CLAUSES OF CONTRACT<br />
B S N L<br />
d) Full assessed value of Secured Advance fresh paid in this quarter (D)<br />
e) Full assessed value of Secured Advance recovered In this quarter (E)<br />
f) Full assessed value of Secured Advance for which<br />
Escalation is payable in this Quarter (D – E)<br />
g) Advance payment made during this Quarter (G)<br />
h) Advance payment recovered during this quarter (H)<br />
i) Advance payment for which escalation is payable in this<br />
Quarter (G – H)<br />
(F)<br />
(I)<br />
j) Extra items paid as per Clause –12 & 12A based<br />
on prevailing market rates during this quarter<br />
(J)<br />
Then,<br />
AA = C (+/-) F (+/-) I - J<br />
BB = 0.85 AA<br />
k) Less cost of material Supplied by the BSNL as per<br />
Clause 10 <strong>and</strong> recovered during the quarter<br />
l) Less cost of services rendered at fixed charges as per<br />
Clause 34 <strong>and</strong> recovered during the quarter.<br />
(K)<br />
(L)<br />
m) Cost of Work for which escalation is applicable: W= BB - (K+L)<br />
iii) Components of materials, Labour, P.O.L., etc shall be pre-determined for every<br />
work <strong>and</strong> incorporated in the conditions of contract attached to the tender papers<br />
included in Schedule ‘E’. The decision of the Engineer-in-Charge in working out<br />
such percentage shall be binding on the contractor.<br />
iv) The compensation for escalation for materials <strong>and</strong> P.O.L. shall be worked out as<br />
per the formula given below:<br />
AA M I --- MIo<br />
a) VM = W x ---------- x -----------------------<br />
100 MIo<br />
VM<br />
W<br />
AA<br />
Variation in material cost i.e. increase or decrease in the amount in<br />
rupees to be paid or recovered<br />
Cost of work done worked out as indicated in sub-para ii) above.<br />
Component of materials expressed as per cent of the total value of work.<br />
MI & MIo : All India wholesale index for all commodities for the period under<br />
reckoning as published by the Economic Adviser to Government. of India,<br />
Ministry of Industry <strong>and</strong> Commerce, for the period under consideration<br />
<strong>and</strong> that valid on the last stipulated date of receipt of tender including<br />
extension if any.<br />
Z (FI---FIo)<br />
b) VF = W x __________ x __________<br />
100 FIo<br />
VF<br />
Variation in cost of fuel, oil <strong>and</strong> lubricants, increase or decrease in rupees<br />
to be paid or recovered.<br />
29