07.11.2014 Views

GhubrahIncidentInves.. - authority for electricity regulation, oman

GhubrahIncidentInves.. - authority for electricity regulation, oman

GhubrahIncidentInves.. - authority for electricity regulation, oman

SHOW MORE
SHOW LESS

You also want an ePaper? Increase the reach of your titles

YUMPU automatically turns print PDFs into web optimized ePapers that Google loves.

Report Number: R 8991<br />

Issue: 1.1<br />

2 FINDINGS<br />

On arrival at site, Senior Sogex personnel (including the site General Manager) were<br />

interviewed to determine the circumstances and the probable root cause of the<br />

incident. Work permits, work orders, procedures, evidence of competencies and<br />

health and safety documents were requested and received. The author received full<br />

and open co-operation from Sogex personnel throughout the investigation.<br />

On the 25/03/06, a Limitation-of-Access (LOA) Permit-To-Work (PTW), LOA<br />

No.10795/L was issued to carry out routine maintenance on the external surfaces of<br />

the Phase 3 Hypochlorite Storage Tanks, C and D (See Appendix A). The permit<br />

was issued <strong>for</strong> (1) cleaning, (2) surface preparation and (3) painting. The cylinders<br />

were to be left in service and the permit clearly states that no isolations were to be<br />

carried out and that the civil department (conducting the painting operation) were to<br />

take all safety precautions. In this respect this specific PTW/LOA covered activity of<br />

a ‘cold’ work nature, although it is observed that the relevant section of the permit<br />

designed to indicate ‘hot’ or ‘cold’ status was left unspecified.<br />

On inspection of the job site on cylinder ‘D’, the civil department reported that the<br />

cylinder jacket was badly corroded and hence a work order (Reference No. LO<br />

42/04/06) was raised on 05/04/06 to the Mechanical Department, to replace the<br />

cladding (hood) on cylinders A, B, and D (See Appendix B). The work order No. LO<br />

42/04/06 references PTW/LOA No. 10795/L.<br />

Evidence was requested regarding the competency and authorisation of the permit<br />

issuer and work order issuer. Sogex personnel produced relevant CVs and<br />

authorisation memos stating that the persons concerned had been assessed and<br />

found competent to sign permits (see Appendix C).<br />

The work to replace the cladding involved the removal of the corroded cladding and<br />

the fabrication and installation of replacement cladding. To replace the cladding it is<br />

necessary to use drills <strong>for</strong> the riveting process.<br />

It appears that the mechanical fitters were left to complete the work with no periodic<br />

site inspections by the management and no safety departmental presence.<br />

Work on the ‘C’ Hypochlorite cylinder had been per<strong>for</strong>med under a separate internal<br />

work order (LO 37/03/06, not included in this report), without incident. However,<br />

during the process of installing the newly fabricated hooding of the ‘D’ cylinder, an<br />

explosion occurred resulting in a ‘fire ball’ that fatally injured the two Sogex<br />

maintenance fitters involved. They reportedly were able to climb down from the top<br />

of the cylinder, a difficult feat, to seek assistance.<br />

Once the incident had been discovered, the Hypochlorite plant was shut down and<br />

the two employees were immediately transferred to hospital where they were placed<br />

in intensive care, but subsequently passed away.<br />

Page 5 / 11

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!