s<br />
Association’s education program, salmon and trout stocking through DFO, bi‐weekly water<br />
quality monitoring, and volunteer cleanups. I would like to thank the Nova Scotia Youth<br />
Conservation Corps for the opportunity to work for the <strong>Sackville</strong> <strong>River</strong>s Association this summer.<br />
I feel as though my experience through the summer will be a great asset to me. I would love to<br />
find a career in fisheries or ocean management.<br />
Cyndi LeBlanc<br />
This has been my first year working with the SRA. I would like to extend sincere<br />
gratitude to the <strong>Sackville</strong> <strong>River</strong>s Association for providing me with the opportunity to explore a<br />
work term with them this summer. I graduated from <strong>Sackville</strong> High School in 2008 and currently<br />
attend Dalhousie University. My interest in environmental issues was sparked at a young age<br />
while participating in the Girl Guides of Canada programs. While working on our river<br />
restoration projects, I have gained a greater appreciation for the community that I live in and<br />
the individuals who contribute to it. I am extremely proud to have such a strong and active<br />
environmental NGO in my hometown, and I am humbled by the true dedication and passion I<br />
have witnessed by volunteers and employees this summer. This was the first time I have<br />
worked in the environmental field, and I hope to continue with the SRA as a volunteer.<br />
John William‐Brunner<br />
I am very thankful to have been employed by the SRA this summer. This is my first<br />
opportunity working here, and my first time living in Nova Scotia. I am from Huntsville Ontario,<br />
and recently graduated from the Ecosystem Management Program at Sir Sandford Fleming<br />
College, in Lindsay Ontario. Last summer I worked on a Northern Flying Squirrel research project<br />
in Fundy National Park and became very fond of the Maritimes. I have had an excellent<br />
experience so far this summer; it’s very satisfying to know many of the things I learned and<br />
practiced in college apply to the real world. It has been great being a part of the restoration and<br />
enhancement of a river and seeing the positive changes first hand. I am extremely thankful to<br />
the NSYCC for giving me, and the rest of our crew, the chance to participate in such great work.<br />
Thank you<br />
We would like to thank the <strong>Atlantic</strong> Salmon Conservation Foundation for funding the<br />
project and both the Nova Scotia Youth Conservation Corps and the Economic and Rural<br />
2 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Development Employment Program for the opportunity to work with the <strong>Sackville</strong> <strong>River</strong>s<br />
Association for the summer. Thank you to Dave Barrett for providing us with the logs to do the<br />
work. Thanks to Thaumus Environmental Consultants for surveying the Lower <strong>Little</strong> <strong>Sackville</strong><br />
<strong>River</strong> and mapping out the digger log locations. Also thanks to Amy Weston from Adopt‐a‐<br />
Stream for helping lay out the river pattern last year.<br />
We would also like to thank Stephen Caines, the SRA Coordinator, for hiring us for the<br />
summer. It was a great pleasure to work with Stephen through the summer and he often<br />
helped out in the field whenever possible. We would also like to thank Colin O’Neil, the SRA<br />
Assistant Coordinator, for organizing the Lower <strong>Little</strong> <strong>Sackville</strong> Project. Colin was a valuable<br />
member of our field team, coming out in the field for most of the summer and his help was<br />
greatly appreciated. Also thank you to Walter N. Regan, president of the SRA, for his guidance<br />
and positivity.<br />
3 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Introductory Information for <strong>2009</strong> <strong>Digger</strong> <strong>Log</strong> <strong>Installation</strong> and<br />
Maintenance<br />
This year, digger logs were installed in the <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> (LSR) between Hallmark<br />
Avenue and the LSR confluence with the <strong>Sackville</strong> <strong>River</strong> (Fig. 1 and Fig. 2.). A number of logs had<br />
