04.11.2014 Views

Review Incident Shin.. - authority for electricity regulation, oman

Review Incident Shin.. - authority for electricity regulation, oman

Review Incident Shin.. - authority for electricity regulation, oman

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

contract with Civil Co (we have only seen a version valid until 26/05/2007), necessary<br />

equipment, tools and instruments are to be provided by the contractor (see section 2.2.5).<br />

2.2.4. People available<br />

For both patrolling and repair of the line, the same applies as <strong>for</strong> spare parts and repair<br />

tools. They should be available in good quality, quantity and close to the line.<br />

We understood that the line crew of OETC started patrolling half an hour after the fault,<br />

which means that they were readily available. Moreover, another patrolling crew was offered<br />

by MJEC and assisted OETC with patrolling. However, this was on an ad-hoc basis<br />

and not as a result of any plan by OETC.<br />

Repair of the line should be organized in such a way that the work order can be issued<br />

without delay. Preferably this should be done either by own personnel or under a (maintenance)<br />

contract (see section 2.2.5).<br />

The operation engineer of OETC on site had to coordinate patrolling, fault investigation,<br />

looking <strong>for</strong> spare parts, repair, safety switching and communication with police and MJEC,.<br />

He was the only person that was authorised to close and open earthing switches in grid stations<br />

as well. In our opinion the operation engineer is in the case of a fault overloaded with<br />

activities, which could negatively influence the duration of the supply interruption.<br />

2.2.5. Maintenance Contract<br />

We have not seen the actual maintenance contract with contractor Civil Co and are unable<br />

to confirm that a maintenance contract was in place at the time of the incident. However, we<br />

received a copy of the contract that was valid until 26/5/2007. This maintenance contract<br />

covered emergency maintenance of 132 kV lines, including the provision of adequate qualified<br />

and experience staff <strong>for</strong> this purpose with all necessary equipment, tools etc. in order to<br />

carry out the maintenance and attending the emergencies in an effective manner. The contract<br />

specifies emergency maintenance <strong>for</strong> woodenpole structures specifically. The specification<br />

includes the replacements of broken insulators and making of mid span joints and<br />

restringing of broken and damaged conductors. However, the responsibility <strong>for</strong> the provision<br />

of spare parts is with the OETC, although collection of the materials is at Civil Co again.<br />

2.2.6. Conclusion<br />

It can be concluded that due to the fact that spare parts and repair tools were not readily<br />

available, the interruption had a longer duration than necessary. If we consider that the fault<br />

location was known at 01.10h on 28 August and that the latest spare parts arrived on-site at<br />

<strong>Review</strong> <strong>Incident</strong> <strong>Shin</strong>as August 2007 9 09.10.2007<br />

vs. 2 (final)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!