31.12.2014 Views

2012-005 - Alberta Utilities Commission

2012-005 - Alberta Utilities Commission

2012-005 - Alberta Utilities Commission

SHOW MORE
SHOW LESS

Create successful ePaper yourself

Turn your PDF publications into a flip-book with our unique Google optimized e-Paper software.

Decision <strong>2012</strong>-<strong>005</strong><br />

Reasons to Decision 2011-439 (November 1, 2011)<br />

<strong>Alberta</strong> Electric System Operator<br />

Need for the Interconnection of<br />

Castle Rock Ridge Wind Farm<br />

AltaLink Management Ltd.<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

January 10, <strong>2012</strong>


The <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong><br />

Decision <strong>2012</strong>-<strong>005</strong>: Reasons to Decision 2011-439 (November 1, 2011)<br />

<strong>Alberta</strong> Electric System Operator<br />

Need for the Connection of Castle Rock Ridge Wind Farm<br />

Application No. 1606460<br />

ATCO Electric Ltd.<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

Application No. 1606668<br />

Proceeding ID No. 778<br />

January 10, <strong>2012</strong><br />

Published by<br />

The <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong><br />

Fifth Avenue Place, Fourth Floor, 425 First Street S.W.<br />

Calgary, <strong>Alberta</strong><br />

T2P 3L8<br />

Telephone: 403-592-8845<br />

Fax: 403-592-4406<br />

Website: www.auc.ab.ca


The <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong><br />

Calgary, <strong>Alberta</strong><br />

Reasons to Decision 2011-439 (November 1, 2011)<br />

<strong>Alberta</strong> Electric System Operator<br />

Need for the Interconnection of<br />

Castle Rock Ridge Wind Farm<br />

Decision <strong>2012</strong>-<strong>005</strong><br />

AltaLink Management Ltd.<br />

Applications No. 1606460 and<br />

240-kV Castle Rock Ridge Switching Station 205S and No. 1606668<br />

240-kV Double-circuit Transmission Line 1071L/1072L Proceeding ID No. 778<br />

1 Introduction<br />

1. On November 1, 2011, <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong> (AUC or the <strong>Commission</strong>) issued<br />

Decision 2011-439, 1 wherein:<br />

1. The <strong>Alberta</strong> Electric System Operator (AESO) application for the needs identification<br />

document (NID) for the Castle Rock 205S substation and the 240-kilovolt (kV)<br />

double-circuit transmission line, 1071L/1072L was approved with reasons to follow.<br />

2. The AltaLink Management Ltd. (AltaLink) application to construct and operate the<br />

Castle Rock Ridge 205S substation, to construct and operate the 240-kV transmission<br />

line 1071L to construct and operate the 240 kV transmission line 1072L, and to alter<br />

and operate the Goose Lake 103S substation was approved.<br />

This decision provides the reasons to Decision 2011-439.<br />

2. The AESO filed a NID with the AUC, pursuant to Section 34 of the Electric <strong>Utilities</strong> Act.<br />

This application was registered on August 13, 2010, as Application No. 1606460. An amendment<br />

to the NID was registered on August 4, 2011.<br />

3. The AESO’s NID application was prepared in response to a request by Enel <strong>Alberta</strong> Wind<br />

Inc. (Enel) for connection of its Castle Rock Ridge wind farm in the Pincher Creek area to the<br />

<strong>Alberta</strong> Interconnected Electrical System. The proposed connection would involve the<br />

construction of a switching station designated as Castle Rock Ridge 205S switching station,<br />

located near Enel’s generating facilities. The interconnection point with the <strong>Alberta</strong><br />

Interconnected Electrical System was proposed to be at a point designated as Point A on the<br />

proposed double-circuit 240-kV transmission line 994L/1071L connecting proposed Fidler 312S<br />

substation with the existing Goose Lake 103S substation.<br />

4. The AESO requested AltaLink assist in conducting a participant involvement program to<br />

notify stakeholders regarding the need for transmission development in the Pincher Creek area.<br />

The AESO stated in its NID application that there were no outstanding concerns related to the<br />

AESO’s assessment of the need for this development.<br />

1<br />

Decision 2011-439: <strong>Alberta</strong> Electric System Operator and AltaLink Management Ltd. Castle Rock Ridge 205S<br />

and Transmission Line Development Needs Identification Document Application and Facility Application,<br />

Application Nos. 1606460 and 1606668, Proceeding ID No. 778, November 1, 2011.<br />

AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>) • 1


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

5. Pursuant to Section 35 of the Electric <strong>Utilities</strong> Act, the AESO directed AltaLink to submit<br />

a facility proposal to the <strong>Commission</strong> to meet the need identified in the NID application and in<br />

NID Approval No. U2011-115 2 for the Southern <strong>Alberta</strong> Transmission Reinforcement.<br />

6. AltaLink filed Application No. 1606668 (facility application) with the AUC on<br />

October 15, 2010, seeking approval to construct and operate the Castle Rock Ridge 205S<br />

substation and 240-kV double-circuit transmission line 1071L/1072L.<br />

7. Both the AESO and AltaLink amended their applications, on August 4 and<br />

August 8, 2011, respectively, to include the nine-kilometre route of the proposed 240-kV<br />

double-circuit transmission line 1071L/1072L from the proposed Castle Rock Ridge 205S<br />

switching station to the existing Goose Lake 103S substation. In its application, Altalink stated<br />

that the proposed Castle Rock Ridge 205S switching station would be located in LSD 7 of<br />

Section 14, Township 7, Range 30, west of the Fourth Meridian. AltaLink requested approval to<br />

expand Goose Lake 103S substation by the addition of five 240-kV circuit breakers. Goose Lake<br />

103S substation is located in LSD 5 of Section 36, Township 6, Range 30, west of the Fourth<br />

Meridian.<br />

8. Both the AESO and AltaLink requested that the <strong>Commission</strong> consider the NID<br />

application and the facility application jointly, pursuant to Section 15.4 of the Hydro and Electric<br />

Energy Act.<br />

2 Relevant legislation<br />

9. In making its decision, the <strong>Commission</strong> considered the following provisions:<br />

With respect to the NID application, Section 34 of the Electric <strong>Utilities</strong> Act states:<br />

34(1) When the Independent System Operator determines that an expansion or<br />

enhancement of the capability of the transmission system is or may be required to<br />

meet the needs of <strong>Alberta</strong> and is in the public interest, the Independent System<br />

Operator must prepare and submit to the <strong>Commission</strong> for approval a needs<br />

identification document that<br />

(a) describes the constraint or condition affecting the operation or performance<br />

of the transmission system and indicates the means by which or the manner<br />

in which the constraint or condition could be alleviated,<br />

(b) describes a need for improved efficiency of the transmission system,<br />

including means to reduce losses on the interconnected electric system, or<br />

(c) describes a need to respond to requests for system access service.<br />

2<br />

Needs Identification Document Approval No. U2011-115, Applications No. 1606564 and No. 1606526,<br />

Proceeding ID No. 748, June 7, 2011.<br />

2 • AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>)


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

10. Section 38 of the Transmission Regulation states:<br />

When considering whether to approve a needs identification document under section<br />

34(3) of the Act, the <strong>Commission</strong> must:<br />

(e) consider the ISO’s assessment of the need to be correct unless an interested<br />

person satisfies the <strong>Commission</strong> that<br />

(i) the ISO’s assessment of the need is technically deficient, or<br />

(ii) to approve the needs identification document would not be in the public<br />

interest.<br />

11. In relation to the facilities application, sections 14, 15, 15.4 and 19 of the Hydro and<br />

Electric Energy Act state:<br />

14(1) No person shall construct a transmission line or any part of a transmission line<br />

unless the person is the holder of a permit issued by the <strong>Commission</strong>.<br />

(2) No person shall make a significant extension or alteration of a transmission line<br />

unless the <strong>Commission</strong> has amended the person’s permit or issued a new permit to cover<br />

the extension or alteration.<br />

…<br />

15 No person shall operate a transmission line unless the person is the holder of a<br />

subsisting licence to operate the transmission line, issued by the <strong>Commission</strong>.<br />

…<br />

15.4 If a person makes an application under this Part and the Independent System<br />

Operator has submitted a needs identification document to the <strong>Alberta</strong> <strong>Utilities</strong><br />