been installed in the LSR years before, yet some were positioned incorrectly and needed to be<br />
changed. Some elements of the river have changed since the logs had been installed and a<br />
hydrology study has projected a different pattern for the river. This year there were seventeen<br />
new logs installed and twelve sites that had to be maintained from previous years. <strong>The</strong>re were<br />
also more sites maintained that are not included in this report. <strong>The</strong> new logs were<br />
approximately eight inches in diameter and five meters long. Most logs were reused from<br />
previous years but new hardwood logs were used for the newly installed logs.<br />
Along this section of the LSR the desired river width is 5.4 meters. Based on this<br />
estimate, there was a distance of 32 meters between each log (six times the river width). In<br />
some instances the wetted width (distance between the beginning of the deflector and the end<br />
of the upstream side of the log) is less than the desired length. This arises because the river can<br />
be narrower than 5.4m or much wider. It has been found during previous projects that when the<br />
pattern is not followed the effectiveness of the logs is greatly reduced. <strong>The</strong>se logs alternate<br />
between left and right pools, the alternating pattern is established to recreate the natural flow<br />
of the river. Some areas of the river were too wide to install one log and two logs were pinned<br />
together to cross the entire river width. In some sections of the river the water was too deep to<br />
install a log. <strong>The</strong>se areas often already had a large pool, which we would improve by removing<br />
additional substrate material.<br />
<strong>Digger</strong> logs have been used for river restoration and to improve fish habitat in the<br />
<strong>Sackville</strong> <strong>River</strong> Watershed for almost twenty years. <strong>Digger</strong> logs imitate naturally fallen trees and<br />
create pools for fish to spawn. Deepening the area immediately following the digger log creates<br />
the pool, which act as areas of refuge and protection for the fish. <strong>The</strong> logs provide oxygenated<br />
water for the fish as well as restore the natural pattern of the river that has been lost over time.<br />
<strong>The</strong> logs also move substrate from the riverbed and deposit it along the shoreline. This prevents<br />
erosion of the riverbank and removes harmful silt from fish spawning areas.<br />
<strong>Digger</strong> logs are installed by pinning them to the substrate using one meter lengths of<br />
rebar. <strong>The</strong> logs are installed at a horizontal angle of 30° and at a vertical angle of 3° (Figure 3).<br />
<strong>The</strong> vertical angle is angled down towards the pool side of the log. <strong>The</strong> pool side is located on<br />
the upstream side of the log and the desired depth is one meter deep. <strong>The</strong>se angles help<br />
restore the natural meander to the river. On the opposite side of the log there is a deflector<br />
located on the downstream side of the log. <strong>The</strong> deflector is angled perpendicular to the log and<br />
reaches to the bank of the river. To help stabilize the deflector from washing out, large rocks or<br />
logs are also placed around the outer edge, acting as a wall. <strong>The</strong> deflector is then backfilled with<br />
rock so it slopes of to the bank naturally. <strong>The</strong> deflector helps to narrow the river to the desired<br />
width and concentrates water flow to improve digging action during high water conditions. On<br />
the upstream side of the log a ramp is created with smaller and flat rocks. <strong>The</strong> ramp helps to<br />
redirect ice over the log during the winter. <strong>The</strong> ramp gently slopes up from the river bottom to<br />
the top of the log. Without the ramp winter ice could wash out the log. <strong>The</strong> ramp also helps<br />
create the digging action by forcing the water over the log.<br />
4 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Table 1. Each site number with the corresponding GPS location and structure type for the Lower<br />
<strong>Little</strong> <strong>Sackville</strong> <strong>River</strong>.<br />
Site Number GPS Type of Structure<br />
