TPS Action Plan<br />

Action Plan Detail<br />

Sep-06 Oct-06 Nov-06 Dec-06<br />

1. Work Site Control<br />

18 - 27<br />

1.1 Check current line (2S&Visual control)<br />

2. Continuous Flow<br />

2.1 Check material flow chart (MFC)<br />

2.2 Re-layout (New line)<br />

5 - 18<br />

3. Standardized Work<br />

27 - 8<br />

3.1 Process efficiency check<br />

3.2 Man-machine chart<br />

3.3 Standard work sheet<br />

4. Pull System<br />

16 - 28<br />

4.1 WIP storage<br />

4.2 Kanban and MIFC<br />

4.3 Pattern post<br />

5. System Improvement<br />

6 - 7<br />

6. Final Presentation Prepared<br />

8<br />

7. Final Presentation<br />

12-15<br />

7.1 CSP Casting Presentation<br />

3