<strong>Commission</strong> under section 34 of the Electric <strong>Utilities</strong> Act in respect of the same<br />

transmission line or part of a transmission line, the application and submission may be<br />

combined and considered by the <strong>Commission</strong>.<br />

…<br />

19(1) On an application for an approval, permit or licence under this Part, or for an<br />

amendment of an approval, permit or licence, the <strong>Commission</strong> may grant the approval,<br />

permit, licence or amendment subject to any terms and conditions that it prescribes or<br />

may deny the application.<br />

(1.1) Notwithstanding subsection (1), the <strong>Commission</strong> shall not refuse an approval of a<br />

transmission line or part of a transmission line designated as critical transmission<br />

infrastructure as defined in the Electric <strong>Utilities</strong> Act on the basis that, in its opinion, it<br />

does not meet the needs of <strong>Alberta</strong>.<br />

(2) Without restricting the generality of subsection (1), the <strong>Commission</strong> may do one or<br />

more of the following:<br />

(a) require changes in the plans and specifications of a hydro development,<br />

power plant or transmission line;<br />

(b) require changes in the location of a hydro development, power plant or<br />

transmission line;<br />

(c) prescribe a date before which the construction of, or operation of, the hydro<br />

development, power plant or transmission line must commence;<br />

AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>) • 3


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

(d) prescribe the location and route of the transmission line as precisely as it<br />

considers suitable;<br />

(e) prescribe the location of the right of way of the transmission line and the<br />

relationship of its boundaries to the transmission line or any part of the<br />

transmission line.<br />

12. Section 17 of the <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong> Act states:<br />

17(1) Where the <strong>Commission</strong> conducts a hearing or other proceeding on an application<br />

to construct or operate a hydro development, power plant or transmission line under the<br />

Hydro and Electric Energy Act or a gas utility pipeline under the Gas <strong>Utilities</strong> Act, it<br />

shall, in addition to any other matters it may or must consider in conducting the hearing<br />

or other proceeding, give consideration to whether construction or operation of the<br />

proposed hydro development, power plant, transmission line or gas utility pipeline is in<br />

the public interest, having regard to the social and economic effects of the development,<br />

plant, line or pipeline and the effects of the development, plant, line or pipeline on the<br />

environment.<br />

(2) The <strong>Commission</strong> shall not under subsection (1) give consideration to whether<br />

critical transmission infrastructure as defined in the Electric <strong>Utilities</strong> Act is required to<br />

meet the needs of <strong>Alberta</strong>.<br />

3 Discussion<br />

13. In its assessment of routing and siting options for the Castle Rock Ridge wind farm<br />

connection, AltaLink stated that it considered the proximity of existing residences and agricultural<br />

operations, potential environmental impacts, existing linear disturbances and the potential to<br />

consolidate the proposed 240-kV double-circuit transmission line with new, and future<br />

transmission facilities. AltaLink submitted that through its siting process, it was only able to<br />

identify one proposed site adjacent to Castle Rock Ridge wind farm in consideration of the<br />

AESO’s direction in its functional specification.<br />

14. In relation to proposed 240-kV double-circuit transmission line 1071L/1072L, AltaLink<br />

considered two potential routes, Route A being 5.5 kilometres in length and Route B being<br />

4.1 kilometres in length. The routes were developed based on the lowest overall impact to<br />

landowners and residents and to meet the requirements of AUC Rule 007: Rules Respecting<br />

Applications for Power Plants, Substations, Transmission Lines, and Industrial System<br />

Designations (AUC Rule 007). However, Route A was rejected after further evaluation and<br />

consideration of landowner and resident input because AltaLink considered that Route A may<br />

have a higher potential impact. Another consideration that favoured Route B was the concern<br />

identified by <strong>Alberta</strong> Tourism, Parks and Recreation that a portion of Route A would cross<br />

through the Oldman Dam protected area.<br />

15. Route B was further evaluated and modified taking into consideration input from<br />

landowners and residents.<br />

4 • AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>)


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

16. AltaLink conducted a participant involvement program between June 2009 and June 2010.<br />

AltaLink notified all landowners within 800 metres of the proposed station site and the potential<br />

routes for the transmission line and conducted personal consultation with persons where facilities<br />

were proposed either on or adjacent to their land. As part of the participant involvement program,<br />

AltaLink held an open house in Pincher Creek where representatives of both AltaLink and the<br />

AESO attended including an expert on electric and magnetic fields to address any electric and<br />

magnetic fields questions.<br />

17. AltaLink addressed concerns with the landowners regarding visual impact, reclamation of<br />

native prairie, weeds, agricultural issues, compensation, liability and future planned development.<br />

No outstanding concerns remained.<br />

18. Additional landowner consultations were held in July 2011 prior to the amendment to the<br />

route for the proposed transmission line. Signed letters indicating that they had no objection were<br />

obtained from all landowners within 800 metres of the proposed transmission line route.<br />