43 44.76045°N, 63.67675°W Right digger log<br />
44 44.76007°N, 63.67674°W Left rock sill<br />
45 44.75985°N, 63.67650°W Right rock sill<br />
48 44.75914°N, 63.67624°W Right digger log<br />
49 44.75892°N, 63.67631°W Left digger log<br />
50 44.75866°N, 63.67652°W Right digger log<br />
51 44.75838°N, 63.67666°W Left digger log<br />
52 44.75785°N, 63.67679°W Right digger log<br />
53 44.75785°N, 63.67681°W No structure<br />
54 44.75760°N, 63.67664°W No structure<br />
55 44.75744°N, 63.67635°W No structure<br />
56 44.75746°N, 63.67600°W No structure<br />
57 44.75766°N, 63.67590°W No structure<br />
58 44.75764°N, 63.67563°W Right digger log<br />
59 44.75759°N, 63.67510°W Left digger log<br />
60 44.75754°N, 63.67470°W Right digger log<br />
61 44.75755°N, 63.67438°W No structure<br />
62 44.75728°N, 63.67418°W Right digger log<br />
63 44.75698°N, 63.67397°W Left digger log<br />
64 44.75676°N, 63.67377°W Right digger log<br />
65 44.75642°N, 63.67344°W Left digger log<br />
66 44.75628°N, 63.67322°W Right digger log<br />
67 44.75635°N, 63.67322°W No structure<br />
68 44.75621°N, 63.6722°W Left digger log<br />
69 44.75607°N, 63.67239°W Right digger log<br />
70 44.75586°N, 63.67216°W Left digger log<br />
71 44.75572°N, 63.67177°W Right digger log<br />
72 44.7550°N, 63.67127°W Left digger log<br />
73 44.75508°N, 63.67074°W Right digger log<br />
74 44.75492°N, 63.67039°W Left digger log<br />
75 44.75474°N, 63.67005°W Right digger log<br />
76 44.75481°N, 63.67005°W Left digger log<br />
77 44.75465°N, 63.6693°W Right digger log<br />
78 44.75438°N, 63.66906°W Left digger log<br />
79 44.75409°N, 63.66887°W Right digger log<br />
5 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Work Area <strong>2009</strong><br />
This year, our digger log installation and reinstallation work began in early June and continued<br />
until the end of July. <strong>The</strong> mapping of the new pattern was completed by Bob Rutherford, of<br />
Thaumus Environmental Consultants, in April <strong>2009</strong>.<br />
Figure 1. Area of the Lower <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> where work was performed, including marks for<br />
each digger log site.<br />
Figure 2. Area of the Lower <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> where work was performed.<br />
6 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
<strong>Digger</strong> <strong>Log</strong> Schematic<br />
Figure 3. <strong>Digger</strong> <strong>Log</strong> Schematic<br />
7 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure Descriptions<br />
Structure 43<br />
Location (44.76045°N, 63.67675°W)<br />
A log was removed from here in previous years and placed on the right bank for reuse. A right digger<br />
log was installed approximately 5m downstream from the previous site. A large tree was located in<br />
an ideal position for a deflector so the tree was used as part of the deflector. A small deflector was<br />
built on the right side as well to keep the bank from eroding. A line of large rocks was also placed at<br />
the end of the pool to keep the water from eroding the bank downstream. Upon completion the<br />
pool was 35cm deep and the wetted width was 5.90m.<br />
Structure 44<br />
Location (44.76007°N, 63.67674°W)<br />
A left rock sill was installed here in previous years. <strong>The</strong> rock sill was still intact, so we deepened the<br />
pool and improved the deflector. <strong>The</strong> pool was 35cm deep and the wetted width was 4.5 m.<br />
8 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 45<br />
Location (44.75985°N, 63.67650°W)<br />
A right rock sill was installed here in previous years. <strong>The</strong> rock sill was still intact, so we<br />
deepened the pool and built up the deflector. <strong>The</strong> pool may need to be maintained next year<br />
because most of the rocks next to the pool were small and easily transported back to the pool.<br />
Upon completion the pool was 38cm deep and the rock sill had a wetted width of 4.10.<br />
Structure 46<br />
Location (44.75971°N, 63.67632°W)<br />
A right log was installed last year; no maintenance was performed at this time.<br />
Structure 47<br />
Location (44.75951°N, 63.67609°W)<br />
No structure was installed here; the deep pool and large river bend did not necessitate a<br />
structure<br />
