Task 2.4 PMP Indicators and Targets<br />
MONITORING AND EVALUATION<br />
Year 1 Year 2 Year 3<br />
Yr 3<br />
Target<br />
Task Indicator Units Baseline Target Actual Target Actual<br />
2.4 Capacity Building of MWRI Personnel<br />
2.4.a Candidates selected Number 0 20 20 50 36 350 36<br />
2.4.b Candidates accepted by<br />
American University Cairo and Number 0 20 15 50 20 50 20<br />
local universities<br />
2.4.c Candidates graduated with M.S.<br />
degrees<br />
Number 0 0 0 0 0 20 2<br />
Actual<br />
Qtr 3<br />
Dr. Wadie Fahim Mankarious (LTTA, Senior Organization/Institutional Development Specialist) is<br />
the coordinator for this Task. STTA is provided by Dr. Mark Svendsen, an expatriate. Activities<br />
carried out during the report period include:<br />
• Drs.Svendsen and Wadie and Andrew Tczap met twice with the USAID COTR and Ms.<br />
Amani Selim, USAID Senior M&E Specialist, to discuss the PMP indicators based on the<br />
comments of the mid- term evaluation team.<br />
• Dr. Abd El Motaleb, MWRI Coordinator, attended a debriefing by Dr. Svendsen. He<br />
supported the M&E activities, and requested that IWRM <strong>II</strong> draft a letter to be addressed to<br />
all IWMDs asking for support in obtaining requested data. Dr. Motaleb encouraged the<br />
project to continue introducing the concept of managing water resources based on volume<br />
instead of water level.<br />
• The M&E team discussed possible collaboration between IWRM <strong>II</strong> and CDIAS on M&E<br />
activities related to BCWUAs with Eng. Nagwa El Khashab, Chairperson of CDIAS.<br />
• IWRM <strong>II</strong> started to collect information on crop area, productivity and farm gate prices in<br />
each district from the MALR Information Center for the summer 2009 and winter<br />
2009/2010 seasons.Work on utilization of the checklist for evaluating IWMD performance<br />
continued.<br />
• An addendum to the project PMP setting out a set of indicators to measure the growing<br />
capacity and performance of BCWUAs and IWMDs was prepared by Dr. Svendsen and<br />
submitted to USAID. These two new indicators are discussed under Tasks 1.1 and 2.2 above.<br />
• A purchase order with EL Zanaty Associates was signed for conducting a field survey of<br />
farmers and for focus group meetings with BCWUA boards. These will cover the IWRM <strong>II</strong><br />
area and the two IWRM I-supported directorates in Lower Egypt.<br />
EDUCATION, COMMUNICATIONS, PUBLIC AWARENESS AND<br />
PARTICIPATION<br />
Cheryl Groff, Senior Communication Specialist, was coordinator for this task and was<br />
demobilized on 30 June 2011. The project works in collaboration with the Water<br />
Communication Unit (WCU) of the MWRI, local STTA consultants and private vendors. Mr.<br />
Abdel Bary Bakr, local Senior Communications Consultant, is providing support on a time basis<br />
since the demands are reducing as the project winds down. Activities carried out during the<br />
report period include:<br />
• “Alternative Crops an Alternative Solution,” a 14 minute video highlighting farmers’ success<br />
in cultivating high value, low water consuming crops is being screened during Task 1.3<br />
workshops. Duplication and distribution of the video will take place in October.<br />
12 Quarterly Report Year 3: 3 rd Quarter (July - September 2011)