F412-1000.1<br />

Safe Work Method Statement<br />

Page: 4 of 5<br />

Date: 05/05/08<br />

7. Connection to Sydney<br />

<strong>Water</strong> & <strong>Waste</strong> <strong>Water</strong><br />

Mains<br />

8. Valve shut down &<br />

Restoring flow<br />

9. Back fill & Restoration<br />

of site<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Trench wall collapse<br />

Gas hazards<br />

Chemicals hazards<br />

Inappropriate equipment<br />

Pipe material (VCP, PVC,<br />

UPVC, PE, etc)<br />

Contact with unhygienic<br />

surfaces<br />

Spillage<br />

Hazardous fumes<br />

Spray electrical current<br />

Flooding<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

<br />

Slips, trips, fall, on wet <br />

surfaces<br />

<br />

Flooding in upstream<br />

maintenance hole <br />

Unable to remove <br />

upstream plug<br />

<br />

Traffic fittings in roadway<br />

Pollution of <strong>water</strong>ways<br />

Moving equipment causing <br />

injury<br />

<br />

Inadequate compaction <br />

Construction refuse causing <br />

hazard to public <br />

Inadequate re-surfacing <br />

Erosion of soil<br />

Install adequate shoring in trenches<br />

Use of tripod <strong>and</strong> safety harness for safe access where appropriate.<br />

Hazardous Gas Check before access <strong>and</strong> continuous gas monitoring during connection by trained personnel<br />

Appropriate equipment <strong>and</strong> procedures used for cutting pipe.<br />

Appropriate PPE used<br />

Manual h<strong>and</strong>ling awareness.<br />

Two valve shut down etc.<br />

Sediment <strong>and</strong> Erosion control devices will be in place around storm<strong>water</strong> drains, upslope of site to detour runoff<br />

around the site <strong>and</strong> downslope to prevent sediment entering <strong>water</strong>ways<br />

Odours will be monitored <strong>and</strong> actioned as appropriate<br />

Sewage contaminated equipment <strong>and</strong> trucks removing contaminated items will be sealed in a <strong>water</strong> tight container<br />

or covered<br />

If maintaining <strong>water</strong> supply is not possible, customers will be notified as per PH02 – Notification of Residents<br />

Storm<strong>water</strong> drains will be protected from spillage by sediment control devices such as s<strong>and</strong>bags being placed<br />

around them<br />

<strong>Water</strong>proof clothing <strong>and</strong> rubber boots will be provided for personnel required to work in wet areas or conditions.<br />

Upstream maintenance hole to be pumped out <strong>and</strong> completely discharged to downstream maintenance hole or<br />

tanker.<br />

Plug removal method employed to avoid confined space entry where possible.<br />

Traffic control in place<br />

Sediment <strong>and</strong> Erosion control devices will be placed around storm<strong>water</strong> drains, upslope of site to detour runoff<br />

around the site <strong>and</strong> downslope to prevent sediment entering <strong>water</strong>ways<br />

Traffic control in place (Traffic control plan)<br />

All trenches will be back filled at the end of each shift<br />

Compaction shall be done <strong>and</strong> met Australian St<strong>and</strong>ards<br />

Site cleared of debris <strong>and</strong> refuse<br />

Re-surfacing to original condition or appropriate trafficable surfacing.<br />

Sediment <strong>and</strong> Erosion control devices will be placed around storm<strong>water</strong> drains, upslope of site to detour runoff<br />

around the site <strong>and</strong> downslope to prevent sediment entering <strong>water</strong>ways<br />

10. Vacate site Collision with vehicle <strong>and</strong> / <br />

or pedestrians<br />

Prepare traffic management plan. Supply observer to assist Machine Operator Warning Signs