9 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 48<br />
Location (44.75914°N, 63.67624°W)<br />
A right log was installed here in previous years, consisting of two logs put together. <strong>The</strong> log was<br />
removed and both the horizontal and vertical angles were corrected. We performed<br />
maintenance and built the deflector out from its previous location to meet the newly installed<br />
log. <strong>The</strong> deflector was extremely large because of the length of the log. <strong>The</strong>re is also a large<br />
rock that was in front of the pool that was unable to be moved that may need to be moved in<br />
years to come. Upon completion the pool was 33cm deep and the wetted width was 5.90m.<br />
Structure 49<br />
Location (44.75892°N, 63.67631°W)<br />
A left log was installed here in previous years. General structure maintenance was performed.<br />
<strong>The</strong> ramp has sustained a lot of damage and substantial improvements were made. Upon<br />
completion the pool was 36cm deep and the wetted width was 5.8m.<br />
10 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 50<br />
Location (44.75866°N, 63.67652°W)<br />
A right log was installed here in previous years; general maintenance was performed at this site.<br />
Upon completion the pool was 31cm deep and the wetted width was 4.7m.<br />
Structure 51<br />
Location (44.75838°N, 63.67666°W)<br />
A left log was installed here in previous years; general maintenance was performed. <strong>The</strong> pool<br />
was fairly shallow so it needed to be improved quite a bit. Upon completion the pool was 36cm<br />
deep and the wetted width was 4.40m.<br />
11 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 52<br />
Location (44.75785°N, 63.67679°W)<br />
A right log was installed here in previous years. <strong>The</strong>re was a log moved up from a previous site<br />
approximately five meters downstream. <strong>The</strong> old deflector was still there, and we moved the<br />
large rocks up to the new log location. We also lined the right shore with large rocks, as there<br />
was a large amount of erosion. <strong>The</strong> pool was fairly shallow so it required a lot of digging. Upon<br />
completion the pool was 33cm deep and the wetted width was 6.8m.<br />
Structure 53<br />
Location (44.75785°N, 63.67681°W)<br />
No structure was installed here. <strong>The</strong> surrounding rock was too large for a digger log to work<br />
effectively and there was already a pool. <strong>The</strong> large pool was dug out and a small deflector was<br />
built upstream to the right of the pool. Upon completion the pool was 38cm deep.<br />
12 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 54<br />
Location (44.75760°N, 63.67664°W)<br />
No structure was installed here. Our environmental consultant is waiting to see if the hydrology<br />
of the river will change once machine work is performed at the s‐turn site.<br />
Structure 55<br />
Location (44.75744°N, 63.67635°W)<br />
No structure was installed here. Our environmental consultant is waiting to see if the hydrology<br />
of the river will change once machine work is performed at the s‐turn site.<br />
Structure 56<br />
Location (44.75746°N, 63.67600°W)<br />
No structure was installed here. Our environmental consultant is waiting to see if the hydrology<br />
of the river will change once machine work is performed at the s‐turn site.<br />
Structure 57<br />
Location (44.75766°N, 65.67590°W)<br />
No structure was installed here. <strong>The</strong>re are various concerns at the s‐turn. <strong>The</strong> site will be reassessed<br />
after machine work is performed later in <strong>2009</strong>.<br />
Structure 58<br />
Location (44.75764°N, 63.67563°W)<br />
A right log was installed here. A large deflector was built where the log ended. A log may need<br />
to be added to the end of the log if the deflector doesn’t hold through the year. A large pool<br />
was filled in to become the existing ramp. Upon completion the pool was 39cm deep and the<br />
wetted width was 4.90m.<br />
13 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 59<br />
Location (44.75759°N, 63.67510°W)<br />
A left log was removed and reinstalled four meters downstream to a new location. <strong>The</strong>re were<br />