19. In addition, AltaLink contacted various government agencies from all levels as well as<br />

non-government organizations.<br />

20. <strong>Alberta</strong> Sustainable Resource Development’s (ASRD) expressed concerns that the<br />

proposed transmission line route would cross a critical ungulate wintering range. Also, the<br />

proposed transmission line would be in close proximity to prairie falcon nests reported in the area.<br />

In addition, some coulees or river breaks may have potential for garter snake hibernacula. ASRD<br />

recommended that AltaLink conduct pre‐construction field surveys to determine if any wildlife<br />

species and unique habitat features (e.g., dens or nests) were present in the vicinity of the<br />

proposed project. In response, AltaLink stated that it had conducted pre-construction field surveys<br />

and in collaboration with ASRD would establish species specific mitigative measures prior to<br />

construction.<br />

21. <strong>Alberta</strong> Culture and Community Spirit notified AltaLink in a letter dated August 12, 2009,<br />

that a historic resources impact assessment was required since known archeological sites were in<br />

the immediate vicinity of the project. AltaLink committed to obtaining a clearance under the<br />

Historical Resources Act, prior to initiating construction of the project and to comply with all<br />

terms and conditions of such approval.<br />

22. The Royal Canadian Mounted Police (RCMP) had concerns with radio interference from<br />

the proposed 240-kV transmission line being in close proximity to one of its communications<br />

towers. AltaLink committed to working with the RCMP to mitigate any effects of the project on<br />

its radio communications.<br />

23. Information requests were sent to both the AESO and AltaLink on September 19, 2011.<br />

AESO responded on September 26, 2011. AltaLink responded on September 27 and<br />

September 29, 2011. Information requests dealt with a number of issues, including updated cost<br />

breakdowns, updated information on environmental issues and the public information process,<br />

and alternate routing options for the transmission line from Point A to Goose Lake 103S<br />

substation.<br />

AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>) • 5


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

24. The <strong>Commission</strong> deemed both applications complete on October 3, 2011, and issued a<br />

joint notice of applications for both applications on October 12, 2011. No interventions were<br />

received in response to the notice. Conversely, a number of local landowners and the Town of<br />

Pincher Creek submitted letters of support for the project.<br />

4 <strong>Commission</strong> findings<br />

4.1 NID application<br />

25. The <strong>Commission</strong> reviewed the NID application and determined that it contains the<br />

information required by the Electric <strong>Utilities</strong> Act, the Transmission Regulation, and<br />

AUC Rule 007. There were no outstanding objections or concerns to the AESO’s assessment<br />

of the need for the proposed development. Considering Section 38(e) of the Transmission<br />

Regulation, which provides that the <strong>Commission</strong> must consider AESO’s assessment of the<br />

need to be correct if there are no objections to the NID. In Decision 2011-439, issued on<br />

November 1, 2011, the <strong>Commission</strong> approved the AESO’s NID application.<br />

4.2 Facility application<br />

26. The <strong>Commission</strong> considered the facility application pursuant to sections 14, 15 and 21 of<br />

the Hydro and Electric Energy Act and finds that it is technically complete and complies with the<br />

requirements prescribed under sections 14, 15 and 21 of the Hydro and Electric Energy Act and<br />

AUC Rule 007, as explained below. The <strong>Commission</strong> further finds that the facility application<br />

satisfies the need as identified by the AESO.<br />

27. AltaLink’s assessment of routing and siting options for the Castle Rock Ridge wind farm<br />

connection considered the proximity of existing residences, existing agricultural operations,<br />

potential environmental impacts, existing linear disturbances, and the potential to consolidate the<br />

proposed 240-kV double-circuit transmission line with new and future transmission facilities. The<br />

<strong>Commission</strong> accepts AltaLink’s submissions that, through its siting process, it was only able to<br />

identify one site for the proposed Castle Rock Ridge 205S switching station located adjacent to<br />

Castle Rock Ridge wind farm considering the AESO’s direction in its functional specifications.<br />

28. In relation to the proposed 240-kV transmission line 1071L/1072L, consultation was<br />

conducted on two routes, Route A and Route B. The routes were developed based on the lowest<br />

overall impact to landowners and residents, and to meet the requirements of AUC Rule 007.<br />

29. The <strong>Commission</strong> finds that AltaLink’s participant involvement program met the<br />

requirements set out in AUC Rule 007. The <strong>Commission</strong> takes note that an open house was held<br />

in Pincher Creek with representatives of both AltaLink and the AESO in attendance.<br />

