1. Project name and date of delivery Construction of small hydro power plant “Zlot“<br />
21/12/2010<br />
2. Name of applicant: Institution / Entity: IGIS IMAKO Ltd.<br />
Public / Private: Private<br />
Core Activity: Trade and service providing<br />
3. Contact Information<br />
Contact: Predrag Armus Direc<strong>to</strong>r<br />
Address: Krunska10 / 6, 11000 Beograd<br />
Tel.: 011 / 3346-768<br />
Fax: 011/3346-769<br />
E-mail: igisimako@ptt.rs<br />
4. Location of <strong>project</strong> activities Region: “Zlot” , on <strong>the</strong> river Zlot<br />
City: Bor<br />
Municipality: Bor<br />
5. Description of <strong>the</strong> <strong>project</strong><br />
Describe <strong>the</strong> <strong>project</strong> activity, <strong>the</strong> main technical<br />
parameters and technology <strong>to</strong> be used, possible<br />
results in terms of reducing emissions of<br />
greenhouse gases, contributing <strong>to</strong> sustainable<br />
development based on <strong>the</strong> criteria of sustainable<br />
development) (maximum 2 pages)<br />
The <strong>project</strong> involves <strong>the</strong> construction of small<br />
hydropower plants, forces of up <strong>to</strong> 500 KW.<br />
SHPP Zlot planned as a flow without reservoir,<br />
consist of water intake (Tyrolean-type), which are<br />
integral parts of a concrete sill and settling along<br />
<strong>the</strong> watercourse, steel pipe for supplying water <strong>to</strong><br />
<strong>the</strong> machine building and machine building itself.<br />
Planned environmental water intake does not<br />
endanger <strong>the</strong> environment and <strong>the</strong> system as a<br />
whole does not affect upstream or downstream<br />
use of <strong>the</strong> remaining available hydro potential of<br />
this river.<br />
The <strong>project</strong> will significantly contribute <strong>to</strong><br />
sustainable development in Serbia and is based on<br />
renewable energy (hydropower).<br />
In this <strong>project</strong> emission reductions will be achieved<br />
by replacing <strong>the</strong> current electric and / or heat<br />
power produced by burning fossil fuels, electricity<br />
and / or heat from a source with zero emission.<br />
• The <strong>project</strong> will result in <strong>the</strong> transfer of money
and modern "green" technology, direct investment<br />
and active participation of local companies<br />
• Data <strong>project</strong> activity leads <strong>to</strong> a reduction in<br />
emissions of greenhouse gases and <strong>the</strong> emission<br />
reductions are "additional".<br />
• The <strong>project</strong> will result in a reduced level of<br />
emissions of CO2, SO2, NO2<br />
• The <strong>project</strong> activity will lead <strong>to</strong> energy efficiency<br />
on <strong>the</strong> supply side of energy systems and demand.<br />
6. Current status of <strong>the</strong> <strong>project</strong><br />
(Pre-feasibility study, feasibility study, only <strong>project</strong><br />
<strong>idea</strong>, preliminary design, detailed design, in<br />
construction, etc.).<br />
Project Idea<br />
7. Additionality (what would happen in <strong>the</strong><br />
absence of <strong>project</strong> activity)<br />
8. Assessment of financing <strong>the</strong> cost of<br />
investment and available funds<br />
9. Time frame<br />
Please estimate <strong>the</strong> time frame for<br />
implementation of <strong>the</strong> proposed <strong>project</strong><br />
The <strong>project</strong> is additional since it faces significant<br />
financial, investment and technological barriers.<br />
Given <strong>the</strong> fact that <strong>the</strong> <strong>project</strong> leads <strong>to</strong> reduction<br />
of CO2 emissions, engaging in a <strong>project</strong> that will<br />
not result in a CER certificates is a major risk <strong>to</strong> <strong>the</strong><br />
<strong>project</strong> owner who is also <strong>the</strong> owner of <strong>the</strong> parcel.<br />
In <strong>the</strong> absence of <strong>project</strong> activity Serbia will miss<br />
<strong>the</strong> opportunity <strong>to</strong> improve <strong>the</strong> criteria of<br />
sustainable development, attract foreign inves<strong>to</strong>rs,<br />
and fur<strong>the</strong>r develop energy efficiency and<br />
renewable energy.<br />
IGIS IMAKO will contribute 20-40% of capital, while<br />
foreign funds <strong>to</strong> finance <strong>the</strong> rest.<br />
Investment costs of <strong>the</strong> <strong>project</strong> are estimated at<br />
around 850 000 Euros.<br />
2010/2011 selection of international financial<br />
institutions for financing <strong>the</strong> <strong>project</strong><br />
2011 The start of <strong>the</strong> implementation<br />
2012 Completion of construction and connection<br />
<strong>to</strong> <strong>the</strong> grid.