not many large deflector rocks nearby so some were brought from surrounding areas. <strong>The</strong><br />
deflector may need some further building up in later years. Upon completion the pool was<br />
37cm deep and the wetted width was 5.1m.<br />
Structure 60<br />
Location (44.75754°N, 63.67470°W)<br />
A right log was installed here in previous years, which we had to re‐align and re‐build. Large<br />
amounts of garbage (mattress, shopping carts, television, etc.) were removed from this site as<br />
well. <strong>The</strong>re was no deflector at this site so we built a small one on top of the bank. Upon<br />
completion the pool was 47cm deep and the wetted width was 5.4m.<br />
14 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 61<br />
Location (44.75755°N, 63.67438°W)<br />
<strong>The</strong>re was a deep pool at this site, no structure was needed.<br />
Structure 62<br />
Location (44.75728°N, 63.67418°W)<br />
A right log was removed and reinstalled upstream approximately 3 meters from the original site.<br />
A large deflector and ramp were built. Upon completion the pool was 41cm deep and the<br />
wetted width was 4.9m.<br />
15 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 63<br />
Location (44.75698°N, 63.67397°W)<br />
A left log was installed here in previous years. A large amount of garbage was removed from<br />
the pool end of the log. <strong>The</strong>re are a lot of trees lining the pool side of the log, which provides a<br />
lot of shade for the pool. To fix the vertical angle we hammered down the pool side of the log<br />
and elevated the deflector side of the log to the proper gradient. Upon completion the pool was<br />
36cm deep and the wetted width was 3.9m.<br />
Structure 64<br />
Location (44.75676°N, 63.67377°W)<br />
A right log was installed here in previous years. <strong>The</strong> log was maintained only. A large ramp was<br />
re‐built. Upon completion the pool was 53cm deep and the wetted width was 4m.<br />
16 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 65<br />
Location (44.75642°N, 63.67344°W)<br />
A left log was installed here in previous years. <strong>The</strong> log was raised at one end to fix the vertical<br />
angle. <strong>The</strong> deflector was improved, yet may need to be built up to the bank next year. Upon<br />
completion the pool was 36cm deep and the wetted width was 4.7m.<br />
Structure 66<br />
Location (44.75628°N, 63.67322°W)<br />
A right log was installed here in previous years. Maintenance was performed here. <strong>The</strong>re was<br />
only a small deflector at this site so we built it up as much as possible given the log length. Upon<br />
completion the pool was 51cm deep and the wetted width was 5.4m.<br />
17 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 67<br />
Location (44.75635°N, 63.67277°W)<br />
Area was a deadwater, so no structure was installed here.<br />
Structure 68<br />
Location (44.75621°N, 63.67239°W)<br />
A rock sill was installed here in previous years. A left log was installed here in front of the rock<br />
sill. <strong>The</strong> rocks from the rock sill were removed and used for both the ramp and the deflector.<br />
<strong>The</strong> riverbank is very high and the deflector will need to be added to next year. Upon<br />
completion the pool was 40cm deep and the wetted width was 4.9m.<br />
18 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 69<br />
Location (44.75607°N, 63.67239°W)<br />
A left log was uninstalled and reinstalled as a right log. <strong>The</strong> log was installed to the right of a<br />
very large point bar made of pebbles and sand. We had to dig into the bank a few feet to install<br />
the log. <strong>The</strong> water was very deep at this point, so we had to add a lot of rocks to the ramp.<br />
Upon completion the pool was 36cm deep and the wetted width was 3.80m.<br />
Structure 70<br />
Location (44.75586°N, 63.67216°W)<br />
A right log was uninstalled and reinstalled as a left log. We uninstalled two logs but only used<br />
one log, as the new positioning of the log didn’t require a second log. <strong>The</strong> log was left on the<br />
bank next to the site. Upon completion the pool was 38cm deep and the wetted width was<br />
4.1m.<br />
19 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 71<br />
Location (44.75572°N, 63.67177°W)<br />