30. The <strong>Commission</strong> considers it important that concerns regarding visual impact, reclamation<br />

of native prairie, weeds, agricultural issues, compensation, liability and future planned<br />

development were addressed by AltaLink. The <strong>Commission</strong> recognizes that no outstanding<br />

concerns remained.<br />

31. Regarding environmental impacts, the <strong>Commission</strong> recognizes that AltaLink has<br />

conducted a pre-construction field survey and will establish species specific mitigative measures<br />

working in collaboration with ASRD staff. The <strong>Commission</strong> considers that this approach will<br />

mitigate the potential environmental impacts of the proposed transmission line.<br />

6 • AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>)


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

32. Also, the <strong>Commission</strong> is cognizant that <strong>Alberta</strong> Culture and Community Spirit notified<br />

AltaLink in a letter dated August 12, 2009, that a historic resources impact assessment was<br />

required since known archeological sites were in the immediate vicinity of the project. AltaLink<br />

has committed to obtaining a clearance under the Historical Resources Act, prior to initiating<br />

construction of the project and has committed to comply with all terms and conditions of such<br />

approval.<br />

33. The <strong>Commission</strong> is aware that AltaLink has committed to working with the RCMP to<br />

mitigate any effects on its radio communications from the project.<br />

34. The <strong>Commission</strong> is cognizant of AltaLink’s commitment to the Municipal District of<br />

Pincher Creek No. 9 regarding the potential to spread weeds during construction of the project<br />

and during its annual right-of-way inspection for up to three years following the completion of<br />

construction<br />

35. The <strong>Commission</strong> agrees that a noise impact assessment was not needed for the new<br />

switching station as no transformer would be included in the switching station equipment. The<br />

<strong>Commission</strong> finds that noise impact assessment for the proposed transmission line complies with<br />

AUC Rule 012: Noise Control.<br />

36. As a result, the <strong>Commission</strong> finds the proposed facilities are in the public interest pursuant<br />

to Section 17 of the <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong> Act. The <strong>Commission</strong> issued Decision 2011-439<br />

on November 1, 2011, that approved both applications and granted a NID approval to the AESO<br />

and facility permits and licences to AltaLink.<br />

5 Decision<br />

37. Pursuant to Section 34 of the Electric <strong>Utilities</strong> Act, the <strong>Commission</strong> approved the<br />

NID for the project in Decision 2011-439, issued November 1, 2011, and issued Approval<br />

No. U2011-385. 3<br />

38. Pursuant to sections 14, 15, 19 and 21 of the Hydro and Electric Energy Act the<br />

<strong>Commission</strong> approved the facility application in Decision 2011-439 and issued Permits and<br />

Licences No. U2011-386, 4 No. U2011-387, 5 No. U2011-388, 6 and No. U2011-389. 7<br />

3<br />

4<br />

5<br />

6<br />

7<br />

Needs Identification Document Approval No. U2011-385, Application No. 1606460, Proceeding ID No. 778,<br />

November 1, 2011.<br />

Substation Permit and Licence No. U2011-386, Application No. 1606668, Proceeding ID No. 778,<br />

November 1, 2011.<br />

Transmission Line Permit and Licence No. U2011-387, Application No. 1606668, Proceeding ID No. 778,<br />

November 1, 2011.<br />

Transmission Line Permit and Licence No. U2011-388, Application No. 1606668, Proceeding ID No. 778,<br />

November 1, 2011.<br />

Substation Permit and Licence No. U2011-389, Application No. 1606668, Proceeding ID No. 778,<br />

November 1, 2011.<br />

AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>) • 7


Reasons to Decision 2011-439 (November 1, 2011)<br />

Need for the Interconnection of Castle Rock Ridge Wind Farm<br />

240-kV Castle Rock Ridge Switching Station 205S and<br />

240-kV Double-circuit Transmission Line 1071L/1072L<br />

<strong>Alberta</strong> Electric <strong>Utilities</strong> Operator and<br />

AltaLink Management Ltd.<br />

Dated on January 10, <strong>2012</strong>.<br />

The <strong>Alberta</strong> <strong>Utilities</strong> <strong>Commission</strong><br />

(original signed by)<br />

Mark Kolesar<br />

<strong>Commission</strong> Member<br />

8 • AUC Decision <strong>2012</strong>-<strong>005</strong> (January 10, <strong>2012</strong>)

Hooray! Your file is uploaded and ready to be published.

Saved successfully!

Ooh no, something went wrong!