Executive Committee (8 November 2012)<br />
Q U A L I C O A T<br />
dated 9 August, ADAL had said it required the AASS test to be increased to 2000<br />
hours for the purpose of the study and also to create a background for collecting data<br />
on how aluminium resisted such a high requirement. In this letter, ADAL had also<br />
pointed out that, even if the equivalence was fully recognised, it was important to be<br />
able to establish a ranking between the different cycles. The results should therefore<br />
be evaluated according to a statistical ranking from Mann & Whitney in order to<br />
compare the different cycles. At this meeting, Mr. Boi gave further details about the<br />
diversified test programme.<br />
Some delegates wondered whether ADAL would accept the test results even if they<br />
showed that the old cycle A was equivalent to the old AA cycle but less good than the<br />
SEASIDE requirements.<br />
Mr. Panam argued that no ranking should be made if we accepted the 2000 hours,<br />
provided the results of the former AA and A cycles were both positive and possibly<br />
even if the results were different.<br />
Mr. Ghalem explained that ADAL expected the AASS test to be extended to 2000<br />
hours for the purpose of the study, whereas the requirements would be the same as for<br />
1000 hours. If QUALICOAT was not willing to increase the requirement to 2000 hours,<br />
ADAL would not accept equivalence between SEASIDE and QUALIMARINE except<br />
between the former cycles AA and OX. ADAL would send another letter and confirm its<br />
position.<br />
7. Strategy<br />
Those present agreed to address strategy issues within the new Accreditation and<br />
Strategy WG.<br />
8. Conferences and contacts with other associations<br />
8.1 Attendance at QUALISINO’s General Assembly<br />
As in previous years, Mr. Boi and Mr. Schoppig had attended QUALISINO’s General<br />
Assembly in June as members of the Steering Committee that monitored the activities<br />
of this association.<br />
Ms. Li explained that QUALISINO did not have the same structure as other national<br />
associations because the registration of associations was quite complicated in China.<br />
However, she would take up the issue of establishing an Executive Committee to<br />
replace the Steering Committee in the future.<br />