A left log was uninstalled and reinstalled as a right log. We constructed a regular deflector as<br />
well as a small deflector on the right side to keep the bank from eroding. An extensive ramp<br />
and a pool were also installed. Upon completion the pool was 49cm deep and the wetted width<br />
was 4.9 m.<br />
Structure 72<br />
Location (44.7550°N, 63.67127°W)<br />
A right log was uninstalled and reinstalled as a left log. Upon completion the pool was 20cm<br />
deep and the wetted width was 5.3m.<br />
20 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 73<br />
Location (44.75508°N, 63.67074°W)<br />
A right log was installed here in previous years. Maintenance was performed only. Upon<br />
completion the pool was 47cm deep and the wetted width was 3.85m.<br />
Structure 74<br />
Location (44.75492°N, 63.67039°W)<br />
A left log was installed here in previous years. <strong>The</strong> vertical angle of the log was fixed and<br />
maintenance was performed. Upon completion the pool was 34cm deep and the wetted width<br />
was 4.4m.<br />
21 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 75<br />
Location (44.75474°N, 63.67005°W)<br />
A right log was installed here in previous years. Two deflectors were built on each side of the<br />
log to stop erosion to the bank. Upon completion the pool was 45cm deep and the wetted<br />
width was 4.2m.<br />
Structure 76<br />
Location (44.75481°N, 63.67005°W)<br />
A left log was installed here in previous years. Maintenance was performed only. Upon<br />
completion the pool was 57cm deep and the wetted width was 4.95m.<br />
22 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 77<br />
Location (44.75465°N, 63.66933°W)<br />
A right double log was installed here in previous years. <strong>The</strong> logs were removed and the vertical<br />
and horizontal angles were fixed. <strong>The</strong> deflector was already built around the old log so only a<br />
few rocks needed to be added. Upon completion the pool was 38cm deep and the wetted width<br />
was 5m.<br />
Structure 78<br />
Location (44.75438°N, 63.66906°W)<br />
A left log was installed here in previous years. <strong>The</strong> vertical angle of the log was fixed. <strong>The</strong> pool<br />
end was already submerged so the deflector end was raised up to create the correct angle. <strong>The</strong><br />
pool was already very deep, yet the ramp required a lot of work. Upon completion the pool was<br />
67cm deep and the wetted width was 3.95m.<br />
23 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Structure 79<br />
Location (44.75409°N, 63.66887°W)<br />
A right log was installed at this site. <strong>The</strong> log had a right pool with a left bank deflector. A small<br />
right bank deflector was built to keep the water from eroding the right bank. Upon completion<br />
the pool was 35cm deep and the wetted width was 3.65m.<br />
24 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Electro-Fishing Survey on <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> July 2 <strong>2009</strong><br />
Crew Leader: Colin O’Neil<br />
Crew: Tim Kelly, John‐William Brunner, Cyndi LeBlanc, Kate MacPhee<br />
Water Quality<br />
pH: 7.7<br />
Water Temperature: 19.5<br />
Weather: Cloudy<br />
Equipment: Smith‐Root Model 15 POW Electrofisher<br />
Voltage Setting: 300<br />
Mode Switches: J‐5<br />
Table 2. Electrofishing survey area<br />
Electrofishing Section Average <strong>River</strong> Width* Electrofishing Section<br />
Length<br />
Electrofishing Section<br />
Area<br />
6.34m 151.83m 962.6m 2 (9.93 Units)<br />
*Average width taken from 5 representative width measures over the area<br />
Table 3. Fish Caught by Number and Density per Unit<br />
Species Population Density (Units)<br />
<strong>Atlantic</strong> salmon 48* 4.98<br />
Brook trout 1* 0.10<br />
American eel 53 5.50<br />
Creek chub 57* 5.92<br />
White sucker 33* 3.43<br />
Common shiner 2* 0.21<br />
*Only actual number of fish caught, population projection not possible<br />
<strong>The</strong> electrofishing survey was performed to establish a benchmark in order to help<br />
determine the effectiveness of restoration activities to be performed in this section of the <strong>Little</strong><br />
