9<br />
a. Electricity<br />
b. Water<br />
c. Oxygen<br />
d. Acetylene<br />
e. Carbon dioxide<br />
f. LPG<br />
g. CSL cranes / Fork lifts / Trailer<br />
46 Any cement that the Engineer-in-charge considers has become stale or unsuitable through<br />
absorption of moisture from the atmosphere or otherwise due to improper transport/ storage/<br />
handling by the contractors shall be rejected.<br />
47 Any admixture if found necessary for concrete items by the contractor to suit his work could<br />
be provided by him at his own cost with prior approval of the Engineer-in-charge. No extra<br />
payment will be made for the same by CSL.<br />
48 Empty cement bags are to be stacked in bundles and to be cleared from site at contractor’s<br />
expense as directed by the Engineer-in-charge.<br />
49 Waste materials are to be cleared from site on a day-to-day basis. Each area of working is to<br />
be cordoned off with necessary signboards and barriers to ensure safe transportation of men<br />
and material by CSL in the area as directed by the Engineer-in-charge.<br />
50 CGM (Tech) shall have the right to take possession of or use completed or partially<br />
completed part of the work. Such possession or use shall not be deemed to be an acceptance<br />
of such work. After completion of all the works, the contractor has to clear all the debris and<br />
make the area neat and tidy at the site. The final bill shall be paid only after the certification<br />
by safety department to this effect.<br />
51 It is the responsibility of the contractor to follow all safety rules and regulations in force,<br />
during the currency of contract in CSL, and any violation of the same during the course of<br />
work will be at the risk and cost of the contractor and will attract penal action. Copy of CSL<br />
Safety manual is available in the Office of CGM (Tech) and the same may be referred before<br />
quoting the rates.<br />
52 Any violation of Safety rules by the contractor, safety department will impose penalty of Rs<br />
1000/- to Rs 5000/- depending on the gravity of violation. Action for debarring the contractor<br />
also will be taken in case of repeated violation. Any accident caused due to safety violation<br />
and any damage to the company property suitable penalty will be imposed by CSL including<br />
termination of contract, if required.<br />