OPERATING EXPENDITURES (US$/TONNE OF CONCENTRATE)<br />
COST PARAMETERS AVERAGE 25 YEARS AVERAGE YEARS 1 TO 5<br />
Mining 22.56 12.13<br />
Concentrating, crushing and processing 4.52 3.97<br />
Site infrastructure, sales and general administration 4.40 3.39<br />
Environmental tailings and management 0.29 0.26<br />
Rail transport 15.52 16.14<br />
Port facilities 3.72 3.57<br />
Equipment Lease Cost 1.67 5.17<br />
Total 52.68 44.63<br />
CAPITAL EXPENDITURES (US$ MILLIONS)<br />
COST CENTRES<br />
$ MILLIONS<br />
Pre-stripping of open pit areas 97.5<br />
Concentrator and site infrastructure including loadout facilities 682.3<br />
Railway (62km distance and 94km total including turnaround loop and sidings) 228.8<br />
Port Facilities: Railcar unloading, stacker/reclaimer, conveyors 96.8<br />
Environmental and Tailings Management 27.9<br />
Other Pre Production Costs 34.0<br />
Sub-total 1,167<br />
Contingency 201<br />
Total 1,368<br />