<strong>Sackville</strong> <strong>River</strong>. <strong>The</strong> electrofishing was performed over an area as listed in Table 2 and included<br />
a variety of habitat areas including pools, riffles and runs. <strong>The</strong> electrofished section was in the<br />
middle of the planned work area for this year, starting at the old digger log on Site 62<br />
(44.75728°N, 63.67418°W) and extending to 15 meters upstream of site 58 (44.757770°N,<br />
63.67580°W), just below the s‐turn. This area was picked as a representative sample of the<br />
entire <strong>2009</strong> work area.<br />
<strong>The</strong> electrofishing was performed using Zippen’s 1 removal method of population<br />
estimation with three sweeps. This method consists of electrofishing the sample area three<br />
times, counting the fish caught in each sweep then removing them from the sample area for the<br />
duration of the survey.<br />
1 Zippin, Calvin. “<strong>The</strong> Removal Method of Population Estimation.” Journal of Wildlife Management 22.1<br />
(1958): 82‐90<br />
25 | <strong>Digger</strong> <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
<strong>Atlantic</strong> salmon<br />
<strong>The</strong>re were a total of 48 <strong>Atlantic</strong> salmon caught during the three sweeps. <strong>The</strong> catch<br />
distribution did not sufficiently follow the Zippen model projections so no population estimate<br />
can be performed. <strong>The</strong> only conclusion that can be arrived at is there is at least 48 <strong>Atlantic</strong><br />
salmon. <strong>The</strong>re are no previous comparable results to analyze this data against.<br />
In the <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> as a general guideline fry are below 6 cm, and 1‐year smolt<br />
above that. <strong>The</strong> number of <strong>Atlantic</strong> salmon measured at ½ cm intervals indicates two age<br />
classes, fry and 1‐year parr (see Figure 4) Elson 2 developed models for optimum <strong>Atlantic</strong> salmon<br />
production that give a production rate of 240 eggs per unit, 29 fry per unit and 38 parr per unit.<br />
<strong>The</strong>re were 10 parr caught during the survey and 37 1‐year parr with one outlier at 7.5 cm. This<br />
gives a ratio of roughly 1:4 of fry vs. parr and a density of 1.04 parr per unit and 3.84 fry per unit.<br />
Using both fry and parr catch to predict egg yield (see table 4) gives us a range of 8.28 to 22.85<br />
eggs per unit. This gives us at the egg stage 3.45‐9.52%, at the fry stage 3.59% and finally at the<br />
parr stage 10.1% of the optimum Elson production levels.<br />
Figure 4. Number of <strong>Atlantic</strong> salmon Caught by Length<br />
2 Elson, P.F. “Number of salmon needed to maintain stocks.” Canadian Fish Culture 21 (1957): 19‐23<br />
Elson, P.F. “<strong>Atlantic</strong> salmon river smolt production and optimal spawning: an overview of natural<br />
production.” International <strong>Atlantic</strong> Foundation Special Publication Service 6 (1975): 96‐119<br />
26 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Table 4. Actual and Projected <strong>Atlantic</strong> salmon Population Using Elson Norms<br />
Life Stage Elson Norm Actual Estimated Yield<br />
Catch<br />
Egg/unit 240 0 using fry catch 8.28, using parr catch<br />
22.85<br />
Fry/unit 29 1.04 using parr catch 2.76<br />
Parr/unit 38 3.84 using fry catch 1.36<br />
Creek chub<br />
<strong>The</strong>re were a total of 57 Creek chub caught during these three sweeps. <strong>The</strong> catch<br />
distribution did not sufficiently follow the Zippen model projections so no population estimate<br />
can be performed. This was probably due to the schooling behavior of the species. <strong>The</strong> only<br />
conclusion that can be arrived at is there is at least 57 Creek chub. <strong>The</strong>re are no previous<br />
comparable results to analyze this data against.<br />
White suckers<br />
<strong>The</strong>re were a total of 33 White suckers caught during these three sweeps. <strong>The</strong> catch<br />
distribution did not sufficiently follow the Zippen model projections so no population estimate<br />
can be performed. This was probably due to the schooling behavior of the species. <strong>The</strong> only<br />
conclusion that can be arrived at is there is at least 33 White suckers present. <strong>The</strong>re are no<br />
