of RCs, if any, including various infrastructures created by NTPC in RCs as well as in Project<br />

Affected Villages.<br />

1.10 State Specific R&R Policies<br />

State Government R&R policy, if any, would be considered if need be and as per the<br />

consultations with the stakeholders while formulating the project specific R&R Plan. In case<br />

PAPs/ District Administration/ Central Government decide, NTPC will suitably consider<br />

State Specific R&R <strong>Policy</strong> / guidelines /directive for implementation in that particular State<br />

for the specific project.<br />

1.11 Power to CMD to approve modification<br />

Should there be any amendment /modification required due to site specific requirements,<br />

while formulating and/or implementing the R&R Plan and which are not explicitly specified<br />

in the policy, the power to approve such modifications would be exercised by the Chairman<br />

and Managing Director (CMD).<br />

1.12 Review of <strong>Policy</strong><br />

The policy may be reviewed normally every three years keeping in view the experiences /<br />

learnings during implementation of this R&R policy and / or there is any significant<br />

change/amendment in the NRRP-07 by the GOI.<br />

1.13 Specific clauses / addendums declared by, GOI<br />

Any specific clauses / addendums declared by Ministry of Power, GOI related to R&R issues<br />

of PAPs w.r.t sector specific / projects of power sector will also be suitably considered in<br />

close coordination with the State Government while formulating the project specific R&R<br />

Plan.<br />

1.14 GOI Hydro <strong>Policy</strong><br />

Any specific clauses / addendums declared by Ministry of Power, GOI related to R&R issues<br />

of PAPs w.r.t projects of hydro sector etc will also be suitably considered in close<br />

coordination with the State Government while formulating the project specific R&R Plan.<br />

1.15 MOEF stimulations<br />

Any specific R&R conditions / stipulations as part of MOEF clearance shall also be made<br />

part of R&R Plan.<br />