L-Duct Joint Assembly<br />

1. Align two L-Duct busduct feeders by<br />

overlapping the conductors.<br />

2. Fix busduct housing with side covers on both<br />

sides.<br />

M5 SCREW<br />

JOINT COVER<br />

3. Connect each phase conductor with screws,<br />

nuts, plain washes and spring washes. Make<br />

sure that the screws are fully tightened.<br />

4. Insert a phase isolator to the joint section.<br />

5. Connect the external earth bars to the earth<br />

bars at the side of busduct housing.<br />

PHASE ISOLATOR<br />

6. Install the joint cover on both sides of busduct<br />

housing to complete the joint assembly.<br />

M8 BOLT<br />

BELLEVILLE WASHER<br />

SPRING WASHER<br />

M8 NUT<br />

M6 SCREW<br />

SIDE COVER<br />

EXTERNAL<br />

EARTH BAR<br />

L1<br />

L2<br />

L3<br />

N<br />

E<br />

JOINT COVER<br />

M5 SCREW<br />

40 | INSTALLATION & MAINTENANCE PROCEDURE