previous comparable results to analyze this data against.<br />
American eel<br />
<strong>The</strong>re were a total of 51 American eels caught during these three sweeps. <strong>The</strong>se<br />
numbered thirty‐four in sweep one, nine in sweep two and five in sweep three. This catch<br />
distribution allowed interpretation through the Zippen model (see Figure 5.) <strong>The</strong> projected<br />
total population was 53± 4.22 at a 95% confidence limit. This gave a per unit distribution of 5.5.<br />
<strong>The</strong>re are no previous comparable results to analyze this data against.<br />
Figure 5. American eels caught During Respective Electrofishing Sweeps<br />
27 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Brook trout & Common shiner<br />
<strong>The</strong>re was only one Brook trout and two Common shiners caught in the electrofishing<br />
survey, the numbers were too low to be significantly analyzed. <strong>The</strong>re are no previous<br />
comparable results to analyze this data against.<br />
28 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Concluding Remarks<br />
<strong>Log</strong>s were set on the riverbank between sites 50 and 51 to be used in the future. <strong>Log</strong>s<br />
that were unused this year were left in the same area. When logs were removed from sites we<br />
set them aside and reused them at the same sites.<br />
<strong>The</strong>re is one site along the Lower <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong> where machine work will be<br />
taking place (structure 57). This work will be completed by the end of August, <strong>2009</strong>. To keep<br />
the banks from eroding at these sites one channel will be blocked and the other will remain<br />
open. Large rocks will also be placed along the bank to prevent more erosion from occurring.<br />
Since the hydrology study was completed and some of the old logs were re‐aligned the<br />
pattern of the digger logs along the river the pattern seems to be working correctly. Most of the<br />
logs that were taken out and replaced were not working correctly. <strong>The</strong> total area restored is<br />
4844m 2 . With the changes made this summer hopefully the logs will remain working correctly<br />
for years to come.<br />
As revealed through the results of our electrofishing it is important for restoration work<br />
to be carried out in this area. According to Elson’s developed models for optimum <strong>Atlantic</strong><br />
salmon production we are at very low levels of salmon production. As stated earlier we are at<br />
3.45‐9.52% of optimum levels for the egg stage, 3.59% for the fry stage and 10.1% at the parr<br />
stage. <strong>The</strong> <strong>Atlantic</strong> salmon is one of the main concerns for the SRA and is extremely important<br />
to our watershed. For us to improve the habitat and raise the levels of production for salmon<br />
we must continue with restoration projects along the <strong>Little</strong> <strong>Sackville</strong> <strong>River</strong>.<br />
29 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Appendix A – Budget<br />
Financial Report<br />
Expenditure/Component Cost Breakdown Contributor<br />
e.g. Time, unit costs, etc.<br />
Materials & Equipment<br />
Other Costs<br />
Labour<br />
Projected<br />
Cost<br />
Expenditure<br />
<strong>Digger</strong> logs with delivery Barrett Lumber $500 (in‐kind) $500 (in‐kind)<br />
Hand Tools/waders HRM Grant $800 $800<br />
Safety Equipment HRM Grant $200 $200<br />
Mileage ASCF $500 $500<br />
Crew ‐ 900 hours<br />
Project Coordinator ‐<br />
SRA, NSYCC,<br />
ASCF<br />
$9,000, $2,000, $9,000,<br />
$3,000 $3,000<br />
$7,000,<br />
$6,500 $7,000, $6,500<br />
SRA, ASCF<br />
675 Hours<br />
SRA Volunteers ‐ 50<br />
Hours SRA $750 (in‐kind) $750 (in‐kind)<br />
<strong>River</strong> Consultant HRM Grant $1,000 $1,000<br />
Contingency SRA $2,925 $425<br />
Chainsaw $500<br />
Total (Full) $32,1 75 $32,175<br />
Total requested from the ASCF $10,000 $10,000<br />
Percentage of funding 31% 31%<br />
30 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Appendix B – Press Release<br />
31 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>
Appendix C – Press Coverage<br />
32 | D igger <strong>Log</strong> <strong>Installation</strong> <strong>2009</strong>